A. Preliminary Works
1. Material & Man power mob demob 1.00 ls 7,573,500.00 1,514,700.00 7,573,500.00 1,514,700.00 9,088,200.00
2. Safety Appliances 1.00 ls 18,176,400.00 3,635,280.00 18,176,400.00 3,635,280.00 21,811,680.00
3. Transportation & Accomodation Double cabin, 4WD 1.00 ls 50,069,250.00 10,013,850.00 50,069,250.00 10,013,850.00 60,083,100.00
4. Documentation and report JSEA, Propose drawing, as-built 1.00 ls 4,626,567.00 925,313.40 4,626,567.00 925,313.40 5,551,880.40
Sub Total A 80,445,717.00 16,089,143.40 96,534,860.40
D. Toilet Modification
1. Install Steel door 2100x700mm Hollow 50x50x2mm, reel, plate 1.2mm 2.00 set 3,870,900.00 774,180.00 7,741,800.00 1,548,360.00 9,290,160.00
2. Additional floor Concrete 8cm, mesh M5 1.00 m3 1,598,850.00 319,770.00 1,598,850.00 319,770.00 1,918,620.00
3. Install Ceramic floor 20x20cm, Asia Tile 5.40 m2 227,205.00 45,441.00 1,226,907.00 245,381.40 1,472,288.40
4. Install Ceramic Wall 20x25cm. Asia Tile 10.80 m2 244,035.00 48,807.00 2,635,578.00 527,115.60 3,162,693.60
5. Install Water Faucet Toto 2.00 set 126,225.00 25,245.00 252,450.00 50,490.00 302,940.00
6. Install Closet W/ Flush Toto 2.00 set 3,323,925.00 664,785.00 6,647,850.00 1,329,570.00 7,977,420.00
7. Install Drain Pipe Wavin, 4mm 12.00 m' 134,640.00 26,928.00 1,615,680.00 323,136.00 1,938,816.00
8. Install Clean Water Pipe PVC 1", 5/8" Wavin 20.00 m' 109,395.00 21,879.00 2,187,900.00 437,580.00 2,625,480.00
Sub Total D 23,907,015.00 4,781,403.00 28,688,418.00
F. Electrical Works
1. Install Socket Plug IP45, 150A Schneider 2.00 ea 589,050.00 117,810.00 1,178,100.00 235,620.00 1,413,720.00
2. Install MCB Breaker 4 Grup MCB 10A, 6A, Incld. Cable 4x6mm2 2.00 grp 1,598,850.00 319,770.00 3,197,700.00 639,540.00 3,837,240.00
3. Lighting Cable Cbl. 2x2.5mm2, 3x2.5mm2, Supreme 1.00 ls 26,591,400.00 5,318,280.00 26,591,400.00 5,318,280.00 31,909,680.00
4. Power outlet Schneider, 16A 14.00 nos 244,035.00 48,807.00 3,416,490.00 683,298.00 4,099,788.00
5. Install Lighting Switch Schneider, 6A 4.00 nos 201,960.00 40,392.00 807,840.00 161,568.00 969,408.00
6. Install Indoor Lamp Phillips SL 14w, Incld. Armature 12.00 nos 277,695.00 55,539.00 3,332,340.00 666,468.00 3,998,808.00
7. Install outdoor Lamp Phillips Bunker type, 20w 4.00 nos 378,675.00 75,735.00 1,514,700.00 302,940.00 1,817,640.00
8. Install Lightning Protection Stick Rod 16mm2, BC 50, incld. Arm & accessories 1.00 ls 5,890,500.00 1,178,100.00 5,890,500.00 1,178,100.00 7,068,600.00
9. Install AC 1 PK Brand LG 2.00 set 6,689,925.00 1,337,985.00 13,379,850.00 2,675,970.00 16,055,820.00
Sub Total F 59,308,920.00 11,861,784.00 71,170,704.00
IN WORD : FIVE HUNDRED AND THIRTY EIGHT MILLION TWO HUNDRED THOUSAND RUPIAHS
HENNY SETIAWAN
Director
TIME SCHEDULE
No. WORK DESCRIPTION VOLUME PROJECT DUR M #01 M #02 REMARKS
% W-1 W-2 W-3 W-4 W-5 W-6
A. Preliminary Works
1. Material & Man power mob demob 1.00 ls 1.69% 1 1.69%
100%
100,00%
2. Safety Appliances 1.00 ls 4.05% 6 0.68% 0.68% 0.68% 0.68% 0.68% 0.68%
3. Transportation & Accomodation 1.00 ls 11.16% 6 1.86% 1.86% 1.86% 1.86% 1.86% 1.86%
4. Documentation and report 1.00 ls 1.03% 6 0.17% 0.17% 0.17% 0.17% 0.17% 0.17%
D. Toilet Modification
1. Install Steel door 2100x700mm 2.00 set 1.73% 2 0.86% 0.86%
2. Additional floor 1.00 m3 0.36% 1 0.36%
3. Install Ceramic floor 5.40 m2 0.27% 1 0.27%
4. Install Ceramic Wall 10.80 m2 0.59% 1 0.59%
5. Install Water Faucet 2.00 set 0.06% 1 0.06%
6. Install Closet W/ Flush 2.00 set 1.48% 1 1.48%
40%
7. Install Drain Pipe 12.00 m' 0.36% 1 0.36%
8. Install Clean Water Pipe 20.00 m' 0.49% 1 35,05% 0.49%