You are on page 1of 4

ITEM RATE LIST FOR ELECTRICAL WORK

Job Number : LE200420


Project description : Design, Supply, Installation and Commissioning of Underground Distribution Network under Kirtipur, Kuleshwor, Baneshwor, Balaju and
Jorparti Distribution Center including Reinforcement and Automation
Client : Nepal Elecctricity Authority
Contractor : Larsen & Toubro Limited
Sub-Contractor :
SC Item Rate (in
Sl No Activity description UOM
NPR) excl VAT
All charges for laying of HT Cable in Pipe or Trench - 3/C 400 mm2 11 kV XLPE Armoured cable. Rate is including all manpower, plant & machineries,
1 Km 71,223
consumables, transportation etc to complete the work in all respect
All charges for laying of HT Cable in Pipe or Trench - 3/C 300 mm2 11 kV XLPE Armoured cable. Rate is including all manpower, plant & machineries,
2 Km 67,269
consumables, transportation etc to complete the work in all respect
All charges for laying of HT Cable in Pipe or Trench - 3/C 150 mm2 11 kV XLPE Armoured cable. Rate is including all manpower, plant & machineries,
3 Km 75,509
consumables, transportation etc to complete the work in all respect
All charges for laying of LT Cable in Pipe or Trench - LT XLPE Armoured 1 Core, 630 sq.mm. cable. Rate is including all manpower, plant & machineries,
4 Km 32,422
consumables, transportation etc to complete the work in all respect.
All charges for laying of LT Cable in Pipe or Trench - LT XLPE Armoured 3.5 Core, 300 sq.mm. cable. Rate is including all manpower, plant & machineries,
5 Km 52,084
consumables, transportation etc to complete the work in all respect.
All charges for laying of LT Cable in Pipe or Trench - LT XLPE Armoured 3.5 Core, 185 sq.mm. cable. Rate is including all manpower, plant & machineries,
6 Km 40,092
consumables, transportation etc to complete the work in all respect.
Termination of 3C X 400 Sqmm Cable; Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
7 Nos 2,280
respect.
Straight Through Jointing Kit of 3C X 400 Sqmm Cable; Rate is including all manpower, plant & machineries, consumables, transportation etc to complete
8 Nos 4,256
the work in all respect
Termination of 3C X 300 Sqmm Cable; Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
9 Nos 1,824
respect
Straight Through Jointing Kit of 3C X 300 Sqmm Cable; Rate is including all manpower, plant & machineries, consumables, transportation etc to complete
10 Nos 3,800
the work in all respect
Termination of 3C X 150 Sqmm Cable; Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
11 Nos 1,520
respect
LT XLPE 630 sqmm cable Glanding and Termination Both End; Rate is including all manpower, plant & machineries, consumables, transportation etc to
12 Nos 228
complete the work in all respect
LT XLPE 300 Sqmm cable Glanding and Termination; Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the
13 Nos 760
work in all respect
LT XLPE 185 sqmm cable Glanding and Termination; Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the
14 Nos 380
work in all respect
RMU 5 way complete with two VCB and three LBS with FRTU and FPI, complete in all respect. Rate is including all manpower, plant & machineries,
15 Nos 7,603
consumables, transportation etc to complete the work in all respect.
RMU 4 way complete with two VCB and two LBS with FRTU and FPI, complete in all respect. Rate is including all manpower, plant & machineries,
16 Nos 7,603
consumables, transportation etc to complete the work in all respect.
RMU 3 way complete with two VCB and one LBS with FRTU and FPI, complete in all respect. Rate is including all manpower, plant & machineries,
17 Nos 6,935
consumables, transportation etc to complete the work in all respect.
RMU 3 way complete with one VCB and two LBS with FRTU and FPI, complete in all respect. Rate is including all manpower, plant & machineries,
18 Nos 6,935
consumables, transportation etc to complete the work in all respect.
RMU 1 way complete with one LBS with FRTU and FPI, complete in all respect. Rate is including all manpower, plant & machineries, consumables,
19 Nos 5,838
transportation etc to complete the work in all respect.
Feeder Pillar type A - complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in
20 Nos 7,603
all respect.
Feeder Pillar type B - complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in
21 Nos 7,603
all respect.
Feeder Pillar type C - complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in
22 Nos 7,603
all respect.
Feeder Pillar type D - complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in
23 Nos 4,071
all respect.
Service Pillar type E - complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in
24 Nos 2,166
all respect.
Earthing Rod - 19mm dia. 2mtr length GI with Clamp- complete in all respect. Rate is including all manpower, plant & machineries, consumables,
25 Nos 733
transportation etc to complete the work in all respect.
MS Flat- 25x6 mm - 6mtr length with CU Cladding- complete in all respect. Rate is including all manpower, plant & machineries, consumables,
26 Nos 31
transportation etc to complete the work in all respect.
HDPE Pipe Laying in HDD method - Single Run, including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
27 Km 8,28,194
respect
HDPE Pipe Laying in HDD method - Double Run including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
28 Km 8,14,981
respect
HDPE Pipe Laying in HDD method - Three Run including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
29 Km 7,80,109
respect
HDPE Pipe Laying in HDD method - Four Run including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
30 Km 7,45,256
respect
HDPE Pipe Laying in HDD method - Five Run including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
31 Km 7,31,488
respect
Accepted by Sub-contractor
Sub-contractor name:
SC Item Rate (in
Sl No Activity description UOM
NPR) excl VAT

Signature:

Date:
SC Item Rate (in
Sl No Activity description UOM
NPR) excl VAT

HDPE Pipe Laying in HDD method - Six Run including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
32 Km 7,20,136
respect
HDPE Pipe Laying in HDD method - Seven Run including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
33 Km 7,12,785
respect
HDPE Pipe Laying in HDD method - Eight Run including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
34 Km 6,92,555
respect
35 HDPE Pipe - Single Run (with HDD manual moling) Km 79,200
36 HDPE Pipe - Double Run (with HDD manual moling) Km 79,200
37 HDPE Pipe - Three Run (with HDD manual moling) Km 79,200
38 HDPE Pipe - Four Run (with HDD manual moling) Km 79,200
39 HDPE Pipe - Five Run (with HDD manual moling) Km 79,200
40 HDPE Pipe - Six Run (with HDD manual moling) Km 79,200
41 HDPE Pipe - Seven Run (with HDD manual moling) Km 79,200
42 HDPE Pipe - Eight Run (with HDD manual moling) Km 79,200
43 Manual HDD (Moling) Km 5,04,000
GI pipe 250mm dia, 14mm thick for crossing - complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work
44
in all respect.
Km 91,200

45 Laying of FO Cable (48 Fiber) inside PLB Duct. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all respect. Km 23,327

46 Laying of HDPE PLB Duct inside 160mm HDPE Pipe. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all respect. Km 26,455

47 24 Fibre (DWSM) OPGW fibre optic cable. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all respect. Km 12,160
Erection of STP Pole including stay - complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
48
respect.
Nos 3,417

HT AB Cable stringing including fixing of clamps/ connectors etc. - Size 3/C 150 mm2 11 kV cable, including all clamps, connecotrs, busbar materials. Rate is including all manpower,
49
plant & machineries, consumables etc (excluding transportation only) to complete the work in all respect.
Km 18,240

LT AB Cable stringing including fixing of clamps/ connectors etc. - Size 120 mm2 cable (3*120+1*95+1*16 sq.mm) , including all clamps, connecotrs, busbar materials. Rate is
50
including all manpower, plant & machineries, consumables etc (excluding transportation only) to complete the work in all respect.
Km 33,053

LT AB Cable stringing including fixing of clamps/ connectors etc. - Size 95 mm2 cable (3*95+1*95*1*16 sq.mm), including all clamps, connecotrs, busbar materials. Rate is including
51
all manpower, plant & machineries, consumables etc (excluding transportation only) to complete the work in all respect.
Km 28,846

52 GO Switch with accessories complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all respect. Nos 5,074
Distribution Transformer including DO Fuse, LA, Structural assembling, earthing, busbar items. Rate is including all manpower, plant & machineries, consumables, transportation
53
etc to complete the work in all respect.
Set 14,378
54 Metering Unit - complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all respect. Nos 1,520
Miscellaneous Structural steel used for rails , plates for rail fixing, gratings, gratings supports etc for transformer foundation, cable supports and earthing cleats, chequered plates,
55
embedments, edge protection angles for cable trenches but excluding the reinforcement steel and steel for lattice and pipe structures which shall be paid seperately.
MT 15,200

56 Danger Plate Enameled- complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all respect. Nos 15

57 Number Plate Enameled- complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all respect. Nos 15
Phase Plate for each phase set of 3- complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
58
respect.
Nos 15
HT & LT Cable RCC Route Marker and Straight Joint marker - complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to
59
complete the work in all respect.
Nos 61

Burried Cable trench - brick Lining and laying of warning tape. (Without HDPE Pipe, With Brick- lining). Excavation/ Backfilling will be paid separately under respective BOQ item.
60
Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all respect.
Mtr 361

Burried Cable trench - brick Lining and laying of warning tape. (With HDPE Pipe, Without Brick- lining). Excavation/ Backfilling will be paid separately under respective BOQ item.
61
Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all respect.
Mtr 351

62 Blacktopping SqM 1,443


63 Dismantling of Conductor (per phase) Km 6,080
64 Dismantling of AB Cable CKm 8,360
65 Dismantling of DTR (for augmentation) Nos 4,408
66 Restoration of Walkway/ Pavement Sqm 324
Service connection - Single phase 6,16 A - complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
67
respect. Excavation will be separate item covered in Civil portion.
Nos 485
Service connection - Single phase 30 A- complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
68
respect. Excavation with backfilling will be separate item covered in Civil portion.
Nos 485
Service connection - Single phase 60 A- complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
69
respect. Excavation with backfilling will be separate item covered in Civil portion.
Nos 602
Service connection - 3 phase upto 25 kVA- complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
70
respect. Excavation with backfilling will be separate item covered in Civil portion.
Nos 836
Service connection - 3 phase 25 to 50 kVA- complete in all respect. Rate is including all manpower, plant & machineries, consumables, transportation etc to complete the work in all
71
respect. Excavation with backfilling will be separate item covered in Civil portion.
Nos 836
Excavation in all types of soil including disposal of excess earth etc. for all leads and lifts. Rate is including all manpower, plant & machineries, consumables, transportation etc to
72
complete the work in all respect.
Cum 288
73 Backfilling including layer by layer compaction as per specification including restoration of footpath/ curb stone arround the excavated area. Cum 96
Local Sand filling and compaction around and under Foundation for backfilling of cable and pit as applicable. Rate is including all manpower, materials, plant & machineries,
74
consumables, transportation etc to complete the work in all respect.
Cum 3,200

Accepted by Sub-contractor
SC Item Rate (in
Sl No Activity description UOM
NPR) excl VAT

Sub-contractor name:

Signature:

Date: