You are on page 1of 3

Satpati

Item Code Description of Item Unit


May June July August September October November December January February March Remarks
1 2 3

Span Length Mtrs

Laying, testing & Commissionig of 11kV, round armoured


XLPE Cable as per specification and standard installation
S4 - 1
practice. This includes the cost of stacking, loading, unloading
and transportation of all materials from stores to site.

Laying of 3x300 Sq. mm 11 KV XLPE insulated cable


S4 - 1.1 Mtrs
underground in HDPE Pipe
0 0 3050

Laying of 3x95 Sq. mm 11 KV XLPE insulated cable


S4 - 1.2 Mtrs
underground in HDPE Pipe
0 0

Laying, testing & Commissionig of 11kV, round armoured


XLPE Cable as per specification and standard installation
S4-2
practice. This includes the cost of stacking, loading, unloading
and transportation of all materials from stores to site.

Laying of 3x300 Sq. mm 11 KV XLPE insulated cable


S4 - 2.1 Mtrs
underground in Trenches

Laying of 3x95 Sq. mm 11 KV XLPE insulated cable


S4 - 2.2 Mtrs
underground in Trenches

Drilling, Laying, testing & Commissionig of 11 kV, round


armoured XLPE Cable as per specification and standard
S4 - 3
installation practice. This includes the cost of stacking, loading,
unloading and transportation of all materials from stores to site.

Drilling & Laying of 11 kV, 3C x 300 sqmm.,round armoured,


S4 - 3.1 Mtrs
XLPE Cable using HDD Method without using HDPE Pipe

Drilling & Laying of 11 kV, 3C x 95 sqmm.,round armoured,


S4 - 3.2 Mtrs
XLPE Cable using HDD Method without using HDPE Pipe

Laying, testing & Commissionig of 1.1 kV, strip armoured


L.T. XLPE Cable as per specification and standard
S4 - 17 installation practice. This includes the cost of stacking,
loading, unloading and transportation of all materials from
stores to site.

3.5C x 300 sq.mm, 1100 V Grade, PVC sheathed steel strip


S4 - 17.1 armoured, aluminum conductor LT XLPE insulated cable in Mtrs
trenches.
220 3500

3.5C x 70 sq.mm, 1100 V Grade, PVC sheathed steel strip


S4 - 17.2 armoured, aluminum conductor LT XLPE insulated cable in Mtrs
trenches.
220 2800

3.5C x 35 sq.mm, 1100 V Grade, PVC sheathed steel strip


S4 - 17.3 armoured, aluminum conductor LT XLPE insulated cable in Mtrs
trenches.
220 3300

Cable Warning tape: Supply of H.T. cable warning tape to be


provided below earth at standard depth after cable laying on
approval as per standard installation procedure on approval of
S4 - 5
the schedule by the project manager. This includes the cost of
loading, unloading and transportation of all materials to the
site.

S4 - 5.1 Cable warning tape kg

S5 - 4 Supply & laying of RCC pipe

Supply & laying of RCC full round pipe 150 mm, 2M as per
specification and standard method of construction for cable
S5 - 4.1 wherever required. This rate also includes stacking, loading, Nos.
unloading, labour and transporting of material fron site store to
site.

Supply & laying of RCC Half round pipe 150 mm, 1M as per
specification and standard method of construction for cable
S5 - 4.2 wherever required. This rate also includes stacking, loading, Mtrs
unloading, labour and transporting of material fron site store to
site.

S5 - 5 Laying of HDPE Pipe

Supply & laying of 160 mm dia. HDPE pipe by Horizontal


drilling by HDD method (trenchless) as per site condition and
standard construction method for laying 11 kV, 3C x 300 & 3C x
S5 - 5.1 Mtrs
95 sq.mm round armoured XLPE cable. This includes cost of
drilling, HDPE pipe, laying of HDPE pipe, stacking, loading,
unloading, transportation upto site etc.
504 2150

Contractor's Representative MSEDCL Representative TPQA Representative

Site Engineer Assistant Engineer Site Engineer


Item Code Description of Item Unit
May June July August September October November December January February March Remarks
1 2 3

Supply of material & Construction of RCC cable trench for HT


S5 -9 & LT Cables in water logging areas (Length- 0.2 Kms.)
complete

Excavation for foundation in soft soil.. including removing the


excavated materials upto a distance of 50 metres beyond the
building area and lift as specified, stacking and spreading,
S5 - 9.1 Cu.M
necessary dewatering unless provided elsewhere, preparing the
bed for the foundation and required backfilling, ramming,
watering, shoring and strutting etc. complete. as directed.

