1. Call the NOC
Call the NOC (+97336031969)
Inform the NOC the WO NO.
Check the existing alarm on site before the activity.
9/13/2014
DONE BY: MAHMOUD HASSAN
2. Check the Existing Alarm
Log in the DUW and check the existing alarms and take snapshots for both cases
clear or have alarm.
9/13/2014
DONE BY: MAHMOUD HASSAN
3. Create CV
Create CV before the activity with known name and set Startable.
9/13/2014
DONE BY: MAHMOUD HASSAN
3. Create CV
On the View selection bar , click Software... to Creating CV
9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Form tools Export the Cabinet and site equipment script form the DUW( make
sure the script are downloaded on your PC.
9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Form tools Delete the Cabinet and site equipment script form the DUW.
9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Wait for the DUW to be ready again after deleting the scripts and can be checked
from hyper terminal
Log in the DUW.
9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
From Tools select Cabinet Equipment Configuration.
9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Then connect the sync cables between the two DUW’s
9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Power on the second DUW.
Then proceed for the cabinet equipment script with extended mode.
If the extended mode with not available cancel the cabinet script and start again.
9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
From Tools select Site Equipment Configuration.
9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Browse the new Site equipment script from you PC and select Automatic (No
Wizard).
9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Wait till the configuration completed successfully.
9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Log in the Hyper terminal with username: rbs and password: rbs
Check the two DUW’s are 100% synchronized.
Call the swap room to check with the integration.
If the site is ok.
9/13/2014
DONE BY: MAHMOUD HASSAN
4. Installation
Label the old jumpers with different colors.
Move the old RUS to the new cabinet and connect the data cables to the DUW.
Connect each same sector RUS’s with data cables from data 2 RUS1 to data 1
RUS2.
Connect the jumpers to the RUS one jumper per each RUS.
Connect the SAU cable to the new cabinet.
9/13/2014
DONE BY: MAHMOUD HASSAN
5. Check the Existing Alarm
If the site is finished from the integration side.
Log in the DUW and check the alarm.
9/13/2014
DONE BY: MAHMOUD HASSAN
6. Call the NOC
Call the NOC (+97336031969)
Check the existing alarm on site After the activity.
Move to the next site…..
9/13/2014
DONE BY: MAHMOUD HASSAN
9/13/2014
DONE BY: MAHMOUD HASSAN