Professional Documents
Culture Documents
DETAIL
FEASIBILITY REPORT
(INITIAL PRELIMINARY
REPORT)
Submitted by:
In JV with
January 2022
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Index
1 PROJECT CONTEXT .............................................................................................................. 6
1.1. INTRODUCTION TO THE CONSULTING SERVICES ...................................................................... 6
1.1.1. Objective of the Project .................................................................................................. 6
1.1.2. Scope of Service .............................................................................................................. 7
1.2. CONTENTS OF THE PRESENT REPORT ....................................................................................... 9
1.3. ANTICIPATION OF THE ASSIGNMENT PROVIDED BY THE CONSULTANT .................................... 9
1.3.1. Arrangements to be realized in the Tubman Road construction .................................... 9
1.3.2. Pre-qualification tender criteria for the construction bidders ..................................... 10
1.4. CONSULTED DOCUMENTS ...................................................................................................... 11
1.5. GENERAL SYNTHETIC DESCRIPTION OF THE MONROVIA WATER SUPPLY DISTRIBUTION SYSTEM
INCLUDING MAIN PIPELINES, EXISTING AND IN CONSTRUCTION RESERVOIRS ................................ 13
Raw water Transmission Pipe from the Mount Coffee Dam to the White Plains Water
Treatment Plant and River Intake .......................................................................................... 14
The Transmission Line............................................................................................................ 15
1.6. COMMUNITIES OUTLETS ALONG PIPE ..................................................................................... 17
1.7. HYDRAULIC FINDINGS OF THE ASSESSMENT PHASE ............................................................... 18
1.7.1. New conduction pipe from the dam to the WTP ........................................................... 18
1.7.2. White Plains Water Treatment Plant - Location .......................................................... 19
The White Plains Water Treatment Plant ............................................................................... 20
1.7.3. Pumping system ............................................................................................................ 22
1.7.4. Route of the 36-inch pipeline ........................................................................................ 22
2 DESCRIPTION OF POSSIBLE FUNCTIONAL SOLUTIONS ......................................... 27
2.1. POSSIBLE FUNCTIONAL SOLUTIONS CARACHTERISTICS.......................................................... 27
2.1.1. Introduction .................................................................................................................. 27
2.1.2. Solution B ..................................................................................................................... 27
2.1.3. Solution MSRF Type A ................................................................................................. 27
2.1.4. Solution MSRF Type B ................................................................................................. 29
2.2. GENERAL DESIGN ANALYSES ................................................................................................. 31
2.2.1. Consumptions and population projection..................................................................... 31
2.2.2. Criteria for water demand projection .......................................................................... 32
2.2.3. Water demand projection ............................................................................................. 32
2.2.3. Existing water infrastructure ........................................................................................ 33
2.3. GENERALITIES ON THE PROPOSED INTERVENTIONS ............................................................... 35
2.4. SOLUTION B: SIMPLE REPLACING OF THE 36” EXISTING PIPE ................................................. 35
2.5. SOLUTION MSRF-TYPE A: REPLACING OF THE 36” EXISTING PIPE + REALIZATION OF A 3.2
MG RESERVOIR IN TOWN AT MORISON FARM + DOUPLE PIPE TO PAYNESVILLE RESERVOIR ........ 39
2.6. SOLUTION MSRF-TYPE B: REPLACING OF THE 36” EXISTING PIPE + REALIZATION OF A 3.2
MG RESERVOIR IN TOWN AT MORISON FARM + BOOSTER TO PAYNESVILLE RESERVOIR .............. 42
3 PROPOSED UPGRADING OF THE WATER SUPPLY CONDUCTION SYSTEM...... 44
3.1. MAIN PIPELINE ...................................................................................................................... 44
3.1.1. Chosen material ............................................................................................................ 44
3.1.2. Technical characteristics of Material........................................................................... 45
3.1.3. Diameter ....................................................................................................................... 46
3.2. NEW RESERVOIR FOR THE CONDUCTION SYSTEM ................................................................. 47
3.3. PHOTOVOLTAIC PANEL FIELD AT THE WTP .......................................................................... 49
LIST OF ACRONYMS
Acronym Definition
DMA District Metered Area
EPML Environmental Protection and Management Law of Liberia
ESIA Environmental and Social Impact Assessment
GRP Glass Reinforced Plastic
HPP Hydro Power Plant
IDA International Development Agency
LEC Liberia Electricity Corporation
LTC Liberia Telecommunication Authority
LUWSP Liberia Urban Water Supply Project
LWSC Liberia Water and Sewer Corporation
PPA Power Purchase Agreement
REC Renewable Energy Certificates
SPE Special Purpose Entity
WP WTP White Plains Water Treatment Plant
TECHNICAL REPORT
Submitted by:
In JV with
SGAPI Srl
Local Partener
BK-Enterprise
1 PROJECT CONTEXT
In order to achieve best services, SARI and SGAPI provide a team of appropriate experts, and appoints
Mr. Fabio Nigrelli as Project Manager and Mr.Eng. Luca Boccardi as Team Leader.
The Consultant will be responsible for all technical and administrative aspects of the Consulting Services
and is hereinafter referred to as "The Consultant".
The submission is in accordance with the "Information to Consultants" given in the invitation, as well as
with the Terms of Reference (ToR). For this evaluation, a work approach has been developed, based on
the requirements indicated in the ToR and the Consultant's initial findings based on a review of available
reports and information. The approach encompasses systematic planning, appropriate utilisation of
available resources and a firm standard but flexible project management with respect to ISO 9001 and
14001, that will allow the Consultant to complete the services with a high degree of technical competence
within the time stipulated.
1.1.1. Objective of the Project
This assignment is to design, prepare cost estimates and prepare tender documents for the:
The replacement is intended to mitigate the interruption of water supply to the Project area (Greater
Monrovia) due to the failure in the main 36-inch line conveying water from the White Plains Water
Treatment Plant.
(a) the consultant will initially review the existing system and determine what mitigations will be
needed for the continuous safe and uninterrupted operation of the 36-inch line to ensure water
supply to Monrovia.
The consultant will also determine which communities are dependent on the main pipeline along
the transmission trajectory.
(b) the consultant will carry out a detailed analysis (hydraulic model) and assessment of the existing
system including the 1 MG Paynesville ground tank (currently under construction); while
considering the projected population growth and water demand over the next years.
The consulting will also review the Water Treatment Plant’s (WTP) current water production and
pumping schedule.
Following the assessment, the consultant will propose options for pipe sizing, pipe materials, pipeline
length and the corresponding costs required to improve the water system’s reliability and conveyance
capacity (increased water volume and required pressure head) which will adequately provide for the water
supply needs of the city.
1) design the selected option for a new transmission line from White Plains to the predetermined
terminal point.
2) propose adjustments to the 36-inch pipe-line that may be needed (repairs, air valves, blow-offs,
pressure regulation, etc.) that will help improve its operation.
3) The Consulting will give consideration to the life cycle costs for the proposed new design and the
financial and technical capacity of LWSC to operate and maintain the proposed new pipeline.
4) Due recognition will be given to the social safeguard and environmental impact within the
context of World Bank Environmental and Social Frameworks.
OUTPUT
The design will include, but not be limited to:
The Design Consultant will consider the option of decommissioning the existing 36-inch main and the
transfer of existing branch lines (4-inch and above) to the proposed new transmission line.
Upon the request of the Client, the detail design of the pipeline stretch along the Tubman Road has been
carried out, according to the urgency to coordinate its works with the ones of the roadway upgrading. The
stretch is included between the following benchmarks:
The design foresees the construction of a box culvert that will host the new pipeline, or the new pipelines,
according to the selected solution, located in the inner side of the large bend of the roadway, i.e. on the
West side, that after the axis rotation turns to North side. The culvert has a U reinforced concrete shape
with an inner base of 3 mt width and 2.5 mt height. The thickness of the foundation and of the vertical
walls is 0.4 mt. The cover consists of prefabricate removable slabs of 0.3 mt thickness and 2 mt length,
that will easily allow the maintenance operations for the pipeline and the appurtenances. The access to the
culvert will be possible through square plan manholes of 0.7 mt open side, located every 24 mt, that is
every 11 slabs. The culvert has been located, where possible, under the walkway on the left – West or
North – side of the main roadway platform. The cross section will anyway entail also part of the service
roadway platform. Approaching the STA 21+700 (-2+340) of the roadway project, where the Electric
Substation of the LEC Company and the close School Building hinder the location of the culvert, the new
pipeline alignment turns to the outer side of the roadway bending, that is the East and South. The vertical
alignment takes into account the crossing of the drain axis, which requires its under passing. Connection
culverts have been foreseen corresponding to the existing outlets off the 36” pipeline, that are recorded as
following:
Outlet Locations Outlet Diameters (")
Somalia Drive (Freeway) 16
Coca Cola Factory 6
Police Academy Road 6
Duport Road 6
Weaver Avenue 6
JC. N Howard Road 4
AB Tolbert Road 4
GSA Road 12
GSA Road 16
ELWA Junction 12
SD. Copper Road 12
SKD Boulevard 12
In order to speed up the bidding procedure for the implementation of the works, the Client required the
Consultant to submit the pre-qualification tender criteria. The document has been delivered on the last
November 1th.
General Construction Experience: Experience under construction contracts in the role of prime contractor,
JV member, subcontractor, or management contractor for at least the last Eight (8) years, starting 4st
January - 2013.
Specific Construction & Contract Management Experience: A minimum number of 5 similar contracts
specified below that have been satisfactorily and substantially completed as a prime contractor, joint
venture member, management contractor or subcontractor;
2 contracts, each of minimum value 25 million; at minimum 70% certified completion.
To have built in the last eight years at least 70 km of water pressure pipeline of diameter not lower than
36” of different materials: GRP, ductile iron, prestressed reinforce concrete, included of all
hydromechanical appurtenance. Minimum capacity to supply, install, implement and test 25km of water
pipeline of different materials for at least one year of the above said period of eight years.
For the Lot 2 the following main requirements will be requested:
General Construction Experience: Experience under construction contracts in the role of prime contractor,
JV member, subcontractor, or management contractor for at least the last Eight (8) years. Specific
Construction & Contract Management Experience: a minimum number of 5 similar contracts specified
below that have been satisfactorily and substantially completed as a prime contractor, joint venture
member, management contractor or subcontractor between 4th January 2013 and Application submission
deadline:
2 contracts, each of minimum value 15 million; at minimum 70% certified completion in urban areas
along the roadways under heavy traffic conditions in crowded and market zones with high environmental
impact.
To have built in the last eight years at least 50 km of water pressure pipeline of diameter not lower than
36” of different materials: GRP, ductile iron, prestressed reinforce concrete, included of all
hydromechanical appurtenance
Minimum capacity to supply, install, implement and test 15km of water pipeline of different materials for
at least one year of the period of eight years.
According to the available funds, the detailed design and the tender documents of the selected solution for
the whole system will be based on a new more detailed model and the overall Project will be divided in
the following lots:
a. The construction of the first 15-16 km of the Main Pipe for an approximate construction cost of 17
M USD, split into 2 lots.
b. The construction of the rest of the main pipe up to the end point at km 25,5.
c. The construction of the deviation to the foreseen Reservoir and of the Reservoir itself.
d. Connection pipeline to Paynesville Reservoir;
e. The construction of the Solar Panel field – PV, Photovoltaic park - at the WTP.
Immediately after the start of the design activities, which took place on 02 August 2021, the Consultant
requested the following data from LWSC:
DATA COLLECTION
Request of information, records and existing studies and reports for review and examination.
A) General
1. Topographical maps, aerial photographs (25.000, 10.000, 5.000, 2.000);
2. Technical cartography of the urban center and the route of the main pipeline;
3. Geological maps of sites crossed by the network;
4. Hydrological / Hydrogeological maps;
5. Land use maps;
6. Hydrological study of the Mount Coffee Dam;
7. Yearly destination of the use of the volume stored in the dam;
D) Others
30. Location of electricity supply lines which could be used for supplying the water treatment works
and the pumping stations;
31. National design manuals and standards;
32. Water supply National standards: water need per inhabitant, water quality’s standards;
On August 13, 2021, LWSC sent the following documents to the Consultant
On August 13, 2021, LWSC sent the following documents to the Consultant
OTHER REPORTS AND DOCS RELATED TO THE AREA OF PEYNESVILLE WHOSE FULL
LIST IS INTO THE ANNEX 0
1.5. General synthetic description of the Monrovia water supply distribution system including main
pipelines, existing and in construction reservoirs
Figure below shows current status of the existing water supply facilities. Monrovia water supply facilities
were severely damaged during the civil war. The details of present condition of water supply system will
be illustrated in the following sections.
Figure 1 – Present Condition of Water supply system in Monrovia before the rehabilitation of 2018-
19 (Source LWSC)
Raw water Transmission Pipe from the Mount Coffee Dam to the White Plains Water Treatment
Plant and River Intake
The nominal potential of the White Plains Water Treatment Plant at the present state is 16 MGD, but
actually only 4 MGD is provided.
The water from Mount Coffee HPP tail water after the first 8 months of service showed lack of discharge
of 2 days, due to the low water level in the dam reservoir. The intake can count only on 3 operational
pumps fed by power supplied by Liberian Electric Company – LEC – for 1 MW and 3 diesel generator
that are sharply synchronized.
The supply of power from Mount Coffee HPP can be reduced during the dry season – October-March, as
it serves as power supplier for the whole Country.
- 4 Settlement Basins, 2 of which shall be cleaned up manually instead via automatic tools –
each Settlement Basin has a potential of 4 MGD.
- 8 Filters, 2 downstream each Settlement Basin. Only 5 of 8 can be used due to severe
problems to the other 3. Each Filter has a potential of 2 MGD.
The Transmission Line consists of a pipe of 36” diameter, composed by a double concrete ring with an
intermediate steel pipe. The alignment from the WTP runs along the Pipeline Road, that has a sharp
profile following the natural depressions created by the creeks, that are the left tributaries of the St Paul
River, from the east side to the west. Some of these depressions can be identified as swamp areas.
The state of the road is scanty, with many bumps and hollows created by streaming water. The service
level of the road dramatically decreased proceeding towards the WTP northward. A detour at 2.4 km from
the Plant allows to overpass a very unstable road leg and the platform of the old railway connecting the
Port of Monrovia with the Bong County.
embankment slope 1/2 - 26°. This approach has allowed the location of the new pipeline on the west side
of the roadway in the stretch North-South oriented outer of the shade of the embankment, in order to ease
the access to the culverts that will be located on the creeks crossing and to the manholes requested for the
outlets, the air offs and blow offs.
A meter counter will be foreseen at each outlet along the main pipeline.
From the hydraulic point of view, the service conditions of the pipeline are not the proper one of a
transmission line. In fact, the continuity with the town distribution network make it very sensitive to the
variation of the amount of the water demand, that also changes the need of the pumping in terms of head
and water flow. This results in a very negative instability of the system operation, that has been confirmed
by the technical staff of the WTP and of the Pumping Station. In fact, according to their released
interviews, the first 2-3 hours of pumping service after the night pause are normally requested to fill back
the pipeline. This means that during the switch off period the night users and the leakage cause the partial
emptying of the pipeline. Considering the present service capacity of the water transmission that supplies
4MGD during the daytime of 18 hours, corresponding to an average water flow of 0.22 MG/h, the 3 hours
filling back of the pipeline results in a recovered volume of 0.66 MG. In terms of length of pipeline,
whose cross section is of 0.64 sqmt, the equivalent empty span would be around:
0.66*1000*4/0.64=4.13 km
This value corresponds to a lower bound of the possible lost volume, as during the first pumping hours
the water flow would be higher than at regime conditions due to the lack or reduced downstream
counterpressure. In terms of hydrogram, instead of the theoric constant water flow during the 18 service
hours – figure 6 -, there will be variable decreasing water flow according to the simulation of figure 7.
1.4
THEORIC HYDROGRAM PLOT
1.2
1
Q (MG/h)
0.8
0.6
0.4
0.2
0
0 4 8 12 16 20 24
t (hour)
Figure 6 theoric hydrogram plot
1.8
1.6
ACTUAL HYDROGRAM PLOT
1.4
1.2
FILLING BACK THE PIPE
Q (MG/h)
0.8
0.6
0.4
0.2
SLOW EMPTYING OF THE PIPE
0
0 5 10 15 20 25 30
t (hour)
There shall be several branches along the route of the pipeline to supply communities. This branch offs
shall serve the following communities and several others.
Mount Barkley
University of Liberia (Fendell)
Dry Rice Market
Wein Town
Coca Cola Factory toward Kakata Highway
Police Academy
Duport Road Community
ELWA Junction to ELWA Hospital
Town Hall
And several other communities
The connection pipeline between the Mount Coffee Dam, located about 5 km upstream the White Plains
Water Treatment Plant along the St Paul River ended on December 2020, and allows to provide the
requested gravity discharge to the plant.
