Professional Documents
Culture Documents
By Netsanet Zelalem
By
Netsanet Zelalem
August, 2008
CERTIFICATION i
CERTIFICATION
The undersigned certify that they have read the thesis: Integration of Hydropower
in the Ongoing Reservoirs Studies of Lake Tana Sub-Basin and here by
recommended for the acceptance by the Arba Minch University in partial
fulfillment of the requirements for the degree of Master of Science in Hydraulic
and Hydropower Engineering.
_____________________________
(Supervisor)
Date _________________________
____________________________
(External Examiner)
Date ________________________
____________________________
(Co-supervisor)
Date _______________________
____________________________
(Internal Examiner)
Date _______________________
I, Netsanet Zelalem Cherie, declare that this thesis is my own work and that it
has been presented and will not be presented by me to any other University for
similar or any other degree award.
Signature ________________________________
Date ________________________________
ABSTRACT
Currently, there are five reservoirs proposed for irrigation purpose only in Lake
Tana sub basin. These are: Gumera-A, Megech, Ribb, Gilgel Abbay-B and Jema.
Among these Megech, Ribb, Gumera-A and Gilgel Abbay-B are the focus of this
study. At Megech reservoir two alternatives are proposed. The first alternative is
for irrigation only and the second is for irrigation and water supply.
The proposed irrigation area of: Megech of alternative one is 14622 ha, Megech
of alternative two is 7311 ha, Ribb 19925 ha, Gumera 1400 ha and Gilgel Abbay-
B 12490 ha.
Final output from sequential routing shows the estimated firm power generation
of Gilgel Abbay-B, Megech alternative two, Gumera-A and Megech alternative
one is 5.614 Mw, 0.61 Mw, 0.13 Mw and 35kw respectively without affecting the
irrigable area. But, from the analysis one can see as the irrigable area decreases
the hydropower generation will increase and vice versa because of the rise of
reservoir water level.
Economic analysis is done for Megech reservoir to show the economic feasibility
of hydropower projects. The result from benefit-cost analysis shows that
hydropower projects have B/C ratio of 1.9 which indicates its feasibility, where as
for irrigation project B/C ratio 0.37 which is not economically feasible.
ACKNOWLEDGEMENT
DEDICATION
TO
TABLE OF CONTENTS
Page
CERTIFICATION……………………………………………………………………………………..i
DECLARATION AND COPYRIGHT ..................................................................................... ii
ABSTRACT………………………………………………………………………………….iii
ACKNOWLEDGEMENT ...................................................................................................... iv
DEDICATION…………………………………………………………………………………………v
TABLE OF CONTENTS ...................................................................................................... vi
LIST OF TABLES ................................................................................................................ ix
LIST OF FIGURES…………………………………………………………………………...x
LIST OF TABLES IN THE APPENDICES ............................................................................ xi
LIST OF FIGURES IN THE APPENDICES ........................................................................ xii
LIST OF ABBREVIATIONS AND ACRONYMS .................................................................. xiii
CHAPTER ONE ................................................................................................................... 1
INTRODUCTION ................................................................................................................. 1
1.1. Background ................................................................................................................. 1
1.2. Statement of the Problem ......................................................................................... 4
1.3. Objective of the Study................................................................................................ 5
1.3.1. General Objective .....................................................................................5
1.3.2. Specific Objective: ....................................................................................5
1.4. Scope and Limitation of the Study .......................................................................... 5
CHAPTER TWO................................................................................................................... 6
LITERATURE REVIEW ........................................................................................................ 6
2.1. General......................................................................................................................... 6
2.2. Irrigation Potentials and Extent of Exploitation in Ethiopia .................................. 7
2.3. Power Potentials and Extent of Exploitation in Ethiopia ...................................... 8
2.4. Power Generation from Irrigation Water Release ............................................... 11
2.5. Turbines ..................................................................................................................... 12
2.5.1. General ...................................................................................................12
2.5.2. Selection of Hydraulic Turbines ..........................................................13
2.6. Review of Previous Studies .................................................................................... 15
2.6.1. Design of Dams in Lake Tana Sub-Basin Projects (Gilgel Abbay, Megech
and Ribb )-WWDSE and TAHALE Pvt. Ltd .......................................................15
2.6.2. Gumera Irrigation Project –WWDSE and ICT Pvt. Ltd ............................15
2.6.3. Country Wide Master Plan Studies – EVDSA/WAPCOS (1988-90)........16
2.6.4. Study by BCEOM in Association with ISL and BRG 1999 ......................16
CHAPTER THREE ............................................................................................................. 18
STUDY AREA .................................................................................................................... 18
LIST OF TABLES
Page
Chapter One
TABLE:1. 1.ENERGY DEMAND PROJECTION (1990-2004) .................................................................................. 4
Chapter Two
TABLE: 2.1. THE OVERALL UNRESTRICTED FULL DEVELOPMENT POTENTIAL OF THE ABBAY BASIN.................... 8
TABLE: 2.2. HYDROPOWER POTENTIAL OF ETHIOPIA ........................................................................................... 9
TABLE: 2.3. MAIN FEATURES OF THE HYDROPOWER PLANT CURRENTLY IN OPERATION .................................. 10
TABLE: 2.4. TYPICAL KAPLAN TURBINE OPERATIONAL RANGE…………………………………………...…...14
Chapter Four
TABLE: 4. 1.SUMMARY OF COMPUTED EVAPORATION………………………………………………………..…32
TABLE: 4. 2. RAINFALL STATIONS IN THE STUDY AREA .................................................................................... ...32
TABLE: 4. 3. REPRESENTATIVE STATIONS OF THE RESPECTIVE PROJECTS ....................................................... 32
TABLE: 4. 4. STATIONS USED TO FILL MISSING RAINFALL AT BAHIR DAR GAUGING STATIONS .......................... 33
TABLE: 4. 5. RELATIVE CATCHMENT AREAS INFLUENCED BY EACH STATION ..................................................... 36
TABLE: 4. 6. ESTIMATED MEAN MONTHLY RAINFALL AT GILGEL ABBAY-B RESERVOIR ..................................... 37
TABLE: 4. 7. LOCATION OF STREAM FLOW GAUGING STATIONS IN THE STUDY AREA ....................................... 37
TABLE: 4. 8. DRAINAGE AREA AT DAM SITES AND STREAM GAUGING STATIONS ............................................... 41
TABLE: 4. 9. IRRIGATION WATER REQUIREMENT OF THE PROJECTS .................................................................. 43
Chapter Five
TABLE: 5. 1. ESTIMATED VALUES OF PARAMETERS FOR GILGEL ABBAY-B AND MEGECH ALTERNATIVE-2 ..... 49
TABLES: 5. 2A. PARAMETERS USED IN SSR FOR MEGECH ALTERNATIVE-2 ..................................................... 49
TABLE: 5.2B. SAMPLE SSR FORMAT FOR MEGECH ALTERNATIVE-2……………………………..………….50
TABLE: 5. 3. CHARACTERSTICS RANGE OF KAPLAN TURBINE………………………………………………......56
TABLE: 5. 4. INVESTMENT COST OF MEGECH IRRIGATIONPROJECT…………………………………………59
TABLE: 5. 5. COMPARISION OF INVESTMENT COST ON PROPOSED CROPS FOR MEGECH
IRRIGATION PROJECT………….………………………………………..…………………………….…60
CHAPTER SIX
TABLE: 6. 1. POWER GENERATION FROM OPTION-ONE ............................................................ 66
TABLE: 6.2. ESTIMATED VALUES OF COEFFICIENT USED IN DEVELOPING RELEASE RUEL…….…...…69
TABLE: 6.3. SUMMARISED POWER OUT PUT FOR DIFFERENT SCENARIOS OF IRRIGABLE AREA
AND AT 95% RELIABILITY OF RESERVOIR…………………………………………………………....74
LIST OF FIGURES
Page
Chapter Two
Figure: 2. 1. Schematic Representation of Hydropower Integration on Irrigation projects…………….12
Chapter Three
Figure: 3. 1. Location of the study Area…………………………………………………..………………...20
Figure: 3.2. Location of Watershed in the Study Area…………………………..…………………………21
Figure: 3.3. Megech Watershed…………………………………………………..…………………………22
Figure: 3.4. Ribb Watershed………………………………………………………………..………………..24
Figure: 3.5. Gumera Watershed…………………………………………………………………………..…25
Figure: 3.6. Gilgel Abbay Watershed……………………………………………………………………..…26
Chapter Four
Figure: 4.1. Location of Meteorological Stations in Lake Tana Sub Basin…….…….………………….29
Figure: 4.2. Double Mass Curve for Gonder Rainfall Station……………………..………………………35
Figure: 4.3. Double Mass Curve for Bahir Dar Station……………………………..………………….…..35
Figure: 4.4. Location of Streamflow Gauging Station…………………………………..…………….……38
Figure: 4.5. Correlation between Gauging Stations at Ribb near Adiss Zemen And
Upper Ribb near Debre Tabor…………………………………………………..………….….39
Figure: 4.6. Correlation between Streamflow Gauging Stations at Addis Zemen
and Azezo…………………………………………………………………………….……….….39
Figure: 4.7. Correlation between Flow at Dam Site and at Gumea Gauging Station and at
Dam Site…………………………………………………………………….…………..………42
Chapter Five
Figure: 5.1. Release Rule Chart for Gilgel Abbay-B Reservoir……..…………………..……….……….51
Figure: 5.2. Reservoir Rule Curve Gilgel Abbay-B reservoir……………………………..……….………51
Figure: 5.3. Range of Specific Speed and Net Head for Different Turbines…………………………………….……54
Figure: 5.4. Cash Flow Diagram for Megech irrigation project……….………………………………...……….……..62
Figure: 5.5. Cash Flow Diagram for Megech Hydropower Project……………………………………….64
Chapter Six
Figure: 6.1. Power Duration Curve of Megech (Alternative-2) Reservoir…………………..……….….66
Figure: 6.2. Power Duration Curve of Gilgel Abbay – B Reservoir………………………..…………….67
Figure: 6.3. Annual Monthly Power of Megech (Alternative-2) Reservoir……………..………………..67
Figure: 6.4. Annual Monthly Power of Gilgel Abbay – B reservoir……………………..………………..68
Figure: 6.5. Annual Monthly Release Volume of Megech (Alternative-2) Reservoir………..………….71
Figure: 6.6. Annual Monthly Reservoir Elevation of Megech (Alternative-2) Reservoir......................72
Figure: 6.7. Relationship between Power Generation and Irrigation Area …………………..………....72
Page
TABLE: A- 1. GORGORA RAINFALL STATION ...................................................................................................... 85
TABLE: A- 10. STATIONS USED FOR THE CONSTRUCTION OF DOUBLE MASS CURVE GROUP-I ....................... 94
TABLE: A- 11. STATIONS USED FOR THE CONSTRUCTION OF DOUBLE MASS CURVE GROUP-2 ...................... 95
TABLE: A- 12. STREAM FLOW FOR MEGECH NEAR AZEZO STATION ................................................................. 96
TABLE: A- 19. STREAM FLOW OF GILGEL ABBAY RIVER AT GAUGING STATION .............................................. 103
Page
FIGURE: B- 1. DOUBLE MASS CURVE OF THE RAINFALL STATIONS IN THE STUDY AREA .................................. 107
FIGURE: B- 3. SSR OUTPUTS OF MEGECH RESERVOIR FOR ALTERNATIVE ONE ............................................. 112
FIGURE: B- 4. SSR OUTPUTS OF MEGECH RESERVOIR FOR ALTERNATIVE TWO ............................................. 123
FIGURE: B- 10. TWO AND THREE DIMENSIONS REPRESENTATION OF THE ELEVATION OF LAKE TANA ........... 164
FIGURE: B- 11. LOCATION MAP OF MEGECH DAM AND GAUGING SITE ............................................................ 165
FIGURE B- 12: LAYOUT AND LOCATION OF THE PROPOSED POWER HOUSE .................................................... 166
FIGURE: B- 14. LOCATION OF MAIN TOWNS DAMS IN THE STUDY AREA ........................................................... 167
CHAPTER ONE
INTRODUCTION
1.1. Background
In developing countries, owing to rapid growth in population, it is unquestionable to
plan development activities which can ascertain fast improvement on living standard
of the nation.
It is preferential to plan Multi-dimensional development activities with limited amount
of resources with consideration for efficient utilization. This can be achieved by
optimum development of water resources.
The need for the optimal development of water resources has become more urgent
than ever before because water is becoming a scarce resource as a result of the
growing demand for various purposes such as hydropower, irrigation, water supply,
etc.
In Ethiopia, most large dam projects were implemented only for single purpose i.e.,
either for power, irrigation or water supply. To do this, there are inevitable
competitions and conflicts of interest between the different water users, and
projects that are often plagued by the lack of a cohesive approach.
Now a days, there is a growing recognition that planning considerations extend far
beyond the interest of single purpose projects, and needed to be viewed at the river
basin multipurpose development aspects, which results in a number of benefits
associated with social well-being such as secure water supply, irrigation for food
production, hydroelectric generation, flood control, watershed management,
improved navigation, etc. that makes the projects economically viable and
environmentally acceptable.
Dams which are planned to be constructed in Lake Tana sub basin are: Megech,
Ribb, Gumera-A and Gilgel Abbay-B, rivers are originally single purpose, only for
irrigation. However, these dams will have importance to generate electricity
immediately at the designed distance downstream of the dam; it can supply water
for the downstream-irrigated land and also for domestic water supply so that these
dams serve for multipurpose uses.
Eighty-three percent of Ethiopians currently lack access to electricity, with 94
percent still relying on fuel wood for daily cooking and heating [18]. This represents
only 17% of the total population of the country has electricity access. This electricity
access is almost entirely concentrated in the urban areas, but although 85% of the
populations live in the rural areas, less than 1% has access to electricity service.
The majority of the populations, primarily living in rural areas, lack a number of
facilities as a result of poverty and insufficient access to energy.
The Ethiopian government is therefore pursuing plans and programs to develop
hydropower and irrigation in an effort to substantially reduce poverty and create an
atmosphere for social change. It has been shown that access to electricity, including
rural electrification, is a key to poverty reduction in Ethiopia.
There are around six irrigation projects that are proposed to be implemented around
Lake Tana sub basin; but this study focuses only on four reservoirs (Megech,
Gumera-A, Ribb and Gilgel Abbay-B)
Preliminary economic analysis and turbine selection is done for Megech only
because of time constraint.
