Professional Documents
Culture Documents
B05162-CLK-XX-XX-RP-FH-1001
Bicester Nominees Ltd and Bicester II Nominees Ltd
MULTIDISCIPLINARY ENGINEERING CONSULTANTS
Contents
1 Introduction ............................................................................................................................ 5
1.1 Overview .................................................................................................................................... 5
1.2 Site Location and Description..................................................................................................... 5
1.3 Proposed Development.............................................................................................................. 6
1.4 Objectives ................................................................................................................................... 6
1.5 Limitations .................................................................................................................................. 6
2 Planning and Flood Risk Policy Review...................................................................................... 7
2.1 Overview of National Planning Policy Framework (NPPF) ......................................................... 7
2.1.1 Sequential Test Process .................................................................................................... 7
2.1.2 Development Vulnerability, Flood Zone Compatibility and the Exception Test ............... 8
2.1.3 Design Flood Event ............................................................................................................ 9
2.1.4 Surface Water Runoff Disposal Hierarchy ......................................................................... 9
2.2 Flood Risk Assessment Requirements ........................................................................................ 9
2.3 Relevant Local Planning Policy ................................................................................................. 10
2.3.1 Cherwell Local Plan 2011 - 2031 – Policy ESD 6 .............................................................. 10
2.3.2 Cherwell Level-1 SFRA (2017) ......................................................................................... 11
2.3.3 Cherwell Level-2 SFRA (2017) ......................................................................................... 11
2.3.4 Oxfordshire Local Flood Risk Management Strategy ...................................................... 11
3 Background Information ........................................................................................................ 12
3.1 Site Levels ................................................................................................................................. 12
3.2 Existing Drainage ...................................................................................................................... 12
3.3 Hydrology ................................................................................................................................. 12
3.4 Geology, Groundwater and Soils.............................................................................................. 13
4 Flood Risk Assessment ........................................................................................................... 14
4.1 Flood Zones and Development Compatibility .......................................................................... 14
4.2 Impact of Climate Change ........................................................................................................ 15
4.3 Fluvial Flood Risk ...................................................................................................................... 16
4.4 Other Sources of Flood Risk ..................................................................................................... 17
4.4.1 Ordinary Watercourse Flooding ...................................................................................... 17
4.4.2 Groundwater Flooding .................................................................................................... 17
4.4.3 Sewer Flooding ................................................................................................................ 18
4.4.4 Surface Water Flooding................................................................................................... 18
4.4.5 Flooding from Artificial Infrastructure Failure ................................................................ 19
4.5 Impact of Development on Flood Risk Elsewhere.................................................................... 20
4.6 Cumulative Impact on Flood Risk ............................................................................................. 20
4.7 Safe Access and Egress ............................................................................................................. 21
4.8 Mitigation and Management Requirements ............................................................................ 21
4.9 Summary Table ......................................................................................................................... 23
5 Summary & Conclusion .......................................................................................................... 24
Executive Summary
The previous FRA (WB02669 – R002) submitted a 1% AEP plus climate change
flood level of 66.02m AOD, derived from modelling undertaken by Buro Happold
in 2009 for the Phase 3 development. This was duly accepted by Cherwell District
Council and the EA. As the EA’s data has not been updated since this time, there
is no reason for the previous decision to be overturned.
A 1% AEP + climate change level of 66.02m AOD would relate to a flood depth of
0.62m at the Site. In accordance with the FD2320/TR2 hazard method, this would
pose a ‘Danger to most’ hazard (which includes the general public). As was put
Flood Sources &
forward in the previous FRA (WB02669 – R002), the 66.02m AOD level is used as
Flood Risk
the ‘design flood’ level here to present a worst-case scenario of a blockage in the
service tunnel and failure of the pumping station. It is therefore judged that
fluvial flood sources pose a moderate risk to the Site.
The Proposal is located within an area at low risk of surface water flooding. This
represents an area with a 0.1 – 1% annual probability of flooding. However, the
EA surface water flood model does not take into account the existing positive
drainage network. The service tunnel and pumping station would also likely
Flood risk from artificial sources, sewers and ordinary watercourses have been
discounted as it has been assessed to be negligible.
