You are on page 1of 89
Chapter 17 Review the Application 1. Introduction ‘Test plans determine what will be tested and in what order. This is where we use all of the knowledge discussed in this fiook and apply it to test relay applications. ‘Test plans should include all of the steps discussed in the next few chapters and can be performed manually or automatically. A summary of these steps are as follows: 1) Review the Relay Application Collect the singledine drawings, threeline drawings, DC schematics, coordination study. and other relay related drawings to compare to the relay manufacturer's manual and customer-supplied relay settings. Pay particular attention to the following items: © CT polarity and loc © CT-and PT input connections © Cand PT ratios © CTand PT test points © Output connections, + Input conn-ctioas, descriptions, and logic assignments + Power supply voltage © Settings match the coordination study and make sense descriptions and logic assignments 2) Establish Communications with the Relay and Apply Settings After the application has been verified and all discrepancies have been resolved, you're ready to start applying settings. Power up the relay, connect your communi and apply the relay settings. Sometimes this can be the hardest step when relay testing, jon cable, 543 Principles and Practice 3) Connect Your Relay Test-Set Connect your test-set to the relay to simulate the actual CTsand PTs, This can often require some creative thinking depending on the application and the make/model of your testset s that will be tested to the testset Connect the relay outputs/input 4) Creating the Test Plan Make a list of elements that affect all output contact, LED, or communication output operation. Review the list and test to ensure the elements are operating correctly and will operate the cerrect outputs. Try to test without changing relay settings. Ifyou must change ttings, minimize the relay setting changes and make sure that any disabled elements are tested after they are enabied. (Do not test an element, disable it to test another element, and then enable it again without verifying it stil operates correctly.) 5) Perform Relay Self-Check and Verify Inputs/Outputs Modern relays perform continuous selfchecks to help detect in-service failures. Run a self-check to see if any problems are detected. Most relay failures occur with the analog/ that cannot be tested with the self-check feature. Apply currents and voltages to the appropriat> inputs and verify that the relay metering is correct. Pulse or operate output contacts and verify operation with an ohmmeter or your testset’s contact-status detector. Apply the correct input voltage to each input and make sure the relay status point digital input changes state, 6) Test Individual Elements for Pickup and Timing ‘Test the pickup and timing for each enabled element and compare to manufacturer's tolerances, 7) Final Output Tests Ifthe pickup and timing functions for elements are tested individually, verify all relay output logic functions to ensure there are no errors. ‘This includes each output contact, LED, and communication output. Apply input currents/voltages/frequencies necessary to enable an element and make sure the correct output signals are created. You should be able to simulate each clement in a relay whose settings have been correctly designed and applied siyou can’t make every element operate during this step, there are redundant settings that i should be questioned. i ‘This s | , J ep can be combined with Step #6 to minimize setting changes. Chapter 17: Review the Application 8) Final Report Document all test results and save a record of all asleft settings. Document all changes, special procedures, and/or questions on the first page of the test sheet for easy review. The settings should be in a format that does not require any special software so that anyone who needs the information can access it. 2. Collecting Information Collect the singledine drawing, three-line drawings, schematic drawings, relay settings, and coordination study with a pad of paper to write down key items. A) Single-Line Drawings Figure 17-1 depicts an example single line drawing. You can follow the lines from any device to find its source or what devices are connected to any source. As drawings become more complex, they can be split into different drawings because of their size or crossing es that can make it nearly impossible to read. In these cases, symbols are often added on each side of a eplit line. The hexagon connected to CT's 4-54 indicate the CTs are connected to RLY-5 on Drawing #2 and Hexagon B indicates the second CT input from CTs 24.26 on Drawing #2. You can draw a mental line between Hexagons C on RLY-1 and VT2 as shown by the light dashed line. ill come 0 Keep 3p SS t cece Jee» = ube Sie (OR ae ey it [Ore 2, s = sass Figure 17-1: Complex Single-Line Drawings 545. Principles and Practice gleline drawings can become quite complex and it’s important to follow the lines correetly. Use the following figures and instructions to learn what information a single line drawing can provide, | cca SE» | cera» 3E-<>>— SS >> L : v eI + | —cccegpn»-3E-»- on 1 | Figure 17-2: Simple Single-Line Drawings 546 Chapter 17: Review the Application Use Figure 17-2 to learn the following information and note it down for our test plan: c ‘The relay should be a Multilin SR-750 (Make sure you have the relay manufacturer's bulletin) and its designation is RLY-12. All relays should have a unique designation as there could he many SR750 relays at this project. This is commonly missed at sites and on drawings. You can make one up or use the designation trom the coordination study that will likely have a unique identifi ‘The CT isa multiatio CT and should be connected with a 2000:5 ratio. (Note: While 1 believe that the single-line should have the CT ratio listed, many companies only list the maximum ratio as shown on the topright drawing. Find out what the standard is and make sure it’s correctly shown.) ‘The CT polarity is connected to the cable and current flows from the cable to the bus. The PT ratio is 4200:120V and is connected open-delta, ‘Test switches are installed for testing, (Good news for relay testers.) ‘50, 51, and 27 elements should be enabled in the relay. (Some companies only show relays as a blank box or circle without any element information like the bottom drawing.) ‘There doesn't appear to be any ground or neutral protection. 547 Principles and Practice Singleline drawings can also provide information regarding the logie settings and output contacts, Any information should be checked against the DC control schematics and the relay settings. Some examples of DC logic on singletine drawings are shown in Figure 173. Various styles of drawings give different amounts of information as you can see from our various examples. Keegy SE <> Se ° 3S Ld Lem Seep» ccc 36a» — SS | 3S :Single-Line Drawings with DC Logic and Settings Figure 17- as. Use the following checkti Relay Designation Phase Rotation TI Location CT atio T1 Polarity PT1 Location PTT Primary Volts PT1 Secondary Volts PTI Ratio PT1 Nominal PriVolts PTI Nominal Sec Volts PT! Connection Outt Initite Out! Connected (Out2 Initiate (Out2 Connected (Outs initiate (Out3 Connected SINGLE-LINE RLY-12 ABC Cable-Breaker 20005 Cable Incoming 4200 120 as a1cov 118.86V Open Delta R1=50451 Trip 86-5 R2=Close 52-5 Close R3=27 Trip 52-5, ‘THREE-LINE Chapter 17: Review the Application DC SCHEMATIC Figure 17-4: Example Relay Information Checklist #1 to record information from the single-line drawing: SETTINGS 549 Principles and Practice B) Three-Line Drawings ‘Threeline drawings are the most important drawings for the A/C connections to the relay. “These drawings should show all of the connections throughout the A/C system from the CT secondary terminals, which determine the CT ratio and polarity to the relay terminals to ensure correct polarity. The following is a threeline drawing for our example. = ve Ce iel Has | rssasac | | EEE om) <4 Noel _ocl, Figure 17-5: Example Three-Line Drawing 550 Chapter 17: Review the Application Carefully inspect the threedine drawing and continue filling out the checklist. Compare any differences between the threeline and singledine drawings. If there is a difference, find out which drawing is correct before testing the relay. SINGLE-LINE THREE-LINE DCSCHEMATIC SETTINGS Relay Designation river? uy-12 Phase Rotation ABC aoe Location Cable Breaker Cable-Breaker T Ratio 20005 2000:5 71 Polarity Cable Cable PTI Location Incoming Incoming PTI PrimaryVols 4200 44200 PTI Secondary Volts 120 120 PT Ratio 351 3501 PTI Nominal Pivots 4160 at60v PT1 Nominal Sec Volts M886V 118.86 (4160/38) (4160/35) PTI Connection Open Delta Open Delta ut! Initiate R1=50451 NA ‘Outt Connected ip 865 NA Out? initiate K2= Close NA Out2 Connected 52-5 Close NA uss titiate R3=27 NA ur Connected Tip 525 NA Figure 17-6: Example Relay