The flow comes from the tail water of the Hydroelectric Power Plant that produce, after the recent
revamping, 88 MW with new 4 vertical shaft Francis turbines. The new pipeline has a diameter of 48"
and runs 5-km to the Treatment Plant. This connection will allow the LWSC not to use the St. Paul River,
that requires the uplifting of the water and risks to provide poor water quality and salty water during the
dry season when river level is low, due to the upstream currents for the Atlantic Ocean. Instead of
retrieving water from downstream and closer to the ocean, the new pipeline will draw water from the
reservoir upstream.
The source of water supply to the system is the St. Paul river. The raw water flows by gravity into an
underground water tank and is lifted through a 36-inch pipeline with four low lift pumps. The raw water
goes through the treatment process and is stored in a 2.5million gallon underground water storage tank
(clear well). Two (2) 4MGD and three (3) 8MGD high lift pumps, pump the treated water to the city of
Monrovia and its environs.
The treated water is pumped through two main pipelines 36-inch diameter and 16-inch diameter pipes.
The 36-inch pipeline is made of reinforced concrete with a stainless steel sandwich between the outer
reinforced concrete and the inner concrete lining. The 16-inch pipe is made of cast iron. The water is
pumped through each pipeline independently. The highest consumer along the 36-inch pipeline is the
Coca Cola factory. The highest consumer along the 16-inch pipeline is the Club Bear Factory. The 16-
inches pipeline is not part of this assignment and no assessment was conducted on it.
According to the LWSC staff, the system was originally designed to deliver 16MGD per day. Due to the
age of the pipeline and the continuous breakdown of the high lift pumps, and above all due to the fact that
the main pipe is not disconnected by the distribution network, the plant is unable to deliver such a volume
of water. The plant is currently delivering only 4MGD per day.
The White Plains Water Treatment Plant was built on 1966 as well as the 36” pipeline, and was expanded
in 1969 to 8MGD (commissioned date) and upgrade in 1983 to 16MGD (commissioned date). It is fed by
the new pipeline 48” from the tail water of the 80 MW HPP of Mount Coffee Dam 5 km upstream,
completed on December 2020, or in alternative by an intake directly from the St Paul River.
The discharge from the HPP is for gravity, the water from the intake is stored into an underground water
tank of 0.5 MG – 2 cum, with 4 low lift pumps.
Downstream the WTP the clean water is stored into 2 reservoirs – one built in 1966 of 1 MG and one in
1979 of 1.5 MG – for a total capacity of 2.5 MG=10 Kcum.
The pumping system consist of 5 high lift pumps. 2 pumps that can provide a total 4 MGD=16 Kcum/d
and 3 more 8 MGD=32 Kcum/d.
The water flow is split into a 16” pipeline towards west along the riverside road to Monrovia, at service of
Club Bear Factory, and into the 36” pipeline whose replacement is the scope of the work.
The 36” pipeline serves also as distribution infrastructure, as it delivers water to several reservoirs and
booster, such as the Sinkor Fish Market reservoir (1 MGD) and water pump, the Newport Street booster
Station, the Duco Reservoir, of 6 MG=24 Kcum and the Mamba Point Reservoir.
The new planned reservoir of Paynesville of 1 MG=4kcum will also receive the water from the 36”
pipeline. Along the pipeline road many intakes are serving villages and communities, they are recorded
by LWSC, the flow amount is not metered although. The University of Liberia Fendell Campus located
on the east side of Pipeline Road counts 40 000 people, that use ground water from wells.
There are five (5) pumps installed. Two (2) 4MGD pumps and three (3) 8MGD pumps.
The pumping system has unveiled heavy service problems due to several causes among which the
following look like the most relevant:
- Conditions of service;
- Supply of energy;
- Maintenance of the equipment.
The conditions of service are not the typical ones for a pumping group of this amount of power. In fact,
the alternate switching on and off of the pumps generate transitions phenomena into the electric and
electromagnetic components of the system that reduce the efficiency and the durability of the
hydromechanics. The new standard of function which the Project is aiming at is based on continuous
service conditions corresponding to the design regime. Furthermore, the alternate stop and go of the
pumps generate continuous water hammer effects in the pipeline. The latter have been surely exalted by
the material of the transmission line, made in concrete. Its high stiffness, and the negligible inelastic
deformation of the pipeline dramatically increase the overstress in the pipeline, with possible local failure
or displacement.
Figure 12 – Rout of the 36-inch pipeline. The Blue Figure 13 – Electricity pylon at the red light
line indicate pipeline rout market
The pipeline runs through a large community called the pipeline community through the busy market area
called the Red-light market. Road construction and a possible interchange are to be constructed at the red
light market area. This interchange connects the SKD Blvd and the Somalia drive. This proposed pipeline
is supposed to follow the same route.
According to observation, the road crossing of the proposed pipeline will be very challenging taking into
consideration the new road width. Figure 13 shows an existing electricity pylon at the red-light market
area which according to LWSC representatives is already in the way of the proposed pipeline route.
According to LWSC representatives, they will convey a meeting with the contractor to resolve any
possible challenges that could hinder the possible route of the new pipeline. From the red-light market
area, the 36-inch pipeline crosses another two busy intersections: the ELWA junction and the Boulevard
junction respectively. The 36-inch pipeline ends opposite Liberia’s Former President (Charles G. Taylor)
residence in Congo town. This is the point where the 36-Inch is reduced to 24-Inch. A line gate valve is
installed at this location and it is secured in a valve chamber.
The pipeline is generally located on the east side of the road. Some intakes may be identified, which
increased from the original number recorded at the time of the construction, 1966. The latter can be listed
in terms of stations locations and diameter of the outlet according to the original design drawings as
follows:
An inspection of LWSC on the pipeline unveiled leakage and some failures of air valves and blow-offs.
Along the leg on Tubman Road, the following outlets were listed by LWSC:
An underground water tank booster pumping station is situated at the fish market Sinkor beyond the end
of the 36-inch pipeline. This booster station supply comes from the 36-inches pipeline. This booster
station is intended to boost water from the fish market to another booster station at Newport street of 1-
milliongallon capacity. The booster station at Newport street would boost the water to the Duco reservoir
of 0.6-million-gallon capacity. At Duco, the water would flow by gravity through a distribution system to
consumers.
1.7.4.2. Summary Report on important topics along the rout of the 36-inch pipeline
Vent well
There are several air relief valves and manholes along the pipeline. There are also wash out valves
without chambers and drain channels. LWSC representative recommended that a lighter weight air relief
valve should be specified during the design stage. This is as a result of the frequent leakages they
experience as a result of the overburden weight of the valve on the 1.5-
inch nipple supporting it.
An electromagnetic water meter is installed to measure the volume of water intake and the volume of
water pumped out of the plant.
Note: The existing 36-inch pipeline is not a dedicated single transmission pipeline. The distribution
network is connected to it.
Hydraulic drawbacks of the scheme
The transmission line, as further discussed in the following, shows service conditions that are not the
proper ones of a conduction pipeline. In fact, the continuity with the town distribution network makes it
very sensitive to the variation of the amount of the water demand, that also changes the need of the
pumping in terms of head and water flow.
This results in a very negative instability of the system operation, that has been confirmed by the
technical staff of the WTP and of the Pumping Station. In order to make back a real transmission line, as
it was in the purpose of the original 1966 design, a disconnection from the distribution network of the
town is strongly requested. This can consist in the construction of a new reservoir whose task is to
compensate the oscillation of the demand along the day, allowing the constant water flow into the
pipeline and the functioning of the pumping station all day long. The closest the reservoir will be to the
users location, ie the town of Monrovia, the longest will be the stretch of the pipeline that will serve as
transmission line. Thanks to the disconnection both the service level of the WTP and of the Pumping
Station will be dramatically benefited, in terms of energy consumption and cost of maintenance.
Besides, due to the huge leakage of the distribution network, the pumping system is now forced to work
only during the consumption hours in order not to waste the water: this implies that the capacity of the
pumps is used only for about 18 hours / day and the total volume of water pumped is less than 70% of the
system potential capacity. To this it has to be added that according to the information get with the
WTP’s technical responsible each day the first 3 hours of pumping are necessary only to recharge the
main pipeline.
2.1.1. Introduction
In the following paragraphs the three analyzed solutions are described from the point of view of the
functioning. Each one of the solution has been analyzed with the hydraulic model in 3 scenarios related to
the temporal horizon of the water demand:
- immediate 16 MGD,
- short term 24 MGD,
- real current water demand of Monrovia 32 MGD.
Which means that the total number of the hydraulic model simulation have been 9.
Besides for each solution it is proposed the support of the photovoltaic panel field at the service of the
pumping station located at the WTP.
2.1.2. Solution B
Simple replacing of the 1966’s pipe, in the three temporal horizon’s scenarios, according to the
assignment scope of work.
From the WTP there will be three deviations in the highlighted area:
1. WTP towards Morison Reservoir
2. WTP towards Paynesville Reservoir
3. Morison Reservoir towards outlets and end point
PIPE:
1. WTP towards Morison Reservoir
2. Morison Reservoir towards outlets, end point and Paynesville Reservoir
4000000
URBANIZATION PATTERNS
3500000
3000000
POPULATION
2500000
2000000
R² = 0.9993
1500000
1000000
500000
0
1970 1990 2010 2030 2050
YEAR
Figure 25 Urbanization patterns
The population in Monrovia was estimated in 2030-2050 according to a third degree polynomial equation with R2=0.9993.
Unit consumption
private connection 16 Gallon/pers/d = 60.5 L/pers/d
Water kiosks 6 Gallon/pers/d = 22.7 L/pers/d
Institutions & commercial connection 96 Gallon/connection/d = 363 L/connection/d
(based on average measured consumption 8hr/day)
Large consumers 5 liters/ha/d
water supply coverage in DOMESTIC WATER CONSUMPTION IN 2020(m3/d) water industrial industrial water mean daily leakage mean daily
2020(%) consumption land area consumption(m3/d) water in pipe water
No. Region Present population households of user of households of user of centralized total of public (ha) demand network demand
non- centralized non-centralized water supply buildings (m3/d) (m3/d) effective
centralized water supply water supply (m3/d) (m3/d)
water supply
1 NEW KRU TOWN 79463 10 90 480.75 4326.76 4807.51 608 36 1555 6970.51 1045.58 8016.09
2 LOGAN TOWN 69528 20 80 841.29 3365.16 4206.44 647 53 2290 7143.44 1071.52 8214.96
3 CLARA TOWN 61323 20 80 742.01 2968.03 3710.04 570 2 86 4366.04 654.91 5020.95
4 WEST POINT 29409 20 80 355.85 1423.40 1779.24 274 2053.24 307.99 2361.23
5 CENTRAL MONROVIA A 70414 40 60 1704.02 2556.03 4260.05 887 5147.05 772.06 5919.10
6 CENTRAL MONROVIA B 52724 30 70 956.94 2232.86 3189.80 577 3766.80 565.02 4331.82
7 SINKOR 51601 30 70 936.56 2185.30 3121.86 565 3686.86 553.03 4239.89
8 LAKPAZEE 48044 30 70 872.00 2034.66 2906.66 526 3432.66 514.90 3947.56
9 OLD ROAD 55419 30 70 1005.85 2346.99 3352.85 607 3959.85 593.98 4553.83
10 CONGO TOWN 33539 20 80 405.82 1623.29 2029.11 312 2341.11 351.17 2692.28
11 PAYNESVILLE 684419 20 80 8281.47 33125.88 41407.35 6365 44 1901 49673.35 7451.00 57124.35
12 GARDENESVILLE 102155 20 80 1236.08 4944.30 6180.38 950 92 3974 11104.38 1665.66 12770.03
13 NEW GEORGIA 65105 20 80 787.77 3151.08 3938.85 605 4543.85 681.58 5225.43
14 BARNESVILLE 46022 20 80 556.87 2227.46 2784.33 428 3212.33 481.85 3694.18
15 JOHNSONVILLE 29345 20 80 355.07 1420.30 1775.37 273 2048.37 307.26 2355.63
16 CALDWELL 42794 20 80 517.81 2071.23 2589.04 398 51 2203 5190.04 778.51 5968.54
TOTAL 1521304 20036.15 72002.74 92038.89 14592 278 12009 118639.89 17795.98 136435.88
Future water demand in Monrovia was estimated to be 49.8 MGD (188.648.81 m3/d) in 2030.
Currently water demand is 36 MGD (136.435.88 m3/d).
General consideration on how to face the main inconvenient and description of the proposed options.
It shall be considered that in order to work correctly the distribution of a water supply system of 24MGD
in a town needs a compensation volume. This compensation volume has to be located upstream the taps
of the consumers and allows to design all the hydraulic works like the WTP, the pumping station and the
conduction pipe for the 24 hours water flow - in this case 1MGH. The hydraulic works downstream the
compensation - distribution system - need to be designed for the peak hour water flow, which amounts
about the double, i.e. 2MGH.
The water compensation volume in Monrovia including the LWSC reservoirs volume in town and, also
considering the new Paynesville reservoir now under construction - November 2021 -, is about 3.2 MG.
The private tanks contribution to further compensation volume, which are unknown, can be realistically
evaluated in not more than 0.5 MG.
Besides that, there is a tank of 10.000 m3 corresponding to 2,65 MG that is located between the WTP and
the clean water pumping station, which can allow to the WTP to work along 24 hours reducing the design
water flow for the WTP. Anyway, it is completely ineffective for the pumping station and the conduction
pipe.
The depicted configuration leads to the evidence that in Monrovia there is a lack of compensation volume
and that a proper location of a Reservoir will allow t, the design water flow of the WTP, of the pumping
station and of the conduction pipe can be reduced, also obtaining the disca meaningful reduction of the
peak water flow for the WTP and the disconnection of the Water Supply Conduction System From the
leakages of the Distribution System.
To achieve a sufficient degree of mitigation of the Water Transmission System, the two basic goals shall
be aimed at:
1. Making the system independent as much as possible on the water flow demand from the
town by disconnecting it from the distribution network operating in the urban area;
2. Making the White Plains Water Treatment Plant less dependent on the power supplied by
the Liberian Electric Company – ELC -, which is not adequate to the needs, promoting
independent source of power, possibly based on renewable energy systems.
1.2
1
Q (MG/h) 0.8
0.6
0.4
0.2
0
0 4 8 12 16 20 24
t(hours)
Figure 27
1.2
1
Q ( MG/h)
0.4
0.2
0
0 4 8 12 16 20 24
t(hours)
Figure 28
The pipeline project is carried out with reference to a criterion of maximum economy. The goal is to
determine a diameter that entails the lowest cost of the system, guaranteeing hydraulic efficiency. The
diameter of the pipeline has been dimensioned in such a way as to assure an adequate water velocity and
an appropriate pressure at the final node. A smaller diameter corresponds to a lower cost of the system
but, since the pressure drops increase, there is a lower residual pressure at the final node.
1.2
1
Q(MG/H)
0.8
0.6 16MGD
0.4 24MGD
32MGD
0.2
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
t(hours)
Figure 29
The diameter of transmission line was defined, considering the current water demand scenario of
32MGD. Furthermore, the diameter was verified for the flow according to the present requested
performance to the WTP at 16MGD, and the future service level after upgrade at 24MGD.
In terms of water flow per hour, scenario 32MGD and 24MGD are the same. The difference
between the two scenarios is for the shutdown of the pumps overnight for the 24MGD demand.
Therefore, there are no differences in terms of diameter dimensioning.
For scenarios of 16MGD and 24MGD demands, the pumping station operates for 18/24h, in the
period of lower demand the pumps will be off. In the scenario of 32 MGD the operations will be
pn 24/24h.
In the 32MGD scenario, having the pumps running 24/24h there will be significant energy
consumption, significant variations in water demand and water losses. To pump 32MGD in
18/24h it would be necessary to size the pumping system WTP, currently it is not able to pump
this flow rate, this 32MGD scenario described only for the real Monrovia water survey but not
applicable in solution B.
- Hm = 80 m head pump: considering a typical characteristic curve of the pump, the operating
head is on average 20% of the maximum head - 20% of 97.5Hmax
- L = 25.2 km (pipeline length).
- Elevation WTP = 9 m.
- Elevation end point = 26 m.
For the choice of the pipeline material, we chose to use GRP pipe.
With reference to these parameters, the table below shows, for each commercial diameter analyzed, the
value of the external diameter De, the thickness s, the internal diameter Di, the area of the water section
A, the velocity V = Q / A, head loss rate J (evaluated with the Hazen-Williams relation), the head losses
ΔH = JL, the head in the final node and the pressure on the final node.
.
10.675 ∗ 𝑄
𝐽=
𝐶 . ∗𝐷 .
DN(inch) DN(mm) De(mm) s(mm) Di(mm) J ΔH H end Elevation Y(m) A(m2) V(m/s)
(m) (m) end (m)
36 900 922 20.28 881.44 0.003443 86.77 0.23 26 - 0.610 2.298
25.77
40 1000 1024 20.28 983.44 0.00202 50.90 36.10 26 10.10 0.760 1.846
44 1100 1126 20.28 1085.44 0.001249 31.48 55.52 26 29.52 0.925 1.515
48 1200 1228 20.28 1187.44 0.000807 20.33 66.67 26 40.67 1.107 1.266
The selected diameter is DN 1200, which gives a velocity V = 1,266 m / s and a pressure on the end node
of 40.67 m H20, this pressure allows the delivery of the flow rate defined by the TOR.
Let's check this diameter in the current scenario (16 MGD):
DN(inch) DN(mm) De(mm) s(mm) Di(mm) J ΔH H end Elevation Y(m) A(m2) V(m/s)
(m) (m) end (m)
48 1200 1228 20.28 1187.44 0.00022 5.6303 81.37 26 55.37 1.107 0.633
Figure 30 Solution B
CRITICAL ISSUES
SOLUTION B with only the redesign of the pipeline assures an average flow rate of 24MGD and does
not consider the uncertainty of the water demand. Namely, during the daily peak, it is not possible to
satisfy the water demand from users.
The two MSRF SOLUTIONs, which we are going to be analyzed, decouple the external adduction from
the distribution system with the construction of a tank. In such the flow rate requested by users with
adequate pressures is assured on daytime. Anyway, even with the construction of the tank, not all the
critical issues in the distribution system are fully soved out.
2.5. Solution MSRF-Type A: replacing of the 36” existing pipe + realization of a 3.2 MG reservoir
in town at Morison farm + Double pipe to Paynesville reservoir
A solution of the current system can be obtained by designed compensation reservoirs that can be located
along the alignment of the pipeline at a proper elevation, in order to avoid any solution of overhead
structure. The latter could involve architectural and environmental complications behind higher
construction costs. The reservoir will allow the Consultant to consider the first stretch of pipeline as a
pure transmission line, not influenced by the variation of the water flow demand, which will be absorbed
by the capacity of the reservoir itself. Downstream, the pipeline will be design according to the results of
proper hydraulic models, that will provide the optimization of the working regime of the network.
A favorable location for the reservoir can be the site of Morison Farm Village, at 16 km south of the
WTP, at 1 km east of the Pipeline Road, at around 50 m elevation above the sea level – SOLUTION
MSRF Mount South Reservoir. With its capacity It will compensate the water demand form the City, and
will assure the constant water flow for the WTP and the connecting pipeline. The outlet toward the 16"
pipeline of the Freeway can be easily planned. The water distribution to Monrovia City will be performed
by gravity. The water flow amount for the first stretch pipeline will be distributed along the 24 hours.
The second 16” pipe will allow to feed the Paynesville reservoir that cannot be filled by gravity from the
Morison reservoir, directly from the WTP’s pumping station. It has to be remarked that the problem of a
lack of pressure will presumably remain for the 24” pipe at the end of the new main pipe line.
The suggested intervention for the other outlets on the other hand are in general to increase the diameters
of the distribution which are so small that the required pressures and velocities to apply with the water
demands are out of the design range of a distribution network. The suggested intervention are reported in
paragraph 4.3 section Rehabilitation as a result of the hydraulic model.
0.8
0.6
16MGD
0.4
24MGD
0.2 32MGD
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
t(hours)
Figure 31
The diameter of transmission line was defined, considering the current water demand scenario of
32MGD. Furthermore, the diameter was verified for the flow according to the present requested
performance to the WTP at the production of 16MGD and the future service level after upgrade at
24MGD.
For scenario 16MGD-24MGD and 32MGD the pumping station operates for 24/24h.
2.6. Solution MSRF-Type B: replacing of the 36” existing pipe + realization of a 3.2 MG reservoir
in town at Morison farm + booster to Paynesville reservoir
As we will see better in the hydraulic model, the MSRF - type B solution does not include the double
pipeline along Tubman Road but the insertion of a booster along GSA Road.
Also for this solution it has to be remarked that the problem of a lack of pressure will presumably remain
for the 24” pipe at the end of the new main pipe line.
The suggested intervention for the other outlets on the other hand are in general to increase the diameters
of the distribution which are so small that the required pressures and velocities to apply with the water
demands are out of the design range of a distribution network. The suggested intervention are reported in
paragraph 4.4 section rehabilitation as a result of the hydraulic model.
Adduction section
The dimensioning of the diameter of the adduction pipeline and the recommendations of the water
hammer are the same as for the MSRF - type A solution.
Distribution system
The tank has been dimensioned to assure the variability of the demand from the users.
The diameters of the pipeline will be dimensioned in the hydraulic model.
Foreword
The choice of the material for the main pipeline followed up a deep comparison between several options,
based not only the minimization of the initial cost, but also on the optimization of the overall economic
analysis for the life cycle of the infrastructure and on the sustainability of the manufacturing of the
product. The ESG – Environmental, Social And Government – standard required to the supplier will be
also taken into account for the proposed solution.
Comparison ‐ Below is the comparison between the unit price of the following materials:
Prices for cast iron and steel were obtained by averaging across various web sites (African and Asian
Market). The difference is in the internal/external lining and the price can vary by 20%.
The GRP material chosen has a lower unit cost than steel and cast iron.
Figure 35
Large diameter pipes are available in nominal diameters ranging from 300 to 4000 mm. Available
standard pressure classes are PN1, 3, 6, 10, 12 and 16 and stiffness classes of 2500, 5000 and 10000 N/m.
The pipe consists of a resin-rich reinforced liner, structural wall and a resin-rich exterior layer. "C" glass
is used at the internal and external pipe surfaces.
Pipe manufactured per this specification will have the following pressure capabilities regardless of pipe
stiffness.
Figure 36
GRP pipes shall have the following characteristics regardless of pressure class.
3.1.3. Diameter
Pipe outside diameter at spigot end; for all stiffness and pressure classes.
Figure 38
Figure 39
Although out of the scope of works, the consultant strongly suggests the construction of a new reservoir
to ensure the correct functioning of the entire water system as illustrated in the previous paragraphs.
The benefits that can be obtained with the reservoirs are many:
Increase the reliability of the water supply, as it provides a reserve in the event of faults in the
upstream hydraulic system;
Optimize the operation of lifting and water treatment systems, limiting the variability of their
flow rates over time;
Determine the pressures in the downstream hydraulic system, releasing them from those of the
upstream hydraulic system;
The tank is served by the pipeline that comes from the WTP and serves the distribution system.
The second goal of the Project can be achieved by designing a local photovoltaic power plant in order to
assure the proper amount of power in the period for which the risk of power shortage is higher.
The solar panels can be easily hoisted by the wide surfaces available on the various component of the
Water Treatment Plant, such as the covers of the Reservoirs, of the Settlement Basins, and of the free land
in the southern area of the compound. In case of upgrade of the Plant from 16 MGD to 24 MGD capacity
treatment, part of the latter area may be removed to allow the construction of the two new settlement
basins.
The lost surface can be easily replaced by covering the new tubs in a similar way as proposed for the
existing ones. Alternative location for the contribution of the southern part of the solar park can be the
area at north-east of the plant, where abandoned old structures stand by.
The available surfaces are as follows:
PV COMPONENT SURFACE - SQ MT
RESERVOIR COVER GROUND - 1966 RESERVOIR 1 008
RESERVOIR COVER GROUND - 1979 RESERVOIR 1 728
OFFICE BUILDING ROOF 720
ROOF 432
SETTLEMENT BASINS 2 592
FREE GROUND AREA (AT SOUTH OR AT NORTH-EAST THE PLANT) 5 112
TOTAL SURFACE 11 592
With the construction of the photovoltaic system, it is intended to achieve significant energy savings and
also to ensure the right amount of power in the period in which the risk of lack of energy is greater.
The potential of the production of the Solar Plant is integrating the one of the Hydro Power Plant of
Mount Coffee. In fact, while the latter’s peak is during the rainy season, the former may reach its best
performance during the dry season, according to the higher values of solar irradiation. The integration
between electric power supplied by LEC and power produced independently by the WTP will make its
working service level more efficient and fully based on renewable source.
Based on a specific contributing average area of 9 m2 per kW, the overall rated power of 1,600 kW will
be available. To cover the kW absorbed by the pump system, considering 3 pumps of 8 MGD in operation
for an average flow rate of 24 MGD, the produced power will match the energy requested by the pumping
system.
Expected pumps consumption after the rehabilitation of the our broken components, according to the
Reports of the Liberia Urban Water Supply Project (LUWSP) are as follows:
The degree of efficiency of photovoltaic systems largely depends on the angle of the sun irradiation on
the panels, which ideally should be 90°, as in the variable set up.
The adjustable photovoltaic panels follow the sun horizontally or vertically. The two-axis trackers, on the
other hand, can follow it both horizontally and vertically, achieving greater precision and therefore
maximum energy efficiency. With this type of trackers it is possible to increase the energy efficiency by
30% (single-axis systems) or even 45% (two-axis systems).
The structure where the panels will be positioned is of the orientable type, in order to increase the daily /
seasonal efficiency of the system and ensure the ordinary and extraordinary maintenance of the tanks
where they are positioned.
In the practical case of fixed systems, the degree of efficiency fluctuates, and consequently the daily and
annual energy yield, which will extend the amortization time of the overall system.
The implementation of the PV system can be set up as a DBO - Design, Building and Operating - contract
with a Private Partner, based on the reimbursement of a fee for the supplied energy, referring to the cost
estimation of a Preliminary Design which will be tendered and bid.
It would consist in a typical Power Purchase Agreement, which (PPA) is an arrangement in which a
third-party developer installs, owns, and operates an energy system on a customer’s property. The
customer then purchases the system's electric output for a predetermined period. A PPA allows the
customer to receive stable and often low-cost electricity with no upfront cost, while also enabling the
owner of the system to take advantage of tax credits and receive income from the sale of electricity.
To be eligible for a PPA, a project must be located in a state or jurisdiction where third-party ownership
of energy generation equipment is allowed.
Under a PPA, the customer signs a contract with a third-party developer to purchase power generated by
photovoltaic panels.
The customer is therefore also known as the offtaker, or the purchaser of power. While the
customer/offtaker often provides the physical space to host the system, this is not a requirement and the
host and customer/offtaker may be separate entities in leased spaces. The developer and its investors own
the equipment for the duration of the PPA. The developer typically provides initial project coordination
services such as bridge financing, design, and permitting with little-to-no cost to the customer. Equipment
installation may be completed in-house by the developer or by a contracted installer.
The electric output generated by the energy system is then purchased by the customer at a rate that is
generally lower than the utility’s retail rate, generating immediate cost savings. The PPA rate usually
increases by 1-5% each year for the contract term (i.e. a price escalator) to account for gradual decreases
in system operational efficiency, operating and maintenance costs, and increases in the retail rate of
electricity. PPAs are generally long-term agreements of 10-25 years. At the end of the contract term, the
customer may be able to extend the term, purchase the system from the developer, or have the equipment
removed from the property.
The utility serving the customer provides an interconnection from the energy system to the power grid,
and will continue service if the system does not produce enough power to meet the customer’s electrical
needs. When the system produces excess power, it can be sold to the utility, typically at the retail
electricity rate.
The developer will typically create a special purpose entity (SPE) for each project that serves as the legal
owner of the energy system. The SPE exists to raise debt and equity investment in the project, resulting in
mutual ownership of the SPE (and therefore the project) by the developer and investor(s). The SPE allows
for investment at the project level without subjecting investors to risks associated with the developer’s
other projects, while also minimizing risk for the developer should the project default or experience other
issues.
The system owner will generally retain all environmental benefits of putting clean energy onto the grid,
such as Renewable Energy Certificates (RECs). RECs are tradable, non-tangible energy commodities that
are issued when one megawatt-hour (MWh) of electricity is generated from a renewable energy source
Project Code: File name: Date: SARI Consulting Ltd 50 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
and delivered to the grid. These certificates are a way for businesses to verify carbon reductions from
specific projects and count towards organizational targets for renewable energy use. Mandatory REC
markets exist in states with renewable energy portfolio standards (RPS), but there are also voluntary REC
markets available for those who want to purchase them. REC arbitrage, which is the near-instantaneous
buying and selling of RECs in different markets, may be an option to decrease overall costs if the
customer is located in a market with high REC prices.
SOLUTION CODE MEANING DESCRIPTION REFERENCE DAILY WATER WTP REQUIREMENT HIGH LIFT PUMP SYSTEM
DEMAND REQUIREMENT
B Base solution To replace the existing 36" pipeline with a new pipeline of 25 km length of 16MGD To be upgraded with 3 more Settlement basins, 3 To be upgraded to a capacity
proper characteristics. The system will be subjected to the variation of the 24MGD Flocculators and 8 Filters=>24 MGD. of 24 MGD.
water demand from the City of Monrovia 32MGD* The future upgrade to a capacity of 32 MGD will be To be upgraded to a capacity
consistent with the pipeline capacity. of 32 MGD.
MSRF - type A Reservoir on To replace the existing 36" pipeline with a new pipeline, construction of a 16MGD To be upgraded with 3 more Settlement basins, 3 To be upgraded to a capacity
Mounty South site compensation reservoir on the hill 16 km south of the WTP, at 1 km east of 24MGD Flocculators and 8 Filters=>24 MGD. of 24 MGD.
Pipeline Road in the Morison Farm Village. The reservoir, of around 3.2MG 32MGD The future upgrade to a capacity of 32 MGD will be To be upgraded to a capacity
- 12.000 cum - capacity will compensate the water demand form the City, consistent with the pipeline capacity. of 32 MGD.
and ensure constant water flow for the WTP and pipeline to the Paynesville
and Morison Farm reservoirs. + Double pipe to Paynesville Reservoir
MSRF - type B Reservoir on To replace the existing 36" pipeline with a new pipeline, construction of a 16MGD To be upgraded with 3 more Settlement basins, 3 To be upgraded to a capacity
Mounty South site compensation reservoir on the hill 16 km south of the WTP, at 1 km east of 24MGD Flocculators and 8 Filters=>24 MGD. of 24 MGD.
Pipeline Road in the Morison Farm Village. The reservoir, of around 3.2MG 32MGD The future upgrade to a capacity of 32 MGD will be To be upgraded to a capacity
- 12.000 cum - capacity will compensate the water demand form the City, consistent with the pipeline capacity. of 32 MGD.
and ensure constant water flow for the WTP and pipeline to the Paynesville
and Morison Farm reservoirs. + booster to Paynesville Reservoir
All the depicted SOLUTIONS can be combined with the construction of the PV Power Plant at the White Plains Water treatment Plant, so that further configurations can be assumed:
SOLUTION
B-PV Base solution with the Photovoltaic Power Plant
MSRF - type A-PV Reservoir on Mounty South site – Morison Farm Village - with the Photovoltaic Power Plant
MSRF - type B-PV Reservoir on Mounty South site – Morison Farm Village - with the Photovoltaic Power Plant
- 4 Settlement Basins, 2 of which shall be cleaned up manually instead via automatic tools – each
Settlement Basin has a potential of 4 MGD
- 8 Filters, 2 downstream each Settlement Basin. Only 5 of 8 can be used due to severe problems to
the other 3. Each Filter has a potential of 2 MGD.
According to the requirements of the TOR, the design of the new pipeline will be based on a water flow
of 24 MGD. In order to assure the amount of clean water requested, the upgrade of the WTP shall foresee:
- 2 more Flocculator;
- 2 more Settlement Basins;
- 4 more Filters.
This in addition to all the works needed to recover the correct service level of the inadequate equipment.
The Reservoir will be located on the top of Rocky Hill in Paynesville and will be connected directly from
mainline at GSA road junction using a 16” pipe in HDPE. A valve will be installed on the inlet pipe near
the connection on the mainline.
The main outlet pipe will connect the Reservoir to Robertsfield Highway, to GSA Road and to Duport
Road.
A sectorization will allow a better control of the water distribution in the area. It consists in isolating the
District Meter Area valves and preventing water from leaving the system. It follows a logical of District
Metering Area (DMA).
With the three newly installed DMA meters, Robertsfield Highway, GSA Road and Duport Road, it is
possible to isolate the system from the rest of Monrovia distribution system.
In order to allow the inflow into the system and to prevent outflow leaving the system, it is proposed to
adapt the three existing DMA by installing an additional check valve, also in the two areas in the photo.
This will allow the water from the main line to enter into the system in order to maintain the existing
pressure, to feed the southern part of Paynesville, and will prevent the water from the Reservoir to leave
the system.
I will be also possible to open the valves when in case of flow shortage in the upper part of Paynesville.
Paynesville pattern
2.5
2
1.5
1
0.5
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
time (hours)
The inlet flow rate into the Paynesville Reservoirs is 7072 m3/d for scenarios 16-24-32MGD.
4.2. Solution B
The operation of the transmission line has been simulated, respectively considering the flow according to
the present requested performance to the WTP at the supply of 16 MGD, and the future service level after
the upgrade up to 24 MGD. In addition, the current water demand scenario of 32MGD was also
considered.
For scenario 16MGD and 24MGD the pumping station operates for 18/24h, in the period of lower
demand the pumps will be off. In scenario 32MGD the operation will be 24/24h.
The model has taken into account all the networks nodes and connections.
Outlets along the main pipeline were not considered because they are currently closed, as defined by
Hydroconseil.