Since the projects are at pre-feasibility some data such as project cost, agricultural
costs are adopted from projects‟ draft report and from master plan and hence some
of the data may be changed through time.
CHAPTER TWO
LITRATURE REVIEW
2.1. General
There are contradictions between power generation and irrigation. Taking water
away from a river or from a reservoir for irrigation will result in a reduction in the
water flow for power generation. Moreover, in most cases the supply schedule for
irrigation does not coincide with that for power generation. However, we can make
use of the drops of head from the irrigation reservoir to develop power generation,
or make use of the tail water of the power station for irrigation, i.e., to let the flow
first pass through the water turbine, and then go on for irrigation.
In the Ethiopian context, the irrigation sub-sector is classified as small (less than
200ha), medium (200 to 3000ha) and large-scale (over 3000ha) schemes.
Ethiopia‟s irrigation potential has been estimated to be in the order of 3.5 million
hectares. The total area currently irrigated by modern irrigation schemes in Ethiopia
is approximately in the order of 160000ha, i.e. 4.6% [25].
The net command area of Gumera-A, Megech of alternative one and two, Ribb and
Gilgel Abbay-B accounts 14000ha, 14622ha (7311ha + Gonder water supply)
19925ha and 12490 ha respectively. For efficient use of Megech reservoir two
alternatives are planned: One alternative is increasing the command area by 100%
of 7311ha. The second alternative, the reservoir used for irrigating 7311ha
command area as well as supplying domestic water supply for Gonder town. These
two cases are considered in our analysis as alternative one and alternative two of
Megech reservoir.
Table: 2. 1. The overall unrestricted full development potential of the Abbay basin
at each sub-basin [31,5]
S.No Sub-Basin Name Sub-Basin Agriculture Maximum Identified
2
Area(km ) Suitable Irrigable Irrigable
Land(km2) Land(km2) Area(ha)
1 Lake Tana 15054 10497 4639 113669
2 North Gojjam 14389 10330 4245 11716
3 Beshelo 13242 8538 3474 -
4 Weleka 6415 3903 1973 -
5 Jimma 15782 6819 6408 11687
6 South Gojjam 16762 11414 5459 19789
7 Mugar 8188 5885 3384 -
8 Guder 7011 3990 3990 8040
9 Fincha 4089 3048 1165 17358
10 Didessa 19630 18235 14809 52617
11 Angar 7901 6684 4177 26563
12 Wombera 12957 9222 3916 2357
13 Dabus 21032 18978 8513 8816
14 Beles 14200 11358 2908 138720
16 Dinder 14016 1975 59555
17 Galegu/Rahad 23160 4655 1794 54995
Total 199812 147572 72829 525957
Presently, the Ethiopian electric power system is essentially based on very few
medium sized hydropower plants, with minor contribution from thermal. The total
firm energy production capacity of the existing hydropower schemes is about 2,338
Gwh/year (see table 2.3), which accounts for 90% of the total electric energy
produced in the country.
To cope up with this energy shortage as we have seen these days, special attention
has recently been given to the development of hydropower sector. This study has its
own role for the contribution of maximizing power coverage.
It is possible to plan a power generation plant using release for: irrigation water
demand, river maintenance, water supply and using reservoir overflow.
When water for irrigation, river maintenance flow, water supply and any other water
utilization, if any, are discharged from the dam to the river through a water utilization
outlet pipe to immediately downstream of the dam are all available for power
generation by utilizing the outlet pipe. This concept of hydropower integration can be
further illustrated in fig.2.1 below.
QI is irrigation discharge
QM is river maintenance
QF is water over flow during full water level
QO is the summations of water supply
and additional flow release for
power maximization or other uses.
P is power house
I is stream inflow
2.5. Turbines
2.5.1. General
Hydraulic turbines are machines which use the energy of water and convert it into
mechanical energy. The most common types of hydraulic turbines are broadly
classified in to the following two types:
1. Reaction Turbines. These turbines use the available energy partly converted in
to kinetic energy and substantial magnitude remains in the form of pressure
energy. These turbines obtain the motive force by deflection of water under
pressure in a closed passage formed by the turbine blades. The most common
reaction turbines listed under this category are: Francis, Kaplan, Propeller and
Driaz.
2. Impulse Turbines. These turbines use all the available potential energy which is
converted in to kinetic energy with the help of contracting nozzles. The impulse
wheel or runner is usually a solid disc or hub upon which are mounted buckets
that are designed to split the jet and cause it to turn through nearly 1700 while
sliding over the inner surface as the bucket travels away from the nozzle. Pelton
wheel and Turgo-impulse are belong to this category.
The details of these turbines is found in [19, 14, 17] and in any hydraulics and
hydropower books.
The selection of turbine for an efficient use is based on the estimated head and
discharge available to generate power.
To produce a given power at a specified head for the lowest possible cost, the
turbine and generator unit should have the highest speed practicable. However, the
speed may be limited by mechanical design, cavitation tendency, vibration and loss
of overall efficiency.
In addition, greater speed requires the turbine to be placed lower with respect to the
tail water, which generally increases excavation and structural costs. The highest
speed need to develop high specific speed which is useful in reducing the runner
size and power house dimensions.
The selection of turbine as mentioned above and from the procedure of selecting
turbine as mentioned in chapter four are mainly based on net head over the turbine
and discharge through the turbine.
The Kaplan turbines are fairly suitable for the purpose of three main reasons:
• Relatively small dimensions combined with high rotational speed
• A favorable progress of the efficiency curve
• Large overloading capacity
Since both head and discharge are highly variable and the net head in the
considered reservoirs are less than 55m Kaplan turbine is found suitable for all
projects.
This turbine works for net heads ranging from 2 m up to 50m; even it can range up
to 60m [6, 17]. Kaplan turbine offers also an advantage with its large range of
capacities up to 500 m3/s.
Because of the importance of the Abbay, very many studies had been carried out in
the past, concerning the basin. Though, there were not very specific studies for the
development of specific project sites in lake Tana - sub basin except the recent
progress works under taken by consultant of water works, design & supervision
enterprise and TAHAL Engineering Ltd., only water exclusively, all the studies under
taken, pertaining to Lake Tana, or Abbay [29].
2.6.1. Design of Dams in Lake Tana Sub-Basin Projects (Gilgel Abbay, Megech
and Ribb )-WWDSE and TAHALE Pvt. Ltd
Important updated data such as crop water requirements, extent of irrigation area,
domestic water supply and reservoir data are taken from these studies reports.
From these studies, I have taken irrigation water requirement data, extent of
irrigation area and reservoir data of Gumera - A reservoir.
These studies were carried out during 1988-90 for country wide water and land
resources development, covering all river basins. These were primarily desk
studies for identifying potential irrigation and the study addressed the Abbay basin
also, along with other basins. The USBR studies were reviewed in detail for the
Abbay basin, and subsequently this study came out with modifications in the
hydropower sites based on country wide data collection and analysis, coupled with
detailed map studies.
The study entitled “Abbay River Basin integrated development Master Plan Project”
has been carried out with the following water resources oriented objectives.
To prepare water allocation and utilization plans under alternative development
scenarios and to generate data, information and knowledge that will contribute to
the future water allocation negotiations with downstream countries.
The hydrological and hydro meteorological studies are more relevant for review in
this section. These aspects have been covered in Section II, volume III of the
master plan study report. The basic climatic features, the climate data of the Abbay
river basin are discussed first. The rainfall data procured by the study was for 173
stations; the data length varied from 3 to 40 years, with associated monthly gaps.
The data for other climatic factors were available for 108 stations.
All data and analysis as well as typical design for structures were presented in the
Phase 2 report - Section II - Volume V - Water Resources Development - Part 1 -
Irrigation & Drainage). Necessary data extracted from this report and additional
details are presented in Appendixes E and G of the master plan.
Data of irrigation dams, irrigation structure, drainage and farm input and livestock
information is surveyed well in this master plan part and I use this information for
economic analysis part.
CHAPTER THREE
STUDY AREA
The Abbay Basin is perhaps the most important basin in Ethiopia. It accounts for
about 17.5% of Ethiopian land area, 25% of its population and 50% of its annual
average surface water resources. In the Lake Tana, it has the country‟s largest
fresh water lake, covering an extent of 3000 km2. The Abbay has an average annual
runoff of about 50 Bm3. The river of Abbay contributes on an average, 62% of Nile
river flows in Aswan dam. [29]
The Lake Tana sub-basin is located at the headwaters of the Abbay (Blue-Nile)
basin (see fig. 3.1). The drainage area of the lake is 15,319 square kilometers, of
which 3000 square kilometers is the lake area. It has maximum dimensions of 78 km
in length, 67km in width and 14m in depth. The geographical location of the Tana sub-
basin extends from 10.95oN to 12.78oN latitude and from 36.89oE to 38.25oE
longitude.
The mean annual rainfall at Bahir Dar (south portion of the basin) is 1450mm,
1200mm at Addis- Zemen (Eastern portion) and 1050 at Gondar Air Port
meteorological station (northern portion), indicating the spatial variation of rainfall in
the basin. Rainfall distribution, both in time and space, decreases northwards in the
basin (see Fig B-9 in appendix-B). Of the total annual rainfall, 70% to 90% occurs
during the June to September rainy season. The mean annual flow at the outlet of
Lake Tana is about 3.5 billion cubic meters and it varies from a maximum of 7 billion
cubic meters to a minimum of 1 billion cubic meters in high and low water years
respectively.
The topography of Lake Tana sub basin (LTB) ranges from flat to cliff. The flat areas
dominantly cover the low-lying areas LTB plains and a gently sloping terrain lies in
between the low-lying and highland areas. The very steep terrain lies mainly along
the boarder of the sub basin and mainly on mount Guna on the east, Armachiho on
north and Sekela high lands on the southern part of the basin. The altitude in the
basin ranges from 1772 to 4100 m asl. at the bed of Lake Tana and the eastern
extreme of the sub basin (mount Guna) respectively.
In Lake Tana sub – basin there are about six proposed irrigation projects at different
level of studies. These are: Gumera-A, Megech, Ribb, Gilgel Abbay-B, Jema and
North East Lake Tana. Among these Megech, Ribb, Gumera-A and Gilgel Abbay are
the focus of this study (see fig. 3.1 and 3.2).
The Megech River originates from the high mountain ranges located to the North and
Northeast of Gonder town, in the Gonder Administrative Region at an elevation of
nearly 2500 m. The catchment area of Megech River up to its entrance to with Lake
Tana is about 700 km2 whereas the catchement area upto the damsite is 432.5 km 2.
The river traverses a length of 55 km before it meets the Lake Tana (see fig. 3.3).
The Ribb River originates from the high range of mountains located to the east of
Lake Tana. The river traverses a length of 114 km before it enters Lake Tana.
The Ribb dam site is located on the Ribb River 47 km from the origin. The riverbed
elevation at the dam axis is about 1,874 m at coordinates E 37° 59‟ 45” and N 12°
02‟ 30”.
Approximate longitudinal section of the Ribb watershed along the main river course
shows that it is characterized as a steep mountainous watershed up to the Ribb
dam site (at about 50 km course), below this point the river slope gets flatter
(See Fig.3-4). The Upper Ribb watershed (844 Km2) is characterized as a
mountainous, wedge shaped and a steep sloped (3.6%) watershed. The highest
elevation of the watershed is about 4,100 m in its south eastern part, where at the
dam site the elevation drops below 1,900 m.
There is hydrological characteristics similarity between the Ribb dam site (685 km 2)
and the Megech dam site watersheds. It should be mentioned that 50 Km
downstream of the Upper Ribb gauging site , the Ribb river slope is gets flatter with
low velocity and deposition of suspended sediment in the river course and over the
banks in case of excessive flooding.
The project area is located in Fogera & Dera woredas of South Gonder
Administrative zone of Amhara Nation Regional state (ANRS). It falls between
Latitude 110-45‟ and 110-55‟N and longitude 37030‟ and 37050‟E. The project area is
situated at a distance of about 35 km from Bahir Dar and at about 42 km from Debre
Tabor. Woreta and Anbesame towns, the capitals of Fogera and Dera woredas,
respectively are very close to the project area.
Gumara River is one of the main streams on the east side, flowing into Lake Tana.
The river along with the tributaries originates from the high mountain ranges to the
east of Lake Tana. The town Debre -Tabor is in the vicinity of the origin. The
general elevation in this zone is 3,050 meters.
The river flows generally in westerly direction for a length of 98 km till Lake Tana
(see fig.3.5). The catchment area from the head to Tana is 1,893 km 2. Map of
Gumera project is shown in appendix Fig. B - 8.
There are two projects proposed for irrigation using Gilgel Abbay river i.e Gilgel
Abbay-A and Gilgel Abbay–B. In this study we consider only Gilgel Abbay-B. The
net irrigation area proposed in the master plan is 12490 ha [4].
This project area is located in the Gilgel Valley, between Wetet Abay and Lake Tana
between altitudes of +1830 and +1860 m asl (see fig. 3.1).
CHAPTER FOUR
4.1 General
Among the meteorological stations in the Lake Tana sub basin(see fig 4.1), the
following meteorological stations have relatively better records: Bahir-Dar, Debre
Tabore, Maksegnit, Zege, Dangila, Gonder, Gorgora and Enjibara from which
rainfall, maximum and minimum air temperature, evaporation, relative humidity,
sunshine hours and wind speed are collected.
The above stations are grouped further to fill the missing rainfall data of
representative Stations (see table 4.3) and used for consistency checking based on
altitude and average area rainfall distribution from Isohyetal map developed for the
area (see appendix fig.B-9)
The location of the key meteorological and hydrological stations around the Ribb
dam site is shown in fig. 4.1and fig.4.4.
The elevation of Ribb dam site is about 1870m asl which is less than the altitude of
Debre Tabor (2612m asl) and hence could not be used for analysis of evaporation
over Ribb reservoir. Since Gonder (1967m asl.) meteorological station is at about
the same elevation as Ribb reservoir, this data has been adopted for evaporation
rate computation over the reservoir.
The other climatic data like the temperature at various resolution levels, mean wind
speed, mean relative humidity and mean sun shine hours were available on
comparatively long term basis at Bahir Dar.
Evaporation over the reservoir of Gilgel Abbay is determined from Bahir Dar and
Dangila meteorological stations as shown in section 4.2.5.
For the present Study the Penman – Monteith method was selected to determine
the monthly evaporation rates at four relevant climate stations: Debre Tabor, Bahir
Dar, Dangila and Gondar.