Information Checklist #2 CT connections can be confusing for some people, but the connections can be correctly interpreted using this method. Power flows from the transformer to the bus in this application so we can trace the flow of power from the A-phase transformer cable to the Acphase CT. Current flows into the CT polarity mark and out the CT secondary polarity mark (H1 & X1). Follow the line from the polarity mark to the test switch and record the number of the CT test switch connected to the relay. The testswitch terminal connected to the relay must always be an odd number or the shorting feature will not work correctly. (More on test switches later in the Test Switches section of this chapter) Keep following the line to the relay, and record the first relay terminal number, Keep following the terminal through the relay and record the outgoing relay terminal, Keep followi..2 the line to the test switch and record the test switch terminal number. Keep following the line and make sure it eventually makes its way back to the CT: Repeat this step for the other two phases and ground, if applicable, 551 Principles and Practice ‘The threc-line drawing adds additi add another connection checklist to record this information. Using the example threeline drawing, follow the A-phase primary bus through the polarity marks of the PT, write down the test switch number, and note whether the odd or even number is connected to the relay. Continue following the line to the relay terminal and record this information, Repeat for the other two phases and ground, ifinstalled. Repeat the previous PT and CT steps on the manufacturer's drawings and record on the Connection Checklist. ounce ar ‘or ac — Senct ssomie ot vomne wanes | CUT ure] Fd, F cana Figure 17-7:GE/Multilin Manufacturer's Typical Wiring Diagram 582. Relay Designation Relay Model €T1 Location <1 Ratio C1 Polarity CTIA Phase Test Switch CT1A-Phaze Relay Connection CTI B-PhaseTest Switch (C718 Phase Relay Connection CTI C Phase Test Switch C1 GPhase Relay Connection CT1.G Phase Test Switch CT1G Phase Relay Connection PT1 Location PTI Connection VII A-phase Test Switch \VT1 Acphase Relay Connection. VT1 8 Phase Test Switch TI B-Phase Relay Connection VT1 G-Phase Test Switch VT1 C-Phase Relay Connection VTINPhase Test Switch \VTIN Phase Relay Connection VTS Phase Test Switch VTS Phase Relay Connection VISN Test Switch VISN Relay Connection Figure 17-8: Example Relay Connection Checklist So far everything SINGLE-1INE ay.12 R750 Cable-Breaker 200055 Cable NA NA NA NA NA NA NA NA Incoming Open Delta NA NA NA NA NA NA NA NA NA NA NA NA Chapter 17: Review the Application ‘THREE-LINE ay2 $R-750 Source-Breaker 20005 Cable Source) T5-52-5-AC (3-1) RUY-12 (G7-H7) TS52-5-AC (7-5) ALY-12(68-H8) 75-52-5-AC (11-9) RLY-12 (G9-H9) NA NA Incoming Open delta TS-52-5-AC (15) ALY.12(G5) T5-52-5-AC (17) LY-12(H5 & HE) TS-52-5-AC (19) RLY-12 (G6) NA NA NA NA NA NA forking fine, Notice that the manufacturer included RELAY SPECS. RLY-12 sR-750 Source-Load NA Source NIA G7-H7 NA cons NA cone NA G10-H10 Incoming Open Delta N/A cs NA HS&H6 NA 66 NIA NIA N/A ca NIA Gs separate window {or open delta connections and we used this connection instead of the wye connection, The most common error for PT connections involves the jumper between V,, and V, It should be installed on nearly every relay when open-delta connected PTs are used. 553 Principles and Practice Let’s look at some examples where CT connections do not look like the drawings but wit Still operate correctly. Follow the power flow into and out of the CT polarity marks into the relay and compare to the checklist to see how the following connections are also correct. of oa) a — | w [ve wa] BO ae a sermas EO mutton 750 eal ool acl vo Figure 17-9: Alternate CT Connection #1 oe mere sa] ae fa peel odode Figure 17-10: Alternate CT Connection #2 554 Chapter 17: Review the Application ‘The following drawing illustrates why polarity mark location is less important that actual CT position and connections. Power flows into the nor-polarity mark, so you must start tracing the flow of powerin the secondary circuit from the non-polarity of the CT secondary. Figure 17-11: Alternate CT Connection #3 I's unlikely you'll ever see this CT configuration in the real world, but it demonstrates why polarity marks are important. Follow the flow of power into the CT polarity and out the secondary polarity mark. Gay a Bs _ ‘ rr ft ey Eg | wane ¢ gm CERT eS ees hI 7 [mld 0 Figure 17-12: Alternate CT Connection #4 Principles and Practice ‘Some companies use A-CB rotation and A-C-B connections with an A-CB configured relay, The following connection is used in these cases. Pay careful attention to the system and relay's rotation when reviewing threeline drawings. en 09] 0c f * % or yT ogee oe bg ee a % crasmens de auvaz Dd rk eal al oc Figure 17-13: Using A-C-B Rotation with an A-C-B Relay 556 Chapter 17: Review the Application ‘The following threetine drawing demonstrates how you can use an AB-C configured relay in an A-C-B configured system, Both CT and PT connections must be swapped in the same ‘manner otherwise the relay will not operate on any phase-related elements and may not correctly measure Watts, VARs, Fower Factor, etc. Fie) re ound fee tet et ae nD) od Figure 17-14: Alternate CT Connection Principles and Practice 558 C) Test Switches ‘Test switches are installed between devices to isolate equipment without removing wiring, You will find test switches in nearly every utility environment, but they create an additional expense and are not as common in industrial environments. The most common test switch used in North America is based on the old Westinghouse “ oh block has ten (or more) switches and each switch can be individually configured to be a simple knife-blade style disconnect switch or; two, side-by-side. switches can be configured for CT connections. When looking from the front as shown in Figure 17-15, the termina numbering starts from the topleft (1), the next number is bottom left (2), moving to the * style test switch, F st top of the next switch to the right (2). Odd numbers are always on top and even numbers are on the bottom. The switches are also labeled “A” to “J” from left to right. Test switeh handles can be nearly every color and some companies colorcode the switches for C ions. If color coding is applied, make sure its consistent throughout PI's, and DC conne: the site. Simple knile-blade style switches can be used in voltage circuits to isolate PTS; or in DC Circuits to isolate trip outputs or relay inputs. Every company has a different standard when connecting test svitches, and itis important not to make assumptions based on what you are used to, Some companies always connect the source of AC circuits (CTs and PTs) ‘on the bottom of the test switch and the relays are always connected to the top. Other companies connect voltage sources on the topside of the switch to prevent the exposed blades from being energized if something metallic is dropped across open blades or to prevent unintentional shocks, Its important that the design is consistent throughout the plied from site, If some test switches are supplied from the boom and others are s the top, make a note on your test sheet and bring it to your client's attention to prevent problems in the future. Figure 17-15 displays a FT test block configured with all voltage 6) which is open. switches. All of the switches are closed except switch "C” (lerminals, Obviously there is no conneetion between ‘Terminals § and 6 when the switch is open ate a ra mish A at i) on [ey nt P J 2 4% eC CET ee) Figure 17-15: Voltage FT Test Switches Chapter 17: Review the Application s are a lidle more complicated and are always installed in pairs when used to with clips that will allow normal current CP switche short CE circuits. The rightside switch is instal flow when opened. A probe can be inserted between the upper and lower clips to directly the current in the cireuil, An isolation device is inserted between the upper nd allel paths. measur lower clips when testing to prevent back fecds into the CTs and remove any pa You can use specially designed test plags, iest probes with opensircuits, wide tiewraps. eae at javerite) store membership cards to isolate the CT cireuits. 