The flood risk management hierarchy found in Section 5 of BS 8533:2017 has
been applied to determine the most appropriate mitigation measures for the
scheme. Broadly, the Site is considered to be safe from all forms of flooding;
however, precautionary mitigation measures have still been recommended.
Groundwater flood risk should be considered, particularly during construction
where excavated areas may experience groundwater emergence. To mitigate
this, relevant contractor health and safety procedures for working in confined
spaces and below ground level should be in place. In extreme cases,
Flood Risk
dewatering/pumping may be required to remove any groundwater present.
Management
Measures
The Proposal is calculated to displace 2.63m3 of the existing “natural” storage
based on the flow associated with design flood event (1% AEP + cc) for the Town
Brook’s. While this is regarded as a relatively minor impact, this volume of “lost”
storage will be compensated for by the excess volume already provided as
compensation for Unit 110.
Additionally, it is assessed that the Proposal will not re-direct or obstruct flows
during this time.
1 Introduction
1.1 Overview
Clarkebond (UK) Ltd was commissioned by Bicester Nominees Ltd and Bicester II Nominees Ltd
to provide a Flood Risk Assessment (FRA) to support a full planning application for the
installation of a fence at the south service yard of Bicester Village (the “Proposal”).
The report has been undertaken in accordance with flood risk policy contained within the
National Planning Policy Framework (NPPF, 2019) and guidance found in the Flood Risk and
Coastal Change National Planning Policy Guidance (NPPG). The assessment of flood risk was
informed by the Level-1 Strategic Flood Risk Assessment (SFRA) 2017 for the Local Planning
Authority (LPA) Cherwell District Council, Lead Local Flood Authority (LLFA) Oxfordshire County
Council documents, Environment Agency (EA) data and information available on government
websites.
The main purpose of this report is to provide sufficient flood risk information to ensure the
development is safe from flooding and would not pose a risk to third parties.
1.4 Objectives
The main objectives of this FRA report, as recommended in the NPPF, are:
• To assess the site suitability in terms of the Sequential Test and, if required, the Exception
Test;
• To identify the probability of flooding at the development;
• To assess the compatibility of the development with the flood risk zone;
• To identify the consequence of flooding at the development and suitable mitigation
measures if required;
• Demonstrate that the development will not increase flood risk elsewhere, and where
possible, will reduce flood risk.
1.5 Limitations
The information, views and conclusions drawn concerning the site are based, in part, on
information supplied to Clarkebond by other parties. Clarkebond has proceeded in good faith on
the assumption that this information is accurate. Clarkebond accepts no liability for any
inaccurate conclusions, assumptions or actions taken resulting from any inaccurate information
supplied to Clarkebond from others.
The process for undertaking the Sequential Test is shown in Figure 2. Flood Zones 1-3 relate to
the risk of flooding from Main Rivers (rivers managed by the EA) and the sea, and are used as
the primary indicator of whether land is suitable for development. Table 1 (taken from Table 1
of NPPG) details the corresponding meaning of flood zones in relation to flood risk.
The Sequential Test is considered to be passed if a site is within Flood Zone 1 or has been
allocated in the Council’s Local Plan where the Sequential Test has already been undertaken. If
neither of these applies, a Sequential Test is required to demonstrate that there are no other
available and suitable sites at a lower risk of flooding.
2.1.2 Development Vulnerability, Flood Zone Compatibility and the Exception Test
After undertaking the Sequential Test, the vulnerability of development to flooding must be
considered so that more vulnerable uses are given priority for lower risk land. This exercise is
undertaken by making reference to Table 2 (Paragraph 066) of NPPG which shows the
vulnerability classifications of various land use types and Table 3 (Paragraph 067) of NPPG which
shows the compatibility of the different vulnerability categories with the Flood Zones and
requirements for the Exception Test.
If a site has a range of flood zones, a sequential approach to development should also be taken
within the site itself to direct development to the areas of lowest flood risk (Flood Zone 1 first,
followed by Flood Zone 2, and finally Flood Zone 3). If it isn’t possible to locate all of the
development in Flood Zone 1, then the most vulnerable elements of the development should be
located in the lowest risk parts of the site (unless there is an overriding reason to choose a
different location).
