You are on page 1of 2

Nakhodka, RUSSIA

Dry dock for The city of Nakhodka is situated in Since land transport of these enor-
the far east of mainland Russia. The mous base structures weighing more
offshore gravity base
company Sakhalin Energy Investment than 100,000 metric tons was close to
structures Company Ltd. was established in 1994 impossible, the investment company
to develop the Sakhalin II project, one opted to build them in a dry dock. By
of the largest integrated oil and gas later flooding this dock, the floatable off-
projects in the world, including the shore structures could easily be towed
Piltun-Asokhskoye oil field and the out to their destination in the open sea.
Lunskoye gas field. The venture called
for the construction of two new produc- The dry docks were constructed with
tion platforms founded on huge con- a 750-m sheet pile wall around all four
crete gravity base structures installed in sides of the rectangular excavation.
the fields in summer 2005. The begin- 550 m of the surrounding sheet pile
ning of year-round oil production for wall was built using AU 25 sheet piles;
both platforms is scheduled for 2007; the remaining 200 m required the
gas production is expected to get under stronger PU 32 sections with a sec-
way by 2008. tion modulus of 3,200 cm³/m. A slope

Huge construction projects were launched to exploit Sakhalin’s natural resources

A dry dock for offshore platforms was built using more than 3,000 metric tons of steel sheet piles

110
The 750-m outer dock wall features AU 25 and PU 32 piles

with wells leads down to the bottom 12-m pieces to ease transportation. until refusal through the denser soil
of the excavation. Three stages of The contractor then spliced the sheet layers. All AU and PU piles were
wells lower the water level below the piles on site. driven as double piles to speed up the
bottom of the dock, thus allowing installation process. Driving caps for
construction to proceed in the dry. The following quantities of sheet piles the impact hammer were provided by
were delivered: Arcelor free of charge for the duration
The sheet piles used for the Sakhalin • 1,940 t AU 25 in steel grade of the works.
II development project were produced S 355 GP. Pile length: 24 m
in Luxembourg and brought by train (12 m + 12 m) Description of the driving equipment:
to their destination in Nakhodka. Each • 1,100 t PU 32 in steel grade • Vibrator hammer: ICE 815, eccen-
wagon was loaded with 40 to 45 t of S 355 GP. Pile length: 29 m tric moment: 46 kgm, nominal
steel sheet piles. Over 3,000 metric (12 m + 12 m + 5 m). centrifugal force: 1,250 kN,
tons of sheet piles were required on maximum frequency: 1,600 rpm.
the job site, in two different lengths: The contractor used a template • Hydrohammer: IHC S70.
24 and 29 m. The piles were cut into and two different hammers (vibra- Maximum energy per blow:
tory and impact hammer) to install 70 kNm, 50 blows per minute,
the steel sheet piles. The soil condi- Drop weight: 3.5 t.
Owner:
tions encountered are a relatively soft
Sakhalin Energy Investment Company
Limited top layer with SPT values (Standard The two offshore gravity base plat-
Contractor: Penetration Test) ranging between form structures were completed after
Quattrogemini Ltd, Finland 10 and 30 blows per 30 cm pen- nearly ten months of uninterrupted
Sheet piles: etration overlying a high-density layer concrete casting. The dry dock was
AU 25 and PU 32 with SPT values from 60 to 90 blows. then flooded and the two gigan-
Pile length: The U-piles were driven through the tic structures were towed to their
24 m and 29 m
soft soil, to a depth of 15 m, with the respective offshore locations some
Steel grade:
S 355 GP
vibratory hammer. The impact ham- 1,000 nautical miles from Nakhodka
Total quantity of sheet piles:
mer was then used to drive the piles in July 2005.
3,040 metric tons

111

You might also like