Open water evaporation (E) is estimated from potential evapotranspiration (ETo)
which is calculated using FAO CROPWAT version 4.3 program which uses the
Penman-Monteith method and then applies an aridity correction factor. The
estimated potential evapotranspiration which is computed by CROPWAT program is
converted to open water evaporation from the principle as stated in [16]. It says, with
a depth of water higher than 5m and if it is clears of turbidity, the conversion factor
ranges from 0.65 to 1.25 for temperate climate condition. For Ethiopia, the aridity
correction factor is estimated to be 1.2 [29, 30].
Project
Name Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Megech 152 147 179 169 176 146 121 126 147 154 145 142
Gumera- 133.
A 1 140.4 180.1 193.8 206.1 174 291.8 261.8 147.0 186.9 142.4 129.2
Ribb 152 147 179 169 176 146 121 126 147 154 145 142
Gilgel 133.
Abbay-B 1 140.4 180.1 193.8 206.1 174 291.8 261.8 147.0 186.9 142.4 129.2
Twenty years of rainfall data of seven stations were collected at seven stations in
the sub-basin.
Various methods are available to estimate missing rainfall records of gauged
stations. The methods used for the analysis of data in this study are the normal-ratio
method.
The normal-Ratio method (NRM) is used where the mean annual precipitation of
any of the adjacent stations exceeds the station in question by more than 10% and it
Nx PA P P P
is given as Px B C ..... n -------------------------------------- (4.1)
n N A N B NC Nn
Table: 4. 4. Stations used to fill missing rainfall at Bahir Dar gauging stations
S.No Name of the Long term mean annual Station precipitation
stations rainfall (mm) (mm)
Nx P1 P P
Px 2 3
3 N1 N 2 N 3
933 65.7 63.4 102.5
Px
3 1520 1465 2370
Px = 40.35 mm
20000
15000
10000
5000
0
876.3
2900
4603
6254
8126
10947
13507
16174
17930
19820
Group M e an Annual Cum m ulative Rainfall
20000
15000
10000
5000
0
1640
3373
5002
6473
8898
10528
12439
14173
15632
17469
19477
21270
23301
25235
26876
28476
30066
31709
33525
35546
Mean monthly rainfall at Gilgel Abbay-B Reservoir is estimated using the following
equation and the values are shown in table 4.6.
P1 A1 P2 A2 P3 A3 ...Pn An )
Pi ( ………………………… (4.2)
A1 A2 A3 ... An
Stream flow records are obtained from the Hydrology Department of Ministry of
Water resources for the following gauging stations. The length of streamflow data
used in this paper is 20 years mean monthly data. Table 4.4 shows the location of
gauging stations from which streamflow data is collected.
Watershed
To fill the missing recorded stream flow gauging data, various methods are
available. The missing values were filled with multiple station correlations. In order
to correlate stations, the stations should have related physiographic, climatic and
drainage characteristics of the catchments, geographic proximity also considered.
Figure: 4. 5. Correlation between gauging stations at Ribb near Adiss Zemen and
Upper Ribb near Debre Tabor.
100
y = 2.4854x - 0.2833
80
R2 = 0.9644 Correlation Between Megech
60
Ribb
and Ribb
40 Linear (Correlation Between
Megech and Ribb)
20
0
0 5 10 15 20 25 30 35
Megech
The area ratio method is commonly used to determine the flow at the required sites
from the main or tributary rivers stream gauge values. This method uses the
drainage area to interpolate flow values between or near gauged sites on the same
stream. Flow values are transferred from a gauged site, either upstream or
downstream to the un-gauged site. [20]
The recommended guidelines for area ratio method to assess the available stream
flow for the potential assessment purpose can be estimated as
n
A
Qsite site Q gauge ---------------------------------------- (4.3)
Agauge
Where: - Qsite - discharge at the reservoir site
Qgauge-discharge at the gauge site
Asite - drainage area at the reservoir site
Agauge - drainage area at the gauge site
n – Varies between 0.6 and 1.2
This method is used under the following conditions.
Asite
If the Asite is within 20% of the Agauge ( 0.8 1.2 ) then n = 1 to be used [21].
Agauge
Area ratio of Megech and Gilgel Abbay-B dam site is in range of 0.8 to 1.2 hence
stream flow at respective dam site is determined by using the simple area ratio
techniques.
Whereas, area ratio for Ribb is less than 0.8, equation 4.3 cannot be applied but we
can estimate from Upper Ribb gauging station which have a drainage area of 844
km2 , it is located near Debre Tabor. There area ratio is 0.81 (685/844) which is
>=0.8 hence equation - 4.3 can be applied.
Stream flow at Gumera-B dam site is estimated using correlation techniques (see
section 4.3.2.2 below).
Correlation technique is used to extend a period of record if one or more sites with
similar flow variations can be found. If good correlation does not exist, other
techniques such as examination of precipitation records should be considered.
The stream flow at Gumera-A, is adopted from the hydrologic report [29] but it is
only eighteen years record, the rest two years is estimated by checking its
correlation with the gauging station near Bahir Dar and it shows good correlation
(see fig. 4.7) and hence from gauging station the streamflow at dam site can be
generated.
150
y = 0.2913x - 0.0648
flow at dam
site(Mm3)
R2 = 0.9992
100
50
0
0 100 200 300 400 500
Mean monthly stream flow Gauging station(Mm3)
CHAPTER FIVE
METHODOLOGY
Where; efficiency ( ) term used in the water power equation represents the
combined efficiencies of the turbine and generator (and in some cases, speed
increasers) Generator efficiency is usually assumed to remain constant at 98
percent for large units and 90 to 95 percent for units smaller than 5 Mw [17].
The smaller standardized Kaplan turbine has an efficiency of 91 percent and an
overall efficiency of 85 percent can be used for this studies.
Flow discharge (Q) used in the water power equation would be the flows that are
available for power generation. Where the sequential streamflow routing method is
used to compute energy, discrete flows must be used for each time increment in the
period being studied.
For preliminary studies and for analysis of projects with short penstocks, it is usually
adopted affixed penstock head loss based on the average discharge as given by
equation 5.5 as shown below.
A preliminary penstock diameter can be estimated by using a velocity of 17% of the
existing velocity [15].
VR 0.17(2 gH ) 0.5 ………………………….…………………... (5.4)
Where VR = velocity of flow in the penstock at the rated discharge, m/s
g = gravitational constant, 9.81m/s2
H = gross head, m
Normally, VR ≤ 7.6m/s and D ≤ 12.2m.
V 1.9
h f 2.58.k s . 1.1 ……………………………………………....(5.5)
D
Where: hf = friction loss in penstock, m per 1000m of penstock length
D = penstock diameter in m.
Diameter of Megech and Ribb = 2.5m and, and 3m for Gumera, 3 m for Gilgel
Abbay [26, 28, 30]
V = average velocity of flow in penstock, m/s
Ks = a constant representing friction loss coefficient
(For steel penstocks, assume Ks = 0.34)
The primary disadvantage of SSR is involvement of a trial and error procedure and
hence very tedious. The routings may be daily, weekly, or monthly intervals. The
analysis here is based on monthly intervals.
70
60
Irr.Req.
50
40
30
20 Firm Flow
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
1890
1885
Average
1880
R.W.L
1875
1870
1865 Maximum
1860 R.W.L
1855
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
Sequential routings are used to coordinate power production with irrigation release
and water supply (in case of Megech) to determine the average annual potential
energy available from the reservoirs.
During the reservoir operation, the user tries to maximize hydropower generation
under the constraints of irrigation water demand and domestic water supply release.
Hydraulic constraints are defined by the reservoir continuity equation.
S(t+1) = S(t) + I(t) – R(t) t = 1,2,…,T, ………………………………………..(5.8)
Where S (t+1) is storage at time step t+1, some times called end storage.
S (t) is storage at time step t, initial reservoir content at time t = 1 is assumed to be
85% of its full capacity.
I (t): Reservoir net inflow at time step t (including reservoir inflow, precipitation, and
evaporation).
R (t): Reservoir outflow at time step t (including irrigation water demand, water
supply and additional flow release to get maximum power during non-irrigation
periods.
T: The total number of time steps in the considered period).
When the routing has been carried out for the time period t to t+1, the reservoir
content at time t+1 will be known. The next step is to compute the reservoir content
at t+2 and so on thought the period to be routed.
For reservoir of Megech irrigation project there are two alternatives of irrigation
planning is proposed.
1. Irrigating 14622 ha only
2. Irrigating 7311 ha and fulfilling domestic water supply of Gonder town
T = Period of generation
For Megech reservoir: Annual energy generation (Gwh) is computed as
E = 9.81*0.85*5.7*(1947.1-1894)*8760/1000000
= 22.11 Gwh/year
Installed power (P) = (E*1000)/ (8760*Pf ) (Mw)………………………………… (5.13)
Where: Pf = Plant factor = (Energy used)/ (Energy available)
It is assumed to be 0.6
P = 22.11 *1000/ (8760*0.6)
= 4.21 Mw
Zelalem Netsanet M.Sc. Thesis August 2008, AMU
CHAPTER – 5 METHODOLOGY 54
Since the flow is highly variable, two turbines are proposed for Megech Reservoir
this alternative.
Power for unit turbine = 2.11 Mw = Pd
FSL =1947.1m
TWL = 1894.37M
Design head = (FSL-TWL)/1.25………………………...………….…….(5.14)
Hd = 42.184 m
2334
Trial specific speed N s from U.S Bureau of Reclamation……….(5.15)
Hd
cs
C
E
d
e
e
I
Ns
Figure: 5. 3. Ranges of specific speed and net head for different turbines
The trial value of N is solved from the specific speed equation using the trial values
of Ns determined in the previous section.
P
From N s N 5
…………………………………………………….. (5.16)
4
H
Where Ns = specific speed
N = rotational speed (r.p.m)
P = Power developed (Kw)
H = effective head (m)
5
4
359.36 * 42.184
N
2105
N = 841.05 r.p.m
N 120 f
p …………………………………………………….. (5.17)
Where: f = frequency cycle/sec (50-60 Hz c/s)
p = number of poles (divisible by 4 for head up to 200 m)
(Divisible by 2 for head above 200 m)
P = 120*50/841.05
= 7.13 8
However, as per the latest trends, the number of poles is used as a multiple of four
for better dissipation of magnetic flux though some standard generators are having
a multiple of 2 poles only.
But according to Donald if the head is expected to vary less than 10% from the
design head, the number of poles taken as the lower multiple of four, otherwise take
the next higher poles.
( H Max H Min )
Head variation = *100% …………………………………… (5.18)
Hd
(51.54 18.37)
Head variation = * 100%
42.184
= 78.63%
Therefore the designed number of poles is 8.
120* 50
The design speed N = 750 r.p.m
8
Since from design speed value = 750 r.p.m, and design head of 42.184m. Kaplan
turbine is best suitable.
The power house shelters the turbines, generating units, control and auxiliary
equipment, and erection and service areas.
The power house can be either surface power house or underground power house.
Since surface power house is cheaper than underground power house we
recommend surface power house for Megech hydropower.
The powerhouse would be located so as to maximize the available head and
minimize the length of the headrace tunnel; this eliminates the need for an upstream
surge-chamber and allows for the shortest possible tailrace.
The location of power house is determined based on the geological conditions and
nature of the topography. But for the calculation of head loss, we locate the power
house at a distance of 150m downstream of the dam (see the general layout in
appendix Fig. B -12).
The power stations have the structures in the order of
Dam Intake Penstock Power station (turbine) Tailrace Outlet
The penstock is comprised of steel and concrete lined vertical shaft, (diameter 3.5
m, 200 m long). Part of the shaft may be lined with concrete only.
5.5.1. General
As we have seen earlier, the power production increases as the irrigable land
decreases (see fig. 6.7) because of the advantage of gross head. To show the
feasibility of integrating hydropower in the irrigation projects we need to perform the
economic analysis. Therefore, the purpose of the economic analysis is to compare
the economic benefits of irrigation projects and hydropower projects. We have done
the economic analysis only for Megech irrigation project.
Where: r = EIRR
5.5.3. Cost of Projects
Generally, the total cost of the projects consists of investment cost on civil, irrigation
cost, and running cost of the project. Further more the administration; legal and
related activities are also incurred under total cost of the project.
It is assumed that the construction (investment) period takes 5 years and the project
will be at full operation for the rest of the period i.e. 45 year.
The annual investment cost of the project is converted in to its present worth by
using present worth factor (PWF) for a service year of the project which is given by:
(1 i )n 1
PWF ………………………………….….……………. (5.22)
(1 i) n .i
Where: i = Annual interest rate
i = 10 % which is adopted in master plan for the project
under consideration.
n = Estimated life of the project
n = 5 years during the investment and 45 years during operation period.
PWF = 3.79 and 9.86 for n = 5 and 45 respectively.
From table 5.4, the annual investment costs = 23,262*7/5
= 32,566.8 birr/ha/year …. (i)
C
32,566.8 birr/ha/year 10,399 birr/ha/year
Designation: B = Benefit, C = Cost
Figure: 5.4. Cash flow diagram for Megech irrigation project
The economic analysis of the projects could take into account the following annual
operation and maintenance costs, as percentage of construction costs:
C
5,710,638 birr/year 856,596 birr/year
Figure: 5.5. Cash flow diagram for Megech hydropower project
CHAPTER SIX
6.1. General
The proposed dam for irrigation is aimed to irrigate maximum potential with
reliability ranges from 80% to 100% as shown in the draft report for the respective
projects.
A reliability different from 100% indicates there will be a deficit some time in the life
of the project; but firm power by its definition is the power we can get for almost all
the time, i.e. its reliability not less than 95% and above [14]. Based on this concept,
the results of this option are shown in table 6.1. From this option Ribb reservoir has
no significant power without irrigable area reduction whereas best result is attained
from Gilgel Abbay-B reservoir and Megech of alternative two give 5.614 Mw and
607.5 kw respectively at 95% dependability (see table 6.1, fig.6.1 and fig.6.2)
1600
1400
1200
1000
800
600
400
200
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
10000
8000
6000
4000
2000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
Power, 12490 ha
16000
Minimum Power
14000
Average Power
12000
Mximum Power
Power, kw
10000
8000
6000
4000
2000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
12 Firm Flow
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
1940 Minimum
R.W.L
Reservoir W.L, masl
1930
1920
Average
R.W.L
1910
1900 Maximum
R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
800
Megech
600
Alt-2
400
200 Megech
Alt-1
0
45 55 65 75 85 95 105
Since the primary purpose of the proposed dams is for irrigation purpose, a criterion
is set not to reduce the irrigated area by more than 50% of the proposed irrigable
area. Based on this different scenario of irrigation areas are analysed in reservoir
sequential routing for 95% reservoir reliability and the results are shown in table 6.3
for different dependability of time.