Certain development may require an Exception Test before it is considered acceptable in Flood
Zones 2 and 3. To pass this test, the following needs to be demonstrated:
1. The development provides wider sustainability benefits to the community that outweigh
flood risk, informed by a Strategic Flood Risk Assessment where one has been prepared;
and
2. the development will be safe for its lifetime taking account of the vulnerability of its users,
without increasing flood risk elsewhere, and, where possible, will reduce flood risk overall.
The development should be flood resistant and resilient including having safe access and escape
routes for the following extreme flood events, also known as the ‘design flood’ (taken from
Paragraph 055 of NPPG):
Climate change is projected to increase the likelihood of flooding from most flood sources and
therefore an assessment of the effects of climate change should be considered over the
estimated development lifetime.
The lifetime of the fence is estimated to be 30 years. Therefore from an assumed date of
construction in 2020, this means assessing the flood risk at the Site to 2050.
Surface water drainage from the proposed development must be dealt with in accordance with
the following hierarchy taken from Paragraph 080 of NPPG:
Guidance on how surface water runoff should be managed, notably the discharge rate with
which is can leave a development site, is taken from the ‘Non-Statutory Technical Standards for
Sustainable Drainage Systems’ (2015).
Footnote 50 of the NPPF states that a site-specific FRA is required for developments which:
• Could be affected by sources of flooding other than rivers and the sea (e.g. surface
water drains, reservoirs) where a development will introduce a more vulnerable use.
The focus of FRAs for the higher risk zones is to fully assess the extent, depth and hazard of
flood waters, detail the required mitigation to manage flood risk (e.g. floor levels and access,
evacuation routes, compensatory storage) and outline a surface water management plan. FRAs
for sites where the risk of flooding from rivers or the sea is classified as low (Flood Zone 1) will
still need to assess all other sources of flood risk, but will have a strong focus on management of
surface water runoff.
Local planning policy provides more specific detail on development requirements based on the
flood risk in the local county or borough. Although these policies will broadly be in line with
national policy, where additional requirements are required this will take precedence.
A list of relevant planning policy documents that were consulted during this FRA include:
The Local Plan was adopted in July 2015 and forms the core of the Local Development
Framework for Cherwell District Council. The key policy relating to flood risk is ‘Policy ESD 6
Sustainable Flood Risk Management’ (Figure 3), which is broadly in line with current national
policy however provides some additional detail and requirements. Other policies such as ‘Policy
ESD 7: Sustainable Drainage Systems (SuDS)’ are also relevant in the management of flood risk.
3 Background Information
3.1 Site Levels
A topographic survey was carried out by Tower Surveys in March 2010, covering the entire
Bicester Village Site. This can be found in Appendix B.
The existing ground level of the area ranges from 65.4 – 65.5m AOD. This is generally >100mm
higher ground than the service yard to the west.
The existing drainage can be determined from the Bicester Village Phase 3 layout drawn by
Faber Maunsell in 2006, provided in Appendix C.
This shows the Site to drain via several high capacity channels to two linear concrete
attenuation tanks before out-falling into the Town Brook. There are no third-party or public
sewers identified within the south service yard.
3.3 Hydrology
According to the EA’s ‘Main Rivers Map’ and ‘Catchment Data Explorer’, the Site is located
within the catchment of a main river, the Town Brook. A main river refers to those watercourses
under the jurisdiction of the EA. Figure 4 shows the extent of the catchment boundary.
As discussed in Section 3.1, the Site is generally sloped to the west where the service yard sits in
a relatively low area. However, water draining to here would be captured by the existing
drainage network outlined in Section 3.2.
The geology of the Site is shown on the 1:50,000 scale British Geological Survey (BGS) map and
on the BGS website’s Geology of Britain viewer. A review of the available data indicates the
anticipated geology at the Site can be summarised as follows:
Superficial Deposits
• Alluvium – comprising Clay, Silt, Sand and Gravel. This is considered to be a Secondary A
Aquifer.
Bedrock
• Kellaways Clay Member – comprising Mudstone, which is considered to be an
unproductive aquifer.