4 will separate the upper and lower plug without permanently bending the clips will work in a pinch. The pair's lefthand switch is a shorting switch. When the switch is opened, the bottom of the switch makes contact with a metal bar that is installed between the nwo switches, When the lefchand switch is fully open, the bottom two (or even numbered) contacts are shorted together and current should flow into the bottom of one switch and out the bottom of the other. This is why itis very important that CTs are always connected {o the bottom of the test switch, Incorrectly installed CT secondary connections can cause ts that can create dangerously high CT secondary voltages. Current ean flow witch is which for test-set connections. opencires into either switch and it’s important to note which s ‘Test switches can be installed in nearly every configuration and incorrectly configured switches is a very common problem at new installations, Switch configurations can be quickly checked by leking for the elipsand shorting barsand comparing them against the drawing terminal numbers. Figure 17-16is a close up picture of a shorting style test block. If you look for the clips and shorting bars, you'll see that there could be three sets of CTs connected to this switch using switches: © APhase = A(-2) and BCH * BPhase = C56) and DG) © CPhase = E@10) and FU 12) Figure 17-16: Current FT Test Switches Principles and Practice ‘The previous test switch example has a very unique configuration because switch “G" has CT test plug clips but no corresponding shorting switch. This test switch is incorrectly configured unless the CT return path flows through this switch as shown in Figure 17-17 to allow for easy neutral cur nt measurements. thy dud my] 6) Figure 17-17: Current FT Test Switch Connection Drawing ‘The following drawings are examples of the most common test switch configurations, 3 + ‘ [ar ae] bef eye wr] Paste | | |G EP Pa PT | | LL ate afrafiadaed | s ; ah opm | cow | om am eh che ee Trois cle aly dy LL le 3 is [bad sb lat erage 18 3b, 58 7 oe riwiae Tde 7d a } afalcf opel rfc nLils af of cf of ey eof way 9] | fl shatskad sha 1 EMSS he ts nln atu | ch tain] ce mane ao he | eb aha | cfu ak whe = Se FROM PT: Figure 17-18: Common FT Test Switch Configurations Chupter 17: Review the Application General Electric also produces a “PK” test block that has a very different principle of jons. The test block uses at housing mounted operation and isnot common in newer install in the panel and a keyed plug is inserted into the housing, connceting the top and bottom terminals during normal operation, ‘The test block can be used for voltage and current applications depending on the metal jumpers installed in the housing. as shown in Fig 1-19, Figure 17-19: General Electric “PK” Style Test Block The two sets of terminals on the left would be used for voltage circuits. When the plug is removed, the shorting link beside “I” connects the top and bottom terminals through, spring clips installed on each terminal. When the normal plug is inserted, the spring clips separate from the link and the two terminals are connected through the plug, Special test plugs ean be configured to separate the top from the bottom, or any insulating material can be inserted between the spring clip and shorting link for testing, The shorting clip is not necessary for correct operation of the test block and may not be desirable, The voltage top or bottom depending on the site requirements, souree can be conneeted to th Current test terminals use the horizontal shorting link to short the phase and return, terminals connected to the CTs, One horizontal link ean be used for each CT, ar all of the links designed to be connected together with the circular short wrap around the alignment bars. The CT ean be connected to the top or bottam of the tes! block but the shorting bars must be connected on the same side These test blocks can be dangerous because vou cannot see the shorting fink configuration until after the plug has been removed. Ifthe configuration is incorrect, dangerously high opencircuit CT secondary voltages can be created. Always wear the appropriate personal protcetive equipment when opening an unproven PK style test block, and be prepared to immediately reinsert the plug ifthe configuration is incorrect. Principles and Practice 562 D) Schematic Drawings Schematic drawings show how the different control and protective devices interact to operate a device; or signal to display status. When relay testing, our primary focus will be the trip and close schematics for isolating devices (circuit breakers, contactors, etc), SCADA or remote monitoring system points, and relay layout drawingsit they exist. Collect all of these drawings to record information to continue our ongoing checklist. “The first drawing to look for is the relay layout drawing, if it exists. This is an extremely. useful drawing for relay testing but can often be left out of a project as another way to cut costs. The drawings usually associated with the relay’s power supply ifithas its own circuit ‘and can look like the following figure. Check the terminals against the manufacturer's drawings and pay particular attention to input connections. The relay can easily be ‘damaged by incorrect input connections. Use the example drawing to fill in the connection checklist we started earlier. Our example drawing has the ideal amount of information, but many real world drawings will be incomplete. Fill in as much information as possible on the checklist from this drawing. (- 1 Te | rr {2 atsoc, Figure 17-20: Example Relay Schematic Drawing | Chapter 17: Review the Application ‘The following figures depict some examples of relay input connections from manuf instruction manuals. > Tet} © me Tow TES aos woe FELT ge Bh 8) «sone S| | OUTPUT CONTACTS r SHOWN WITH NO 7 mum CONTROL POWER sopeus'[Efra| nore {ME SELF-TEST WARNING OUTPUT RELAY 1S FALSAFE. Figure 17-21: Example DC Output Connections Dry Contact Connection Wet Contact Connection 101760 RELAY {sro revay rmvoc ~en~ savoc (ow logereut eT? logempas | et voc = mvoc ccningane B15 ochegane (BFR Figure 17-22: Example DC Input Connections 563 Principles and Practice 64 Relay Designation (M1 Location. CT Ratio CT! Polarity PTT Location PTT Primary Volts PTI Secondary Volts PTT Ratio PT1 Nominal PriVolts PTI Nominal Sec Volts PT1 Connection Relay Power ut Initiate ‘Out Connected Out2 Initiate (ut2 Connected ‘Out3 initiate (0ut3 Connected Out4 Initiate Outs Connected (Outs initiate (0.85 Connected Outs initiate (Outs Connected (Out? initiate (Out? Connected Outs initiate (Outs Connected INT Initiate IN1 Operate IN2 Initiate IN2 Operate SINGLE-LINE ruy2 Cable-Breaker 200035 cable Incoming 4200 120 351 a16ov nigesv (4160/35) Open Delta NA RI=50451 TRIP 86-5 R2=CLOSE 52-5 CLOSE 3-27 Trip 52-5 NA NA NA NA NA NYA NA wa NA NA wa NA NA NA 3 LINE ruy-t2 Cable-Breaker 20005 cable Incoming 4200 120 35:1 at6ov vies6v (4160735) Open Delta NA WA NA NA A NA NA NA NA Na NA NA WA NA NA NA NA NA NA NA NA DC SCHEMATIC RLY-12 NA NIA NIA NA NA NA NA NA NIA NA 12svoc 50451 TRIP 6-5 PB. 52-5 CLOSE 27 TRIP 52-5 SPARE SPARE SPARE ‘SPARE SPARE ‘SPARE 50451427, SCADA RELAY FAIL SCADA 520/525 NA SPARE NIA Figure 17-23: Example Relay Information Checklist #3 SETTINGS / NAMEPLATE Chapter 17: Review the Application ‘Sometimes the relay layout drawing is a copy of the manufacturer's drawing with site specific information added that makes it easier to find the information you need. An example of this, kind of drawing follows: Bo ey Figure 17-24: Example Manufacturer's Connection Diagram Use the information from the relay layout drawing to quickly locate the relay inputs and outputs on the related schematic drawings. Compare each schematic to the checklist and ensure that everything matches. 565, Principles and Practice Ifthe relay layout schematic does not exist, look through each schematic until you locate all of the inputs and outputs related to the application. This can be tricky or difficult as the drawings become more complex. Sometimes it’s necessary to look at the back of the relay to determine which outputs and inputs are connected to external wiring to find out how many are used, Our example application for RLY-12 uses five outputs as shown in the relay layout diagram on Figure 1720. Three of these outputs can be found on drawing § DC1 as shown by the shaded areas in Figure 17-25. Without the relay layout drawings, you would have to look at all of the DC schematics related to the SCADA system and 525 to find all five outputs. ‘The relay layout drawing helps us by specifying drawings 525 DC1, 525 DC2, and SCADA-L Figure 17-25: Example Trip / Close Schematic 58 Chapter 17: Review the Application E) Settings ‘Most of the problems found during relay testing occur when comparing the settings to all, of the information we've gathered so far: The most common problems are listed below and should be carefully reviewed. Sometimes it seems that the drawings are not even reviewed when settings are issued! © CT/PT ratios and conace*ians don't match the drawings + Outputs are assigned in the relay but not connected to anything * Outputs are connected to circuits and not assigned inside the relay Settings can be provided in their native software, as Microsoft Word™, Adobe Acrobat™ (pdf) documents, or in any combination. Print the settings (if necessary), collect the coordination study (if provided) and complete the checklist. I prefer to wait unti! 'm sitting in front of the relay and am entering the settings into the relay fur two reasons: First, relays are constantly evolving and manufacturers keep adding new features, correcting mistakes, and creating new revisions of the relay’s operating software. The provided settings could have been created using an older version or incorrect relay model and some settings might be missing. Sometimes the provided relay settings are outside acceptable ranges and this problem won't be noticed until the are applied to the relay. By waiting until the settings are applied, I can hopefully find all of the problems at once. The second reason is more a personal preference. Ifind it difficult to catch mistakes when they are simply printed on a page. Especially, when relays have dozens of setting pages for nple fenctions and 90% of the settings do not apply. Some relays will automatically block: unused Settings from view when an element is disabled but will print every setting making: it difficult to separate the wheat from the chaff, Most people pay more attention when doing instead of reviewing, and this helps me find mistakes, On the other hand, waiting till the last minute can delay testing as you try to resolve the You are inevitably going to discover discrepancies between all of the information that you've collected and already know what needs (0 be done to correct it. It’s important that you realize that you are not the engineer responsible for this project and should not unilaterally make changes based on the information you have. It’s common to be provided drawings that are out of date that will make your changes obsolete. There may also be bigger-picture reasons for settings that you are unaware of. Summarize all of the problems, “om to the engineer in charge. Document all changes suggest corrections, and submit and submit the final settings to the appropriate parties, 967 Principles and Practice ‘The following figure contains the pertinent information for the Multiin SR-750 relay in our example, ‘82 System Setup Current Sensing Phase CT Prisnary 2000 A Ground CT Primary SOA Sensitive Gnd CT Primary 1000 A Power System _ __ Nominal Frequency one Phase Sequence ABC Costof Energy 5.0¢/kWh Bus VT Sensing Type Delta Nominal VT Sec. Voltage 1is9v Ratio 35.01 Line VT Sensing _ _ Type Vab Nominal VT Sec. Voltage 1g9v Cost of Energy 35.08 $3 Logic Inputs Logic Inputs Setup Input Asserted Logic Contact Close Input2 Asserted Logic Contact Close Logic Inputs Input? Name 52-5 52a Input2 Name Logic Input 2 54 Output Relays Relay 1 Trip Seal InTime 0.045 568 Relay 2 Trip Seal in Time Relay 3 Auxiliary Name Non-operated State Output Type Relay 4 Auxiliary Name Non-operated State Output Type Relay 5 Auxiliary Name Non-operated State Output Type Name Non-operated State Output Type Relay 7 Auxiliar Name Non-operated State Output Type $5 Protection-Phase Current Ph: Function Relays Pickup Curve Multiplier Reset Direction Voltage Restraint Chapter 17: Review the Application 0.045 27Trip De-energized Self-esetting AUXILIARY De-energized Self-esetting AUXILIARY De-energized Self-esetting AUXILIARY De-energized Self-resetting SCADA De-energized Self-resetting Trip 7 1.00x CT Normally inverse 3.00 Instantaneous Disabled Disabled 569 Principles und Practice 570 Phase Time Overcurrent 2 Function Phase Instar:taneous Overcurrent 1 Function Relays Pickup Delay Phases Required for Operation Direction Phase Instantaneous Overcurrent 2 Function Phase Directional Function $5 Protection-Voltage Bus Undervoltage 1 Function Relays Pickup Curve Delay Phases Required for Operation Minimum Operating Voltage Bus Undervoltage 2 Function Relays Pickup Curve Delay Phases Required for Operation Minimum Operating Voltage Disabled Trip —7 9.00 x CT 10s Any One Disabled Disabled Disabled Control 347 0.90xvT Definite Time 600s Any One 030XVT Control 3—7 085 XVT Definite Time 200s Any One 030XVT Figure 17-26: Example Setting Printout Relay Designation T1 Location CT Ratio CT! Polarity PT1 Location PTI Primary Volts PTI Secondary Volts PTT Ratio PTT Nominal ri Volts PTT Nominal Sec Volts PT! Connection Relay Power (Out! Initiate Outt Connected Out2 initiate (ut2 Connected Outs initiate (Out3 Connected uta initiate ‘Oura Connected Outs Initiate (Outs Connected Outs Initiate Out6 Connected Out7 initiate (ut? Connected Outs initiate (Outs Connected INT Initiate INT Operate IN2 Initiate IN2 Operate Figure 17-27: Example Relay Information Checklist #4 SINGLE-LINE Run? Cable-Breaker 20005 cable ncoming 4200 120 35:1 a160v nesev (4160/35) Open veka NA RI=50+51 TRIP 66-5 R2=CLOSE 52-5 CLOSE R3=27 Trip 52-5 NA NA NA NA Na. NA Na NA NA NA NA NA NA Na SINE rua Cable-Breaker 20005 Cable Incoming 4200 120 351 4160V 1e.26v (4160/35) Open Delta NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA. NA NA NA NA NA Chapter 17: Review the Application DC SCHEMATIC RLY? NA Nia. NA NA NA NA NA NA N/A NA 12svoc 50451 TRIP 86-5 PB 52-5 CLOSE 7 TRIP 52-5 SPARE SPARE SPARE ‘SPARE SPARE SPARE 50451+27 SCADA RELAY FAIL SCADA S2A/525 NA SPARE NA SETTINGS / NAMEPLATE RLYI2 NA 2000:5 NA NIA NA NA 3: NIA 189 Delta 90-300vDC From Nameplate Trip=50+51 NA Close N/A Bus27-1 + Bus27-2 NIA NIA NA NA NA NIA NA 50+51 4 Bus27-1 + Bus27-2 NIA NA NA sza NA NA NIA 71 Principles and Practice “There were 25 pages of information in the original printout of settings from the relay that was narrowed to the information presented previously. I prefer connecting to the relay and opening every option screen in the software to find out what settings are enabled, The ' following screen captures show the same settings through the relay communication software. = wet SE iy = a Lani - wines [Logietrpat =e sen vem tee fl] sown faa —— ed SINS = = . ila == cme ageupat —————femens] sree Roget ————— mers] imenin— Flogic pat [CommerCiom x} tune Cagenyarie ————~ fewer] =o fe (sk ——— rs | vimentin (Seg (ee orem Yum Tae =

45A=(.1s ‘You can test any relay from any manufacturer with this information to ensure that itis working correetly and will operate the correct outputs at the correct time, I realize that getting descriptic1, of operations from overworked design engineers is an ide-ti situation that is unlikely to be realized in most cases, but it usually doesn't hurt to ask so that you can make your relay testing easier, more effective. and more efficient of the ‘The following practical tips will help you create a test plan for any situation regardl test technique you wish to employ. Principles and Practice A) Traditional Pickup and Timing Tests Collect all of the ch: are enabled and assigned to an output. Outputs can be L status points transferred between relay ion, and the standard relay output contacts. It is sometimes e ep by starting with the ‘output settings. ‘The SR-750 relay uses the individual element approach to relay setting. and there are no independent output settings so we must look at every element setting in the example. A summary of our example settings can be found in the following chart, but I strongly recommend using values from the coordination study whenever possible to censure that the relay will trip when the coordination study requires it to and not when the relay is programmed to operate. It is very possible that the two times do not match due to asetting error. ‘ed in previous steps and determine what elements or inputs Ds on the front of the relay ts via communic aasier to reverse engineer {hi ELEMENT PicKUP ‘CURVE TIMEDIAL RELAYS. 51(TOC) 1xCT(S.04) Normally Inverse (NI) 3.00 Trip &R7 50100) #41 SxCT (45) Definite ime (OT) 10s Tipar7 27 (BUv) #1 o.9xvT (108v) or 60.05 F3aR7 271BUV) #2 OBSXVT(TO2V) or 2000s RSaR7 Figure 18-12: Example Relay Settings Review the settings and look for overlapping protection that will interfere with testing The overcurrent settings are straightforward, This relay has one pickup LED for all clements that can be used for SLelement pickup testing without interference from other elements. Timing tests can be performed up to 9x pickup without interference from the 30-element. The bus voltage during both tests must be greater than 108V to ensure the voltage protection does not interfere with the overcurrent tests The 50-clement tests require a litle more finesse. ‘The pickup LED can only be used for pickup testing if the 5-element is disabled. Ifthe 51-element is disabled for pickup testing, it must be tested after the 50-clentent testing is complete. You could also test 50-clement pickup using the relay trip (R2 or R7) contacts without any setting changes. Using the ‘turer's formula, the 5t-element time delay for a Normally Inverse curve at the 50element pickup level is 0.73s. This is far greater than the 50-elements 0.15 time delay The 50-element pickup is tested by performing timing tests and increasing the current in 0.24 increments starting from 5% less pickup. ‘The test current that causes the time delay to drop to approximately 0.1s is the pickup current. This method is preferred when such large currents are involved to prevent damage to the relay. The timing test is performed at 1.1x the pickup value to ensure correct operation. Chapter 18: Preparing to Test ‘The 27-1-clement pickup testing is also straightforward using the front LED to test for pickup as long as the test current is less than 5.0A. I always apply a current (typically 1.0 A) below any overcurrent pickup value when testing 27-clements because some relays will block 27-clement operation when no current is flowing (o prevent nuisance tips. Timing tests are usually performed at 10% below the pickup (97.2V) but this value would cause the 27-2-element to operate first The timing test should be performed at a level significantly higher than the 27-2clement and would be performed at 103V. A second test could bc justified to prove a definite time element and both tests should be performed between the two pickup voltages. A prefault voltage above 108V is required for 27-element testing. ‘The 27-2 pickup testing cannot be tested with the pickup LED when the 27-1-clement is operational. The 27-J-element could be disabled before testing the 27-2-clement pickup, but the 27-1 pickup tests must be performed afterwards to ensure it is left enabled. 