TUBMAN ROAD
Outlet locations Outlet diameters (") L(m)
Somalia Drive (Freeway) 16 11867
Coca Cola Factory 6 3290
Police Academy Road 6 2591
Duport Road 6 7523
Weaver Avenue 6 370
Howard Road 4 889
A.B tolbert Road 4 1390
GSA Road 12 284
4 1366
16(RES) 2300
ELWA Road 12 1764
10 3003
8 695
SD. Copper Road 12 129
4 1164
SKD 12 5015
END POINT 24 /
WTP
16" WTP 16 /
It should be noted that while in the main Transmission Line the head values appear adequate for a correct
functioning of the system, in the section of Somalia Drive the head losses increase strongly due to the
reduction of the diameter and for the high flow rate required (area in progress development). This can
result in a water supply shortage in some communities such as Logan Town, New Georgia, Gardenesville,
Barnesville, and Johnsonville even in the present state of service.
The system has very low velocities, which do not affect the flow and pressure provided in the distribution,
only in the Somalia Drive outlet there are high velocities (2 m/s).
Below the balance between the inflow and the outflow reservoir Paynesville is reported.
V-t
4000
3500
3000
volume (m3)
2500
2000
1500
1000
500
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
hours
Figure 46 Reservoir Paynesville
Future upgrade of the WTP: 24MGD
The future upgrade of WTP will allow a water flow of 1404 l/s for the operation 18/24 hours.
SKD 51.07
END POINT(48"-24") 351.04
WTP 16" 116.59
TOTAL 1404.55
The results of the model simulation are summarized in the following plot showing water pressure in the
nodes.
It should be noted that while in the main transmission line the head values appear to be adequate for a
correct functioning of the system, in some outlets of the network the head losses increase strongly due to
the reduction of the diameter and to the increase of the required flow rate. This can result in a water
supply shortage in some communities such as Logan Town, New Georgia, Gardenesville, Barnesville and
Johnsonville, even some stretches of paynesville such as SKD and Coca Cola Factory.
Velocities are in some cases high due to the low-dimensioned diameters for this flow.
Below the balance between the inflow and the outflow reservoir Paynesville is reported.
V-t
4000
3500
3000
volume (m3)
2500
2000
1500
1000
500
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
hours
Figure 49 Reservoir Paynesville
The results of the model simulation are summarized in the following plot showing water pressure in the
nodes.
It should be noted that while in the main transmission line the head values appear to be adequate for a
correct functioning of the system, in some outlets of the network the head losses increase strongly due to
the reduction of the diameter and to the increase of the required flow rate. This can result in a water
supply shortage in some communities such as Logan Town, New Georgia, Gardenesville, Barnesville and
Johnsonville, even some stretches of paynesville such as SKD and Coca Cola Factory.
Project Code: File name: Date: SARI Consulting Ltd 63 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Below the balance between the inflow and the outflow reservoir Paynesville is reported.
V-t
4000.00
3500.00
3000.00
2500.00
volume (m3)
2000.00
1500.00
1000.00
500.00
0.00
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
hours
Figure 52 Reservoir Paynesville
current operating system involves some criticalities to the pumping system, such as water hammer and
therefore continues pump failures.
2. Outlet from main pipeline are under dimensioned for the actual water demand. These outlets
diameters are able to assure only the flow rate of 16 MGD, except in the section of Somalia Drive.
For the first criticality of the network, the MSRF solution was proposed. The reservoir will compensate
for the water needs of the City, and will ensure constant water flow for the WTP and the connecting
pipeline, which feeds the two Reservoirs, including Paynesville Reservoir. The distribution of water in
Monrovia City will be by gravity, ensuring the peak flow rate as well.
The demand on the pumping system will be reduced compared to the current conditions and to
SOLUTION B, thanks to the hydraulic head downstream.
As shown below, the MSRF solution assures the variably of water demand but cannot guarantee operation
in many sections of the network.
For the second criticality it is advisable to rehabilitate some sections of the network, in particular it is
advisable to increase at least the diameters of Coca Cola Factory and Somalia Drive pipelines cross
sections for the 16 MGD scenario. For a possible future water flow, it is advisable to rehabilitate the
network by replacing the sections with larger diameters or to double the pipeline.
Below rehabilitation of the diameters of the outlets, in the condition of 32 MGD is shown.
TUBMAN ROAD
Outlet locations Outlet diameters existing (") L stretch (m)
Somalia Drive (Freeway) 16 11867
Coca Cola Factory 6 3290
The simulation was successful with adequate loads and ensuring the water flow rate of 32 MGD by
increasing the diameters along Somalia Drive (40”) for 6880m and along Coca Cola Factory (16”) for
1140m.
TUBMAN ROAD
Outlet locations Outlet diameters rehabilitation (") L stretch (m)
40 6880
Somalia Drive (Freeway) Existing diameter 16 4987
16 1140
Coca Cola Factory Existing diameter 6 2150
From the WTP there will be three deviations in the highlighted area:
1. WTP towards Morison Reservoir
2. WTP towards Paynesville Reservoir
3. Morison Reservoir towards outlets and end point
For about 5km along Tubman Road two pipelines will be implemented, one directed towards Paynesville
Reservoir (GSA Road) and one carrying t the flow along the network - outflow Morison Reservoir.
The choice of the parallel pipelines was made to ensure the filling of the Paynesville Reservoir with the
head load of the WTP pumps.
TUBMAN ROAD
Outlet locations Outlet diameters (") L(m)
Somalia Drive (Freeway) 16 11867
Coca Cola Factory 6 3290
Police Academy Road 6 2591
Duport Road 6 7523
Weaver Avenue 6 370
Howard Road 4 889
A.B tolbert Road 4 1390
GSA Road 12 284
4 1366
16(RES) 2300
ELWA Road 12 1764
10 3003
8 695
SD. Copper Road 12 129
4 1164
SKD 12 5015
END POINT 24 /
WTP
16" WTP 16 /
1.5
0.5
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
hours
30000
20000
10000
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
time (hr)
Figure 58 inflow/outflow curve
50000
40000
30000
20000
10000
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
time (hr)
Figure 59 inflow/outflow curve
60000
40000
20000
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
time (hr)
Figure 60 inflow/outflow curve
16MGD
inlet consumption V simulated V reservoir (m3)
m3/h m3/h m3 3500.00
0-1 2029.367 1052.21 977.16 4477.16
1-2 2029.367 1052.21 977.16 5454.31
2-3 2029.367 1052.21 977.16 6431.47
3-4 2029.367 1331.40 697.97 7129.44
4-5 2029.367 2168.96 -139.59 6989.84
5-6 2029.367 3006.52 -977.16 6012.69
6-7 2029.367 3425.30 -1395.94 4616.75
7-8 2029.367 2727.34 -697.97 3918.78
8-9 2029.367 2308.55 -279.19 3639.59
9-10 2029.367 2168.96 -139.59 3500.00
10-11 2029.367 1750.18 279.19 3779.19
11-12 2029.367 2029.37 0.00 3779.19
12-13 2029.367 2308.55 -279.19 3500.00
13-14 2029.367 1819.98 209.39 3709.39
14-15 2029.367 2029.37 0.00 3709.39
15-16 2029.367 2308.55 -279.19 3430.20
16-17 2029.367 3006.52 -977.16 2453.05
17-18 2029.367 3425.30 -1395.94 1057.11
18-19 2029.367 3006.52 -977.16 79.96
19-20 2029.367 1959.57 69.80 149.75
20-21 2029.367 1470.99 558.37 708.13
V-t
8000.00
7000.00
6000.00
volume (m3)
5000.00
4000.00
3000.00
2000.00
1000.00
0.00
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
time
24MGD
inlet consumption V simulated V reservoir (m3)
m3/h m3/h m3 5500.00
0-1 3166.45 1613.40 1553.05 7053.05
1-2 3166.45 1613.40 1553.05 8606.10
2-3 3166.45 1613.40 1553.05 10159.14
3-4 3166.45 2057.13 1109.32 11268.46
4-5 3166.45 3388.31 -221.86 11046.60
5-6 3166.45 4719.50 -1553.05 9493.55
6-7 3166.45 5385.09 -2218.64 7274.91
7-8 3166.45 4275.77 -1109.32 6165.59
8-9 3166.45 3610.18 -443.73 5721.86
9-10 3166.45 3388.31 -221.86 5500.00
10-11 3166.45 2722.72 443.73 5943.73
11-12 3166.45 3166.45 0.00 5943.73
12-13 3166.45 3610.18 -443.73 5500.00
13-14 3166.45 2833.65 332.80 5832.80
14-15 3166.45 3166.45 0.00 5832.80
15-16 3166.45 3610.18 -443.73 5389.07
16-17 3166.45 4719.50 -1553.05 3836.02
17-18 3166.45 5385.09 -2218.64 1617.38
18-19 3166.45 4719.50 -1553.05 64.33
19-20 3166.45 3055.52 110.93 175.26
20-21 3166.45 2278.99 887.46 1062.72
V-t
12000.00
10000.00
8000.00
volume (m3)
6000.00
4000.00
2000.00
0.00
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
time
Figure 62 Volume Reservoir 24 MGD
32MGD
inlet consumption V simulated V reservoir (m3)
m3/h m3/h m3 7400.00
0-1 4221.94 2123.87 2098.08 9498.08
1-2 4221.94 2123.87 2098.08 11596.15
2-3 4221.94 2123.87 2098.08 13694.23
3-4 4221.94 2723.32 1498.63 15192.85
4-5 4221.94 4521.67 -299.73 14893.13
5-6 4221.94 6320.02 -2098.08 12795.05
6-7 4221.94 7219.19 -2997.25 9797.80
7-8 4221.94 5720.57 -1498.63 8299.18
8-9 4221.94 4821.39 -599.45 7699.73
9-10 4221.94 4521.67 -299.73 7400.00
10-11 4221.94 3622.49 599.45 7999.45
11-12 4221.94 4221.94 0.00 7999.45
12-13 4221.94 4821.39 -599.45 7400.00
13-14 4221.94 3772.35 449.59 7849.59
14-15 4221.94 4221.94 0.00 7849.59
15-16 4221.94 4821.39 -599.45 7250.14
16-17 4221.94 6320.02 -2098.08 5152.06
17-18 4221.94 7219.19 -2997.25 2154.81
18-19 4221.94 6320.02 -2098.08 56.74
19-20 4221.94 4072.08 149.86 206.60
V-t
16000.00
14000.00
12000.00
volume (m3)
10000.00
8000.00
6000.00
4000.00
2000.00
0.00
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
time
24MGD
DESCRIPTION
Capacity of storage
m3 MG
Effective volume 11268 2.98
Reserve volume 732 0.19
total volume 12000 3.2
32MGD
DESCRIPTION Capacity of storage
m3 MG
Effective volume 151923 4
Reserve volume 807 0.22
total volume 16000 4.22
The 16MGD scenario was simulated only to check the trend of the inlet and outlet volumes, but this
hypothesis is excluded due to the ever-increasing demand water. It is proposed to build a Reservoir with a
capacity of at least 3.2MG.
The minimum pressures in the system during the peak flow are shown. In the Coca Cola Factory and
Somalia Drive stretches negative pressures aries, not guaranteeing operation during the daily peak.
During the day, on average, the system works correctly.
From the results of the analyses, the filling of the Paynesville Reservoir is assured.
Red=water demand
Green=water inlet
With the realization of the reservoir it is possible to deliver a maximum flow of 951 LPS, equivale to
3423.6 m3/h (9MG for hour maximum request) in the scenario 16MGD.
The results of the model simulation are summarized in the following plot showing water pressure in the
nodes.
The minimum pressures in the system during the peak flow rate are shown. Negative pressures on all
branches of distribution are foreseen, not guaranteeing operation during the daily peak. At the end point
of the Tubman Road pipeline an approximately 27m of load during maximum demand sorts out.
From the results of the analyses, the filling of the Paynesville Reservoir is assured.
Red=water inlet
Green=water demand
With the realization of the Reservoir it is possible to deliver a maximum flow of 1500 LPS, equivale
to 5400 m3/h (14MG for hour maximum request) in the scenario 24MGD.
The results of the model simulation are summarized in the following plot showing water pressure in the
nodes.
The minimum pressures in the system during the peak flow rate are shown. Negative pressures arise on
all branches of distribution, not guaranteeing operation during the daily peak. At the end point of the
Tubman Road pipeline an approximately 22m of load during maximum demand sorts out.
From the results of the analyzes, the filling of the Paynesville reservoir is assured.
With the realization of the reservoir it is possible to deliver a maximum flow of 2015 LPS, equivale
to 7254 m3/h (19MG for hour maximum request) in the scenario 32MGD.
TUBMAN ROAD
Outlet locations Outlet diameters (“) L(m)
Somalia Drive (Freeway) 16 11867
Coca Cola Factory 6 3290
Police Academy Road 6 2591
Duport Road 6 7523
Weaver Avenue 6 370
Howard Road 4 889
A.B tolbert Road 4 1390
12 1764
ELWA Road 10 3003
8 695
The simulation was successful with adequate loads and ensuring the water flow rate of 32 MGD, by
increasing the diameters along Somalia Drive (40”) for 10471m, along Coca Cola Factory (16”) for
2290m, along Duport Road (16”) for 1625m, along Weaver Avenue (16”) for 370m, along Howard Road
(12”) for 889m, along A.B tolbert Road (12”) for 760m and along ELWA Road (24”) for 4764m.
TUBMAN ROAD
Outlet locations Outlet diameters rehabilitation (“) L stretch (m)
40 10471
Somalia Drive (Freeway) Existing diameter 16 1396
16 2290
Coca Cola Factory Existing diameter 6 1000
16 1625
Duport Road Existing diameter 6 5898
Weaver Avenue 16 370
Howard Road 12 889
12 760
A.B tolbert Road Existing diameter 4 630
24 4764
ELWA Road Existing diameter 8 695
PIPE:
3. WTP towards Morison Reservoir
4. Morison Reservoir towards outlets, end point and Paynesville Reservoir
Insert a booster to ensure the filling of the Paynesville Reservoir. The head of the system does not exceed
10/15 m.
The dimensioning of the tank remains the same also for the MSRF - typeB solution.
TUBMAN ROAD
Outlet locations Outlet diameters (") L(m)
Somalia Drive (Freeway) 16 11867
Coca Cola Factory 6 3290
Police Academy Road 6 2591
Duport Road 6 7523
Weaver Avenue 6 370
Howard Road 4 889
A.B tolbert Road 4 1390
GSA Road 12 284
4 1366
16(RES) 2300
ELWA Road 12 1764
10 3003
8 695
SD. Copper Road 12 129
4 1164
SKD 12 5015
END POINT 24 /
WTP
16" WTP 16 /
The minimum pressures in the system during the peak flow are shown. In the Coca Cola Factory and
Somalia Drive stretches negative pressures arise up, not guaranteeing operation during the daily peak.
During the day, on average, the system works correctly.
The results of the analyses assure that the Paynesville reservoir will be filled with a booster located along
the GSA Road outlet. Water flow rate of 81.85 LPS over the 24 hours with a head of about 10-15 m.
Project Code: File name: Date: SARI Consulting Ltd 87 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
The minimum pressures in the system during the peak flow rate are shown. Negative pressures rise on all
branches of distribution, not guaranteeing operation during the daily peak. At the end point of the
Tubman Road pipeline an approximately 27m of load during maximum demand is assured.
The results of the analyses guarantee that the Paynesville Reservoir will be filled with a booster located
along the GSA Road outlet. Water flow rate of 81.85 LPS over the 24 hours with a head of about 10-15
m.
The results of the model simulation are summarized in the following plot showing water pressure in the
nodes.
The minimum pressures in the system during the peak flow rate are shown. Negative pressures rise up on
all branches of distribution, not guaranteeing operation during the daily peak. At the end point of the
Tubman Road pipeline an approximately 21 m of load during maximum demand is secured.
The results of the analyses guarantee that the Paynesville Reservoir will be filled thanks a booster located
along the GSA Road outlet. Water flow rate of 81.85 LPS over the 24 hours with a head of about 10-15
m.
TUBMAN ROAD
Outlet locations Outlet diameters (“) L(m)
Somalia Drive (Freeway) 16 11867
Coca Cola Factory 6 3290
Police Academy Road 6 2591
Duport Road 6 7523
Weaver Avenue 6 370
Howard Road 4 889
A.B tolbert Road 4 1390
12 1764
ELWA Road 10 3003
8 695
The simulation was successful with adequate loads and ensuring the water flow rate of 32 MGD by
increasing the diameters along Somalia Drive (40”) for 10471m, along Coca Cola Factory (16”) for
2290m, along Duport Road (16”) for 1625m, along Weaver Avenue (16”) for 370m, along Howard Road
(12”) for 889m, along A.B tolbert Road (12”) for 760m and along ELWA Road (24”) for 4764m.