According to ‘Magic’ maps, the Site is not located in a groundwater vulnerability area or within a
Source Protection Zone (SPZ).
According to LandIS ‘Soilscapes’, the Site is underlain by ‘Soilscape 18’: this comprises slowly
permeable, seasonally wet, slightly acid but base-rich loamy and clayey soil’. This area is known
to have impeded drainage and is likely to drain to a stream network, rather than groundwater. A
review of available historic borehole data does not indicate a high groundwater table.
Figure 5: EA 'Flood Map for Planning'(Light Blue = Flood Zone 2, Dark Blue = Flood Zone 3)
As it is the LPA that provides distinction between Flood Zone 3a and 3b, the Level-1 SFRA (2017)
was consulted. As shown in ‘Figure B6-J’ (Appendix D), the Site is located in Flood Zone 3b. This
equates to an area with a greater than 5% annual exceedance probability (AEP), or an area
where flood water needs to be stored during extreme events i.e. the functional floodplain.
Flood Risk
Essential Water Highly More Less
Vulnerability
Infrastructure Compatible Vulnerable Vulnerable Vulnerable
Classification
Zone 1
Exception
Zone 2
Test required
Flood Zones
Where means the development is appropriate and X means the development should not be permitted
EA guidance on climate change allowances to support the NPPF came into effect in February
2016. The Site is situated within the Thames River Basin district with a development lifespan of
~30 years up to 2050. Based on NPPG guidance for ‘Water Compatible’ development in Flood
Zone 3b, the central allowance should be used as shown in Table 3.
Table 3: Peak River Flow Allowances for Thames River Basin District
Table 4 shows the recommended allowances for peak rainfall intensity for different statistical
likelihoods. The upper end allowance should be used in areas where there are known flooding
issues and there is highly vulnerable development in the downstream sewer network.
This provided a flood level for a range of different probability events, as shown in Table 5. This
included the 1 % AEP event with a 20% allowance for climate change, which exceeds the 15%
that would be required.
Table 5: Flood Level Data from the ‘Landford Brook (Bicester) & Pingle-Back-Bure 2010’ Model
In relation to the existing ground levels at the Site, this would equate to a flood depth of a
maximum of 1.3m and 1.7m during a 5% AEP event and 0.1% AEP event, respectively. In
accordance with the FD2320/TR2 hazard method (Figure 6), this could pose a ‘Danger to all’
hazard (which includes the emergency services).
However, the previous FRA (WB02669 – R002) submitted a 1% AEP plus climate change flood
level of 66.02m AOD, derived from site specific hydraulic modelling undertaken by Buro Happold
in 2009 for the Phase 3 development. This was accepted by Cherwell District Council and the EA.
As the EA’s product 4 data has not been updated since that time, there is no valid reason for the
EA not to accept the flood level data contained in the previous FRA submission.
A 1% AEP + climate change level of 66.02m AOD would relate to a flood depth of 0.62m at the
Site. In accordance with the FD2320/TR2 hazard method, this would pose a ‘Danger to most’
hazard (which includes the general public).
In practice, depths above 65.60m AOD is not considered likely as flood water would flow away
from the Site via the service tunnel below the A41 (connecting to south of the service yard). The
pumping station can also extract water from the Site at 3.8 l/s which also assists with the
drainage of the service yard. A flood level of 65.60m AOD would relate to a depth of 200mm,
posing a low hazard.
As was put forward in the previous FRA (WB02669 – R002), the 66.02m AOD level is used as the
‘design flood’ level here to present a worst-case scenario of a blockage in the service tunnel and
failure of the pumping station. It is therefore judged that fluvial flood sources pose a moderate
risk to the Site (taking into account the low vulnerability of the development).
According to the EA’s historic flood map, there is no record of past flooding at the Site.
Groundwater flooding typically occurs when water levels rise up above surface elevations from
underlying rocks or springs following prolonged rainfall. The two most common mechanisms of
groundwater flooding are:
permeable and impermeable strata (where the groundwater table is naturally closer to the
ground surface).
The Level-1 SFRA provides a general assessment of groundwater flood risk in Cherwell, providing
a map of 1km2 grid areas with varying susceptibility to groundwater (Appendix F). The Site is
located in an area where between 25 – 50% of the land is susceptible to groundwater flood risk.
It should be noted that this provides an assessment of the ability for groundwater to emerge
(based on ground conditions) and not the probability of occurrence. The presence of historic
flooding provides a better measure of probability.
As discussed in Section 3.4, the underlying bedrock does not have significant groundwater
present. However, the superficial deposits atop the bedrock may have groundwater storage
potential.
While this gives an indication of where the conditions conducive for groundwater emergence
are, it is an unreliable assessment of groundwater flood risk. A more reliable measure of
groundwater flood risk is whether there have been recorded groundwater flood events in the
past. The Level-1 SFRA makes no mention of any recorded flood events within the vicinity of the
Site attributed to groundwater.
As the Proposal will not be developing in a manner sensitive to groundwater flooding (such as
basement dwelling etc.), nor does the geology suggest a high groundwater presence, the risk
from groundwater flooding is considered to be low.
Thames Water is the statutory water undertaker and keeps a record of historic sewer flood
events in a database called the DG5 register. According to data presented in the Level-1 SFRA,
taken from the DG5 register, there have been 0-5 reported flood incidents in Bicester. It should
be noted the DG5 register provides a ‘snapshot’ in time and will be outdated by the addition of
new properties. However new properties may in fact create betterment, from both application
of the SuDS Hierarchy and the potential for capital investment in the public sewer system.
It has been established that based on historic flood records the probability of sewer flooding is
low at the Site. The prevailing topography indicates that if sewer flood water emerged from the
manholes/inspection chambers in the service yard, they would not preferentially flow towards
the Site, as it is situated at a higher elevation.
For the reasons discussed, and the relationship between probability and impact, the baseline
risk to the Site from sewer flooding is determined to be negligible.
Surface water flooding is caused by heavy rainfall events that cause significant surface runoff
and ponding of accumulated water. The probability and impact of flooding is heavily dependent
on the topography of a site, as well as the ground conditions and its infiltration capability. The
EA states that “flooding from surface water is difficult to predict as rainfall location and volume
are difficult to forecast”.
Figure 7: EA Surface Water Flood Map (Light Blue = Low Risk, Blue = Medium Risk, Dark Blue = High Risk)
As can be seen from the EA surface water flood map (Figure 7), the Proposal is located within an
area at low risk of surface water flooding. This represents an area with a 0.1 – 1% annual
probability of flooding.
It should be noted that the EA surface water flood model does not take into account existing
positive drainage, which as discussed in Section 3.2 the Site benefits from. Furthermore the
service tunnel and pumping station would likely reduce surface water flooding at the Site.
Therefore the risk from surface water flooding to the Site is considered to be low.
The proposed development site is not within an area at risk of flooding from reservoirs,
therefore the risk posed to the site from Artificial Infrastructure Failure is none.
The Site is assessed to be at risk from the 1% AEP fluvial flood event with an allowance for
climate change, referred to as the ‘design flood event’. If left unmitigated, any changes on Site
could displace or re-direct floodwater during this event. In terms of displacement, the volume of
the fence is calculated to be 2.63m3 assuming a flood depth of 0.62m. This is for both the
bracing legs and supporting columns of the fence as well as the Armco protective barrier; see
calculations below:
Fence Bracing Legs = (0.1m x 0.06m cross section) x 0.62m depth x 21 structures
Fence Columns = (0.23m x 0.075m cross section) x 0.62m depth x 21 structures
Armco Standard Beam = (0.085m x 0.31m cross section) x 85 estimated barrier length
Armco RSJ Post = (0.127m x 0.087m cross section) x26 posts x 0.31m height
As was agreed in the previous FRA (WB02669 – R002), this is considered to be a very minor
displacement of water having a negligible effect on the overall flood level. However, to be in line
with EA policy, compensatory storage is discussed in Section 4.8.
In terms of re-direction of flows, the fence design allows for the bottom of the fence to be ~3m
above ground level (raised on columns). As was previously agreed, a flood depth of 0.62m would
be allowed to pass freely underneath the fence. Therefore, the Proposal will not obstruct or re-
direct flood water. Pathways for water to enter and exit the service yard (i.e. the service tunnel)
will remain unaltered.