Table: 6. 3. Summarised power out put for different scenarios of irrigable area
and at 95% reliability of reservoir
Net Dependable Power , kw
Project Reduction Area 50 55 60 65 70 75 80 85 90 95 100
Name % ha % % % % % % % % % % %
0 14622 570.4 68.71 68.7 68.7 63.5 59.7 54.9 50.1 44.8 35.5 24.5
95 13890.9 541.9 242.4 242 242 221 210 190 175 158 120 86.4
Megech
90 13159.8 538.9 300.4 300 300 273 258 233 218 195 144 107
of Alt-1
85 12428.7 550.1 523.5 523 521 470 445 404 376 327 240 187
80 11697.6 618.9 618.9 619 602 554 524 480 444 380 297 221
75 10966.5 653.3 653.3 653 634 581 553 514 468 400 336 233
70 10235.4 656.7 656.7 657 638 589 556 523 471 402 371 234
65 9504.3 709.1 709.1 709 673 640 592 570 507 443 404 253
60 8773.2 846.7 846.7 846 789 745 698 649 595 543 467 302
55 8042.1 980.8 980.8 949 902 852 800 759 686 584 509 350
50 7311 1001 1001 981 926 872 830 775 699 600 512 357
G+100% G+7311 1424 1377 1287 1229 1159 1102 1034 953 865 608 456
Megech G+95% G+6945 1361 1356 1307 1231 1172 1104 1049 964 854 616 490
Of Alt-2 G+90% G+6580 1414 1385 1354 1290 1197 1138 1082 999 864 642 515
G+85% G+6214 1444 1363 1333 1301 1244 1165 1115 1017 839 671 538
G+80% G+5849 1488 1418 1324 1288 1253 1202 1150 1043 813 700 564
G+75% G+5483 1516 1421 1349 1294 1243 1214 1180 1035 827 698 592
G+70% G+5118 1514 1451 1384 1295 1251 1182 1142 1035 835 663 604
G+65% G+4752 1470 1427 1369 1311 1246 1145 1117 1037 874 730 602
G+60% G+4387 1455 1415 1388 1345 1284 1248 1134 1019 838 634 504
100 14000 1946 1806 1480 790 733 644 534 455 178 129 54.3
95 13300 1849 1768 1530 902 768 700 612 548 518 426 205
90 12600 1760 1682 1503 1284 1156 1006 908 841 761 654 300
Gumera
A 85 11900 2212 1773 1671 1551 1472 1296 1147 1087 959 623 395
80 11200 2290 2153 2030 1743 1599 1518 1463 1400 1203 589 546
75 10500 2214 1942 1787 1735 1645 1531 1446 1335 1222 929 635
70 9800 2341 2234 2051 1838 1768 1635 1508 1414 1305 1089 663
65 9100 2300 2225 2077 1985 1935 1828 1662 1571 1459 1199 830
60 8400 2429 2232 2147 2084 1954 1831 1735 1625 1555 1217 893
55 7700 2455 2352 2239 2136 2016 1909 1803 1691 1622 1387 930
50 7000 2421 2360 2296 2231 2077 1993 1896 1827 1746 1442 1092
N.B: G = Gonder domestic water supply
Determination of some of the costs used for our analysis needs experience and
detail market survey. We adopt unit costs from the master plan developed in
1998/99.
Since our aim is to compare the economic benefits gained from irrigation and
hydropower, the unit cost doesn‟t alter the results because generally the cost varies
proportionally for both irrigation and hydropower conditions.
The out put result of economic analysis which is done for Megech reservoir shows
that the benefit cost ratio for irrigation project is 0.37 and for hydropower condition
1.9. This indicates that integrating hydropower with irrigation reservoirs is
economically feasible. For different options of irrigable area as cited earlier, we can
come up with the corresponding power generation but the extent of irrigable area
may be determined by social and intangible economic reasons.
CHAPTER SEVEN
7.1 Conclusion
Hydropower integration is done for Megech of alternative one and two, Gumera-A,
Ribb and Gilgel Abbay-B of which Gilgel Abbay-B project shows better result for firm
power generation. We can get also significant firm power from Megech in both
alternatives and Gumera-A as shown in chapter six. On the other hand Ribb
irrigation project has no considerable firm power with option one.
When we evaluate the projects for option two all of the five projects have substantial
power as shown on table 6.3.
Generally, from the total expenses of hydropower projects large share is allocated
for dams and appurtenant structures. The cost of dams in Lake Tana projects is
more than 63% of the total investment cost. Since most of the expenses are already
incorporated in the irrigation projects, additional expenses for power generation due
to cost of turbine, intake, penstock, generator, civil costs, etc. constituting very small
amount as compared to the total investment costs for full hydropower development
if it were isolated project. The economic analysis (see 5.4.2) demonstrates this fact.
The benefit cost ratio result indicates that Megech irrigation project is not
economically feasible.
Nevertheless, it has been noticed that the household income in the command area
is very small, 295 Birr/year [4] and improving the situation in this area could be a
sufficient reason for implementing the proposed irrigation project.
7.2 Recommendations
Based on the current study the following recommendations can be drawn for
maximum power generation:
Even though power is a function of reservoir head water level and discharge,
the power is highly fluctuated with head variation due to irrigation release.
Irrespective of the economic analysis and other factors, the power can be
maximized with slight reservoir height increment.
Since the routing is done manually and it is a trial and error procedure on
spreadsheet, it is cumbersome to analyse variation of power in every hectare
increment and decrement. The power production in every area reduction can
be analysed for detail analysis using latest softwares such as: HEC-5, HEC-
ResSim.…etc.).
The data, especially irrigation water requirements, are taken from draft
reports and it may be changed during final design in that case the results
found so far may be changed and updated data should be analysed with
time.
The data considered in this paper is 20 years monthly data and monthly basis
routing a better analysis can be drawn if short time steps and long years of
historical records are considered.
Economic analysis for other projects should be done to see the feasibility of
the respective projects.
REFERENCES
23. U.S Army Corps of Engineers (31 October 1997) “Hydrologic Engineering
Requirements for Reservoirs” Civil Engineering manual Publication Number,
EM 1110-2-1420
24. U.S Army Corps of Engineers (31 December 1985) “Engineering and Design –
Hydropower” Civil Engineering manual Publication Number, EM 1110-2-1701.
25. UNESCO, World Water Assessment Program (December 2004) “National
Water Development Final Report For Ethiopia” Addis Ababa – Ethiopia
26. WAPCOS - Water and power consultancy service, (1990) “Preliminary Water
Resource Development Master Plan For Ethiopia” Main report, Annex G
Multipurpose and Major Irrigation Projects.
27. WaterWatch (2006), “Remote Sensing Studies of Tana-Beles Sub Basins.
WaterWatch Remote Sensing Services, A Nile Basin Initiative project”
www.waterwatch.nl
28. Water Works Design & Supervision Enterprise, in association with
Intercontinental Consultants and Technocrats Pvt. Ltd. (Jun 2007) “Gumara
Irrigation Project, Irrigation and Drainage Report”
29. .Water Works Design & Supervision Enterprise, in association with
Intercontinental Consultants and Technocrats Pvt. Ltd. (Jun 2007) “Gumara
Irrigation Project, Meteorological and Hydrological Report”
30. Water Works Design & Supervision Enterprise, in association with
Intercontinental Consultants and Technocrats Pvt. Ltd. (Jun 2007) “Megech,
Ribb, Irrigation Project, Meteorological and Hydrological Report”
31. . Yilma Demissie E. (2006) “Assessement of Impact of Abbay Basin
Irrigation Development on the Water Resource of the River, A Case of
Tributaries Development Scenario”, M.Sc. thesis, Arba Minch Universrty
APPENDICES
APPENDIX - A
TABLES
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 0 0 0 11.6 112.7 64.7 132.3 210 126.5 60.7 34.6 0
1988 0 7.9 0.6 0 34.5 183.6 357.4 286 105.9 68.6 0 0
1989 0 0.355 18.3 37.56 31.2 238.6 293.3 207 46.8 40.9 0 0
1990 4.8 0 2.048 23.39 22.582 91.99 251.5 173 163.9 18.66 0.304 0
1991 0 2.356 0 71.37 22.278 92.31 199.2 209 105.7 64.76 9.99 0.863
1992 0 0.131 0 4.2 24.128 55.9 155.3 308 86.1 59.28 4 0
1993 0 1.3 16.6 33.4 66.5 193.4 125.1 251 117.9 17.6 25.2 0
1994 0 0.253 1.479 8.103 47.259 272.1 335.5 287 176.4 0 11.7 0
1995 0 0 14.8 2.8 88 130.1 297.8 238 110 22.6 0 0
1996 0 0 53.2 68 113.7 316.9 413.8 341 286.8 0 30.7 0
1997 0 0 26 30.2 203.9 138.8 294.9 152 99.7 434.3 91 5.3
1998 0 0 34.9 13.7 54.1 298 376.3 186 91.8 29.1 0 0
1999 9.5 0 0 24 44.1 285.5 225.5 201 50.4 233.4 0 5.2
2000 0 0 0 64.1 35.3 327.5 310.9 191 83.9 161.7 18.2 0
2001 0 0 0 13.9 196.8 149.7 318.9 374 172.9 1.4 4.2 10.3
2002 0 3 3.5 6.7 3.5 238.5 252.6 245 142.1 30 0 0
2003 0 7 4.357 1.155 30.441 158.9 225.3 210 153.4 33.57 0 0
2004 0 0.7 0 52.1 18.8 173.2 311.8 242 136.7 58.7 8.6 2.5
2005 0.6 1.1 45.5 11.7 63.4 176.6 217 198 190 4.5 8.6 0
2006 0 0 0 30.9 112.3 168.6 257.2 298 204.6 93 0 13.2
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 3.509 0 3.526 27.4 106.73 168.7 210.4 208 91.9 194.9 4.3 0
1988 0 11.5 0.5 2.9 153.7 153.1 355.7 244 138.6 177.3 29 0
1989 0 0 16.9 87.8 135.2 154.8 320.2 246 135.3 82.2 10.4 0
1990 3.9 0 1.3 32.3 52.2 153.3 257.3 208 237.2 59.4 0 0
1991 0 0 0 231.6 24.103 99.87 195.8 250 149.8 139.1 2.9 2.8
1992 0 0 0 49.5 0 56.36 165.3 223 118.5 64.14 27.2 0
1993 0 1.9 5.1 143.3 112.5 109.3 320.1 233 292.9 117.9 4.2 0.7
1994 0 0.366 2.133 12.1 50.3 281 214.4 273 215.5 42.4 3.7 14.1
1995 0 0 57.9 33.8 111.5 155.9 300.6 320 121.6 41 6.8 0.2
1996 0 6.9 37.8 62.4 72.8 269.3 204.8 196 166.6 30.8 28.3 0
1997 0 0.5 6.1 95.4 156.6 203.4 208.1 195 134.2 227 75.6 0
1998 0 0 17.4 2.7 92.7 235.8 311 326 117.4 124.6 1.6 0
1999 0 0 0 27.7 120.8 157.4 391 274 189.1 154.3 0 4.4
2000 0 0 4.2 81.5 100.7 137.3 268.8 244 202 202.5 45.9 0
2001 0 3.6 2 29.5 144.8 267.3 307.6 290 104.3 120.8 0 0
2002 0 0 0 1 100.7 185 238.4 323 174.6 69.7 0 0
2003 0 6.9 0.3 2.5 34.7 143.1 225.3 223 221 54.8 0 0
2004 0 0 11 50.9 2.5 185.6 320.7 208 138.7 90.8 23.2 0
2005 0.216 3.467 36.8 18.6 40.6 234.8 261.5 72.4 157.1 20.36 7.871 0
2006 2.6 0 2.3 21.2 219.5 115.9 364.6 284 231.2 155.7 0 0
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 0 0 13.4 200 214.8 225.8 244.9 290 145.5 55.6 0.5 0
1988 0 8.2 0 0 87.2 99.3 422.1 335 243.8 53.1 0 0
1989 0 0 0.2 0.2 130.1 97 335.8 406 93.3 27.1 15.2 0
1990 0 0 0 0 0 28.5 134.4 319 304.8 36.2 0 0.8
1991 6.478 2.487 52.98 65.74 147.19 319.7 1.63 600 399.4 163.8 2.012 2.934
1992 0 0 9.756 99.46 82.087 149.9 332 444 210.4 183.8 73.11 13.88
1993 2.449 2.74 47.9 67.64 168.51 235.4 463 392 301.2 150.9 26.5 1.087
