1.

The main characteristics of a project are:


All answers are correct (*)

2. Use navigation arrows to adjust the structure of the WBS hierarchy. True or False.
benar (*)

3. Which of the following resources is not measured in units of time?


Material (*)

4. When you open a project in ….. mode, you are the only user who can change the data in
the project.
Exclusive (*)

5. Activity type determines whether an activity uses and activity calendar or the calendar of
its assigned resources(s). True or False

benar (*)

6. When you set a date limit on a project schedule using 'Start On or After
Constraint', what will be happening?

Affect the start date of activity and the start date of subsequent
activities. (*)

7. Which of the following constraints must project management address?


Cost

8. What is the vertically shaded area called on a Bar Chart?


Curtain. (*)

9. the is not an option after incorporating a reflection project into a


project resource?
Export reflection (*)

10. Temporary effort undertaken for the purpose of creating a unique


product, service, or result, that is the definitions of…
Project (*)

11. The following statements are true regarding project constraints,


except:
The use of constraints can exceed 10% (*)

12. Lowest level of a WBS must, except:


General work (*)
13. In P6 Professional, toolbar icons and menu options can both be
customized. True or False
benar (*)

14. Which of the following can be modified in the Wizard Report?


All answers are correct (*)

15. When you create a new project, the root level of the WBS is created
with the same name as the project. True or False
benar (*)

16. the of the following statements are true about resources on


primavera:
Equipment can be considered as resources (*)

17. The access mode used to allow a project to be accessed and changed


by multiple users is called?
Shared (*)

18. The project management life cycle consists of the following 5 groups,


except:
Developing process group (*)

19. Every organization has its own variations of what documents are


requred to initiate a project. It's importan to identify the project need,
stakeholders, and main goals. True or False
benar (*)

20. Mr. Algo is laying bricks while mixing cement to stick the bricks. Mr.
Algo will stop mixing the cement when all the bricks have been installed.
The activities of 'laying the bricks' and 'stirring the cement' are related as:
Finish to Finish Relationship (*)

21. If we choose the global calendar, then..


The calendar system will apply to all our projects in the Primavera
database (*)

22. We can set the timeline range in our layout (per week/ quarterly/ per
month, etc) in the menu?
Timescale (*)

23. Which one below that is not included in the company data:


Risks (*)
24. Choose one of the following which includes Enterprise Data
OBS (*)

25. Which of the following is not a Project characteristic?


Having Problems (*)

26. Which type of Work Time indicates a day off from work and there is
no work agenda on that day?
NON WORK (*)

27. The type of relationship that is simulated with if activity A starts,


activity B also starts is the type of relationship…
Start to Start (SS) (*)

28. The estimation of the total budget or the overall budget plan needed
in the project is what kind of budget?
Original Budget (*)

29. To update the status of a completed activity, what data need to be


entered?
Actual Finish dates (*)

30. The traditional way to calculate project schedules and determine


minimum duration is called?
Critical path method scheduling (*)

31. What is the proper file format when importing/exporting data to make


it compatible with Microsoft Project 2002 or later?
Primavera P6 (XML) (*)

32. Which of the following options is a way to shorten the project?


A and B (*)

33. A document that will be submitted to the customer is?


Work-Product Document (*)

34. A feature used to compare two project plans, a revised plan and a
basic plan and create a report on the differences between the plans with
points such as: Items added, Items removed, values changed are the
meanings of…
Schedule Comparison (*)
35. Before creating a project on Primavera P6, what should you do first?
Enterprise Project Structure (*)

36. Identify one instance of Enterprise specific data


Enterprise Project Structure (*)

37. Which do not include constraints that must be balanced to achieve


project success are:
Baselines (*)

38. EPS stands for…


Earning Project Structure (*)

39. Follow-up activities that are carried out after a suspend activity occurs
are called?
Resume date (*)

40. Even if projects are not completed, they should not be formally


closed. True or False
Palsu (*)

41. Here is the meaning of the role, namely:


Job title or skill required to complete an activity (*)

42. How to create a new project in Primavera is


View - layout
Project - Activities
Project - WBS
Enterprise - enterprise project structure (*)
Incorrect
(0/1) Point
43. Which of the following statements is FALSE?
Project can be divided into several Enterprise Project Structure (*)
Work Breakdown Structure describes the division of work in a project
Work Breakdown Structure can be divided into several activities
Enterprise Project Structure describes the project structure within a
company
Correct
(1/1) Point
44. Which statement best describes the essence of project management?
Produce unique products/services
Have tempo
Complex and consists of very many tasks
A and B (*)
Correct
(1/1) Point
45. There are several works should be done on Project Time Management
(except)
Cost control (*)
Activity Resouce Estimating
Schedule development
Activity sequencing
Schedule control
Incorrect
46. Which type of activity is used when work must be completed within a
certain timeframe, regardless of the availability of the specified resource?
Level of effort
Task dependent (*)
Milestone
Resource dependent
Correct
(1/1) Point
47. In analyzing a project, which should not be done?
Identify resource availability issues
Doing project re-estimation (*)
Making changes to maintain important milestones
Perform cost analysis
Incorrect
(0/1) Point
48. Menu progress spotlight, means..
Shows the activity with the most total float
Show activities with the most resources
Shows the next closest activity (*)
Show activities with the largest budget
Incorrect
(0/1) Point
49. The import format that can be used by Primavera Contractors and has
an independent database is?
Spreadsheet (XLS)
Primavera P6 (XML)
Primavera PM (XER)
Primavera Contractor (XER) (*)
Incorrect
(0/1) Point
50. In creating a WBS, what component is the root node?
PROJECT (*)
SUB-ACTIVITY
ACTIVITY
NODE
Correct