As the Site is currently impermeable, the Proposal will not adversely affect surface water flood
risk elsewhere by increasing impermeable area. Typically a fence may present a barrier to flows
and therefore re-direct them elsewhere. However, as the fence is to be elevated on columns,
flows will be allowed to pass underneath the fence in its existing manner.
The majority of the existing Town Brook upstream catchment and floodplain is developed;
therefore there are few opportunities for new development to have a significant impact on
flood risk (i.e. increase impermeable area). In fact, new development would be expected to
create an improvement through the implementation of recent policy and best-practise (e.g.
SuDS).
Access and egress from the south service yard is possible to the west, towards Bicester Village.
The Site is approximately 100m from Flood Zone 1, which represents approximately 1 minute of
walking. As there will be no cause for any vulnerable people to be at the Site (e.g. elderly,
infirm), it is thought that safe access and egress is possible from the Site.
Flood risk mitigation and management measures for the development are determined by way of
the hierarchical process outlined in Section 5 of the BS 8533:2017 ‘Assessing and Managing
Flood Risk in Development – Code of Practice’. Application of this hierarchy is as follows:
3. Stage 3 – Substitution:
It is not possible to substitute the development without compromising the utility of the
Proposal.
6. Stage 6 – Safety:
Safe access and egress is possible to and from the Site, as there is an un-impeded route
100m west of the Site to Flood Zone 1.
As discussed in Section 4.5, it is calculated that the Proposal would displace 2.63m3 of
floodwater if unmitigated. While this represents a minor impact to the floodplain, in line with EA
guidance this should be compensated for. It was previously agreed that the excess
compensatory storage proposed for Unit 110, which equalled 8m3, would be able to
accommodate the displacement caused by the fence. See Appendix G for Unit 110
compensatory storage.
Broadly, the Site is considered to be safe from all forms of flooding. Groundwater flood risk
should however be taken into consideration, particularly during construction where excavated
areas may experience groundwater emergence. To mitigate this, relevant contractor health and
safety procedures for working in confined spaces should be in place. In extreme cases,
dewatering/pumping may be required to remove any groundwater present.
Current
Flood Source Level of Mitigation Required Residual Risk
Risk
Fluvial None Required
Ordinary
Watercourse
Sewer
Artificial
Infrastructure
Flood Risk to
Utilise excess compensatory storage
Elsewhere
The EA ‘Flood Map for Planning’ shows that the Site is located within Flood Zone 3b. This means
the Site has an annual exceedance probability (AEP) of flooding greater than 5% (1 in 20 year
return period) from fluvial sources.
The previous FRA (WB02669 – R002) submitted a 1% AEP plus climate change flood level of
66.02m AOD, derived from modelling undertaken by Buro Happold in 2009 for the Phase 3
development. This was duly accepted by Cherwell District Council and the EA. As the EAs data
has not been updated since this time, there is no reason for the previous decision to be
overturned.
A 1% AEP + climate change level of 66.02m AOD would relate to a flood depth of 0.62m at the
Site. In accordance with the FD2320/TR2 hazard method, this would pose a ‘Danger to most’
hazard (which includes the general public). As was put forward in the previous FRA (WB02669 –
R002), the 66.02m AOD level is used as the ‘design flood’ level here to present a worst-case
scenario of a blockage in the service tunnel and failure of the pumping station. It is therefore
judged that fluvial flood sources pose a moderate risk to the Site.
As the Proposal will not be developing in a manner sensitive to groundwater flooding (basement
dwelling etc.), nor does the geology suggest a high groundwater presence, the risk from
groundwater flooding is considered to be low.
The Proposal is located within an area at low risk of surface water flooding. This represents an
area with a 0.1 – 1% annual probability of flooding. However, the EA surface water flood model
does not take into account existing positive drainage, the service tunnel and pumping station
would likely reduce surface water flooding at the Site.
Flood risk from artificial sources, sewers and ordinary watercourses have been discounted or
considered negligible.
