Professional Documents
Culture Documents
At Project Value Delivery we firmly believe that tools as to enable the identification of the Critical Path of
should be suited to the use that is made of them, and to the Project. It is used to monitor and control
the needs of the user. effectively the execution of the Project. It can be
resource-loaded for specific critical resources,
The Fundamental Schedule Levels • Level 4-5: detailed work schedules that show only
Different schedules are thus meant for different uses and one particular area of Project execution. They can be
different users. There are three main schedule levels: by trade/ function, work phase or by work area and
• Strategic level, where the schedule provides an are designed to be used directly by the site or
overview allowing long-term decisions and function managers for their day-to-day execution
orientations: financing principles, contract planning, progress tracking and reporting.
placements, taskforce and key equipment This hierarchy of schedules is very general and does not
localization and mobilization, etc., relate to the usage made by the Project Manager of these
• Project coordination level, where the proper schedules. Levels 1 and levels 2 are generally only used by
consolidation of available information from all senior management or for contractual purposes.
project contributors (engineering capabilities,
Project Value Delivery’s Recommended
construction needs, external constraints, etc.) is
performed. This allows logical Critical Path analysis, Project Execution Schedule Hierarchy
trending and reforecasting, From the Project manager’s perspective, during Project
• Operational level, where the priorities decided by execution, the ‘Integrated Project Schedule’ (level 3) is
management are cascaded down in a the key document. We will
detail that only the specific functions discuss in other White
Don’t try to strategize your Project
can have a real control on. This Papers the appropriate
on very detailed schedules!
allows the management of the work characteristics and level of
It would be similar to planning a
at the lowest granularity. From those detail of such schedule.
transcontinental trip on a very
details, the operational level also detailed local map! However it is also
allows to feed back up the necessary important to keep a high
statistical data for trends and level view of the entire
reforecasting, as well as progress measurement. Project schedule that can fit on one page, and ideally,
shows a good representation of the main workflows,
Conventional Schedule Hierarchies where they are supposed to converge, and of the most
When executing a large and complex Project, a number critical deliverables. This is the ‘Convergence Plan’,
of schedules are used with different levels of detail and which has the advantage on being a better-adapted tool
scope. These different schedules need to remain for complex projects’ management than simple higher-
consistent. level roll-up schedules.
There are a number of more or less standardized The actual hierarchy of schedules recommended by
schedule levels (ref. for example to AACE international’s Project Value Delivery to be used by the Project Manager
recommended practice): during execution is thus the following:
• Level 1: high level schedule showing the major • Convergence Plan – a graphical representation of
components and contractual milestones of the the Project workstreams, convergence points, and
Project. It is generally a 1-2 pages schedule key deliverables. It does not include linkages. It
consisting of less than 100 activities, serves as a high level overview and is updated
• Level 2: a schedule that can be more detailed than regarding progress. It is posted in the Project area
the level 1, in particular regarding milestones and for all to see and to monitor as part of Visual
trade/ function-specific activities. It is typically a Management. On a large Project the Convergence
schedule of less than 300 activities. It can be used as Plan contains around 100 to 150 key deliverables for
a ‘sign-off’ schedule for contractual purposes and is the entire Project,
in effect rarely used by the Project manager, • Integrated Project Schedule – a fully linked
• Level 3: the Integrated Project Schedule: a schedule schedule covering the entire Project execution scope
that has a level of details and the adequate linkage so with an adequate level of detail to take decisions at
© Project Value Delivery, 2015 2015-14 rev 0 Discover more on: www.ProjectValueDelivery.com
Page 2 of 2