3 Carrier

rd
Integrating process
1. Call the NOC
Call the NOC (+97336031969)
Inform the NOC the WO NO.
Check the existing alarm on site before the activity.

9/13/2014
DONE BY: MAHMOUD HASSAN
2. Check the Existing Alarm
Log in the DUW and check the existing alarms and take snapshots for both cases
clear or have alarm.

9/13/2014
DONE BY: MAHMOUD HASSAN
3. Create CV
Create CV before the activity with known name and set Startable.

9/13/2014
DONE BY: MAHMOUD HASSAN
3. Create CV
On the View selection bar , click Software... to Creating CV

© Ericsson AB 2009 Ericsson Internal 5 Bassem Alphonse 2009-11-02


3. Create CV
Click Create .

© Ericsson AB 2009 Ericsson Internal 6 Bassem Alphonse 2009-11-02


3. Create CV
 On the Name Field , Enter site name & date of CV creation.
 On the comment filed , Enter Your name.

© Ericsson AB 2009 Ericsson Internal 7 Bassem Alphonse 2009-11-02


3. Create CV

© Ericsson AB 2009 Ericsson Internal 8 Bassem Alphonse 2009-11-02


3. Create CV
 Right click on the created CV, click Set Startable.

© Ericsson AB 2009 Ericsson Internal 9 Bassem Alphonse 2009-11-02


4. Preparation
Turn off the DUW and install the DUW on the new cabinet.
Connect the Ethernet cable between the DUW and TCU.
Turn on the DUW in the new location and wait till it is loaded.
Log in the DUW again.

9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Form tools Export the Cabinet and site equipment script form the DUW( make
sure the script are downloaded on your PC.

9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Form tools Delete the Cabinet and site equipment script form the DUW.

9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Wait for the DUW to be ready again after deleting the scripts and can be checked
from hyper terminal
Log in the DUW.

9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
From Tools  select Cabinet Equipment Configuration.

9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Then connect the sync cables between the two DUW’s

9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Power on the second DUW.
Then proceed for the cabinet equipment script with extended mode.
If the extended mode with not available cancel the cabinet script and start again.

9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
From Tools  select Site Equipment Configuration.

9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Browse the new Site equipment script from you PC and select Automatic (No
Wizard).

9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Wait till the configuration completed successfully.

9/13/2014
DONE BY: MAHMOUD HASSAN
4. Commission
Log in the Hyper terminal with username: rbs and password: rbs
Check the two DUW’s are 100% synchronized.
Call the swap room to check with the integration.
If the site is ok.

9/13/2014
DONE BY: MAHMOUD HASSAN
4. Installation
Label the old jumpers with different colors.
Move the old RUS to the new cabinet and connect the data cables to the DUW.
Connect each same sector RUS’s with data cables from data 2 RUS1 to data 1
RUS2.
Connect the jumpers to the RUS one jumper per each RUS.
Connect the SAU cable to the new cabinet.

9/13/2014
DONE BY: MAHMOUD HASSAN
5. Check the Existing Alarm
If the site is finished from the integration side.
Log in the DUW and check the alarm.

9/13/2014
DONE BY: MAHMOUD HASSAN
6. Call the NOC
Call the NOC (+97336031969)
Check the existing alarm on site After the activity.
Move to the next site…..

9/13/2014
DONE BY: MAHMOUD HASSAN
9/13/2014
DONE BY: MAHMOUD HASSAN