The Proposal is calculated to displace 2.63m3 of the Town Brook’s design flood event. While this
is regarded as a relatively minor impact, this will be compensated for by the excess volume
already provided as compensation for Unit 110. Additionally, it is assessed that the Proposal will
not re-direct or obstruct flows during this time.
This report has satisfied the objectives set in Section 1.4, demonstrating that the Site is not at a
significant level of flood risk from any of the sources of flood hazards assessed and that the
Proposal will not increase flood risk elsewhere. Appropriate mitigation and flood management
measures have been recommended for the proposed development.
Ordnance Survey 1:25k colour raster base mapping; If you will be carrying out computer modelling as part of your Flood Risk
Flood Zone 2 and Flood Zone 3; Assessment, please read the enclosed guidance which sets out our
Relevant model node locations and unique identifiers (for cross referencing to the water requirements and best practice for computer river modelling.
levels, depths and flows table);
Model extents showing defended scenarios; This information is based on that currently available as of the date of this
FRA site boundary (where a suitable GIS layer is supplied); letter. You may feel it is appropriate to contact our office at regular intervals,
Flood defence locations (where available/relevant) and unique identifiers; (supplied to check whether any amendments/ improvements have been made. Should
separately) you re-contact us after a period of time, please quote the above reference in
Flood Map areas benefiting from defences (where available/relevant); order to help us deal with your query.
Flood Map flood storage areas (where available/relevant);
Historic flood events outlines (where available/relevant, not the Historic Flood Map) and This information is provided subject to the enclosed notice which you should
unique identifiers; read.
Statutory (Sealed) Main River (where available within map extents); This letter is not a Flood Risk Assessment. The information supplied can be
used to form part of your Flood Risk Assessment. Further advice and guidance
regarding Flood Risk Assessments can be found on our website at
A table showing:
i) Model node X/Y coordinate locations, unique identifiers, and levels and flows for http://www.environment-agency.gov.uk/research/planning/82584.aspx
defended scenarios.
ii) Flood defence locations unique identifiers and attributes; (supplied seperately) If you would like advice from us regarding your development proposals you
iii) Historic flood events outlines unique identifiers and attributes; and can complete our pre application enquiry form which can be found at
iv) Local flood history data (where available/relevant).
http://www.environment-agency.gov.uk/research/planning/33580.aspx
Kilometres
0 0.09 0.18
Legend
Main River
Flooding from rivers or sea (FZ3)
Extent of extreme flood (FZ2)
© Environment Agency copyright and / or database rights 2015. All rights reserved. © Crown Copyright and database right. All rights reserved. Environment Agency, 100024198, 2015.
Contact Us: National Customer Contact Centre, PO Box 544, Rotherham, S60 1BY. Tel: 08708 506 506 (Mon-Fri 8-6). Email: enquiries@environment-agency.gov.uk
Defence information THM_76896
Description: This location is not currently protected by any formal defences and we do not currently have any flood alleviation
works planned for the area. However we continue to maintain certain watercourses and the schedule of these can
be found on our internet pages.
Description: The information provided is from the Langford Brook (Bicester) & Pingle-Back-Bure 2010 detailed mapping
project. The study was carried out using 2D modelling software (ISIS-Tuflow).
Mapped Outputs:
1 in 5 / 20% AEP; 1 in 20 / 5% AEP; 1 in 50 / 2% AEP; 1 in 100 / 1% AEP; 1 in 100+20% / 1% AEP with climate
change and 1 in 1000 / 0.1% AEP
Model accuracy:
Levels ± 250mm
Kilometres
0 0.09 0.18
Flood Zone 1
Legend
Flood Point 2
Main River
!
( 20% AEP
!
( 5% AEP
1% AEP
!
( 0.1% AEP
Flood Point 3
© Environment Agency copyright and / or database rights 2015. All rights reserved. © Crown Copyright and database right. All rights reserved. Environment Agency, 100024198, 2015.