17-2-clement pickup tests couid also use the method described above for the 50-element testing. This method coul” take some time while waiting more than 20s between tests and isn't practical unless time is not an issue. ‘The third method that can be used to test the pickup of the 27-Zelement uses the ‘communication software between the computer and relay. This method is not as accurate as those described previously for this relay brand but can be used. Use the software to open the status screen and change between a prefault nominal voltage and a pickup voltage. Count out the time delay between the voltage change and the computer target display. Start the test voltage 5% higher than the pickup and lower the voltage in small voltage increments. Wait for the previously counted time delay to elapse between increments and stop when the 27-2 pickup target is displayed. Timing tests for this element are very straightforward and are tested at 10% below the pickup (@18V) Calculate the expected tolerances as discussed in the Pickup Test Procedure section starting ‘01 page 110 to determine a pass or fail test result 593 Principles and Practice 594 B) Combining Pickup, Timing, and Logic Tests 1 relay element does not fall out of calibration...it either works correctly ng this principal, the pickup and timing test can be combined into one test Logic testing can also be adcied to the test by connecting all of the outputs to the testset inputs and applying multiple timers. We can apply this test type to each element using the following steps: 1. Configure your test-set to stop if any assigned output for the element under test operates and ignore any output not assigned to the relay element under test. 2. Apply a normal, prefault voltage to the relay for a few seconds to simulate an in-service normal condition. 3. Apply’a fault condition that is just outside the relay’s pickup setting and manufacturer's accuracy speci cations. 4. Apply a fault condiuon that is just inside the relay’s pickup setting and manufacturer's, accuracy specifications. Start a timer for each relay-output assigned to the element. Stop the timers when the appropriate output operates. E/Multilin SR-750 relay instruction bulletin: ‘The following specifications are from the BUS AND LINE VOLTAGE zea ote spect Braen semana cath 150 ‘For open dali. the caedates phase seca Figure 18-13: GE Multilin SR-750 Specifications We can use these specifications to create a combination test plan, We'll Element (60 Instantaneous Overcurrent) using the following steps: 1. The relay TRIP, R3, and R7 are connected to the test-set status inputs. The te set to ignore any R3 operation because the 50-clement does not operate the R3 relay- output. 2. We can set the prefault voltage to the nominal 118.9V,,,,0n all three phases 120° apart in the correct phase-sequence for 2 seconds to prevent the 27 relay from operating, 3. We can set the 1* fault as follows: a. Set the fault voltage to any number larger than 108V to prevent the 27 relay from operating. We'll leave it at 118, 9V,,, to simplify the test procerture. Chapter 18: Preparing to Test s is a Phase element) with B-phasc b. Set the fault current for an A-B phase test (Thi current 180° from A:phase current. should be less than the pickup setting ‘The current magnitude on beih pha minus the relay accuracy. Test Amps < Pickup - Accuracy Fest Amps < 458 — (1% of 20) Test Amps < 458 - (0.2) Test Amps < 44.80, Test Amps = 44.78 d. ‘The relay should be allowed time to operate and then automatically transfer to the 2 fault state. The element time delay is 0.1s and we'll set the maximum duration in the 1* fault state to 0.2s. 4. We can set the 2" fault as follows: a. Timer 1 starts when the 2*! fault state starts and stops when the TRIP input operates. b. Timer 2 starts when the 2"! fault state starts and stops when the R7 input operates Set the fault voltage to any number larger than 108V to prevent the 27 relay from operating. We'll eave it at 118, 9V,,, to simplify the test procedure, 4. Set ihe fault current for an A-B phase test with Bphase current 180° from A-phase current. e. The current magnitude on both phases should be more than the pickup setting, plus the relay accuracy. ‘Test Amps > Pickup + Accuracy Test Amps > 45A- (0.2) Test Amps > 45.24 Test Amps = 45.34 £ The relay should be allowed time to operate. The element time delay is 0.1 and welll set the maximum duration to match the 1* fault state which is 0.2s, Ifthe relay. does not trip, the test should stop to prevent relay damage. g. The TRIP or R7 relay-output should stop the test if wey operate. Principles and Practice 596 We can create a chart of the test plan as follows using phase angles as the SR-750 would display: ABPIOCTEST Aa Voltage BOVoltage covoltage AO Current 80 Current co Current Max Duration Timer 1 Start Timer 1 Stop Timer 2 Start Timer 2 Stop PREFAULT 68.ssveo" 6a.6sve120° 8.65240" 0.000A@0° 0.0008@120" 0.000A@240" 2,000; FAULT! 68.65V30" 68.65va120"° 68650240" 44,700Ka0° 4470080180" 0.0004@240" 0.200: Fauur 2 es6svao" 68.65Va120" 8.65240 45300820" 45,0040 180" o.00R@240° 0.2008 Fault 2 Start TRIP Operate Fault 2Start R7 Operate Create a test plan for the other two phase combinations by rotating the applied current in by 120° to ensure the element will operate for any 0-0 fault. the two fault states 8-CPIOCTEST ABVoltage BO Voltage Voltage AO Current BO Current OCurrent Max Duration Timer 1 Start Timer 1 Stop Timer 2Start Timer 2 Stop PREFAULT 68.55Va0" 68.65Va120"° 68.65Ve240" 0.000@0° 0.0004@120"° ‘.000A@240" 2.0008 FAULT 63.65va0" 68650120" 68.65Ve240" 0.0000" 44,700A@120° 44,7008@300" 0.2008 FAULT 2 esesva0" 8.65va120° esesve2s0” o.c00R@0" 453002120" 4530042300" 0200s Fault 2 Start TRIP Operate Fault 2 Start R7 Operate Chapter 18: Preparing to Test CAPIOCTEST PREFAULT FAULT FAULT 2 ABVoltage 68.65ve0" 68.6500" 68.6sve0" BOVoltage 68.65V@120" 68.65V0120° 68.65V0120"° OVoltage esesverau" ea.ssve240" 68.65V@240" AO Current 0.000820" 44.700K@60° 45.300A@60° 80 Current ‘.000@120° ‘.00008170"° 0.0004@120" Current .0008@240° 44,7008 @240" 4530040240" Max Duration 2.0005 0200s 0.2005 Timer 1 Start Fault 2 Start Timer 1 Stop TRIP Operate Timer 2 Start Fault 2 Start Timer 2 Stop R7 Operate If we run this test and Timer 1 and Timer 2 are within the relay timing specifications, we can pass the relay element's pickup, timing, and output logic because: © The pickup is between 44.7A and 45.3A which is only slightly outside the relay tolerance. There are no adjustments, so we are looking for setting mistakes or gross errors whenever performing tests on a digital relay. The relay pickup is acceptable for service. © The time delay is set correctly if Timer 1 or Timer 2 has a time which is within the relay tolerance. * The output logie values working correctly if Timer 1 and ‘Timer 2 have nearly identic 597 Principles and Practice ‘The same philosophy can be applied to the BUV-1 Element with the following steps using realistic voltage settings as described in Chapter 15: Line Distance (21) Element Testing 1. The relay TRIP, R3, and R7 are connected to the test-set status inputs, The test-set is set to ignore any TRIP operation because the 27-clement does not operate the TRIP relay-output. 