1994 1.968 7.729 7.988 27.07 131.12 275.3 381.6 449 227.7 30.25 22.33 20.32
1995 0.142 2.617 33.62 33.93 62.1 212 557.4 346 172.1 0 0 0
1996 0 0 34.6 32.6 148 323.5 460 411 288.8 20.9 53.1 0
1997 0 0 20.7 2.1 265 240.5 373.4 193 245 204.9 4 2.7
1998 0 0 30.9 0 56.2 271.5 434.7 679 270.5 114.3 0 2.7
1999 39.5 0 0 2 26.7 193.5 552.8 638 176.8 251.1 16.3 0
2000 0 0 0 86.3 102.67 151.2 464.3 516 140.5 148.1 3.6 0
2001 0 0 0 0.9 29.7 268.7 322.8 365 287.7 84.4 10.4 1.3
2002 0 1.4 0 15.4 5 386.7 648.9 508 204.3 37.1 0 0
2003 0 0 0 0 0.1 168.6 572.3 503 344.1 42.1 0.2 0
2004 2.1 0 9.5 1.2 2.1 143.8 538.4 385 305.5 154.3 11.9 0
2005 0 0 78.6 31.9 74.7 199.8 384.4 381 343.8 94 35.2 0
2006 0 0 0 1.6 195.3 189.6 663.6 391 268 162.1 4.015 4.267
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 16.1 0.3 58.3 21.4 155.8 146.7 273.8 369.6 56.1 65.1 27.2 0.0
1988 0.1 66.0 3.6 17.2 54.9 223.0 435.1 366.7 261.6 144.3 23.4 3.5
1989 6.2 0.2 84.3 45.8 94.8 85.3 304.7 425.5 139.3 103.6 6.6 37.7
1990 7.9 2.5 8.5 8.6 49.2 129.9 438.2 442.4 287.3 54.3 4.6 0.3
1991 6.2 2.4 51.1 63.4 141.9 308.1 438.6 578.4 385.0 157.9 1.7 2.8
1992 0.0 0.0 12.8 86.0 38.6 115.9 329.5 393.4 133.8 99.7 68.1 5.9
1993 0.8 2.0 86.3 74.5 199.4 137.2 429.8 289.9 208.8 118.6 23.3 1.1
1994 1.8 9.1 7.7 17.0 89.7 237.7 493.8 631.5 248.0 10.0 24.8 31.7
1995 0.0 0.0 22.7 34.6 100.4 73.0 399.7 403.6 186.9 5.0 23.4 25.3
1996 4.3 1.2 49.4 92.1 146.1 187.0 369.4 374.0 155.4 30.6 76.2 4.4
1997 3.4 0.0 73.7 43.1 197.6 215.1 439.7 359.0 197.0 305.0 12.3 82.5
1998 13.6 0.0 21.2 6.9 203.6 126.2 399.6 410.8 245.4 75.9 0.5 0.0
1999 34.5 0.0 0.0 9.5 44.3 181.4 476.5 345.7 182.1 275.0 11.2 19.5
2000 0.0 0.3 6.3 118.3 61.1 168.1 423.6 462.4 232.2 137.8 35.1 0.5
2001 0.0 1.3 17.2 24.0 95.4 197.5 496.7 410.0 184.8 60.1 4.5 7.2
2002 0.4 0.0 60.2 45.1 47.2 203.3 256.6 313.4 132.8 2.9 16.0 18.8
2003 0.0 13.9 24.1 28.1 10.5 86.2 435.7 396.8 221.7 16.7 33.3 14.8
2004 0.5 37.6 33.7 75.5 19.1 141.0 333.7 295.2 120.8 85.8 42.5 12.7
2005 1.3 0.0 34.1 10.3 56.3 224.4 473.6 436.0 384.1 86.8 22.8 0.0
2006 0.0 1.4 6.8 63.2 147.3 170.0 482.2 452.5 255.0 47.5 0.0 7.9
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 20.9 0.0 33.1 70.0 286.0 363.8 555.8 444.3 251.2 297.7 22.8 25.8
1988 8.9 33.4 15.1 9.8 252.6 345.9 452.9 586.9 399.3 163.3 28.9 0
1989 2.6 1.6 80.4 57.4 200.3 342.3 620.4 674.9 288.3 122.5 20.64 20.48
1990 30.4 0.0 45.1 4.2 186.2 221.4 510.2 480.4 418.3 105.4 22.4 0
1991 20.2 7.5 82.6 102.5 229.5 498.4 709.4 935.6 622.7 255.4 3.03 3.431
1992 0.0 0.0 14.0 164.2 194.7 249.2 367 483.9 407.9 223.2 53.9 25.5
1993 0.0 10.9 60.4 142.2 212.9 367.2 436.2 545.3 421.6 239.6 56.4 5
1994 7.0 22.3 0.0 42.6 209.0 435.7 416.1 560.3 383.4 75.4 37.5 42.3
1995 0.0 5.9 61.4 45.6 195.5 266.8 411.1 480.6 389.4 58.4 12.6 23.3
1996 2.6 7.9 76.6 164.8 300.0 297.8 555.1 587.9 247.5 153.2 9.6 0
1997 7.2 3.9 21.2 47.6 317.5 367.9 543.1 515.1 367.4 327.8 272.7 37.2
1998 13.3 0.0 10.3 27.6 262.5 439.2 401.1 441 359.7 249.3 46 4.7
1999 17.4 0.0 0.0 69.3 295.3 517.5 388.4 497.1 441.9 347.3 98 14.5
2000 0.0 0.0 6.5 100.2 186.2 444.6 425.4 536.3 484.9 400.8 62.8 48.4
2001 0.0 20.0 24.2 68.2 191.3 327.6 418.4 521.5 529 137.7 43.5 20.8
2002 21.8 0.0 24.7 29.3 93.3 372.9 576.2 500.2 336.6 159 39.9 2.5
2003 0.0 18.1 61.8 14.9 75.0 375.3 570.4 397.3 402.8 80.2 81.4 4.3
2004 18.8 9.1 21.6 103.4 55.4 320.2 605.1 388 422.3 133.3 71.3 44.1
2005 1.2 5.9 51.0 25.6 76.8 385.2 490 494.9 621.3 140.4 36.85 0
2006 2.2 8.1 4.4 44.8 325.0 380.7 604.1 603.7 406.1 268 15 0
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 12.8 0 2.1 36.5 210.6 207.5 232.6 195.2 125.1 90.6 17.4 3.7
1988 0 32.6 0 12.2 62.2 190.5 306.6 304.1 92.1 83.3 7.7 0.7
1989 0 1.4 38.7 32.4 59.7 206.4 269.1 279.7 108.1 34.5 7 11.9
1990 4.2 0 6.5 29.7 18 59.4 361.1 235.2 127.1 1.4 1.2 0
1991 0 9.3 0 93.89 29.308 35.9 285.9 269.9 67.5 64.9 35.9 0
1992 0 0 2.7 51.7 80.7 86.8 249.5 218.2 117.6 79.6 11.9 21.6
1993 0 3.5 30.8 78.5 104.2 166.6 305.4 201.9 136.6 86.7 16.5 0.5
1994 0 1 0 7.8 84.5 156 289.4 265.9 125 37.9 20 2.8
1995 0 0 34.5 23.9 99.3 105.9 283 307.1 91.8 11.9 0.9 19.8
1996 0 4.4 22.2 83.6 183.8 194.7 249.3 290 75.8 67.7 23.2 0.4
1997 0 1.8 28.4 42.8 124.2 176.8 239.9 230.4 33.1 200.3 40.2 13.7
1998 0 0 10 3.7 88.5 169.2 241.3 359.5 79 79.6 3 0
1999 22.2 0 0 26.4 80.1 92.5 285.4 242.5 133.4 239.6 7.1 33.1
2000 0 1.4 2.6 46 38.4 229.5 284.7 232.6 105.5 169.2 1.2 0
2001 0 0.6 2.1 29.4 56 254.8 358.5 310.4 74.5 91.6 10 0
2002 0 1.402 6.895 16.6 87.1 197.4 312.7 247.6 76.8 45.2 5.8 4.2
2003 0 22.1 11.1 0 37.9 244.2 318.7 280.7 134.9 21.7 0 0
2004 1.6 3.7 5.9 37.6 1.4 181.4 378.3 312.3 112.4 67.6 65.7 0
2005 0 11.2 60.8 12.1 24.2 137.5 304.1 274.2 169.3 42.8 17.4 0
2006 0 0 10.8 27.8 152.6 98.7 291.5 305.3 192.5 87.4 29.9 35
Table: A- 10. Stations used for the construction of Double Mass Curve Group-I
Table: A- 11. Stations used for the construction of Double Mass Curve
Group-II
Zege. D/Tabor. B/Dar. Dangila Engibara Group Group Group Group Group
1987 1390.904 1190.4 1191.6 1607.937 2371.404 1590.335 1640.461 1640.1 1536.07 1345.21
1988 2639.504 2789.739 2502.8 3395.437 4668.404 3339.095 3301.536 3373.2 3150.11 2831.87
1989 3744.004 4123.786 4103.4 5041.337 7100.208 5092.183 4997.237 5002.3 4767.84 4253.13
1990 4567.604 5557.531 5521.6 6642.680 9124.208 6711.505 6464.023 6473.0 6192.73 5572.35
1991 6331.975 7694.973 7124.322 8969.656 12594.52 9095.868 8755.118 8897.7 8436.44 7530.23
1992 7929.877 8978.673 8522.932 10426.81 14778.02 10676.61 10414.41 10528. 10052.3 8964.57
1993 9789.278 10550.37 10107.13 12140.81 17275.72 12518.51 12328.23 12439. 11930.6 10646.8
1994 11371.28 12353.17 11183.63 13458.71 19507.32 14125.71 13880.23 14172. 13603.8 12091.7
1995 12791.29 13627.77 12370.04 14651.51 21457.92 15526.81 15317.69 15632. 15061.7 13360.1
1996 14563.29 15117.87 13750.04 16335.01 23860.92 17265.96 17127.31 17469. 16823.0 14941.5
1997 16114.89 17046.27 14967.57 18057.21 26689.52 19190.14 18957.30 19476. 18704.5 16546.4
1998 17974.99 18549.97 16390.17 19612.21 28944.22 20874.14 20730.40 21270. 20464.8 18131.8
1999 19871.69 20129.67 17864.57 21572.41 31630.92 22799.39 22734.90 23301. 22374.2 19859.5
2000 21484.56 21775.37 19428.37 23351.44 34327.02 24720.55 24647.85 25234. 24253.8 21509.9
2001 22855.76 23274.07 20963.47 24742.94 36629.22 26402.42 26297.85 26875. 25930.6 22959.0
2002 24662.16 24370.77 22472.17 26084.03 38785.62 27928.15 28000.99 28475. 27572.6 24397.2
2003 26292.16 25652.57 24123.57 27453.53 40867.12 29524.20 29684.09 30066. 29233.8 25880.4
2004 27845.76 26850.67 25475.77 29080.63 43059.72 31116.70 31365.47 31709. 30807.9 27313.2
2005 29469.46 28580.35 26963.37 30662.06 45388.89 32898.67 33120.94 33525. 32600.5 28918.8
2006 31348.78 30214.15 28646.57 32568.76 48050.99 34870.12 35153.77 35545. 34565.1 30694.5
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 0.72 0.281 0.187 0.166 2.49 6.24 11.28 47.72 10.48 3.13 1.52 0.48
1988 0.209 0.24 0.067 0.043 0.16 0.82 64.85 99.07 26.2 11.5 4.51 1.38
1989 0.704 0.23 0.391 0.456 1.61 5.66 11.83 43.31 11.07 1.07 0.33 0.1
1990 0.324 0.14 0.088 0.075 0.31 1.57 29.6 37.02 19.07 3.14 1.09 0.69
1991 0.362 0.227 0.313 0.573 0.27 7.35 11.95 50.99 10.9 3.61 1.1 0.46
1992 0.276 0.15 0.26 1.125 0.67 1.1 20.58 52.25 40.13 6.77 3.41 1.98
1993 0.828 0.612 0.675 0.757 2.15 8.92 23.89 64.88 35.91 11.8 3.2 0.81
1994 0.865 0.373 0.249 0.23 1.03 6.55 31.36 107 32.45 4.1 2.28 1.26
1995 0.672 0.414 0.415 0.381 2.49 9.06 32.19 117.4 17.02 1.25 0.4 0.24
1996 0.075 0.034 0.032 0.52 4 29.9 40.89 89.01 20.27 5.51 2.55 1.29
1997 0.795 0.472 0.512 0.498 2.89 15.6 61.06 51.78 11.14 7.72 4.11 1.36
1998 0.549 0.402 0.576 0.536 1.01 5.61 66.63 142.9 41.53 15.5 2.87 5.46
1999 4.746 3.505 3.715 3.888 8.12 7.39 32.12 95.9 47.15 28.9 16 12.4
2000 10.17 6.493 7.577 10.75 10.2 13.5 34.03 71.41 32.15 23.5 12.1 9.77
2001 8.274 7.858 11.91 11.78 14.8 6.7 59.1 115.3 24.79 7.33 3.78 1.49
2002 0.996 0.525 0.595 0.38 0.76 3.39 47.96 50.69 18.97 7.12 5.41 4.45
2003 3.538 3.162 3.351 2.911 2.89 16.8 44.9 104.1 30.54 13 7.37 6.3
2004 4.261 3.675 3.766 5.606 3.81 10.4 55.75 90.86 23.58 16.2 9.48 7.94
2005 6.801 5.671 7.384 6.183 6.55 41.7 39.03 87.87 48.81 21.4 13 9.71
2006 8.366 7.088 7.517 7.655 11.4 5.64 63.77 157.3 62.32 28.1 18.3 14.2
Table: A-14: Stream flow for Ribb near Addis Zemen Station
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 0.434 0.251 0.25 0.166 2.317 3.317 6.927 34.95 12.705 1.78 0.73 0.322
1988 0.162 0.123 0.039 0 0.197 2.633 58.64 91.36 47.428 15.34 2.976 1.171
1989 0.99 0.572 0.495 0.506 0.639 4.782 26.93 68.06 22.126 6.911 2.673 1.806
1990 1.153 0.771 0.508 0.471 0.393 1.043 34.32 55.89 45.929 7.833 3.019 2.495
1991 1.831 0.699 0.508 1.301 1.36 20.39 48.57 96.72 70.417 6.227 2.032 1.149
1992 0.425 0.138 0.081 2.032 1 1.102 49.12 123.2 42.275 10.36 21.071 0.991
1993 1.091 0.541 0.389 1.613 4.189 4.807 41.08 54.38 44.819 10.46 2.341 0.62
1994 0.349 0.087 0.053 0.074 0.764 7.221 66.89 95.26 50.059 1.992 0.709 0.445
1995 0.309 0.243 0.231 0.66 0.565 1.42 33.16 71.47 29.139 1.838 1.032 0.828
1996 0.548 0.419 0.602 1.467 7.904 29.167 65.58 83.99 22.321 7.225 2.951 1.368
1997 0.742 0.4 0.659 0.457 4.638 7.617 44.29 52.27 13.02 8.562 7.808 1.631
1998 0.707 0.318 0.258 0.175 1.288 3.856 48.36 66.48 43.012 12.4 3.983 0.945
1999 0.805 0.491 0.363 0.298 0.386 3.416 45.27 70.81 39.862 41.03 12.955 13.08
2000 5.046 0.467 0.303 0.987 0.682 2.009 40.95 77.41 35.076 16.2 5.193 1.499
2001 0.803 0.481 0.492 0.427 0.531 15.312 57.55 73.22 26.7 5.056 1.844 0.881
2002 0.543 0.284 0.286 0.452 0.13 7.594 22.83 46.65 24.059 3.115 1.243 1.226
2003 0.704 0.509 0.565 0.131 0.062 3.974 44.27 65.97 44.303 8.415 4.071 3.103
2004 2.247 1.819 1.375 2.431 1.597 4.83 38.73 55.68 22.251 7.631 3.599 2.306
2005 1.293 0.880 1.585 0.627 0.955 9.082 44.826 60.456 40.669 10.574 4.841 3.406
2006 2.535 1.981 0.563 0.764 5.095 10.551 50.809 81.374 54.444 15.671 8.740 7.063
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 1.4325 0.8514 0.9179 1.0023 0.8562 3.3828 4.1295 3.585 3.6896 3.7472 1.1574 0.9066
1988 0.5779 0.6347 0.3328 0.1575 0.9528 3.8689 60.684 63.622 18.454 9.7028 3.7277 2.7684
1989 2.5046 2.1857 2.5988 2.3066 1.9243 3.8738 7.7209 50.026 32.38 8.4773 0.9844 0.5855
1990 0.2851 0.1094 0.2186 0.2027 0.1691 0.2345 15.544 25.464 20.883 3.3581 1.1435 0.9025