Contact Us: National Customer Contact Centre, PO Box 544, Rotherham, S60 1BY. Tel: 08708 506 506 (Mon-Fri 8-6). Email: enquiries@environment-agency.gov.uk
Modelled floodplain flood levels THM_76896
The modelled flood levels for the closest most appropriate model grid cells for your site are provided below:
Flood Event Code Flood Event Name Start Date End Date Source of Flooding Cause of Flooding
No Historic Data
Please note the Environment Agency maps flooding to land not individual properties. Floodplain extents are an indication of the geographical extent of a
historic flood. They do not provide information regarding levels of individual properties, nor do they imply that a property has flooded internally.
Start and End Dates shown above may represent a wider range where the exact dates are not available.
0 5
N
Legend
KILOMETRES
Client
t
___I Cherwell District Boundary Areas Suscept ib le to Gro undwater Flooding THIS DOCUMENT HAS BEEN PREPARED IN
ACCORDANCE WITH THE SCOPE OF AECOM'S
Cherwell
I<25 percent APPOINTMENT WITH ITS CLIENT AND IS DI STRICT COUNI ~
b > d Level 1 SFRASites :=~
I>=25 percent <SO percent AECOM ACCEPTS NO LIABILITY FOR ANY USE OF
THIS DOCUMENT OTHER THAN BY ITS CLIENT
NORl H O XFORDSl'tlRE
Drawing Status
:====: AND ONLY FOR THE PURPOSES FOR WHICH IT
WAS PREPARED AND PROVIDED.
~-I >=50 percent<75 percent @AECOM INFRASTRUCTURE & ENVIRONMENT
FINAL
UK LTD 2017
0."lle Suflii, AECOM ln friStuc'~ &. Envlronmonl UK lld
- >=75 percent
JCJbTitle
CHERWELL LEVEL 1
Copyr{ghl
© Copyr1ght. All figM• reserved. Environment Agency 2016.
Drawing Tiiie
-~.41 ScaleatA3: AS SHOWN
Drawn RS .Approved MT Date os-2011
::fc'f:'.n.
;18Sl- ~'7SlB
~
~ ' AECOM..
AREAS SUSCEPTIBLE
This map ts based upon Ordnance SUtYey matefial With the behalf al the Controller f~1
STRATEGIC FLOOD RISK ot H"' ~J$Sly' S<all""..Y Orlloa. Cl Crtw1n copyrlg h~ Unaull\Oti•ed reP'Odur.OOn TO GROUNDWATER Notes FuonAsnm
lnllinges Crown cop ytlg~I and may lea<I lo prosecullon or dvlt proceedlf19S. THIS DRAWING MAY BE USED ONLY FOR
ASSESSMENT UPDATE Ct..twGll O!!W1d Coone!! . llcenoe No. 100024316, 20 16. FOODING (ASTGWF) THE PURPOSE INTENDED Drawing Numlier Rev
FIGURE 88
Plot Dale: 17/0512017
FJlepath: \\Ch·wip-001\CH_Water\Projects\60494538 - Cherwell l 1 SFRA Upoate\0000 GIS_Data\01-WIPl01_02-0ata_Worklng1WOR\Flg 08 - AStGWF w o~
MULTIDISCIPLINARY ENGINEERING CONSULTANTS
23
UNIT 111 VOID
FLAT ROOF
4A 24A 4A FFL: +75.575
24978
12415
Extent of mezzanine above
UNIT 110
15190
15190
UNIT 110 VOID (MEZZANINE)
FLAT ROOF
FFL: +75.575
9900
FFL: +66.775 FFL: +70.775
24228 24228
UP
2 2 2
P-2207 P-2207 P-2207
UNIT 108
(MEZZANINE)
SERVICE
YARD
FFL +65.350
SERVICE SERVICE
YARD YARD
10000
P-2204 - Proposed Ground Floor Plan P-2204 - Proposed Mezzanine Floor P-2204 - Proposed Roof Plan
1 1 : 200 2 1 : 200 3 1 : 200 N
0 2 8m
APPROXIMATE
NORTH
1:200
LYONS+SLEEMAN+HOARE Ltd
Job N Drg N Rev Scale Status Job
08/032 / P-2204 D NTS
As indicated WORK IN PROGRESS Bicester Village, Upgrades - Unit 110 Extension
tel: +44 (0)117 929 2244 tel: +44 (0)1392 369098 tel: +44(0)20 7939 0959
www.clarkebond.com