2, We can set the prefeult voltage to the nominal 118.9V,,, and prefault current to 1.00A on all three phases 120° apart in the correct phase-sequence for 2 seconds to prevent the 27 relay from operating. The prefault current is set to 1.00A to ensure the 27-element will operate even if its internal logic requires current to flow. 3. We can set the 1* fault as follows: a. The fault current equals 1.000A to match the prefault current. b. Set the fault voltage for an A-B phase test (This is a Phase element). The fault voltage is a combination of the A and B @-N voltages added vectorally and should be more than the pickup setting plus the relay accuracy. This is opposite of the ‘S0-element test because we are testing an wxdervoltage instead of an overcurrent element. ‘Test Volts > Pickup + Accuracy Test Volts > 108V + (20.25% of full scale) Test Volts » 108V - (20.0025 240v) Test Volts ~ 108V = (1.2) Test Volts > 109.2 Test Volts - 109.3 c. The relay should be allowed time to operate and then automatically transfer to the 2 fault state. The element time delay is 60s and we'll set the maximum duration in the 1 fault state to 65s, 4, We can set the 2" fault as follows: a. Timer 1 starts when the 2 fault state starts and stops when the R3 input operates. b, Timer? starts when the 2" fault state starts and stops when the R7 input operates, & The faull current equals 1.000A to match the prefault current, d. Set the fault voltage for an A-B phase test. The fault voltage i Aand B ON voltages added vectorally and should be less than the pickup set minus the relay accuracy. combination of the ing Test Volts « Pickup - Accuracy Test Volts ~ 108V - (1.2) Test Volts « 106.8V Test Volts 106.7v Chapter 18: Preparing to Test ‘The relay should be allowed time to operate and then automatically stop the test if the inputs do not operate. The element time delay is 60S and we'll set the maximum duration to match the 1" fault state which is 65s. f. The R3 or R7 relay-output should stop the test if they operate. 5. Wecan create a chart of the test plans as follows using phase angles as the SR-750 would display: ALL BUV-1 TESTS. Max Duration Timer 1 Start Timer 1 Step Timer 2 Start Timer 2 Stop AO Current. 8a Current COCurrent A-BBUY-1TEST ABVoltege BOVoltage Voltage B-CBUV-1 TEST AQVoltage 80 Voltage OVoltage C-ABUV-1TEST Ad Voltage 80 Voltage COVoltage PREFAULT 2.0008 1.000Aa0° 1.0008@120° 1.000240" 68.65va0" 68650120" 68.65ve240" 68.65V@0" 68.65Ve120"° 68.65V@240" 68.65Ve0" 68650120" 68.65ve240" FAULT 65.005 .000n@0" 1.0008@120° 1.0008@240° o4s4ve2i3) o4savelt787 es6svero" AB = 109.3030" 68,650.00 64.54v@122.13 6454ve237.87° 8.C= 109.3V@90" 6454V@035787° 68.65Va120"° 64540242.13° GA=1093Ve210° FAULT 2 65.005 Fault 2Start 3 Operste Fault 2Siart R7 Operate 1.00080" 1.0008@120" 1.000R@240" e3aave76 e3.4aveni7.24° 8.65240" AB = 106,7Ve30" 68.65¥a0,00" 63.4aven2276° 63.44v@237.24° B-C= 106.7V@90" 63.44V0357.24° 68.65V0120" e3.44ve242.76° CA=106.7Ve210° 599 Principles and Practice 600 ‘The test plan for the BUV.2 tests are essentially the same as the BUV-1 tests with different voltage magnitudes and a shorter time delays because the BUV-2 time delay is 20s instead of the BUY-I time delay of 60s. The sum of the Fault 1 and Fault 2 times for the BUV.2 test must be less than the BUV- time delav or else the BUV-1 element will operate first. Well set the fault times to 25¢ each to allow the relay to operate and the entire test will be 50s so the test will stop before BUV-1 can operate. Fault 1 Volts > Pickup ~ Accuracy Fault 2 Volts > Pickup - Accuracy Fault 1 Volts » 102V + (1.2) Fault 2 Volts > 102 ~(1.2) Fault 1 Volts > 103.2V Fault 2 Volts > 100.0V Fault 1 Volts = 103.3 Fault 2 Volts = 100.7V ALL BUV-1 TESTS, PREFAULT FAULTY Fautr 2 ‘Max Duration 2.000 25:00 25.005 Timer 1 Start Fault 2 Start Timer 1 Stop 3 Operate Timer 2 Start Fault 2 Start Timer 2 Stop R7 Operate A Current ‘.000a@0° 1.0008@0° 1.000820" 80 Current 100080120" .0008@120° .esoA@120" OCurrent .0008@240" 0008@240° 1.000A@240" A-BBUV-1 TEST Voltage 68.65Va0" 202ve361" 094Ve4.28" BoVoltage 6865ve120° 6202V@116.39" 60.94ve115.72° COVoltage ea6sve24o" e8.6sva240" 68.65va240" AB=1033V030" AB = 100730" B-CBUV-1TEST AQ Voltage 68.6sve0" 68.65.2000" 68.6500.00" BOVoltage 68.6sve120" e2o2ve12361" 60.94V @124,28° COVottage 68650240" 6202423639" 6094v @235.72° B= 1033290" BC = 1007Va90" (-ABUV-1TEST AD Voltage 68.65Ve0" 6202V@35639" 60.94ve355.72" BaVonage 6865Ve120"° 68.6sva120° 68.65Va120° COVoltage 68650240" e2o2vera3.6r" 60.94va244.28" CA=1033Va210" A= 100.2V@210" Chapter 18: Preparing to Test ‘The TOC element (51 or timeovercurrent) can be tested with a similar technique that has been modified to testan inverse curve instead of afixed time delay. The TOC element would probably never operate if set slightly above the pickup setting, but if our goal for this test is to ensure tite TOC element does not operate below the pickup setting and should operate a specific time when a specific amperage is applied, we can use the identical calculation ickup for Fault 2. We can even add enough time in Fault any of the standard pickup for Fault 1 and use a multiple of 1 to allow you to see if the relay has picked up in Fault usi methods to ensure that the pickup is correct. ‘We also need to make sure that all test magnitudes are less than the IOC element because the instantaneous element would then operate first. That isn't a problem for this test plan because the IOC setting is 9x the pickup, but if the IOC setting was 5xCT we would not be able to perform the standard timing tests at 6x the pickup setting. We could disable the JOC element but that would defeat the purpose of the combination test which tests the relay with inservice settings to prove the relay will operate correctly when required. If we ask ourselves “Why do I need (o perform three timing tests at these multiples?” we can imagine several answers’ Ifthis is ts. your answer, relay timing “Because that’s the way we've always tested overcurrent relays. you should think about why we've always performed these t could drift over time due to their nature. Three tests were performed at different points along the curve because you could also change the curve shape when adjusting the relay. Multiple tests were important because it was very possible to get one timing: test multiple in tolerance and unknowingly change a third point outoftolerance. Microprocessor-based relays use a formula to determine timing and will never drift One test multiple could be considered acceptable but you should probably perform at least two tests just in case that one timing test unluckily hits a point where different curves cross with the same settings. We can just eliminate the test that exceeds the 50element, 2. “Because ny test sheet requires 3 test points.” If this is your answer, then you can change the multiples of your test plan. Ifthe IOC element was set to 5s the TOC pickup, you can perform timing tests at 2x, 4x. and 4.5x pickup. People chose whole numbers n the past because there were no formulas to calculate time delays and it was much easier to pick numbers off graph when you could follow the line... .especially on a log- log graph. You can use your calculator or a spreadsheet to easily determine the time delay at any multiple of pickup. 3. “Because the NERC/FERC plan ex, If this is your answer, you have no choic ble the IOC elem another output to only operate for a TOC trip for the multiples that exceed the IOC pickup setting. However, many people assume the NERC/FERC plans were mandated eo Principles and Practice by NERC/FERC, but the NERC/FERC rules only mandate that the organization have aplan and that they implement the plan as specified. Those NERC/FERC plans can be changed at any time by following the appropriate procedures for the relay owner and it would probably make everyone's life easier if they were changed. Always remember that the accepted relay test pian is in place until the dat it changes and you will be asked to prove that the old plan was implemented as written until the date of change, even if the plan did not make sense to begin with, The following calculations and chart prepares us to perform a combination test for the ‘TOC element on all three phases with 2x, 4x, and 6x muitiples: ‘Test Amps = Pickup ~ Accuracy Test Amps <5A (0.2) Test Time =m! A+ Test Amps < 4.84 ey ‘Test Amps = 4.78 (;L]-Pctups test Mute reste ounes 3 ttl as De Test Amps = 5A«2 veranesb om 228, 4, De Test amps = 108 foe ‘4x Test Amps = 584 ) 22614 4.1899 | 9.1272 (9°03 ((4)-0.7""()-03)} Test Time = 3./ 0.0274 + “4x Test Amps = 208 ‘Test Time = 1.5385 6x Test Amps = 5A «6 . = Test Time = 3. 0.0274 - 2.2614 san) 6x Test Amps = 308 (6-03 (6-03) (6-03 Test Time = 1.03335 602 Chapter 18: Preparing to Test ‘ALL BUV-1 TESTS PREFAULT FAULTY FAULT 2 Max Duration 2.0005 60.00 5500s Timer 1 Start Fault 2 Start Timer 1 Stop TRIP Operete Timer 2 Start Fault2 Start Timer 2 Stop R7 Operate Ad Voltage 68.65Ve0" 68.65Va0" 68.55Va0" BOVoltage 68.65Ve120" 68.65V0120"° 68.65Ve120"° COVolrage 68.65Ve240" 68650240" 68.65ve240" A-B2XTOCTEST A@ Current 0.000A@0° 470020" 10.0000" 80 Current 0.000A@120° 4.7008@120° 10.000A@180" CO Current .000x@ 240" o.0004@240" 0.000240" 8-C 2xTOCTEST AQ Current. .000@0" .00000° .00A@0° 80 Current 0.0008@120" 4700R@120° 10.000A@120° OCurrent (0.0004@240" 470088240" 10.0008@300" CA 4XTOCTEST AD Curcent ‘.000A@0" 4700@0° 10.000A@0" 80 Current 0.0008@120" 0.00A@120° o.00A@120° COCurrent 0.000240" 470002240" 10.0008@240" AB AXTOCTEST AO Current o.000A@0° 470000" 20.0000" 80 Current ‘0.0008@120° 4.700A@120° 20.000A@180" CO Current c.000R@240° ‘.000A@240" ‘.000R@ 240° B-C 4XTOCTEST AO Current ‘.000A@0° 0.00000" .00neo" 80 Current (0.0008@120" 47008@120" 20000120" Current (.000@240" 4.7004@240" 20.0004@300" C-A2XTOCTEST AO Current ‘0.000A@0" 470000" 20000800" 80 Current ‘c.o00n@ 120° o.00a@120° 0.008@120° CO Current .0gn@ 240° 4700R@240° 200008@240 AB AXTOCTEST AO Current .000A@0" 4.70000" 30.000Aa0" 80 Current 0.008120" 4700A@120° 30.000A@180" CO Current 0.000240" 0.0008@240° 0.0008@240° B-C4XTOCTEST AO Current 0.0000" 0.00030" .00A@0" 80 Current .000A@120° 4700A@120° 30.000A2130° CO Current 0.000240" 4700R@240° 30.0004@300" C-A2XTOCTEST AD Current o.000A@0" 4.70060" 20.000A@0° BO Current 0.0008@120" 0.00a@120° 0.00a@120° CO Current 0.0004@240" 4700R@240° 30.000A@240° 603 Principles and Practice 604 ° All this may seem like a lot of work as described, but remember that most of this work is necessary for the traditional tests. Once the plans have been created, the actual test time will be drastically reduced and the test plans can be re-used in future maintenance plans or modified for similar relays with different pickup and time delays. See the drastic reduction of tests required in the next section as an example Feeder Protection Test Plan After reviewing the settings, it’s time to decide how we're going to test the relay. Create a test plan with all of the steps required to test the relay. This information doesn't need to be written down and can be incorporated into your test sheet. The following diagrams show three different test plans for our application, one using setting changes, and one without setting changes, and one using the combination test plan. Also, the last two plans can be run in any order because no setting changes are required. i) Test Plan #1—Setting Changes 1. Record relay nameplate information 2. Review events for abnormalities 3. Set time and date 4, Test input and outputs 5. Test metering 6. Disable 5l-element 7. Disable 27-Lelement 8. Disable 27:2 clement 9. Connect testset timing input to R7 10. Test 50-element pickup using pickup LED (AB, B-C, 11. Test 50-element timing at 1.1 x pickup (AB, BC, C-A) 12. Connect test-set timing input to TRIP 13, Test 50-element timing at 1.1 x pickup (AB, BC, C-A) 14, Enable 51-clement 15, Test 5L-element pickup using pickup LED (AB, BC, C-A) 16, Test SL-clement timing at 2x pickup (A‘B, BC, CA) 17. Test 51-element timing at 4x pickup (A-B, BC, C-A) 18. Change test-set timing input to R7 19. Test Sl-element timing at 6x pickup (A-B, B-C, C-A) 20. Enable 27:2 21. Test 27-2 pickup using pickup LED (A:B, B-C, C-A) 22. Test 27-2 timing at 0.9x pickup (A-B, B-C, C-A) 23. Connect testset timing input to R3 24, Test 27-2 timing at 0.9x pickup 25, Enable 27-1-clement ii) Chapter 18: Preparing to Test 26. Test 27-1 pickup using pickup LED (AB, B-C. C-A) 27. Test 27-1 timing at @7-2 pickup + 1V) (AB, BC, C- 28. Change testset timing input to R7 29. Test 27-1 timing at (27. 30. Press close pushbutton on relay and monitor R2 trip 31. Review event logs to ensure all styles of trips have been recorded 32. Clear event logs 33, Review settings to ensure no changes have been made 34, Save setting file 35, Save test sheet Test Plan #2—No Setting Changes 1. Record relay nameplate information 2. Review events for abnormalities 3. Set time and date 4, Test input and outputs 5. Test metering 6. Connect testset timing input to R7 7. Test 5L-element pickup using pickup LED 8, Test SL-element timing at 2x pickup 9. Test 5l-element timing at 4x pickup 10. Connect testset timing input to TRIP 51element timing at 6x pickup 50-element pickup using TRIP and timing results 1 timing input to R7 50-element timing at 1.1 x pickup 7-1 pickup using pickup LED 16. Test 27-1 timing at (27-2 pickup + 1V) 17. Connect test-set timing input to R3 18. Test 27-1 timing at (27-2 pickup + 1V) 19. Test 27-2 pickup using computer status display 20, Test 27:2 timing at 0.9x pickup 21. Change test-set timing input to R7 22, Test 27-2 timing at 0.9x pickup 23. Press close pushbutton on relay and monitor R2 operate 24, Review event logs to ensure all styles of trips have been recorded 25, Clear event logs 26. Save setting file 27. Save test sheet 605 Principles and Practice 606 iii) Test Plan #3—Combination Test 1. Record relay nameplate information 2. Review events for abnormal 3. Set time and date 4, Test input and outputs, 5. Test metering 6. Connect test-set timing inputs to TRIP, R3, and R7 7. Create or load the IOC test described in the previous section and run the test pla 8. Create or load the BUV-1 test described in the previous section and run ihe test plan. 9. Create or load the BUV-2 test described in the previous section and run the test plan. 10. Create or load the 1% TOC test described in the previous section and run the test plan. 11. Create or load the 2 TOC test described in the previous section and run the test plan, 12. Create or load the 3°' TOC test described in the previous section and run the test plan. 13. Press close pushbutton on relay and monitor R2 operate 14, Review event logs to ensure all styles of trips have ven recorded 15. Clear event logs 16. Save setting file 7. we test sheet D) Generator Protective Relay Test Plan Generator protective relays have more complex functions than a simple feeder protective relay, Each of these functions protects the generator froma different problem and, if tested in the correct order and set properly, most do not interact with each other. For example, the distance, reverse power, and loss of field protection will only operate i in the correct direction, The negative sequence clement will not pickup during 3-phase the current flows balanced tests. jon will have to be disabled until the Unless 6 channels are available, the differential protect end, [usually disable the undervoltage protection to remove the nuisance and confusion of undervollage trips every time the test stops. The two elements most likely to interact is the overvollage and volts/hertz protection. Disable the volts/hertz protection before testing lage protection. the overvol Chapter 18: Preparing to Test Generator protection schemes usually apply different protection clements to different, ‘outputs and you may not even need to disable some functions that interact because they might be assigned to different outputs. Here isa typical test plan for generator protective relays: Generator Proteciive Relay Test Plan 1. Record relay nameplate information 2. Set time and date 3. Test input and outputs 4, Test metering 5. Disable Differential (87) element 6. Disable Undervoltage (27) element 7. Disable Volts/Hertz (24) element SOBF) element 9. Test distance element (21) using via phase 10. Test Loss of Field (40) elenvent using via $phase 11, Test Reverse Power (32) element using via 3phase fest Reverse Power (51V) clement using single phase 13. Test Negative Sequence (46) clement using singlephase with nominal amps on two phases and zero 2mps on the third phase 14, Test Overvoltage (59) element using via phase 15, Enable 24 clement 16. Test Volt/Hertz (24) clement using via 17, Test Frequency (81) element using via 3-phase 18, Test Inadvertent Energization (50/27) element using via S-phase 19. Enable (60BF) protection st Breaker-fil (50BF) using single-phase Enable (87) protection est Differential Protection (87) using :iphase and singe-phase testing est Neutral Overvoltage (59N) clement est Neutral 3" Harmonie Undervoltage (27TN) element 2. Enable 27 protection 26. Test Undervoltage (27) element using via 3-phase 27. Review event logs to ensure all styles of trips have been recorded 23.1 28. Clear event logs, 29. Review settings to ensure no changes have been made we setting file 31, Save test sheet 607 Principles and Practice E) Line Distance Protective Relay Test Plan A typical distance relay test plan follows: Line Distance Protective Relay Test Plan 1. Record relay nameplate information 2. Set time and date 3. Test input and outputs 4, Test metering 5. Test Zone 1 Distance element (21) using phase 6. Test Zone 2 Distance element using S-phase 7. Test Zone 3 Distance element using S-phase 8. Test Zone 1 Distatice clement (21) using phaseto-phase connect t Zone 2 Distance element using phase-to-phase connections st Zone 3 Distance element using phase-to-phase connections 11, Test Zone 1 Distance element (21) using phase-to-neutral connect 12, Test Zone 2 Distance element using phase-to-neutral connect 13. Test Zone 3 Distance element using phase-to-neutral connecti ne Overcurrent (61) functions using Phase connections unless neutral ov. rcurrent protection is enabled and then use phase-o phase connections. 15, Test Phase Instantaneous Overcurrent (50) functions using I-Phase connections. unless neutral overcurrent protection is enabled and then use phase-o-phase tions conncetions. 