Providing dry trap/rubble stone soling 15 cm to 20 cm thick


S5 - 9.2 Cu.M
including hand packing and compacting etc. complete.
S5 - 9.3 Prov. and casting R C C M-20 Cu.M
S5 - 9.4 Prov. and fixing steel reinforcement MT

Providing internal cement plaster 20mm thick in two coat, 1;4


without neeru finish to brick masonry or concrete surface in all
S5 - 9.5 positions including scaffolding, racking out joints, providing Sq. Mtr.
groove at joints of stone masonry and concrete members and
curing etc. complete.

Providing and fixing required size reinforced cement concrete


cover of approved quality and make, 10cm thick over manhole
S5 - 9.6 Cu.M
and inspection chamber including mild steel reinforcement, curing
testing etc. complete.

S5 -13 Excavation and Road reinstatment / restoration

Earth work excavation in soil by manual means all operatioal,


incidental, labour charges such as shoring, sheeting, planking,
S5 -13.1
strutting, dewatering, seigniorage, etc. complete for finished item
of work for following types of trench.

S5 -13.2 Type-1: 1000 mm (W) and 1200mm (D) Cu.M 0

Length in Mtrs Mtrs

Width in Mtrs Mtrs

Depth in Mtrs Mtrs

S5 -13.3 Type-2: 800mm (W) & 1200mm (D) Cu.M 0

Length in Mtrs Mtrs

Width in Mtrs Mtrs

Depth in Mtrs Mtrs

Contractor's Representative MSEDCL Representative TPQA Representative

Site Engineer Assistant Engineer Site Engineer


Item Code Description of Item Unit
May June July August September October November December January February March Remarks
1 2 3
S5 -13.4 Type-3: 1000mm (W) and 1200mm (D) Cu.M 0 613.2 48 3000
Length in Mtrs Mtrs 511 40 2500
Width in Mtrs Mtrs 1 1 1
Depth in Mtrs Mtrs 1.2 1.2 1.2
S5 -13.5 Pits for HDD, foundations etc. Cu.M

Back filling the cable trenches and restoring up to the ground


level with selected available earth from trench excavation
including watering, consolidation in layers of 15 cm thickness
including depositing and spreading of the surplus earth with a lead
S5 -13.6 Cu.M 0
of 200 Mtrs, after forming with sand all round the cable and
when required in the excavated cable trench. The excess and
non suitable excavated material should be dumped at designated
places.
108.5 2945

Length in Mtrs Mtrs


140 3800

Width in Mtrs Mtrs


1 1

Depth in Mtrs Mtrs


0.775 0.775

Conveyance charges for machinery (Tippers/Trucks)


for transporting of excess excavated earth/muck for disposal to a
S5 -13.7 Cu.M
designated location as directed by the Engineer in charge. Rate
includes loading, un loading and idle hire charges of machinery.

S5 -13.8 Road Reinstatement/Restoration Charges for Bitumen Road Sq. Mtr.


S5 -13.9 Road Reinstatement/Restoration Charges for Paver Block Road Sq. Mtr.
S5 -13.10 Road Reinstatement/Restoration Charges for RCC Road Sq. Mtr.
Back fillng with watering & restoring the pavers/tiles in
consumer premises to make it as original as per standard
S5 - 15 installation practice including supply of all material. This Sq. Mtr.
includes cost of material, labour, stacking, loading, unloading,
transportation upto site.

Contractor's Representative MSEDCL Representative TPQA Representative

Site Engineer Assistant Engineer Site Engineer

You might also like