1991 0.597 0.0763 0.2186 0.3532 0.5852 8.7741 20.9 41.620 32.148 2.6193 0.6895 0.2833
1992 0.1829 0.0594 0.0349 0.6895 0.2148 0.2617 22.352 56.439 19.202 4.521 9.4478 0.2106
1993 0.53 0.3401 0.3855 1.0015 1.6818 1.7255 19.426 19.134 17.838 4.5647 0.6542 0.0399
1994 0.1542 0.0909 0.0852 0.0893 0.198 3.0765 30.526 43.576 22.783 0.6711 0.241 0.1355
1995 0.0641 0.0381 0.3806 0.9788 0.0146 0.8116 20.699 32.633 25.211 1.6411 0.2295 0.1356
1996 0.2776 0.1737 0.4959 1.2921 2.6799 11.59 45.413 59.754 17.211 2.6767 1.6557 1.1225
1997 0.6891 0.4529 0.5795 0.8993 1.6395 4.7049 38.327 38.668 6.7096 2.6166 7.8077 1.6638
1998 1.4203 0.0893 0.0641 0.0357 0.4618 1.5924 41.447 30.336 20.359 3.1166 0.3271 0.1355
1999 0.53 0.2492 0.1583 0.1161 0.1615 1.258 13.974 18.074 5.4768 5.3769 2.4754 1.3075
2000 0.8433 0.5657 0.4074 1.163 0.6412 2.7254 14.965 27.895 10.506 7.2315 4.6651 2.3634
2001 2.0152 1.6882 0.6793 0.6956 0.6744 4.2139 26.229 33.435 14.434 5.8769 4.364 0.823
2002 0.6907 0.5032 0.6509 0.5349 0.3685 4.4533 6.6779 4.2877 2.1094 0.646 0.3693 0.3263
2003 0.1642 0.1184 0.1776 0.036 0.0364 0.8326 11.066 16.066 12.005 2.7975 1.2544 0.7512
2004 0.5057 0.4734 0.3497 0.7474 0.416 1.9766 10.497 13.160 7.4898 3.5647 1.4269 0.965
2005 0.3497 0.1596 0.4837 0.0431 0.1938 3.9326 20.376 27.565 18.463 4.6188 1.9818 1.3215
2006 0.9211 0.6659 0.0136 0.1061 2.0987 4.6082 23.128 37.188 24.8 6.9637 3.7753 3.0039
Table: A- 156. Upper Ribb Gauging Station, Latitude: 12: 3: 0 N, Area: 844.0 sq km
Longitude: 37:59: 0 E, Time-Series Type: Mean Flow (m3/s)
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 1.765 1.049 1.131 1.235 1.055 4.168 5.088 4.418 4.546 4.617 1.426 1.1
1988 0.712 0.782 0.41 0.194 1.174 4.767 74.77 78.39 22.737 11.96 4.593 3.4
1989 3.086 2.693 3.202 2.842 2.371 4.773 9.513 61.64 39.896 10.45 1.2129 0.7
1990 0.3513 0.135 0.269 0.2497 0.208 0.289 19.153 31.38 25.73 4.138 1.409 1.1
1991 0.7356 0.094 0.269 0.4352 0.721 10.811 25.752 51.28 39.61 3.227 0.8495 0.3
1992 0.2253 0.073 0.043 0.8495 0.265 0.3224 27.541 69.54 23.659 5.57 11.641 0.2
1993 0.653 0.419 0.475 1.234 2.072 2.126 23.935 23.58 21.979 5.624 0.806 0.1
1994 0.19 0.112 0.105 0.11 0.244 3.7907 37.612 53.69 28.071 0.827 0.297 0.2
1995 0.079 0.047 0.469 1.206 0.018 1 25.504 40.21 31.063 2.022 0.2827 0.2
1996 0.342 0.214 0.611 1.592 3.302 14.28 55.954 73.63 21.206 3.298 2.04 1.4
1997 0.849 0.558 0.714 1.108 2.02 5.797 47.223 47.64 8.267 3.224 9.62 2.1
1998 1.75 0.11 0.079 0.044 0.569 1.962 51.067 37.38 25.085 3.84 0.403 0.2
1999 0.653 0.307 0.195 0.143 0.199 1.55 17.218 22.27 6.748 6.625 3.05 1.6
2000 1.039 0.697 0.502 1.433 0.79 3.358 18.439 34.37 12.945 8.91 5.748 2.9
2001 2.483 2.08 0.837 0.857 0.831 5.192 32.318 41.2 17.784 7.241 5.377 1.0
2002 0.851 0.62 0.802 0.659 0.454 5.487 8.228 5.283 2.599 0.796 0.455 0.4
2003 0.2024 0.146 0.219 0.0444 0.045 1.0258 13.635 19.8 14.792 3.447 1.5455 0.9
2004 0.6231 0.583 0.431 0.9209 0.513 2.4354 12.933 16.21 9.2283 4.392 1.7581 1.2
2005 0.4309 0.197 0.596 0.0531 0.239 4.8454 25.105 33.96 22.749 5.691 2.4418 1.6
2006 1.1349 0.82 0.017 0.1307 2.586 5.6779 28.496 45.82 30.556 8.58 4.6516 3.7
year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 4.2 2.4 1.8 1.1 9 38.8 92.5 340.1 110.6 27.4 12.4 5.5
1988 2.5 1.4 0.9 0.6 1.1 5.2 436.7 426.4 229.1 147 25.5 11.8
1989 5.7 2.7 1.6 1.3 2.3 27.6 166.8 391.1 169.7 41.921 14.939 13.2
1990 6.4 2.2 1.6 1 1.4 3.5 144.2 487.1 285.3 53.4 10.7 5.2
1991 2.7 1.3 1 1.2 2.2 37.8 224.6 452.9 200.7 63.5 12.5 12.9
1992 8.2 5.2 7.4 2.2 5.1 5.4 114.4 426.9 184.9 135.8 38.7 17.1
1993 7.2 3.2 1.9 2.4 5.7 26.6 232.3 376.5 261.3 101.2 30.4 12.7
1994 6.4 3.2 1.6 0.9 2.8 52.2 230 523 317.6 53.7 18.2 11.1
1995 5.8 4.1 4 3.6 4.2 13 167.1 402.1 256.4 66.5 44.1 34.1
1996 19.9 9 9.1 9 21.8 148.4 481.9 540 264.5 99 57.4 40.8
1997 28.9 19.3 17.8 12.9 20.3 125.4 381.9 402.7 207.5 158.8 141.7 45.3
1998 9.551 7.442 7.3 6.8502 5.1 27.8 181 372.2 240.7 74.4 22 22.4
1999 17.4 3.9 1.8 1.3 1.8 12.9 198.4 263.8 136.1 160.5 32.7 24.02
2000 36.82 9.465 8.76 6.6 4.7 34.5 292.8 467.5 136.1 130 33.1 13.9
2001 8.3 4.6 4.5 3.3 4.7 37.5 249.2 537.9 149.9 36.7 15.2 9.7
2002 7.4 4.8 5.2 4.3 3.1 64.6 246.7 421.1 207.7 33.1 17.6 13.7
2003 10.1 7.4 8.3 6.1 5.9 37.5 241.6 471.9 407.4 124.9 20.7 13.5
2004 9.9 7.9 6.9 7.8 6.4 24.4 209.4 284.8 137.9 55 21 14.1
2005 4.13 3.388 3.73 2.6979 3.546 14.26 76.8 121.7 132.13 40.333 9.2774 6.037
2006 4.391 3.585 3.41 3.3684 6.764 17.77 90.67 189.29 140.84 24.924 9.7686 5.862
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 2.11 1.22 0.93 0.62 4.05 15.8 35.1 118 41.33 11.79 5.601 2.654
1988 1.29 0.73 0.52 0.37 0.61 2.48 145 144.9 81.61 53.9 10.87 5.402
1989 2.76 1.39 0.88 0.73 1.17 12 80.5 133.8 61.8 21.02 12.83 5.961
1990 3.06 1.15 0.87 0.58 0.78 1.68 52.2 163.4 100.3 21.12 4.923 2.528
1991 1.35 0.7 0.57 0.63 1.14 14.1 80.5 148.3 71.84 25 5.593 5.843
1992 3.84 2.43 3.38 1.14 2.42 2.51 43.8 144.5 67.01 50.48 15.93 7.56
1993 1.6 0.7 0.42 0.53 1.27 5.87 51.2 83.01 57.62 22.31 6.698 2.803
1994 1.41 0.7 0.36 0.2 0.61 11.5 50.7 115.3 70.02 11.84 4.012 2.449
1995 1.28 0.89 0.87 0.8 0.94 2.87 36.8 88.67 56.54 14.65 9.731 7.528
1996 4.4 1.91 2.01 1.98 4.81 9.87 106 119.1 58.33 21.84 12.66 8.977
1997 6.38 4.27 3.91 2.85 4.46 12.4 84.2 88.8 45.75 35.01 31.26 10
1998 1.43 0.8 0.7 0.48 1.12 6.12 39.9 82.06 53.07 16.41 4.847 4.945
1999 3.84 0.86 0.4 0.29 0.4 2.83 43.8 58.17 30.02 35.4 7.201 2.473
2000 1.95 1.1 0.95 1.46 1.04 7.61 64.6 103.1 30.02 28.67 7.299 3.063
2001 1.83 1.02 1 0.73 1.03 8.28 54.9 118.6 33.05 8.087 3.361 2.15
2002 1.63 1.06 1.15 0.95 0.68 14.2 54.4 92.85 45.8 7.292 3.871 3.024
2003 2.24 1.64 1.83 1.33 1.31 8.28 53.3 104.1 89.83 27.55 4.557 2.984
2004 9.95 7.88 6.9 7.77 6.44 24.4 209 284.8 137.9 55.03 21 14.13
2005 1.138 0.922 1.02 0.721 0.97 4.09 22.3 35.39 38.42 11.68 2.638 1.694
2006 1.214 0.98 0.93 0.916 1.91 5.11 26.3 55.08 40.96 7.196 2.781 1.643
Yea Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1987 4.9 3.7 3.1 2.7 14.7 68.2 165.1 199.8 155.8 78.1 24.7 11.5
1988 7.2 5.2 3.3 2.3 5.1 35.6 192.0 256.4 192.0 89.2 24.3 10.4
1989 6.1 3.8 4.0 3.7 8.9 48.7 240.6 284.3 172.0 54.7 16.0 10.6
1990 6.3 4.4 3.2 2.4 3.6 17.2 125.5 217.7 164.9 50.7 12.0 6.7
1991 4.6 3.1 2.5 5.4 10.9 68.3 235.4 268.4 201.0 52.0 13.6 7.8
1992 5.2 3.6 2.8 4.7 8.2 37.7 150.0 241.6 179.2 110.9 36.3 13.5
1993 6.8 4.7 3.9 6.2 11.1 92.5 232.1 221.5 191.2 110.8 28.3 10.1
1994 5.9 4.2 3.0 2.6 8.9 76.0 182.3 219.4 146.5 28.9 12.9 7.9
1995 4.4 3.1 2.3 2.4 13.7 55.8 114.4 245.7 162.7 31.4 12.6 7.0
1996 4.4 2.8 5.0 4.8 24.4 105.2 250.7 276.1 175.0 105.6 84.1 59.1
1997 3.6 2.4 2.2 2.1 22.7 75.1 198.7 243.0 154.5 78.5 44.1 13.0
1998 5.5 3.1 2.3 1.6 12.5 79.4 176.2 227.9 189.9 118.7 22.6 8.1
1999 4.6 2.6 1.8 2.1 11.0 71.3 201.4 230.8 157.0 151.3 24.3 9.4
2000 4.2 2.5 1.8 3.8 7.5 60.6 180.4 251.0 165.7 156.8 45.3 11.1
2001 4.7 2.9 2.2 2.2 7.4 83.0 186.4 254.3 158.9 50.9 17.1 6.7
2002 3.8 2.2 1.7 1.3 1.2 47.2 179.0 207.9 123.1 35.8 12.5 5.2
2003 2.7 1.9 1.5 0.8 1.1 53.7 220.4 227.5 214.6 40.4 12.6 5.0
2004 2.9 1.7 1.2 2.8 1.4 33.9 169.7 205.0 170.0 79.0 14.1 6.3
2005 3.2 1.8 2.0 1.3 2.1 41.6 161.7 146.0 148.5 62.1 19.5 17.5
2006 15.0 12.1 10.6 10.0 39.6 103.9 172.7 268.1 231.4 93.0 60.8 41.2
R.H (%) 60 53 50 49 59 72 79 82 76 70 67 63
S.H(hour) 9.7 10.3 10.7 10.1 9.2 6.5 4.9 5.4 6 9.5 8.4 9.3
W.S(Km/day) 43.2 51.8 51.8 69.1 60.5 60.5 51.8 51.8 51.8 51.8 51.8 43.2
Gonder
o
T Max( C) 27.8 28.9 29.9 29.5 28.6 25 22.9 22.9 25.3 26.2 27 27.2
o
T Min( C) 11.5 12.9 14.8 15.7 15.5 14.1 13.3 13.3 12.9 12.6 12.4 11.8
R.H (%) 41.9 38.4 37.2 40.3 50.4 63 78.9 79.2 72.3 60.8 50.8 45.6
S.H(hour) 9.4 8.9 8.3 7.6 7.1 4.9 4.2 5 7.2 7.5 8.7 8.9
W.S(Km/day) 138 153 162 155 162 164 124 109 121 117 125 131
Debre Tabor
o
T Max( C) 23.9 24.4 24.5 24.8 24.3 22.3 19.1 19 20.4 21 21.6 22
o
T Min( C) 8.6 9.6 10.4 11 11 10 9.4 9.4 8.9 8.6 8.4 8.1
R.H (%) 46.7 43.8 46.5 48.9 57.4 75.9 86.8 86.6 80.1 71.2 61.9 56
S.H(hour) 8.2 7.8 7.8 7.1 7.3 5.4 4.6 5.2 6.6 7.2 7.8 8
W. 101 109 111 111 118 120 94.8 107 104 83.1 84.8 92.2
S(Km/day)
Dangila
o
T Max( C) 25.9 27.5 28.1 27.9 26.6 24.1 22.1 22.3 23.6 24.3 24.9 25.6
o
T Min( C) 4.2 5.8 7.8 9.3 10.1 10.6 10.9 10.9 10.3 8.8 6.9 4.9
R.H (%) 60 62 58 77 71 79 83 83 81 75 68 64
S.H(hour) 9 9.7 7.9 9.1 7.5 5.2 3.6 5.1 6.5 7.1 9.1 7.9
W.S(Km/day) 69.1 69.1 69.1 77.8 77.8 77.8 77.8 77.8 69.1 69.1 60.5 60.5
N.B: T = Tempratur, R.H = Relative Humidity, S.H = Sunshine Hours, W.S = Wind Speed
APPENDIX – B
FIGURES
Figure: B- 1. Double mass curve of the rainfall stations in the study area
15000
10000
5000
0
1003
2091
3088
3934
4860
5615
6680
7596
8526
9775
11089
12297
13660
14904
16282
17243
18146
19193
20136
21403
Group mean annual cummulative Rainfall
20000
Cummulative Average
Rainfall,Chilga(Aykel)
15000
10000
5000
0
914.6
2834
4415
6069
7844
10648
13091
15672
17451
19453
Group Mean Annual Cummulative Rainfall
20000
15000
Series1
10000
5000
0
968.8
3153
4942
6823
8913
11514
13817
16247
18189
20198
Dangila
20000
15000
10000
5000
0 1536
4768
8436
11931
15062
18705
22374
25931
29234
32601
Goup Mean Anuual Cummulative Rainfall
20000
15000
10000
5000
0
1590
5092
9096
12519
15527
19190
22799
26402
29524
32899
Group Mean Annual Rainfall
20000
15000
10000
5000
0
1640
4997
8755
12328
15318
18957
22735
26298
29684
33121
Engibara
40000
30000
20000
10000
0
1345
4253
7530
10647
13360
16546
19860
22959
25880
28919
Group Mean Annual Cummulativa Rainfall
20000
15000
10000
5000
0
1640
5002
8898
12439
15632
19477
23301
26876
30066
33525
Group Mean Annual Rainfall
20000
15000
10000
5000
0
2900
4603
6254
8126
876.3
10947
13507
16174
17930
19820
1960
1950
1940
1930
Elevation,m asl
1920
1910
1900
1890
1880
1870
0 25 50 75 100 125 150 175 200 225 250 275 300 325 350 375 400
Volume (Mm3)
TOTAL VOLUME (MCM) AREA (km2)
(A)
Elevation~Area~Volume of Ribb Reservoir
Area, Km 2
11 10 9 8 7 6 5 4 3 2 1 0
1940
1930
Elevation, masl
1920
1910
1900
1890
1880
1870
0 20 40 60 80 100 120 140 160 180 200 220 240 260
(B)
12 11 10 9 8 7 6 5 4 3 2 1 0
1965
1960
1955
1950
Elevation, m asl
1945
1940
1925
1920
0 25 50 75 100 125 150 175 200 225 250 275 300 325
Volume,Mm3 Volume~Elevation
Area~Elevation
(C)
1890
1880
1870
1860
1850
1840
1830
1820
0 100 200 300 400 500 600
Volume(Mm3) Elevation~Volume
Elevation~Area
(D)
2400
2100
1800
1500
1200
900
600
300
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 14622 ha
4000
Minimum Power
3500
Average Power
3000
Power, kw
Maximum Power
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 14622 ha
30
Release Volume
25 Irr.Req.
Volume, Mm3
20
Firm Flow
15
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
2500
Maximum R.W.L
2000
1500
1000
500
0
Jan Feb M ar Apr M ay Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 13890.9 ha
3900
3600
3300
3000
2700
Power, kw
2400
2100
1800
1500
1200
900
600
300
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 13891 ha
35000
Series1
30000
Series2
25000 Series3
Power, kw
20000
15000
10000
5000
0
Year Jan Feb Mar Apr May Jun Jul Aug Sep
Months
(B)
Release Volume, 13891 ha
25
Releas e Volum e
20 Irr. Req.
Firm Flow
Volume, Mm3
15
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
1940 Minimum
1920 Average
R.W.L
1910
1900 Maximum
R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 13159.8 ha
3900
3600
3300
3000
2700
Power, kw
2400
2100
1800
1500
1200
900
600
300
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 13160 ha
4000
Minimum Power
3500
Average Power
3000
Maximum Power
Power, kw
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release volume, 13160 ha
25
Releas e volum e
20 Irr.Requirem ent
Firm Releas e
Volume, Mm3
15
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
1930
Average
1920 R.W.L
1910
Maximum
1900 R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 12428.7 ha
3900
3600
3300
3000
2700
Power, kw
2400
2100
1800
1500
1200
900
600
300
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, kw
(A)
Power, 12428.7 ha
4000
Mi nimum Power
3500
Average Power
3000
Maximum Power
Power, kw
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume,12428.7 ha
25
Release Volume
20 Required Release
Firm Release
Volume, Mm3
15
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Months
(D)
PDC for 11697.6 ha
3900
3600
3300
3000
2700
Power, kw
2400
2100
1800
1500
1200
900
600
300
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 11698 ha
4000
Minim um Power
3500
Average Power
3000
Maxim um Power
Power, kw
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 11698 ha
25
Release Volume
20 Irr. Req
Volume, Mm3
Firm Flow
15
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Minimum
1940
R.W.L
Average
1920
R.W.L
1910
Maximum
1900
R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 10966.7 ha
3900
3600
3300
3000
2700
Power, kw
2400
2100
1800
1500
1200
900
600
300
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 10967 ha
4000
Minimum Power
3500
Average Power
3000
Maximum Power
Power, kw
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 10967 ha
20
18 Release Volume
16 Irr.Req.
Volume, Mm3
14 Firm Flow
12
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
1910
Maximum
R.W.L
1900
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 10235.4 ha
3900
3600
3300
3000
2700
Power, kw
2400
2100
1800
1500
1200
900
600
300
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 10235 ha
4000
Minimum
3500
Average Power
3000
Maximum Power
Power, kw
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 10235 ha
20
18 Releas e Volum e
16 Irr.Req.
14 Firm Flow
Volume, Mm3
12
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Minimu
1940
m R.W.L
Reservoir, m asl
1930
Average
1920 R.W.L
1910
Maximu
1900 m R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 9504.3 ha
4000
3500
3000
Power, kw
2500
2000
1500
1000
500
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 9504 ha
4000
Minimum Power
3500
Average Power
3000 Maximum Power
Power, kw
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 9504 ha
18
16 Release Volume
14 Irr.Req.
Volume, Mm3
12 Firm Flow
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Minimu
1940
m R.W.L
1920
Average
R.W.L
1910
1900 Maximu
m R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 8773.2 ha
3900
3600
3300
3000
2700
Power, kw
2400
2100
1800
1500
1200
900
600
300
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 8773 ha
4000
Minimum Power
3500
Average Power
3000
Maximum Power
Power, kw
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 8773.2
16
Release Volum e
14
Irr. Req.
12
Volume, Mm3
Firm Flow
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
1940 Minimum
1920 Average
R.W.L
1910
1900 Maximum
R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 8042.1 ha
3900
3600
3300
3000
2700
Power, kw
2400
2100
1800
1500
1200
900
600
300
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 8042 ha
4000
Minim um Power
3500
Average Power
3000
Maxim um Power
Power, kw
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 8042 ha
16
Releas e Volum e
14
Irr. Req.
12
Volume, Mm3
Firm Flow
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
1940 Minimum
1920 Average
R.W.L
1910
1900 Maximum
R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 7311 ha
3900
3600
3300
3000
2700
Power, kw
2400
2100
1800
1500
1200
900
600
300
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 7311 ha
4000
3500 Minimum Power
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 7311 ha
16
Firm Flow
14
Release Volume, Mm3
Irr.Req.
12
Release Volume
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
1940
Minimum
R.W.L
Reservoir W.L
1930
1920 Average
R.W.L
1910
1900 Maximum
R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
( D)
Figure: B- 4. SSR outputs of Megech reservoir for alternative two
(A). Power duration curve (C). Release Volume
(B). Annual power generated (D). Reservoir Rule Curve
PDC for G.W.S + 7311 ha
2600
2400
2200
2000
1800
Power, kw
1600
1400
1200
1000
800
600
400
200
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 7311 ha + G.W.S
3000
Minimum Power
2500
Average Minimum Power
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Volume, Mm3
12 Firm Flow
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir W.L, 7311 ha + G.W.S
1950
1940 Minimum
R.W.L
Reservoir W.L, masl
1930
1920 Average
R.W.L
1910
1900 Maximum
R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for G.W.S + 6945.45
2600
2400
2200
2000
1800
Power, kw
1600
1400
1200
1000
800
600
400
200
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 6946.45 ha + G.W.S
2500
Minimum Powere
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Volume, Mm3
10 Release Volume
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir W.L, 6945.45 ha + G.W.S
1950
1940 Minimu
Reservoir W.L, m asl
m R.W.L
1930
1920
Average
R.W.L
1910
1900
Maximu
1890 m R.W.L
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
( D)
PDC for G.W.S + 6579.9 ha
2400
2200
2000
1800
1600
Power, kw
1400
1200
1000
800
600
400
200
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 6579.9 ha + G.W.S
2500
Minimum Power
2000 Average Power
Maximum Power
Power, kw
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Volume, Mm3
Firm Flow
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir W.L,6579.9 ha + G.W.S
1950
Minimum
1940
R.W.L
Reservoir W.L,m asl
1930
1920 Average
R.W.L
1910
1900 Maximum
R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for G.W.S + 6214.35 ha
2400
2200
2000
1800
1600
Power, kw
1400
1200
1000
800
600
400
200
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 6214.35ha + G.W.S
2500
Minimum Power
2000 Average Power
Maximum Power
Power, kw
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Volume, Mm3
Firm flow
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 6214.35 ha + G.W.S
1950
1940 Minimum
Reservoir W.L, m asl
R.W.L
1930
Average
1920
R.W.L
1910
Maximum
1900
R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for G.W.S + 5848.8 ha
2400
2200
2000
1800
Power, kw
1600
1400
1200
1000
800
600
400
200
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 5848.8 ha + G.W.S
2500
Minimum Power
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Volume, Mm3
Firm Flow
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 5848.8 ha + G.W.S
1950
Minimu
1940 m
Reservoir W.L, m asl
R.W.L
1930
Average
1920 R.W.L
1910
Maximu
1900 m
R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for G.W.S + 5483.25 ha
2400
2200
2000
1800
Power, kw
1600
1400
1200
1000
800
600
400
200
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 5483.25 ha + G.W.S
2500
Minimum Power
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Volume, Mm3
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 5483.25 ha + G.W.S
1950
1940 Minimum
R.W.L
Reservoir W.L, m asl
1930
Average
1920
R.W.L
1910
Maximu
1900 m R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for G.W.S + 5117.7 ha
2400
2200
2000
1800
1600
Power, kw
1400
1200
1000
800
600
400
200
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 5117.7 ha + G.W.S
2500 Minim um Power
Average Power
2000 Maxim um Power
Power, kw
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Volume, Mm3
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 5117.7 ha + G.W.S
1950
Minimum
1940 R.W.L
Reservoir W.L, m asl
1930
1920 Average
R.W.L
1910
1900 Maximu
m R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for G.W.S 4752.15 ha
2400
2200
2000
1800
1600
Power, kw
1400
1200
1000
800
600
400
200
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 4752.15 ha + G.W.S
2500 Minim um Power
Average Power
2000
Maxim u Power
Power, kw
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Volume, Mm3
Firm Flow
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 4752.15 ha + G.W.S
1950
Minimum
1940
R.W.L
Reservoir W.L, m asl
1930
Average
1920 R.W.L
1910
Maximu
1900 m R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for G.W.S + 4386.6 ha
2600
2400
2200
2000
1800
Power, kw
1600
1400
1200
1000
800
600
400
200
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 4386.6 ha + G.W.S
2500
Minimum Power
Average Power
2000
Maximum Power
Power, kw
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Volume, Mm3
10
8
6
4
2
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 4386.6 ha + G.W.S
1950
Minim
1940 um
Reservoir W.L, m asl
R.W.L
1930
Avera
1920 ge
R.W.L
1910
Maxim
um
1900
R.W.L
1890
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
6000
5000
Power, kw
4000
3000
2000
1000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power,15940 ha
7000
Minimum Power
6000
Average Power
5000
Power, kw
Maximum Power
4000
3000
2000
1000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume,15940 ha
50
45 Monthly Releas Volume
40 Irr. Req
Volume, Mm3
35 Firm Flow
30
25
20
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir W.L,15940 ha
1950
1940 Minimum
Reservoir W.L, m asl
R.W.L
1930
1920 Maximum
R.W.L
1910
1900
Average
1890 R.W.L
1880
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 14943.75 ha
7000
6000
5000
Power, kw
4000
3000
2000
1000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power,14944 ha
7000
Minimum Power
6000
Average Power
5000
Maximum Power
Power, kw
4000
3000
2000
1000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 14944 ha
50
Release Volume
45
40 Irr. Req
Firm Flow
Volume, Mm3
35
30
25
20
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level,14944 ha
1950
1940 Minimu
m R.W.L
Reservoir W.L, m asl
1930
1920 Maximu
m R.W.L
1910
1900
Average
1890 R.W.L
1880
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 13947.5 ha
7000
6000
5000
Power, kw
4000
3000
2000
1000
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 13948 ha
7000
Minimum Power
6000 Average Power
5000 Maximum Power
Power, kw
4000
3000
2000
1000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 13948ha
45
Release Volume, Mm3
40
35
Irr. Req.
Volume, Mm3
30 Firm Flow
25
20
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir W.L,13948 ha
1950
Minim
1940 um
Reservoir W.L, m asl
1930 R.W.L
1920 Averag
e
1910 R.W.L
1900 Maxim
1890 um.R.