16, Test Neutral Time Overcurrent (51) functions using phase-toneutral connections, 17. Test Neutral Instantaneous Overcurrent (50) functions phase-to-neutral connections. 18. Test Ground Time Overcurrent (51) functions using /Phase ground connect 19, Test Ground Instantaneous Overcurrent (50) functions Phase ground connect 20. Review event logs to ensure all styles of trips have been recorded 21. Clear event logs 22. Review settings to ensure no changes have been made 23. Save setting file 608 Chapter 19 Testing the Relay All of the preparation is finally complete, and it's time to start testing. It's been a long time coming, but all of your hard work so far will help make testing a breeze. 1, Perform Relay Self-checks Some relay manufacturers have selfcheck commands or display screens that provide a mmary of the self-check results, Perform the selfcheck function, if possible, and record the s. The “STA” command in SEL relay s will perform the seli-check, and you can cut and paste the results into your setting sheet or test result, Document the relay serial and sofiware version number on your test sheet. 2. Verify Digital Inputs and Outputs ‘The testing applied in this book includes acceptance testing of the relay and all inputs and ‘outputs should be verified to ensure that they function correctly. This is especially important because relay sel-checks cannot detect 1/0 failures and all 1/0 should be shecked at least lifetime. However, some relay manufacturer's make this very difficult (ike the 50 relay in our example) and require many setting changes in order to test the acceptable to only test the inputs that arv being used because are required. Test each input and output and record the results on your once ina Muttilin SR7: input status. In these najor setting chang test sheet. This step also helps reduce connection errors that can be frustrating during later testing when you're trying to figure out why the test is not working. A) Input Testing As we discussed in the previous chapter, itis important that you review the manufacturer's, literature to determine whether the input uses external power or its own internal power supply. Use the relay’s front panel or software to display the input status and apply a jumper input power to each input and ensure the status point changes state. You can skip ing as long as they are tested later as part of the logic testing or logi inputs used in the logic se soy Principles and Practice B) Output Testing Most relays have a test function that allows you to operate each relay independently. The “PUL" command in SEL relays will perform this function. GE Multilin relays have a test function to operate relays, Beckwith Electric relays have an output test function in the diagnostic menu from the from screen. Use your test-set input or a meter to monitor each output status and operate each output relay and ensure it changes state. You can skip outputs in-use as their function will be tested during final output testing. TRPUTIOUTPUT CHECKS. Tess % 7 Figure 19-1: Example Digital Input/Output Test Sheet 3. Verify Current and Voltage Inputs Like digital inputs discussed previously. the current and voltage inputs cannot be verified by self-check features and are offen the most common failures in modern relays. Metering. able test that proves the relay is functioning correctly, the wiring is correct and the relay, and that you've made the correct connections, verification isa; between your tes ‘Two single-phase tests will prove that you have connected cach phase of your test-set to the correet phases of the relay. Apply single-phase, nominal current and voltage into the relay. Monitor the relay’s metering function from the front panel or relay software, and ensure that the voltage and current are measured on the correct phase. Apply current and voltage to another phase, and ensure that the measured current is in the correet phase. If the relay monitors zero-sequence vollage and/or current, record the zero-sequence values on the (esl sheet, When single-phase voltage current/voltage is applied, the zero-sequence value should match the applied value. Zero sequence components cannot occur in delta connected systems, and there will not be zero-sequence measurements iur delta conneeted PTs. You can repeat n verified to be connected correctly, nts, es have be this test for the third phase, but once two pha the following 3-phase tests can be used for all other measu 610 Chapter 19: Testing the Relay Apply 3-phase, nominal current and voltage to the relay, record the metering results on your test sheet, and compare them to the CT and PT ratios. Ifthe relay also displays phase angles, record these values and ensure that they are in the correct phase relationship. You might think. that correct phase-angle relationships can be used in place of the single-phase tests above, but the relay nses its own reference for phase angles which ¢-n mislead you. For example, if all three phases were rolled to the next position (A@ to BO, BO 10 CO, C6 to AG) your test-set and the relay would both incicete the correct phase engies for each phase AGC", BO=120°, CO=120" but AG current/voltage from the testset would be injected into BO of the relay. | your test-set and the relay could use different references when displaying phase angles that can be confusing as shown in Figure 19:2. For example, the phase relationships displayed by the GE/Multlin SR-750 in our example would be 0°, 120°, 240° LAG and an SEL relay with the same settings and connection would display 0”, -120°, 120°. Ifthe relay monitors positive sequence components, record the current and voltage values on your test sheet. The positive quence value should match the applied current and voltage and the negative sequence and zero-sequence voltages should be almost zero. eo A? = \* PS « / Figure 19-2: Phase Angle Relationships Watt and VAR measurements can also help determine if the correct connections have been made, When three phase, balanced current and voltage is applied; maximum Watts and almost zero VARS should be measured. Rotate all three currents by 90° and maximum VARs and almost zero Watts should be measured. Any connection problems will skew the Watt and VAR values, and should he corrected If the relay monitors negative sequence, reverse any (wo phases and record the negative sequence values. The negat: ¢ sequence value should be equal to the applied value, and the i nd zero-sequence values should be nearly zero, Some relays display 3x the negative sequence values. In this case, the negative sequence value will be three times the applied value. on Principles and Practice Ifthe relay has a neutral input for voltage and/or current. apply a nominal value and compare metering values to the CT/PT ratios, Acompleted test sheet can look like the following: METERING ‘CURRENT (AMPST can Ta me ae Fase ana [ne Tatas] vets L SecnOneT a ET Zoos me Sr c VOLTAGE WOUTS? ase ota" Taek —| sane SPHASE METERING FREGUENCY aT POWERFACTOR zener [ime [wees ee} eee et ae POWERTMWT ‘VARS (AVANT ERT eine | eR SER [SER Tes 003 | 035 [aw —] ox | “ooteny [9380] aw] of sur acertn ws for Sleeves Figure 19-3: Example Metering Test Sheet 4, Element Testing We've finally reached the part that most people call relay testing. Follow the test plan created in the previous chapter and test all of the clements that create any kind of output from the relay. Try to group similar functions together that will require the minimum number of connection and testset configuration changes, For example, some relays can have many overcurrent ‘clements enabled. Instead of performing pickup testing and timing testing for each overcurrent clement in order, try performing all of the pickup tests first, then perform the timing tests for all clements. You can also speed up your testing and minimize connection changes by testing all elements for one phase and moving on to the next phase. Instead of following a dogmatic approach to testing, think about the reason for the tests. For example, we perform a time overcurrent test to ensure the settings are correct, we've entered the settings correctly, and the relay will operate correctly on cach phase. Following the testing er Chapter 19: Testing the Relay procedure from clectromechanical relays, you would test for pickup on all three phases, then time each phase at 2x, 4x, and 6x the pickup value. This isa perfectly acceptable test procedure but most modern relays use the same timer for all three phases. Testing pickup on all three phases ard performing the 2x timing test on AQ, 4x timing test on BO, and 6x tinving tost on and remove 6 tests from yur test plan. Standard timing test CO will prove all of our crite values were used in the past because results were based on graphs, a more accurate to determine the expected result from the graph using witoie numbers. You can choose any two or three multiples between the pickup value and the 50-

You might also like