TUBMAN ROAD
Outlet locations Outlet diameters rehabilitation (“) L stretch (m)
40 10471
Somalia Drive (Freeway) Existing diameter 16 1396
16 2290
Coca Cola Factory Existing diameter 6 1000
16 1625
Duport Road Existing diameter 6 5898
Weaver Avenue 16 370
Howard Road 12 889
12 760
A.B tolbert Road Existing diameter 4 630
24 4764
ELWA Road Existing diameter 8 695
To each one of these parameters a base score has been assigned for every solution in terms of one point
for every achieved advantage. To each parameter a weight to multiply the correspondent score has been
set up according to the following table:
PARAMETER WEIGHT
WTP EFFICIENCY 15
PUMPING STATION EFFICIENCY 15
PIPELINE REGIME 30
RESPONSE TO FUTURE NEED 15
ENERGY SAVING AND CARBON FOOT PRINT EFFECT 15
ECONOMY IMPACT 10
TOTAL 100
The economic impact evaluation is based on the Preliminary Cost estimates of Annexes 3a, 3b, 3c,
3d, that are summarized in the following table.
CODE POSSIBLE COMBINED WEIGHT SCORE WEIGHT SCORE WEIGHT SCORE WEIGHT SCORE WEIGHT SCORE WEIGHT SCORE FINAL
SCENARIOS SCORE-
WEIGHED
BALANCE
15 15 30 15 15 10
WTP PUMPING PIPELINE REGIME RESPONSE ENERGY SAVING ECONOMY
EFFICIENCY STATION TO FUTURE AND CARBON IMPACT
EFFICIENCY NEED FOOT PRINT
EFFECT
B NEW PIPELINE
REPLACEMENT
ELIMINATION OF 1 6 LEVEL 6
LEAKAGE LOWER CAPEX
DURABILITY OF THE 1
PIPELINE
SUB-TOTAL 0 0 2 0 0 6 1.2
B+PV NEW PIPELINE
REPLACEMENT AND
PHOTOVOLTAIC
PLANT AT WHITE
PLAINS WATER
TREATMENT PLANT
REDUCED 1 ELIMINATION OF 1 HIGH EFFECTS 1 5 LEVEL 5
RISK OF LEAKAGE ON CARBON FOOT LOWER CAPEX
ENERGY PRINT
BLACKOUT REDUCTION
POSSIBLE 1 DURABILITY OF THE 1
RECOVERY PIPELINE
OF UNUSED
REN ENERGY
SUB-TOTAL 2 0 2 0 1 5 1.55
MSRF- NEW PIPELINE
Type A REPLACEMENT AND
MONUT SOUTH
RESERVOIR IN
MORISON FARM
WITH CONNECTION
PIPELINE TO
PAYNESVILLE
STEADY 1 STEADY STATE 1 ELIMINATION OF 1 RESPONSE 1 NO ENERGY 1 3 LEVEL 3
STATE OF OF PUMPING LEAKAGE TO THE CONSUMPTION LOWER CAPEX
CLEAN ALL TIMES FUTURE FOR
WATER NEED OF PAYNESVILLE
PRODUCTION WATER FEEDING
PROCESS DEMAND
REDUCED 1
MAINTENANCE
COSTS
SUB-TOTAL 1 4 3 1 1 3 2.25
MSRF- NEW PIPELINE
Type REPLACEMENT AND
A+PV MONUT SOUTH
RESERVOIR IN
MORISON FARM
WITH CONNECTION
PIPELINE TO
PAYNESVILLE AND
PHOTOVOLTAIC
PLANT AT WHITE
PLAINS WATER
TREATMENT PLANT
STEADY 1 STEADY STATE 1 ELIMINATION OF 1 RESPONSE 1 HIGH EFFECTS 1 1 LEVEL 1
STATE OF OF PUMPING LEAKAGE TO THE ON CARBON FOOT LOWER CAPEX
CLEAN ALL TIMES FUTURE PRINT
WATER NEED OF REDUCTION
PRODUCTION WATER
PROCESS DEMAND
REDUCED 1 REDUCED 1 DURABILITY OF THE 1 NO ENERGY 1
RISK OF DEMAND OF PIPELINE CONSUMPTION
ENERGY PUMPING HEADS FOR
BLACKOUT PAYNESVILLE
FEEDING
POSSIBLE 1 REDUCED 1 INCREASED AMOUNT 1
RECOVERY ENERGY OF DELIVERED
OF UNUSED CONSUMPTION WATER
REN ENERGY
REDUCED 1
MAINTENANCE
COSTS
SUB-TOTAL 3 4 3 1 2 1 2.5
MSRF- NEW PIPELINE
Type B REPLACEMENT AND
MONUT SOUTH
RESERVOIR IN
MORISON FARM
WITH BOOSTER AT
THE CONNECTION
PIPELINE TO
PAYNESVILLE
STEADY 1 STEADY STATE 1 ELIMINATION OF 1 RESPONSE 1 4 LEVEL 4
STATE OF OF PUMPING LEAKAGE TO THE LOWER CAPEX
CLEAN ALL TIMES FUTURE
WATER NEED OF
PRODUCTION WATER
PROCESS DEMAND
REDUCED 1 DURABILITY OF THE 1
DEMAND OF PIPELINE
PUMPING HEADS
REDUCED 1 INCREASED AMOUNT 1
ENERGY OF DELIVERED
CONSUMPTION WATER
REDUCED 1 PIPE LENGHT 1
MAINTENANCE OPTIMIZATION
COSTS
Project Code: File name: Date: SARI Consulting Ltd 94 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
SUB-TOTAL 1 4 4 1 0 4 2.5
MSRF- NEW PIPELINE
Type REPLACEMENT AND
B+PV MONUT SOUTH
RESERVOIR IN
MORISON FARM
WITH BOOSTER AT
THE CONNECTION
PIPELINE TO
PAYNESVILLE AND
PHOTOVOLTAIC
PLANT AT WHITE
PLAINS WATER
TREATMENT PLANT
STEADY 1 STEADY STATE 1 ELIMINATION OF 1 RESPONSE 1 HIGH EFFECTS 1 2 LEVEL 2
STATE OF OF PUMPING LEAKAGE TO THE ON CARBON FOOT LOWER CAPEX
CLEAN ALL TIMES FUTURE PRINT
WATER NEED OF REDUCTION
PRODUCTION WATER
PROCESS DEMAND
REDUCED 1 REDUCED 1 DURABILITY OF THE 1
RISK OF DEMAND OF PIPELINE
ENERGY PUMPING HEADS
BLACKOUT
POSSIBLE 1 REDUCED 1 INCREASED AMOUNT 1
RECOVERY ENERGY OF DELIVERED
OF UNUSED CONSUMPTION WATER
REN ENERGY
SUB-TOTAL 3 4 4 1 1 2 2.75
2.5
1.5
0.5
0
B B+PV MSRF-Type A MSRF-Type A+PV MSRF-Type B MSRF-Type B+PV
Figure 81
6 SELECTED SOLUTION
6.1. Introduction
The selected solution, based on all the above analyses and comparison, is the MSRF-Type B, whose total
score from the Benefit Matrix is at maximum rate. The solution actually responds to the need to create a
disconnection between the transmission line and the local hydraulic distribution network in the town,
thanks to the construction of a new Reservoir not far from the City, that is the location of the most
resident users. The solution foresees the installation of a proper booster at the GSA outlet of the feeding
pipeline to allow the full filling of the Paynesville Reservoir, avoiding by this way, the implementation of
a double pipeline along Tubman Road – solution MSR – Type A.
The transmission Pipeline running for 25.5 km from the White Plains Water Treatment Plant to the
connection with the existing 24” pipeline (end point) just in front of the Health Ministry Office in
Monrovia;
A booster will be necessary along GSA Road to ensure the filling of the Paynesville Reservoir.
From the WTP there will be two deviations:
1. WTP towards Morison Reservoir, length pipe about 18km with diameter 48”
2. Morison Reservoir towards outlets and end point (Tubman Road)
TUBMAN ROAD
Solution length (km) Diameter (")
3 48"
MSRF - 0.85 40"
type B
1.65 24"
will be implemented once the fund availability will allow it. Based on the ongoing Project, all the works
are ready and fully designed since the present time, in order to achieve a complete financial plan.
STEPPING PROCEDURE
STEP SUBJECT PHASE WHEN
NO.
1 CONSULTANT IMPLEMENTATION OF THE FULL DETAIL DESIGN IMMEDIATELY
OF THE SOLUTION MSRF – TYPE A OR B
2 CONSULTANT SPLITTING THE DESIGN INTO 5 LOTS
LOT CONTENTS
1 CONSTRUCTION OF MAIN TRANSMISSION LINE CONSTRUCTION – AROUND STA 0-8.500
2 CONSTRUCTION OF MAIN TRANSMISSION LINE CONSTRUCTION – AROUND STA 8.500-17.000
3 CONSTRUCTION OF MAIN TRANSMISSION LINE CONSTRUCTION – AROUND STA 17.000-25.500
4 CONSTRUCTION OF THE NEW RESERVOIR AND THE CONNECTING PIPELINES
5 DBO CONTRACT FOR CONSTRUCTION OF THE PHOTOVLTAIC PARK AT THE WTP
The people in the semi urban region of the project study area are predominantly farmers and apart from
crops, they also practice animal husbandry. The animals reared include dairy animals, poultry, pigs, goats,
sheep, cows and guinea pigs on a smaller scale.
In 2016, more than 2.2 million Liberians were unable to meet their basic food needs, of which almost 1.5
million (68%) resided in rural areas, 1.6 million were below the food-poverty line, and 670,000 lived in
extreme poverty. Regional and urban-rural disparities in poverty rates widened in the wake of the Ebola
crisis and the collapse of global commodity prices.
The project is agriculturally friendly, which means to say that the soil is rich for agro activities and the
rivers support fishery. However, the economic potential of these assets remains largely untapped.
7.2. Religion
Most of the project area residents are mainstream Christians with the major denominations being the
Roman Catholic, Pentecost and other protestant churches.
7.3. Sanitation
Approximately 99.78 per cent of the households within the project area use toilet facilities. Out of these,
65.97 percent use flush toilets, 25.97 percent use VIP latrines and the rest use ordinary pit latrines. The
majority of people living in the market and trading centers use ordinary pit latrines, “which is commonly
called government toilet.”
7.7. Brief description of the project and key environmental and social components
The proposed LWSC 36” Main Transmission Pipeline of Treated Water Supply, Which Transport Treated
Water from the White Plains Water Treatment Plant to Monrovia City and its Environs is a semi urban
and urban water supply project that will rehabilitate the water supply systems of the White Plains Water
Treatment Plant, improve water resource management and address sanitation and hygiene challenges in
three townships, one sub city and one major city; namely, White Plains Township, Johnsonville
Township, Congo Township, Paynesville City and Monrovia City. It will also support capacity building
with particular emphasis on women and the youth, monitoring and evaluation as well as enhancing sector
reforms.
The project is located in Montserrado County, precisely in the White Plains Township and traverses
across Johnsonville Township, Paynesville City and Congo Township. The project entails the
construction of 25 Km of 36” Main Transmission {(914.4mm outside diameter (OD))} Treated Water
Pipeline of UPVC material from White Plains Water Treatment Plant to Congo Township. The proposed
project will transport treated water from the White Pains Treated Water Reservoir mainline supply and
will be constructed along the existing public road reserve and traverse some few parcels of land. The
project is funded by the World Bank through the Water Services Trust Fund as a results and impact based
loan; and SARI Consulting Ltd. (Lead Consultant) and BK Enterprise, local consultant are performing the
Engineering Design.
The project’s main target population is in Montserrado County especially Monrovia City and its Environs.
The project aims at triggering the construction of the 36” inches (914.4mm) diameter distribution network
as well as metering of new connections within the target area. The main project activities will be digging
and backfilling of the pipeline trench and construction of associated valve chambers and pipes.
The proposed project is a continuation of a national program receiving funding from the World Bank,
among other lenders, for which Phase I is in completion, i.e. preparation of all tender documents and
feasibility study. The project will be implemented over a period of 24 months commencing in 2022.
The project will have two main components namely: (i) Water Infrastructure/Sanitation and Hygiene, and
(ii) Capacity Development and Project Management.
The treated water supply infrastructure component will focus on construction of the 36” main
transmission pipeline which transport treated water to three (3) townships one sub city and Monrovia City
and its Environs. The project has been initiated to address the challenges low water supply coverage,
dilapidated infrastructure, which is less than 70% to Monrovia City and its environs. In addition, the
quality of water from groundwater sources (boreholes, shadow wells, streams/creeks and handpumps) is
salty, unsafe and untreated and as such, not potable. The proposed intervention to provide piped water
supply from treated water source is considered to be the best solution to address the water quality
concerns in the county.
The project will support catchment protection measures to sustain the raw water sources for the plant. It
will also support the installation of treated water supply monitoring and stream valves stations in key
locations and rehabilitation of water quality laboratory at the plant to enhance water quality and pollution
monitoring.
Project Code: File name: Date: SARI Consulting Ltd 100 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
The sanitation and hygiene component will support the promotion of open defecation free (ODF)
communities, improved household sanitation through sanitation marketing, improved hygiene practice
and communal facilities for schools, markets and health centers.
Capacity development and project management component will focus primarily on supporting the district
councils to develop capacity to play the rightful role assigned to them under the country’s
Decentralization Policy which includes management, maintenance, and oversight of Water, Sanitation
and Hygiene (WASH) services to improve on sustainability of the proposed investments. The support will
also be directed to supporting the sector to review its policies on water and sanitation to address the
current needs of the sector.
The objective of the project is to contribute to socio-economic growth of Liberia by improving health and
livelihoods of the population through clean and sustainable water supply and improved sanitation.
Through the project, water points will be increased in number and this will contribute to efforts by
government of reducing walking distance to water sources.
The benefits of this intervention include time savings associated with better access to water and sanitation
facilities.
The gain in productive time due to less time spent on fetching water, health sector and patients costs
saved due to less treatment of diarrhea diseases, and the value of prevented deaths.
The main contributor to benefits is the saving of time associated with better access to water supply and
sanitation services.
In addition, improved water supply services will contribute significantly on reduction to households and
the Government spending on water borne diseases, increase LWSC revenue generation and reduce none
revenue supply from illegal connection.
Improved and reliable water supply for the residents of Monrovia City and its environs
Residents of Monrovia City and its environs will benefit from an improved source of water. Incidence of
diseases that occur as a result of using raw water from shallow wells, streams and unprotected springs
will reduce. The stabilized water supply will also result in improved hygiene and sanitation practices.
Increased reliability of water supply to the residents of the County & Sub – Cities
The local communities in White Plains, Johnsonville, and Paynesville city and beyond complained of
irregular discharge of water supply from the treatment plant. Cases of water rationing around has also
been observed. During the construction of the new pipeline, the residents of Monrovia and Sub-Cites will
benefit from improved discharge from the plant.
Project Code: File name: Date: SARI Consulting Ltd 101 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
The revenues generated from water supply fees by LWSC will provide capital to the corporation to
improve existing water supply infrastructure and develop new infrastructure. This will enable the
corporation to expand its areas of coverage, reduce Non-Revenue Water (NRW) and improve its customer
experience and services. This will contribute to improvement in the level of satisfaction of citizens to the
service delivery by the corporation.
Negative Impacts
The sub-project components involve mainly construction of LWSC 36” Main Transmission Pipeline;
simple, appropriate, low cost technology that do not pose any significant environmental consequences.
Nevertheless, the project may have some minor and temporary environmental impacts resulting mainly
from the construction of water supply and sanitation facilities. Surface water abstraction usually impacts
downstream users during low river/stream flows. Drilling of boreholes will generate noise, dust and
fumes and the construction process will generate solid waste and other debris. These impacts will be
minor, temporary and confined to the areas immediately surrounding the construction. Intense
groundwater abstraction may deplete the aquifers and therefore the project will include provision of
groundwater monitoring wells in each project area. Other negative impacts include:-
Project Code: File name: Date: SARI Consulting Ltd 102 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Further, the Project’s sanitation and hygiene program will focus on the need to adopt proper sanitary
practices. This will lead to environmental improvements, added health benefits, and increased
productivity, resulting in direct economic benefits.
Project Code: File name: Date: SARI Consulting Ltd 103 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
General environmental protection measures to be taken at any work site shall include:
To minimize the effect of dust on the environment resulting from earth mixing sites, vibrating
equipment, construction related traffic on temporary or existing access roads, etc. to ensure
safety, health and the protection of workers and communities living in the vicinity of work sites
and access roads.
(b) Ensure that noise levels emanating from machinery, vehicles and noisy construction activities
(e.g. excavation, blasting) comply with EPA standards and are generally kept at a minimum for
the safety, health and protection of workers within the vicinity of high noise levels and nearby
communities.
I Ensure that existing water flow regimes in spring, rivers, streams and other natural or irrigation
channels are maintained and/or re-established where they are disrupted due to works being
carried out.
(d) The Contractor shall provide mechanisms to protect soils and vegetation from being washed
to the rivers during construction.
(e ) Any site affected by the site work will be restored to its initial condition. This applies to
vegetation removed, grounds dug and soils removed, etc. Topsoil will be stripped ahead of any
earthmoving, stored near the construction site, and replaced in its original location after the re-
contouring of the area affected by the works.
(f) Prevent any construction-generated substance, including bitumen, oils, lubricants and waste
water used or produced during the execution of works, from entering into springs, rivers, streams,
dams, irrigation channels and other natural water bodies/reservoirs.
(g) Avoid or minimize the occurrence of standing water in holes, trenches, borrow areas, etc.
(h) Prevent and minimize the impacts of quarrying, earth borrowing, piling and building of
temporary construction camps and access roads on the biophysical environment including
protected areas and arable lands; local communities and their settlements. Restore/rehabilitate all
sites to acceptable standards.
(i) Upon discovery of graves, cemeteries, cultural sites of any kind, including ancient heritage,
relics or anything that might or believed to be of archeological or historical importance during the
execution of works, immediately report such findings to the
Township/City Council and the proponent so that the authority in charge of Culture may be expeditiously
contacted for fulfillment of the measures aimed at protecting such historical or archaeological resources.
(j) Prohibit construction workers from engaging in the exploitation of natural resources such as hunting,
fishing, and collection of forest products or any other activity that might have a negative impact on the
social and economic welfare of the local communities. Prohibit explicitly the transport of any bush meat
in Contractor’s vehicles.
Project Code: File name: Date: SARI Consulting Ltd 104 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
10 GENDER MAINSTREAMING
10.1. General
Specific steps to enhance women’s participation in the Project include:-
Youth Participation: It is anticipated that jobs will be created during project implementation and
the project will ensure youth participation especially in the construction of the pipeline.
The key verifiable indicators which will be used to monitor the impacts (depending on the nature, size
and scope of the project) are presented in Table 2 below. The Framework Environmental Monitoring Plan
for the project is presented in Table 3.
Table 2: Key environmental and social monitoring indicators for the water projects:
Component Indicators
Communicable Diseases Prevalence rates (evolution over time) of diseases such as malaria,
schistosomiases and diarrhea.
Non-Communicable Prevalence of poisoning and goiter.
Diseases
Gender
Roles and Responsibilities Time allocation of women before and after the project.
Table 3: Framework Environmental and Social Monitoring Plan for the Project
Pre-construction phase
Socio-economic Creation of Number of LWSC Quarterly
awareness consultation
about the meetings
project
Construction Phase
Socio-economic Creation of Number of Township/City Labor Officer Quarterly
employment people
opportunities employed
Skill transferto Number of people Township/City LaborOfficer Quarterly Cost
local employed covered
communities above
Project Code: File name: Date: SARI Consulting Ltd 105 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Occupation safety and Injuries due to Reported cases of Department of Bi-annual Cost
health construction injuries/accidents Occupation Safety covered
works and Health above
Project Code: File name: Date: SARI Consulting Ltd 106 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Project Code: File name: Date: SARI Consulting Ltd 107 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
The LWSC will constitute, within the Corporation and made up of corporation staff, a Project
Coordination Team (PCT), comprising a Project Coordinator, Water and Sanitation Engineer,
Procurement/Contracts Management Expert, Accountant, Social/Community Mobilization Expert (who
has experience in gender mainstreaming activities), Environment and Social Safeguards Officer, Financial
Management Expert and M&E Expert. The PCT will report to the Project Task Force (comprising all the
Directors in the LWSC) on a monthly basis. Actual implementation including monitoring of the project
will be at the Township/City Council level through the Township/City Council Coordination Team, while
complex schemes like gravity fed schemes will be implemented through the PCT. The Township/City
Council Co-ordination Team comprises the Township/City Commissioner or delegated representative,
Township/City Council Water Officer, Township/City Council Environmental Officer, Township/City
Council Health Officer, Township/City Council M& E Officer.
The Capacity Building Program proposed for the project will include; (i) Training of Township/City
Council Coordination Teams and Extension Workers; (ii) Formation, training and capacitation of end
user; (iii) Strengthening of M&E systems including training in collecting, analyzing and reporting on
gender & social issues; (iv) Review of National Water Policy and review of the policy’s gender and social
equity dimensions; and (v) Preparation of a gender responsive Township/City Council Investment Plans.
Project Code: File name: Date: SARI Consulting Ltd 108 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Consultations with the communities were conducted in the project area with the help of the local
administration especially the chiefs, assistant chiefs, youth leaders, residence and business owners. The
discussions during these public meetings were centered on key emerging issues relating to the project as
well as the communities. A total of three public consultative meetings were held at the following
locations; Pipeline Community, Johnsonville Community and the White Plains Community.
One-on-one interviews with county and national government agencies and institutions in the project area
were undertaken i.e. from White Plains Township office in White Plains, Johnsonville Township Office
in Johnsonville, Pipeline Community and the Congo Township Office in Congo town. The interview was
carryout in the water departments, the roads department, local Public Health Offices in the Environment
Departments.
These interviews were conducted to augment and confirm data and information obtained using the other
tools and methodologies.
Figure 82
Project Code: File name: Date: SARI Consulting Ltd 109 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
11 WORK SCHEDULE
Project Code: File name: Date: SARI Consulting Ltd 110 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
ANNEXES:
ANNEX 1: LIST OF DOCUMENTS SUPPLIED BY LWSC AND BY OTHER PROVIDERS
Z:\COMMESSE\J-K-L\LIBACQ\PAYNESVILLE
| tree.txt
| Camp Johnson Rd.jpg
| tree1.txt
|
+---4. GIS Training documents
| +---Tutorial for QGIS
| | TUTORIAL for QGIS_Monrovia case.docx
||
| \---Training documents
| Spatial coordinates Hydroconseil.pptx
| Introduction to GIS Hydroconseil.ppt
| GIS Training_planning and objectives.docx
|
+---1. Reference documents
| | IMG_4253.jpg~RF2fc4a4b7.TMP
| | IMG_4253.jpg
||
| +---Reports on LWSC
| | | LWSC-AUDIT Final Report 04-18-2013 A4.pdf
|||
| | +---ADB_ PPPs
| | | 140403 NRW PPP v2.pdf
| | | 131216 Bulk Water PPP discussion document.pdf
| | | 140524 Service extension PPP discussion document.pdf
| | | Monrovia PPPs_OBA_ Presetation to World Bank.ppt
|||
| | \---USAID Project
| | SUWASA Liberia COS and Tariff Model User Manual Final.pdf
| | 2013 LDHS CBT evaluation special report - 12-18-2013.pdf
| | Liberia COS Ratemaking General for Workshop.pdf
| | SUWASA Presenation for Liberia Workshop.pdf
| | Liberia COS Ratemaking Detailed for Training.pdf
| | Liberia_cost_of_service_data_tracker_FINAL.xlsx
| | Liberia Tariff Model_KAKATA.xlsx
| | Overview of COS & Tariff Model.pdf
| | Liberia Tariff Model_FINAL.xlsx
||
| +---2008 census
| | CSO-Liberia.pdf
| | poverty profile Liberia WB 2012.pdf
| | NPHC 2008 Final Report.pdf
| | Population Projection final 110512.pdf
| | Population size 210512.pdf
||
| +---Drawings
| | | IMG_4180.JPG
| | | IMG_4213.JPG
| | | IMG_4217.JPG
| | | IMG_4179.JPG
| | | IMG_4216.JPG
Project Code: File name: Date: SARI Consulting Ltd 111 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
| | | IMG_4214.JPG
| | | IMG_4211.JPG
| | | IMG_4219.JPG
| | | IMG_4215.JPG
| | | IMG_4218.JPG
| | | IMG_4212.JPG
|||
| | +---Surveyed network and extension lines
| | | +---Doe community and Clara town
| | | | | Clara town - Doe community_georef.tif
|||||
| | | | \---Shapefiles
| | | | Buffer zone expansion network CT.qpj
| | | | Existing network - Doe community.shp
| | | | Expansion line 2 - Doe Community.prj
| | | | Buffer zone expansion line CT.prj
| | | | Buffer zone expansion network CT.shp
| | | | Buffer zone expansion line CT.qpj
| | | | Valves - Clara Town.prj
| | | | Valves - Doe community.shp
| | | | Buffer zone 2 - Clara town.shp
| | | | Expansion line Doe Community.shx
| | | | Valves - Clara Town.qpj
| | | | Existing network - Clara Town.dbf
| | | | Buffer zone DC and CT.qpj
| | | | Buffer zone 2 - Clara town.dbf
| | | | Buffer zone expansion network CT.shx
| | | | Expansion line - Clara Town.qpj
| | | | Valves - Doe community.shx
| | | | Expansion line 2 - Doe Community.dbf
| | | | Existing network - Clara Town.shx
| | | | Expansion line Doe Community.dbf
| | | | Buffer zone 3 Clara Town.shx
| | | | Expansion line 2 - Doe Community.shx
| | | | Existing network - Clara Town.prj
| | | | Buffer zone Expansion line DC.qpj
| | | | Expansion line 2 - Doe Community.qpj
| | | | Expansion line Doe Community.shp
| | | | Buffer zone 3 Clara Town.shp
| | | | Valves - Clara Town.shx
| | | | Buffer zone 2 - Clara town.shx
| | | | Existing network - Doe community.qpj
| | | | Buffer zone 2 - Clara town.qpj
| | | | Buffer zone expansion line CT.shx
| | | | Buffer zone Expansion line DC.dbf
| | | | Buffer zone DC and CT.shx
| | | | Buffer zone Expansion line DC.shp
| | | | Existing network - Doe community.shx
| | | | Buffer zone Expansion line DC.shx
| | | | Buffer zone 2 - Clara town.prj
| | | | Expansion line - Clara Town.shx
| | | | Expansion line 2 - Doe Community.shp
| | | | Valves - Doe community.dbf
Project Code: File name: Date: SARI Consulting Ltd 112 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Project Code: File name: Date: SARI Consulting Ltd 113 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Project Code: File name: Date: SARI Consulting Ltd 114 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Project Code: File name: Date: SARI Consulting Ltd 115 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Project Code: File name: Date: SARI Consulting Ltd 116 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
| | | IMG_4459.JPG
| | | IMG_4456.JPG
| | | IMG_4457.JPG
|||
| | +---O&M Arrangement
| | | O&M Arrangement for Satellite System.doc
| | | O&M_Minutes of Meeting.doc
| | | O&M Arrangement for Hand Pump.doc
|||
| | +---Transmission main drawings AHB 1966
| | | Existing 36-inch transmission.zip
| | | IMG_4240.JPG
| | | IMG_4230.JPG
| | | IMG_4251.JPG
| | | IMG_4209.JPG
| | | IMG_4248.JPG
| | | IMG_4195.JPG
| | | IMG_4182.JPG
| | | IMG_4243.JPG
| | | IMG_4203.JPG
| | | IMG_4222.JPG
| | | IMG_4189.JPG
| | | IMG_4206.JPG
| | | IMG_4200.JPG
| | | IMG_4202.JPG
| | | IMG_4183.JPG
| | | IMG_4204.JPG
| | | IMG_4220.JPG
| | | IMG_4207.JPG
| | | IMG_4180.JPG
| | | IMG_4192.JPG
| | | IMG_4239.JPG
| | | IMG_4213.JPG
| | | IMG_4186.JPG
| | | IMG_4210.JPG
| | | IMG_4236.JPG
| | | IMG_4238.JPG
| | | IMG_4223.JPG
| | | IMG_4217.JPG
| | | IMG_4184.JPG
| | | IMG_4237.JPG
| | | IMG_4245.JPG
| | | IMG_4208.JPG
| | | IMG_4226.JPG
| | | IMG_4179.JPG
| | | IMG_4216.JPG
| | | IMG_4228.JPG
| | | IMG_4229.JPG
| | | IMG_4214.JPG
| | | IMG_4224.JPG
| | | IMG_4250.JPG
| | | IMG_4227.JPG
| | | IMG_4198.JPG
Project Code: File name: Date: SARI Consulting Ltd 117 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
| | | IMG_4211.JPG
| | | IMG_4187.JPG
| | | IMG_4219.JPG
| | | IMG_4221.JPG
| | | IMG_4201.JPG
| | | IMG_4235.JPG
| | | IMG_4215.JPG
| | | IMG_4196.JPG
| | | IMG_4197.JPG
| | | IMG_4244.JPG
| | | IMG_4191.JPG
| | | IMG_4218.JPG
| | | IMG_4188.JPG
| | | IMG_4199.JPG
| | | IMG_4205.JPG
| | | IMG_4249.JPG
| | | IMG_4212.JPG
| | | IMG_4193.JPG
| | | IMG_4225.JPG
| | | IMG_4242.JPG
| | | IMG_4234.JPG
| | | IMG_4190.JPG
| | | 36 inch Transmission water main.zip
| | | IMG_4185.JPG
| | | IMG_4247.JPG
| | | IMG_4231.JPG
| | | IMG_4181.JPG
| | | IMG_4232.JPG
| | | IMG_4194.JPG
| | | IMG_4233.JPG
| | | IMG_4246.JPG
|||
| | +---Location plan ABH 1966
| | | IMG_4290.JPG
| | | IMG_4289.JPG
| | | IMG_4274.JPG
| | | IMG_4254-1.jpg
| | | IMG_4292.JPG
| | | IMG_4269.JPG
| | | IMG_4261.JPG
| | | IMG_4296.JPG
| | | IMG_4260.JPG
| | | IMG_4263.JPG
| | | IMG_4279.JPG
| | | IMG_4294.JPG
| | | IMG_4278.JPG
| | | IMG_4298.JPG
| | | IMG_4291.JPG
| | | IMG_4284.JPG
| | | IMG_4287.JPG
| | | IMG_4255.JPG
| | | IMG_4286.JPG
| | | IMG_4283.JPG
Project Code: File name: Date: SARI Consulting Ltd 118 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
| | | IMG_4258.JPG
| | | IMG_4285.JPG
| | | IMG_4271.JPG
| | | IMG_4266.JPG
| | | IMG_4276.JPG
| | | IMG_4282.JPG
| | | IMG_4297.JPG
| | | IMG_4259.JPG
| | | IMG_4281.JPG
| | | IMG_4272.JPG
| | | IMG_4270.JPG
| | | IMG_4253.JPG
| | | IMG_4262.JPG
| | | IMG_4273.JPG
| | | IMG_4288.JPG
| | | IMG_4253_1.jpg
| | | IMG_4254.JPG
| | | IMG_4295.JPG
| | | IMG_4268.JPG
| | | IMG_4275.JPG
| | | IMG_4280.JPG
| | | IMG_4265.JPG
| | | IMG_4257.JPG
| | | IMG_4256.JPG
| | | IMG_4277.JPG
| | | IMG_4293.JPG
| | | IMG_4264.JPG
| | | IMG_4267.JPG
|||
| | +---Drawings 1974 & 1978
| | | IMG_4484.JPG
| | | IMG_4461.JPG
| | | IMG_4487.JPG
| | | IMG_4494.JPG
| | | IMG_4470.JPG
| | | IMG_4496.JPG
| | | IMG_4472.JPG
| | | IMG_4488.JPG
| | | IMG_4462.JPG
| | | IMG_4466.JPG
| | | IMG_4460.JPG
| | | IMG_4498.JPG
| | | IMG_4492.JPG
| | | IMG_4489.JPG
| | | IMG_4493.JPG
| | | IMG_4483.JPG
| | | IMG_4479.JPG
| | | IMG_4465.JPG
| | | IMG_4464.JPG
| | | IMG_4467.JPG
| | | IMG_4463.JPG
| | | IMG_4491.JPG
| | | IMG_4490.JPG
Project Code: File name: Date: SARI Consulting Ltd 119 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
| | | IMG_4458.JPG
| | | IMG_4474.JPG
| | | IMG_4471.JPG
| | | IMG_4486.JPG
| | | IMG_4497.JPG
| | | IMG_4476.JPG
| | | IMG_4468.JPG
| | | IMG_4473.JPG
| | | IMG_4482.JPG
| | | IMG_4499.JPG
| | | IMG_4485.JPG
| | | IMG_4475.JPG
| | | IMG_4495.JPG
| | | IMG_4478.JPG
| | | IMG_4481.JPG
| | | IMG_4454.JPG
| | | IMG_4469.JPG
| | | IMG_4455.JPG
| | | IMG_4477.JPG
| | | IMG_4459.JPG
| | | IMG_4456.JPG
| | | IMG_4457.JPG
|||
| | \---AFDB-UWSSP
| | | FEASIBILITY STUDY REPORT- WATER & SANITATION 31082009.pdf
| | | 3-REVISED WATER WORKS BOQ_ Blank_N003.xlsx
| | | 4-MAIN COVERS FOR WATER WORKS DWGS_N003.dwg
| | | Revised Priced BoQ N003.xlsx
| | | WATER WORKS BoQ_corrected_N003.xlsx
| | | 2-BD_W-N003_Final__20130913-ma.pdf
|||
| | +---6-Kakata DWG
| | | 3 - PUMP STATION 1 .dwg
| | | 6 - SITE DRAWINGS.dwg
| | | 5 - RESIDENCE.dwg
| | | 7 - KAKATA_EXISTING LAYOUT.dwg
| | | 1 - ADMIN BUILDING.dwg
| | | 4 - PUMP STATION 2.dwg
| | | 0 - KAKATA COVERS.dwg
| | | 2 - OPERATIONS.dwg
|||
| | +---7-Zwedru DWG
| | | 4 - ZWEDRU_EXISTING LAYOUT.dwg
| | | 1 - ADMIN.dwg
| | | 3 - SITE DRAWINGS.dwg
| | | 2 - OPERATIONS - GEN.dwg
| | | 0 - ZWEDRU COVERS.dwg