W.L
1880
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 12951.25 ha
6000
5000
4000
Power, kw
3000
2000
1000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 12951 ha
6000
5500 Minimum Power
5000 Average Power
4500
Maximum
Power, kw
4000
3500
3000
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 12951 ha
40
Release Volume
35
Irr.Req.
30
Firm Flow
Volume, Mm3
25
20
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
( C)
Reservoir W.L, 12951 ha
1950
Minim
1940 um
Reservoir W.L, m asl
R.W.L
1930
1920 Averag
e
1910 R.W.L
1900
Maxim
1890 um
R.W.L
1880
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 11955 ha
6000
5000
4000
Power, kw
3000
2000
1000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 11955 ha
6000
Minimum Power
5000 Average Power
Maximum Power
4000
Power, kw
3000
2000
1000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 11955 ha
40
35
Release Volume
30 Irr. Req.
Volume, Mm3
25
Firm Flow
20
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir W.L, 11955 ha
1950
Minimu
1940 m
Reservoir W.L, m asl
1930 R.W.L
1920 Average
R.W.L
1910
1900 Maimu
1890 m
R.W.L
1880
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 10958.75 ha
5000
4000
Power, kw
3000
2000
1000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 10959 ha
5000
4500 Minimum Power
4000 Average Power
3500 Maximum Power
Power, kw
3000
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 10959 ha
35
Release Volume
30
Irr. Req.
25
Volume, Mm3
Firm Flow
20
15
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir W.L,10959 ha
1950
Minimu
1940
Reservoir W.L, m asl
m
1930 R.W.L
1920 Averag
e
1910 R.W.L
1900 Maxim
um
1890
R.W.L
1880
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
PDC for 9962.5 ha
4500
4000
3500
Power, kw
3000
2500
2000
1500
1000
500
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 9963 ha
4500
Minimum Power
4000
3500
Average Power
3000 Maximum Power
Power, kw
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 99623 ha
35
Release Volume
30
Irr.Req.
25 Firm flow
Volume,Mm3
20
15
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir W.L, 99623 ha
1950
Minimu
1940 m
Reservoir W.L, m asl
1930 R.W.L
1920 Average
R.W.L
1910
1900 Maximu
1890 m
R.W.L
1880
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
5600
4800
Power, kw 4000
3200
2400
1600
800
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 14000 ha
7000
Minimum Power
6000
Average Power
5000
Power, kw
Maximum Power
4000
3000
2000
1000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 14000 ha
50
Release Volume
45
40 Irr.Req
Volume, Mm3
35 Firm Flow
30
25
20
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 14000 ha
1970
1960 Minimum
Reservoir W.L, m asl
R.W.L
1950
1940 Average
R.W.L
1930
1920
Maximum
1910 R.W.L
1900
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
3500
3000
2500
2000
1500
1000
500
0
0 10 20 30 40 50 60 70 80 90 100 110
Time, %
(A)
Power, 13300 ha
6000 Minimum Power
5000 Average Power
Maximum Power
Power, kw
4000
3000
2000
1000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release, 13300 ha
45
40 Release Volume
35 Irr.Req
Volume, Mm3
30 Firm Flow
25
20
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 13300 ha
1970
Minimum
Reservoir W.L, m asl
1960
R.W.L
1950
1940 Average
R.W.L
1930
1920
Maximum
1910 R.W.L
1900
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
5000
4000
Power, kw
3000
2000
1000
0
0 10 20 30 40 50 60 70 80 90 100 110
Time, %
(A)
Power, 12600 ha
6000
Minimum Power
5000 Average Power
Maximum Power
4000
Power, kw
3000
2000
1000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release, 12600 ha
45
40
Release Volume
35
Irr.Req.
Volume, Mm3
30
Firm Flow
25
20
15
10
5
0
1 2 3 4 5 6 7 8 9 10 11 12
Months
(C)
Reservoir Water Level, 12600 ha
1970
1960 Minimum
R.W.L
Reservoir W.L, m asl
1950
1940
Average
R.W.L
1930
1920
Maximum
1910 R.W.L
1900
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
5000
4000
Power, kw
3000
2000
1000
0
0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 90.0 100.0 110.0
Time, %
(A)
Power, 11900 ha
6000
Minimum Power
5000
Average Power
4000
Power, kw
Maximum Power
3000
2000
1000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release, 11900 ha
40
35 Release Volume
Volume, Mm3
30 Irr.Req.
25 Firm Flow
20
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 11900 ha
1970
1960 Minimum
Reservoir W.L, m asl
R.W.L
1950
1940
Average
1930 R.W.L
1920
Maximum
1910 R.W.L
1900
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
5000
4000
Power, kw
3000
2000
1000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 11200 ha
6000
Minimum Power
5000
Averag Power
4000 Maximum Power
Power, kw
3000
2000
1000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release, 11200 ha
40
35
Release
Volume, Mm3
30 Irr.Req.
25 Firm Power
20
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 11200 ha
1970
1960 Minimum
Reservoir W.L, m asl
R.W.L
1950
1940
Average
1930 R.W.L
1920
Maximum
1910
R.W.L
1900
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
5000
4000
Power, kw
3000
2000
1000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 10500 ha
6000
Minim um Power
5000
Average Power
4000
Power, kw
Maximum Power
3000
2000
1000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release, 10500 ha
35
Release Volume
30
Irr.Req.
25 Firm Flow
Volume, Mm3
20
15
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 10500 ha
1970
1960 Minimum
Reservoir W.L, m asl
R.W.L
1950
1940 Average
R.W.L
1930
1920
Maximum
1910 R.W.L
1900
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
3000
2500
2000
1500
1000
500
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 9800 ha
5000
4500 Minimum Power
4000 Average Power
3500 Maximum Power
Power, kw
3000
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release, 9800 ha
35
Release Volume
30
Volume, Mm3
Irr.Req.
25
Firm Flow
20
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 9800 ha
1970
1960 Minimum
Reservoir W.L, m asl
R.W.L
1950
1940 Average
R.W.L
1930
1920
Maximum
1910 R.W.L
1900
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
2500
2000
1500
1000
500
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 9100 ha
4500
Minimum Power
4000
Average Power
3500
Maximum Power
Power, kw
3000
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release, 9100 ha
30
Release Volume
25
Irr.Req.
Volume, Mm3
20 Firm Flow
15
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 9100 ha
1970
Reservoir W.L, 9100 ha
1960 Minimum
R.W.L
1950
Average
1940
R.W.L
1930
Maximum
1920
R.W.L
1910
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
2500
2000
1500
1000
500
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 8400 ha
4500
4000 Minimum Power
3500 Average Power
3000 Maximum Power
Power, kw
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release, 8400 ha
30
Release
25 Irr.Req.
Volume, Mm3
20 Firm Flow
15
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 8400 ha
1970
Reservoir Water Level
1960 Minimum
R.W.L
1950
1940 Average
R.W.L
1930
1920 Maximum
R.W.L
1910
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
3000
2500
2000
1500
1000
500
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 7700 ha
5000
4500 Minimum Power
4000 Average Power
3500 Maximum Power
Power, kw
3000
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release, 7700 ha
30 Release Volume
25 Irr.Req.
Volume, Mm3
Firm Flow
20
15
10
5
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 7700 ha
1970
Minimu
Reservoir W.L, m asl
1960 m
R.W.L
1950
Average
1940 R.W.L
1930
Maximu
1920 m
R.W.L
1910
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
3000
2500
2000
1500
1000
500
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 7000ha
5000
4500 Minimum Power
4000 Average Power
3500 Maximum Power
Power, kw
3000
2500
2000
1500
1000
500
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release, 7000 ha
30
Release
25 Irr.Req.
Firm Flow
Volume, Mm3
20
15
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 7000 ha
1965
1960 Minimum
1955 R.W.L
Reservoir W.L, m asl
1950
1945
Average
1940
R.W.L
1935
1930
1925 Maximum
1920 R.W.L
1915
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
10000
8000
6000
4000
2000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 12490 ha
16000
Minimum Power
14000
Average Power
12000
Mximum Power
Power, kw
10000
8000
6000
4000
2000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 12490 ha
100
90 Release
80 Volume
Volume, Mm3
70
60
Irr.Req.
50
40
30
20 Firm Flow
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 12490 ha
1905
1900
Minimum
1895 R.W.L
Reservoir .W.L, m asl
1890
1885
Average
1880
R.W.L
1875
1870
1865 Maximum
1860 R.W.L
1855
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
10000
8000
6000
4000
2000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 11865.5 ha
16000
Minimum Power
14000
Average Power
12000 Maximum Power
Power, kw
10000
8000
6000
4000
2000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 11865.5 ha
100
Release
80 Volume
Volume, Mm3
60
Irr. Req.
40
20 Firm Flow
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 11865.5 ha
1905
1900 Minimu
Reservoir W.L, m asl
m
1895
R.W.L
1890
1885 Averag
1880 e
1875 R.W.L
1870
Maximu
1865 m
1860 R.W.L
1855
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
10000
8000
6000
4000
2000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 11241 ha
16000
Minimum Power
14000
Average Power
12000
Maximum Power
Power, kw
10000
8000
6000
4000
2000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 11241 ha
100
90 Release
80 Volume
Volume, Mm3
70
60
Irr.Req.
50
40
30
20 Firm Flow
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 11241 ha
1905
1900 Minimu
m
Reservoir W.L, m asl
1895
R.W.L
1890
1885 Averag
1880 e
1875 R.W.L
1870
Maxim
1865
um
1860 R.W.L
1855
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
10000
8000
6000
4000
2000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 10616.5 ha
16000
Minimum Power
14000
Average Power
12000
Maximum Power
Power, kw
10000
8000
6000
4000
2000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 10616.5 ha
100
90 Release
80 Volume
Volume, Mm3
70
60
Irr. Req.
50
40
30
20 Firm Flow
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 10616.5 ha
1905
1900 Minimu
m,
Reservoir W.L, m asl
1895
R.W.L
1890
1885 Average
1880 R.W.L
1875
1870
Minimu
1865 m R.W.L
1860
1855
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
10000
8000
6000
4000
2000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 9992 ha
16000
Minimum Power
14000
Average Power
12000
Maximum Power
Power, kw
10000
8000
6000
4000
2000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 9992 ha
100
90 Release
80 Volume
Volume, Mm3
70
60 Irr. Req.
50
40
30 Firm Flow
20
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 9992 ha
1905
1900 Minimu
m
Reservoir W.L, m asl
1895
R.W.L
1890
1885 Averaeg
1880 R.W.L
1875
1870
Maximu
1865
m
1860 R.W.L
1855
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
10000
8000
6000
4000
2000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 9367.5 ha
16000
Minimum Power
14000
Average Power
12000 Maximum Power
Power, kw
10000
8000
6000
4000
2000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 9367.5 ha
100
90 Release
80 Volume
Volume, Mm3
70
60
Irr.Req.
50
40
30
20 Firm Flow
10
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 9367.5 ha
1905
1900 Minimu
m
Reservoir W.L, m asl
1895
R.W.L
1890
1885 Averag
1880 e R.W.L
1875
1870 Minimu
1865 m
1860 R.W.L
1855
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
8000
6000
4000
2000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 8743 ha
16000
Minimum Power
14000
Average Power
12000
Maximum Power
Power, kw
10000
8000
6000
4000
2000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 8743 ha
120
Release
100 Volume
Volume, Mm3
80
Irr. Req.
60
40
Firm Flow
20
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 8743 ha
1905
1900 Minimum
Reservoir W.L, m asl
1895 R.W.L
1890
1885
Average
1880
R.W.L
1875
1870
1865 Maximum
R.W.L
1860
1855
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
10000
8000
6000
4000
2000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 8118.5 ha
18000
Minimum Power
16000
14000 Average Power
Power, kw
(B)
Release Volume, 8118.5 ha
120
Release
100
Volume
Volume, Mm3
80
Irr. Req.
60
40
Firm Flow
20
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 8118.5 ha
1905
1900 Minimu
Reservoir W.L, m asl
1895 m R.W.L
1890
1885
Average
1880 R.W.L
1875
1870
1865 Maximu
m R.W.L
1860
1855
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
10000
8000
6000
4000
2000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 7494 ha
18000
Minimum Power
16000
Average Power
14000
12000
Maximum Power
Power, kw
10000
8000
6000
4000
2000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 7494 ha
120
Release
100
Volume
Volume, Mm3
80
Irr. Req.
60
40
Firm Flow
20
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 7494 ha
1905
1900 Minimu
Reservoir W.L, m asl
R.W.L
1895
1890
1885 Averag
1880 e
1875 R.W.L
1870 Maximu
1865 R.W.L
1860
1855
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
12000
10000
8000
6000
4000
2000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 6869.5 ha
18000
Minimum Power
16000
Average Power
14000
Maximum Power
12000
Power, kw
10000
8000
6000
4000
2000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Releaswe Volume, 6869.5 ha
120
Release
100
Volume
Volume, Mm3
80
Irr. Req.
60
40
Firm Flow
20
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 6869.5 ha
1905
1900 Minimum
Reservoir W.L, m asl
1895 R.W.L
1890
1885
Average
1880
R.W.L
1875
1870
1865 Maximum
1860 R.W.L
1855
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
Power, kw
10000
8000
6000
4000
2000
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0
Time, %
(A)
Power, 6245 ha
18000
16000
Minimum Power
14000 Average Power
12000 Maximum Power
Power, kw
10000
8000
6000
4000
2000
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(B)
Release Volume, 6245 ha
120
Release
100
Volume
Volume, Mm3
80
Irr. Req.
60
40
Firm Flow
20
0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(C)
Reservoir Water Level, 6245 ha
1905
1900 Minimu
Reservoir W.L, m asl
1895 m
R.W.L
1890
1885 Average
1880 R.W.L
1875
1870
Maximu
1865 m
1860 R.W.L
1855
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Months
(D)
T o Go nd ar
37o 45'E 38 o 00 ' E
12 o 00' N
Ribb
n a
Ta
N
ke
La
ta
ere
W
Hod Gebeya
De bre Ta bo r
ara
Ha
um ara
S en dega G Dr y W eather Road
11 o 4 5' E
Roa d
ar
rD
To A nbe sam e
hi
Mi Me
Ba
m Towns
a
it t era
To
ar
y
m
Gu
Lak e
Ri ver
0 10 20 30 Kilom eters
Figure: B- 10. Two and three dimensions representation of the elevation of Lake Tana
sub basin [27].
Figure: B- 11. Location map of Megech dam and gauging site [30]
Figure: B- 14. Location of main towns and dams in the study area