|||
| | +---8-DWG -STANDARD DWGS_BIDDING_N003
| | | 16-Pressure Vessel.dwg
| | | 1-2-4-7-8-14-Standard dwgs - others.dwg
| | | 3-10-VALVE CHAMBERS ALL_PIPE MARKERS.dwg
| | | 6-VALVE CHAMBER REINFORCEMENT.dwg
Project Code: File name: Date: SARI Consulting Ltd 120 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Project Code: File name: Date: SARI Consulting Ltd 121 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
| | | Bidding Documents_Final.docx
|||
| | +---Study IGIP Buchanan Kakata Zwedru
| | | | bidding doc buchanan kakata zwedru.pdf
||||
| | | +---vol3
| | | \---vol2
| | +---Colan_detailed design
| | | Report cover.doc
| | | Summary of Proposed Wrks-with justification.doc
| | | Final Detailed Design Report-1.doc
|||
| | +---Chinese Feasibility Study Report
| | | +---New Fiama Sewage Treatment Plant
| | | | 1.pdf
| | | | 3.pdf
| | | | 20130601.pdf
| | | | 3.pdf
| | | | Fiama--20130601-.pdf
| | | | 2.pdf
||||
| | | \---Expansion Project of WPTP and network
| | | -20130601.pdf
| | | 1.pdf
| | | --20130601.pdf
| | | 4.pdf
| | | .pdf
| | | 3.pdf
| | | 2.pdf
|||
| | +---GPOBA
| | | PIPE_LAYING_INSTR.jpg
| | | COMMUNAL_STANDPIPE-final-2.jpg
| | | reseau_liberia-couleur.jpg
| | | COMMUNAL_STANDPIPE-final-2.2.jpg
| | | volume of annex V3.pdf
| | | EIA final ECH.doc
| | | COMMUNAL_STANDPIPE-final-1.jpg
| | | Typical_House_Connection.jpg
| | | Ground water option as water source for the OBA project final.pdf
| | | Final_Report V4.pdf
| | | operation manual V2.pdf
| | | Final Final_Report submitted.pdf
|||
| | +---Liberia Sector Strategic Plan
| | | Liberia WASH Sector Operating Matrix 2012 - 2017 FINAL.pdf
| | | Liberia WASH Sector Investment Costing 2012 - 2017 FINAL.xlsx
| | | Liberia WASH Sector Action Plan 2012 - 2017 FINAL.pdf
| | | Liberia WASH Sector Strategic Plan 2012 - 2017 FINAL.pdf
|||
| | +---Monrovia WPTP project
| | | White_Plains_Review DD & Tend Doc. Vol1 - 17.05.2014.doc
|||
Project Code: File name: Date: SARI Consulting Ltd 122 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Project Code: File name: Date: SARI Consulting Ltd 123 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
| QGIS-OSGeo4W-2.8.2-1-Setup-x86_32bits.exe
| QGIS-OSGeo4W-2.8.2-1-Setup-x86_64bits.exe
| googleearthinstall.log
| BaseCamp_447.exe
|
+---0-paynesville reservoir-hydroconseil
| Complementary note - Booster station Paynesville - V1.pdf
| Appendix 1.1_Preliminary Design Report.pdf
| Complementary note - Booster station Paynesville - V1.3.docx
| Appendix 1.2_Attached files of the Preliminary Design Report.pdf
|
+---3. PDF maps
| Customers-zone-2.pdf
| Customers-zone-1.pdf
| Water supply network.pdf
| Customers-zone-3-4-5-6.pdf
| Health and Educational Institutions.pdf
| Customers all 10 March 2015.pdf
| Customers-zone-7-8-9-10-11-12.pdf
|
\---2. NIS layers
| GIS_Monrovia.qgs~
| GIS_Monrovia.qgs
|
+---Satelite Layer
| MONR_D2
| MONR_B5
| MONR_C1
| MONR_A2
| MONR_A12.tif
| MONR_D8
| MONR_A8
| MONR_B6
| MONR_C2
| MONR_B8
| MONR_D5
| MONR_D7
| MONR_09
| MONR_D6
| MONR_A6
| MONR_A3
| MONR_A1
| MONR_A7
| MONR_C5
| MONR_B4
| MONR_0-GENERAL MAP.tif
| MONR_A4
| MONR_C3
| MONR_B7
| MONR_B1
| MONR_C6
| MONR_D1
| MONR_D9
Project Code: File name: Date: SARI Consulting Ltd 124 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
| MONR_D4
| MONR_B2
| MONR_C4
| MONR_C8
| MONR_A13.tif
| MONR_D3
| MONR_B3
| MONR_C7
|
+---Water Supply Network
| commercial zones lwsc.qpj
| NIS_equipment.shx
| Water_Supply_Network.prj
| commercial zones lwsc.shp
| Water_Supply_Network.qpj
| enumerated_customers_10march15.shx
| Water_Supply_Network.shp
| Water_Supply_Network.dbf
| NIS_equipment.prj
| NIS_equipment.dbf
| enumerated_customers_10march15.shp
| Water_Supply_Network.shx
| NIS_equipment.qpj
| commercial zones lwsc.prj
| enumerated_customers_10march15.prj
| enumerated_customers_10march15.qpj
| commercial zones lwsc.shx
| NIS_equipment.shp
| enumerated_customers_10march15.dbf
| commercial zones lwsc.dbf
|
+---General layers
| Liberia_Administrative_Border_1.sbx
| districts_2007.sbn
| LBR_water_areas_dcw.prj
| Liberia_50k_G744.prj
| centre_sant‚_online_3.shp
| roads.prj
| Liberia_50k_G744.dbf
| Liberia_Educational_InstitutionsCopy.prj
| roads.dbf
| LBR_adm2.prj
| LBR_water_lines_dcw.prj
| LBR_adm0.sbn
| LBR_water_lines_dcw.shx
| intervention_point.dbf
| roads.shx
| Liberia_Educational_Institutions.shx
| Liberia_Educational_InstitutionsCopy.shx
| Liberia_Hydrology.sbx
| LBR_adm1.sbn
| Liberia Electricity Transmission Network.shp
| LBR_adm3.shx
Project Code: File name: Date: SARI Consulting Ltd 125 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
| centre_sant‚_online_3.shp.xml
| LBR_adm2.shp
| Liberia Electricity Transmission Network.prj
| Liberia_50k_G744.sbn
| LBR_adm1.sbx
| Liberia_Educational_InstitutionsCopy.sbx
| Liberia_Administrative_Border_2.dbf
| Liberia_Administrative_Border_2.sbx
| county_2007.shp.xml
| Intervention_line.shx
| LBR_adm2.sbn
| Liberia_Educational_InstitutionsCopy.shp.xml
| Intervention_line.qpj
| cities_towns.sbn
| LBR_adm1.shp
| centre_sant‚_online_3.shx
| cities_towns.shp
| Liberia_Administrative_Border_2.sbn
| LBR_adm1.prj
| centre_sant‚_online_3.prj
| LBR_adm3.sbx
| Liberia_Hydrology_Polygons.sbx
| GIS Monrovia.qgs~
| clan_2007.sbn
| districts_2007.prj
| intervention_point.prj
| county_2007.shx
| LBR_adm2.shx
| districts_2007.shp.xml
| health_facilities.shx
| health_facilities.dbf
| LBR_adm0.prj
| Liberia_Hydrology_Polygons.shp
| Liberia_Hydrology_Polygons.prj
| centre_sant‚_online_3.dbf
| LBR_adm2.dbf
| intervention_point.shp
| Liberia_Hydrology.sbn
| LBR_adm2.sbx
| LBR_adm3.csv
| cities_towns.dbf
| GIS Monrovia.qgs
| Liberia_Administrative_Border_1.prj
| LBR_roads.sbn
| Liberia_Administrative_Border_1.cpg
| LBR_water_areas_dcw.shp
| Liberia_Educational_Institutions.CPG
| centre_sant‚_online_3.CPG
| roads.sbn
| Liberia Electricity Transmission Network.shp.xml
| LBR_readme.txt
| cities_towns.shp.xml
| districts_2007.dbf
Project Code: File name: Date: SARI Consulting Ltd 126 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
| clan_2007.shp.xml
| Liberia Electricity Transmission Network.sbn
| Liberia_Educational_Institutions.dbf
| LBR_adm1.shx
| cities_towns.prj
| Liberia Electricity Transmission Network.shx
| roads.shp
| Liberia_50k_G744.shp
| Liberia_Administrative_Border_2.shp
| county_2007.shp
| Intervention_line.dbf
| districts_2007.sbx
| districts_2007.shx
| LBR_adm3.shp
| Liberia_Educational_InstitutionsCopy.sbn
| LBR_adm0.shx
| Liberia_Hydrology.shp.xml
| districts_2007.shp
| Liberia_Educational_Institutions.sbn
| clan_2007.dbf
| intervention_point.shx
| cities_towns.sbx
| clan_2007.shp
| Liberia_Educational_Institutions.shp.xml
| LBR_water_areas_dcw.dbf
| health_facilities.sbx
| Liberia_Administrative_Border_1.sbn
| Liberia_50k_G744.sbx
| centre_sant‚_online_3.sbx
| Liberia_50k_G744.cpg
| LBR_adm1.dbf
| Liberia Electricity Transmission Network.dbf
| Intervention_line.shp
| LBR_water_lines_dcw.shp
| Liberia_Hydrology_Polygons.sbn
| cities_towns.shx
| LBR_water_lines_dcw.dbf
| LBR_roads.sbx
| intervention_point.qpj
| county_2007.sbx
| roads.sbx
| LBR_roads.shp
| Liberia Electricity Transmission Network.sbx
| Liberia_Administrative_Border_2.cpg
| Liberia_Hydrology_Polygons.cpg
| clan_2007.shx
| LBR_roads.dbf
| clan_2007.prj
| Liberia_Administrative_Border_1.shp
| LBR_adm2.csv
| health_facilities.sbn
| LBR_adm0.sbx
| LBR_water_areas_dcw.shx
Project Code: File name: Date: SARI Consulting Ltd 127 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
| Liberia_Administrative_Border_2.prj
| Liberia_Administrative_Border_1.dbf
| LBR_adm3.dbf
| LBR_adm0.csv
| Liberia_Administrative_Border_2.shx
| Liberia_Hydrology.shp
| county_2007.dbf
| Liberia_Educational_Institutions.shp
| clan_2007.sbx
| health_facilities.shp
| health_facilities.prj
| Liberia_Educational_Institutions.sbx
| Liberia_Hydrology.shx
| Liberia_Hydrology.CPG
| Liberia_Hydrology_Polygons.dbf
| Intervention_line.prj
| Liberia_Administrative_Border_1.shx
| Liberia_Educational_InstitutionsCopy.CPG
| county_2007.sbn
| Liberia_Hydrology.dbf
| Liberia_Educational_Institutions.prj
| LBR_adm0.dbf
| Liberia_Educational_InstitutionsCopy.dbf
| LBR_roads.prj
| Liberia_Hydrology.prj
| LBR_adm3.prj
| LBR_adm0.shp
| Liberia_50k_G744.shx
| county_2007.prj
| LBR_adm1.csv
| LBR_adm3.sbn
| centre_sant‚_online_3.sbn
| LBR_roads.shx
| Liberia_Hydrology_Polygons.shx
|
\---Enumeration customers
Enumeration 10 March 2015-masterfiles.xlsx
LWSC Enumeration (by region) - 10th March 2015.xlsx
Enumeration 10 March 2015-masterfiles.txt
Project Code: File name: Date: SARI Consulting Ltd 128 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Geological map;
Geomorphological map;
Hydrogeological map
Drillings
During the on-site investigation the followings drillings shall be performed:
13 exploratory borings located into the depression of the alignment – LOWER POINTS
Taking in consideration that the depth of the foundation of the pipeline will be up to 3 mt, the drilling
will be done up to 6‐7 meters, according to the quality of crossed layers. The goal of the investigation
is to detect the thickness of the soft layers – alluvium made of clay or silt – and their mechanical
properties. Drilling will stop after 0.5 meter drilling into rock or hard layer. If no rock layer is reached
out, the drilling will stop when the local site relative density of the soil is at least 70%. Standard
penetration tests and split spoon or open end drive sampling shall be conduct in the borings at 0,6m,
1,5m, and at 1,5m foot below the estimated foundation depth of the pipe line with estimated intervals
thereafter. On cohesive layer the Pocket Penetrometer or Vane Test shall be performed every cored
sample. Measure of the water table after reaching the steady state will be also provided.
Sampling and laboratory testing shall be performed
Sampling with Shelby or Denison samplers‐ In situ moisture and density testing shall be conducted
within the borings utilizing an open ring sampler at depths of 1,5m and 2,0m below 3 meters from the
ground level.
Subsurface soils where visually shall be logged and classified. Sampling and laboratory testing shall
be performed to confirm visual classification.
Project Code: File name: Date: SARI Consulting Ltd 129 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
At the end of the drilling an in situ permeability test will be performed, preferably of Lefranc type, at
variable hydraulic head, as the most layer is deemed to be loose soil. If the test is made only on rock
layer, the Lugeon Test will be carried out at constant hydraulic head.
Pit testing
In order to detect the type of material that will be excavated to place the new pipeline, pit excavation
will be performed with excavator with a width of 3 mt and depth of 3.5 mt.
The cross stratigraphy shall be accurately described and rock samples, if matched, will be taken for a
total of 6, to be submitted to Laboratory Testing, only for the measurement of the unconfined uniaxial
compressive strength. If within the 3.5 mt only soil layer has been excavated, a Plate Load Test – PLT
– shall be performed according to the relevant ASTM specification: 300 mm dia plate, pressure up to
0.25 MPa.
Laboratory testing
Selected samples shall be tested in the laboratory to determine engineering properties of the soils.
Moisture contents and dry densities shall be determined to evaluate the various soil deposits with
depth.
The results of these tests shall be shown on the boring logs.
Sieve analysis and Atterberg limits tests shall be performed to aid in soil classification.
The results of these tests shall be presented in the Summary of Laboratory Results and on the
individual test reports shall be presented in a section of geotechnical report.
Standard Penetration Test (SPT)
In this investigation the SPT shall be carried out in regular intervals in the overburden, at each of the
borehole. The performance of this test is based on the test method specified in BS 1377. Disturbed
samples of soil shall be collected from SPT tube. Field Permeability Test
Field permeability tests shall be carried out in the Boreholes.
The method used shall be Variable Head Method (Falling Head Method) as specified in Section 4:
25.4 of BS: 5930:1999.
Project Code: File name: Date: SARI Consulting Ltd 130 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Laboratory Investigation
Laboratory investigations shall be taken place in order to the sub surface assessment in geotechnical
investigation. In connection with the entire laboratory testing the performance shall be made as per
BS 1377 part 4: unless otherwise stated.
Geotechnical report
Introduction
The design of the construction of the 36” pipe/waterline for the supply of water from White Plains to
ELWA has been awarded to SARI Consulting Ltd. in association with BK Enterprise Inc.; the local
Liberian consultant. The contract generally requires the preparing and submission of detailed
engineering design for the construction of 25km 36-inch waterline. In view of the aforementioned, the
geotechnical investigation is to be carried out by the local consultant to inform the design process.
Objectives
Generally, the geotechnical investigation is to inform the detailed design of the 36-inch diameter
waterline.
Specifically, the objectives of the investigation are:
i. Determine the basic soil characteristics within the Laboratory of the materials collected from ten
(10) test pits located at hilly sections along the site area
ii. Conduct drilling at thirteen (13) selection ss locations at depressions along the site area
iii. Determine the SPT values (0.6, 1.5, 2.0, 3.0 and 5.5m) at each of the thirteen selected locations as
required in section 2 of the Geological and Geotechnical Specifications
iv. Process test results of both field and laboratory works
Scope of Work
The site covers a 25km route leading from the White Plains to Monrovia and its environs
Methodology
Tables 2.1 and 2.2 contains the tests and corresponding tests references of field and lab tests
respectively.
Table 2.1: List of Laboratory Tests and Methods
No. List of Tests Test Method
Employed
1 Sieve Analysis AASHTO T-27
2 Atterberg Limits (LL, AASHTO T-89 & T-90
PL, PI)
3 Moisture-Density AASHTO T-180
Relationship
4 Direct Shear tests
Table 2.2: List of Field Tests and Methods
No. List of Tests Test Method
Employed
1 Standard Cone BS 1377
Penetrometer Tests
2 Permeability Tests BS: 5930:1999.
Project Code: File name: Date: SARI Consulting Ltd 131 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Project Code: File name: Date: SARI Consulting Ltd 132 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Laboratory Test
below in Table 3.2 is the summary report of the laboratory works.
Project Code: File name: Date: SARI Consulting Ltd 133 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Conclusion
The geotechnical investigation for the construction of 36” waterline has been concluded and the
summary of
works are listed below:
• Thirteen (13) boreholes were drilled
• In each of the thirteen (13) boreholes, SPTs were taken at 0.6m, 1.5m, 2.0m, 3.0m and 5.5m
• Ten (10) test pits were excavated and samples were collected for laboratory tests (moisture content,
unit weight, grain size distribution, atterberg limits)
• Field and Laboratory Test Results were summarized and analyzed
Project Code: File name: Date: SARI Consulting Ltd 134 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Prepared By
Seidu Tanko M. Rufai
Figure 83
Project Code: File name: Date: SARI Consulting Ltd 135 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
EXECUTIVE SUMMARY
BK Enterprise, Inc. herein referred to as the Local Consultant for the Consulting Services for the Detailed
Feasibility Study Report, Detailed Design Report, Environmental/Social Safeguards, Studies and Tender
Documents for the Replacement of the 36-Inch Main Transmission Which Transports Treated Water from
White Plains Treatment Plant to Monrovia - Liberia therefore required that a detail cross sections
topographic and mapping survey be carried along the entire 25km length existing 36” pipe line from the
water treatment plant in white plains to the point where 36” pipe changes to 24” in Cong town. This is to
provide the designer with sufficiently accurate information both general and specifics about the profile of
the existing pipe line and the nature of the actual ground levels within 20m corridor along the line using
the center of the existing pipe as reference, on the basis of which a safe and economic alignment can be
designed as per the project specification in accordance to ASSHTO approved hydraulics standards.
Generally, the topography of the route line is fairly flat but appears undulating at some few sections from
STA 25+065 to STA13 at Johnsonville with patches of swampy lands.
The general alignment of the existing line is fairly gentle with few horizontal and vertical curves. In
addition to the topographic & mapping, the survey established permanent bench marks (reference primary
& secondary controls) at safe and inter visible locations along the project corridor. These bench marks
were defined in three-dimensional axis X, Y, Z in the UTM_WGS84-29N reference coordinates system.
A total of 22 bench marks were established for the project.
Residential and commercial buildings, drainage structures, stream crossings, utilities such as water &
sewage lines, communications & electric poles as well as all major and minor junctions were all mapped
& detailed.
TABLE OF CONTENT
Executive summary
1.0 Introduction
1.1 Background
1.2 Project objectives
1.2.1 Scope
2.0 Survey methodology
2.1 Reconnaissance survey
2.2 Field work
2.3 Building of bench marks
2.3.1 Coordinates system
2.3.2 Static Survey
2.3.3 Leveling
2.3.4 Traversing ( RTK)
4.0 Topographic survey
4.1 Cross section survey & detailing
5.0 Discussion of survey
5.1 Site location and accessibility
5.1.2 Vegetation & climate
5.1.3 General topography of the area
6.0 Conclusion & recommendations
Appendix A List of tables
Appendix B List of figures
Fig. 1 Google map showing the location of the bench marks
Fig. 2 Topographical map of the project area
Project Code: File name: Date: SARI Consulting Ltd 136 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Background:
This report presents the results of the alignment as well as the plan & profile of the existing pipe line
based on the bench marks established at the various locations for the surveys. The primary controls were
established at an interval of 5km and two inter visible secondary controls were established at an interval
of 500m.
An interval of 25m detailed cross sections topographic and mapping surveys was carried out at the width
of 20m and 50m corridors within the rural and urban section of the project respectively with the center of
the existing pipe line used as reference center of the corridors.
Project Objectives: The objectives of the survey were to provide the following information to the
designer;
1. Determine the plan & profile of the existing pipe line
2. Determine the actual ground levels & conditions beyond the edges of the existing pipe line not less
than 10m in the rural areas and 20m in the urban areas on both sides from the center of the
existing pipe respectively.
3. The location of all the existing structures and utility lines within the 20m and 40m corridors
respectively
4. The details of the existing drainage structures
5. Details of the outlets of the distribution pipe
Scope : A total of 16 Global Positioning System (GPS) UTM_WGS84-29N referenced coordinates
system bench marks were established. These bench marks were established inter visibly in pairs at an
intervals of 5km for the primary controls and 2km for the secondary controls respectively within the
project limits. They were strategically positioned to ensure proper connectivity in order to provide a well-
adjusted network (X , Y, Z). They are also positioned in such a way that they will not be affected by the
construction activities of the contractor or the civilian populace. The ‘X & Y’ coordinates are referenced
to the Latitude and Longitudes whilst the elevation ‘Z’ is referenced to the mean sea level
An open loop leveling and a close loop traverse was then run on the bench marks to adjust the elevations
errors and angular miss closure respectively.
A Real Time Kinematic (RTK) was then deployed to collect the topographic survey data at a cross section
of 25m interval along the 20m and 40m corridors of the 25km long existing pipe line from the water
treatment plant to Congo town. Details such as the existing buildings, drainage structures, electric &
telecommunication lines, water & sewage lines, streams and swampy grounds were all mapped.
Survey methodology:
Reconnaissance survey was carried out in September last year 2021 alongside the team from SARI
Consulting LTD (Lead Consultant)/BK Enterprise, Inc. (Local Consultant) and the client – the Liberia
Water & Sewer Corporation (LWSC) as a way of introducing the survey team to the site and to determine
the conditions of the site and also to find out of the availability of any reference bench marks existing on
the ground . The survey team then went back to site following the joint site visit to select the most
suitable locations for the establishment of the bench marks and to plan the field survey works.
The topography and the general layout of the site was studied to inform on the right equipment needed to
obtain a well-adjusted network of bench marks acceptable by the supervision design team.
From the reconnaissance survey it was find out that there were two UTM_WGS-84 29N existing
reference Control or Bench Marks B01 and B02 on the LWSC treatment plant site at white plains and the
Mt. Coffee Hydro Power Plant staff compound respectively and so there was an urgent need to initiate the
surveys from these two controls for the project.
Project Code: File name: Date: SARI Consulting Ltd 137 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
25 cm
T.N.
40-50 cm
40-50cm
50 cm
40 cm 20-25 cm 20-25 cm
Figure 84
Static mode (continuous observations) GPS Survey
Project Code: File name: Date: SARI Consulting Ltd 138 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Using Real Time Kinematics - RTK(GPS) Survey to establish the Secondary Control
One of the already established primary control say (B01) was selected and used as a based station. A base
GPS receiver was set and leveled over it, at one second collection rate and at 13 degrees elevation mask, on a
fixed height tripod, and then input its coordinates previously established. A rover receiver supported with the
radio antennae, was then used to coordinate the secondary controls. Consequently, the rover receiver was set
Project Code: File name: Date: SARI Consulting Ltd 139 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
at one (1) second collection rate and 15 degrees elevation mask on a secondary control point. The rover rod
was kept always at 2m fixed height and was set and bubbled on the point with the use of a bipod for stability
and verticality.
The radio link between the base station and the rover was constantly monitored.
Before starting the RTK surveys the system on the data collector was initialized in order to resolve the
integer ambiguity.
List of Primary and Secondary Controls established along the project area
Leveling Survey : Differential leveling is the process of measuring vertical distances from a known
elevation point to determine elevations of unknown points. A fly over levels was run for each of the open
loop using the base reference as the main reference point with an automatic leveling instrument. The leveling
process continues on each of the pillars built and observed whilst introducing temporal point along the
leveling route. The reduced levels were adjusted where necessary using the Bowditch rule of adjustment. The
figure below shows the route of the leveling from the base reference point A0
Project Code: File name: Date: SARI Consulting Ltd 140 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Figure 87
Topographic survey: The Real Time Kinematic (RTK) survey was deployed to carry out the topographic,
mapping and detail surveys using the Tremble Brand Differential Global Positioning System (DGPS)
Receiver units (Base & rover) with a data logger. The base units was mounted, leveled and centered on a
tripod over the reference base station (with known X,Y,Z). It was then switched on and connected to the data
logger. The logger was then use to set up the Receiver at the base station with all the necessary parameter in
UTM_WGS84-29N coordinates system. The Rover unit was then switched on and similarly all the set ups
were made. We then connected the Rover with the Receiver unit on the base station through blue tooth
connection using the tracked satellites. The Rover was then used to observed on another known point to
ensure that there was excellent communication and proper orientation between the Receiver - Rover units
through a process called initialization. Once the rover was initialized (results of the test was within the
tolerance), we then proceeded with the topographic, mapping and detail cross sections survey. About five
major junctions were detailed up to 50m off the main pipe line.
The entire topographic, mapping and detail survey was done in two phases ;
Phase 1: The first phase of survey included the following;
1. Building of permanent secondary control survey pillars
2. Establishment of secondary controls and differential leveling
Phase 2: The second phase of the survey included the following,
1. Topographic (25m cross sections) surveys of the existing 36” pipe line
2. Detailing of the existing structures within the 20m corridor along the route of the existing pipeline
3. Drawing of the Plan & Profile of the existing pipe line
Project Code: File name: Date: SARI Consulting Ltd 141 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Discussion of results :
All the bench marks (primary and secondary controls) are accessible through the project corridor from the
Water Treatment Plant WTP & Mt. Coffee Hydro Power Plant MCHPP to Congo town . Specifically, the
primary controls can be located on the compound of LWSC treatment plant and the MCHPP staff
compound and the secondary controls are located at secure places around the communities in the urban
areas. Each of the bench marks has a unique inscription boldly written on top of the pillar for easy
identification. The figure below shows the locations of the bench marks on the google image.
Vegetation and Climate
The climatic conditions in Liberia allow the vegetation to develop into a tropical high forest, which most
probably covered the entire land area except a very narrow strip along the coast where mangrove
vegetation alternates with coastal Savannah.
Today, tropical high forest and old secondary forest cover only one-third of the country, while the
remaining 65% is composed of young secondary forest, intermediate forest and grass woodlands.
Although the general climatic conditions are nearly uniform throughout the country, rainfall and humidity
decrease toward the interior. Consequently, vegetation is banded into zones more-or-less parallel to the
coastline.
The project area falls within the Coastal Savannah of Liberia. These consist of low grasses with scattered
low trees. It also contains palm and coconut trees along with mangrove trees and Raphia palms (Wiles,
2005).
The climate of Liberia is marked by an even and fairly warm temperature throughout the year and above
all by the very high humidity, above 90% much of the time. Unlike the temperate zones, the seasons are
not determined by changing temperatures but by the prevailing precipitation.
Therefore, a rainy and a dry season with transitional periods can be differentiated. Rainfall is heavy and
intense. There is little year-to-year variability in the climate. The rainfall is heavier than on any other part
of the west coast of Africa. The annual rainfall near the coast is nearly 4550 mm (180 inches) but the
amount has exceeded this in some years. Generally, a fairly distinct dry season extends from about
November to April and a wet season the remainder of the year. The months of heaviest rainfall vary
somewhat in different parts of the country, but normally are June, July and September. The project area
falls within a tropical monsoon and is classified by Kӧppen and Geiger as Am. (Anon, 2017).
Project Code: File name: Date: SARI Consulting Ltd 142 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Figure 89
Project Code: File name: Date: SARI Consulting Ltd 143 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
ANNEX 4: MOBILIZATION
Project Staff
Management - Direction
Local Staff
Eng. Abel Folokulah- Local Project Manager
Eng. Seidu Tanko M. Rufai – Chief Surveyor
Eng. Isaac N. Vaye – Geotechnical Engineer
Mr. Andrew N.T. Sio Jr. – Environmental Expert
Eng. Austin Kerkula – Support Engineer
Working Group
Here below name and email addresses for the Working Group.
PIU/LWSC
"N. Pawon Boayue" <npboayue@yahoo.com>,
“Walker R Richards” wrrmonrovia@gmail.com
"Riggs Logan" riggslogan225@gmail.com
"Ka-Rufus Morris" morris123karu@gmail.com
"Zohn Doebo" zdoebo1982@gmail.com
SARI
Goffredo De Pascale g.depascale@sariltd.com
BK Boakai Kollie bkenterpriselib@gmail.com
Fabio Nigrelli f.nigrelli@sariltd.com
Luca Boccardi l.boccardi@sariltd.com
Valter Santoro v.santoro@sariltd.com
IIU/MPW
Emmanuel K. Baker emmanuel.baker.sre@iiu-mpw.org
Geoff Arnold Geoff.Arnold@imcworldwide.com
Shaun Pearton Shaun.Pearton@imcworldwide.com
Augustine K. Maimie: augustine.kmaimie@yahoo.com
Stakeholders Consultations
For the leg between Red Light and ELWA junction LWSC expressed the urge to get the cross sections for
the lodgment of the new pipeline, namely for the span between Red Light Market and the sta where the
already built platform ends. Restricted timeline was recommended to the Consultant, in order to let the
Client start the bidding procedure before March 2022. The solution to be proposed will foresee a box
culvert located under the footery. For the trunk whose platform has been already built, the alignment of
the new pipeline shall step away the right – west – edge of the roadway in order not to interfere with the
Electric Sub Station of LEC and the close school complex.
Project Code: File name: Date: SARI Consulting Ltd 144 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
The evaluation for each solution is based on parametric unit cost and on similar projects in the area
SOLUTION B
NEW PIPELINE REPLACEMENT
Cost per meter of new transmission line Unit Qty Unit price US$ Total - US$ Km Total - US$
Area preparation Lump 1 20.00 20.00
Excavation sq mt 10 10.00 100.00
Bed filling and compaction cu mt 4 25.00 100.00
Pipe - supply and installation Mt 1 500.00 500.00
Filling back cu mt 5 15.00 75.00
Reinforced concrete culvert– broken cu mt 0.1 280.00 28.00
down on the pipeline
Total 823.00
Contingency and overheads 20% 164.60
Project Code: File name: Date: SARI Consulting Ltd 145 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
ANNEX 5B_Solution MSRF-Type A: replacing of the 36” existing pipe + realization of a 3.2 MGD reservoir in town at Morison farm +
Double pipe to Paynesville reservoir
SOLUTION MSRF-TYPE A
NEW PIPELINE REPLACEMENT AND MONUT SOUTH RESERVOIR IN MORISON FARM WITH CONNECTION PIPELINE TO PAYNESVILLE
Cost per meter of new transmission line Unit Qty Unit price US$ Total - US$ Km Total - US$
Area preparation Lump 1 20.00 20.00
Excavation sq mt 10 10.00 100.00
Bed filling and compaction cu mt 4 25.00 100.00
Pipe - supply and installation mt 1 500.00 500.00 12 000 000.00
Filling back cu mt 5 15.00 75.00
Reinforced concrete culvert – broken cu mt 0.1 280.00 28.00
down on the pipeline
Total 823.00
Contingency and overheads 20% 164.60
987.60 28 500.00 28 146 600.00
New reservoir 3.2MG=12kmc Lump 1 7 000 000.00 7 000 000.00 7 000 000.00
Connection to Paynesville pipeline mt 5 000.00 150.00 750 000.00 750 000.00
Grand total 35 896 600.00
Project Code: File name: Date: SARI Consulting Ltd 146 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
ANNEX 5C_Solution MSRF-Type B: replacing of the 36” existing pipe + realization of a 3.2 MGD reservoir in town at Morison farm +
booster to Paynesville reservoir
SOLUTION MSRF-TYPE B
NEW PIPELINE REPLACEMENT AND MONUT SOUTH RESERVOIR IN MORISON FARM WITH BOOSTER AT THE CONNECTION PIPELINE TO
PAYNESVILLE
Cost per meter of new transmission line Unit Qty Unit price US$ Total - US$ Km Total - US$
Area preparation Lump 1 20.00 20.00
Excavation sq mt 10 10.00 100.00
Bed filling and compaction cu mt 4 25.00 100.00
Pipe - supply and installation mt 1 500.00 500.00 12 000 000.00
Filling back cu mt 5 15.00 75.00
Reinforced concrete culvert– broken cu mt 0.1 280.00 28.00
down on the pipeline
Total 823.00
Contingency and overheads 20% 164.60
987.60 28 500.00 28 146 600.00
New reservoir 3.2MG=12kmc Lump 1 7 000 000.00 7 000 000.00 7 000 000.00
Supply and installation of a Booster with Lump 1 150 000.00 150 000.00 150 00.00
its appurtenances
Grand total 35 296 600.00
Project Code: File name: Date: SARI Consulting Ltd 147 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
SOLUTION PV
PHOTOVOLTAIC PLANT AT WHITE
PLAINS WATER TREATMENT PLANT
Unit Qty Unit price - US$ Total - US$
Supply and installation of solar panel kW 1 600.00 1 060.00 1 696 000.00
for an overall Peak Power of 1 MW
General electric connections - inverters Lump 1.00 350 000.00 350 000.00
– accumulators
Complementary works - preparation, Lump 1.00 500 000.00 500 000.00
supports, connections
Total 2 546 000.00
Contingency and overheads 20% 509 200.00
3 055 200.00
Project Code: File name: Date: SARI Consulting Ltd 148 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Project Code: File name: Date: SARI Consulting Ltd 149 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22
LIBERIA Replacement of the 36-Inch Main Transmission Line which transports Document Title
(LWSC) treated water form White Plains Water Treatment Plant to Monrovia Detail Feasibility Study
Project Code: File name: Date: SARI Consulting Ltd 150 Page
LR_004_WS_03 Libacq-FS-report-REV 10/01/22