Professional Documents
Culture Documents
4, 2014
Translated from Denki Gakkai Ronbunshi, Vol. 133-B, No. 1, January 2013, pp. 37–44
44
current, and impedance below are all vector quantities.
Ż −1 −Ż −1 0
⎡İ ⎤ ⎡ sys sys ⎤
⎢
⎢0⎥ = ⎢−Ż −1 Ż −1 + Ż −1 + Ż −1 ̇ −1 ⎥
sys sys L1 line
−Zline ⎥
⎢ ⎥ ⎢ ⎥
⎣0⎦ ⎣0 ̇
−Zline−1 ̇ −1 ̇ −1
−Zline + −ZL1 ⎦
⎡V̇ G ⎤
⎢ ⎥
× ⎢V̇ 1 ⎥ . (1)
⎢V̇ ⎥
⎣ 2⎦
The short circuit current ISC and the short circuit ca-
pacity PSC at the observation point can be calculated by
Fig. 1. Power system and measurement points. [Color
Thévenin’s theorem.
figure can be viewed in the online issue, which is available
The short circuit impedance as seen from the mea-
at wileyonlinelibrary.com.]
surement point is given by
( ( ))
Ż L2 Ż sys Ż L1 + Ż line Ż sys + Ż L1
̇ZSC = .
of measurement during normal operation as described, we Ż sys Ż L2 + Ż L1 Ż L2 + Ż sys Ż L1 + Ż line (Ż sys + Ż L1 )
improve the accuracy of the method by introduction of time
differences in the measured data, correcting the phasor by (2)
using a reference phasor, and filtering out the outliers. We The load impedances ZL1 and ZL2 can be calculated from
then confirm the effectiveness of the proposed methods. the measured values of the voltage and current phasor:
V̇ 1
Ż L1 = , (3)
̇I1 − İ 2
2. Basic Principle and Evaluation with an Analog
Simulator V̇ 2
Ż L2 = . (4)
İ 2
2.1 Summary of basic principle
The short circuit current and the short circuit capacity
The overall flow of the short circuit current estimation are
method is as follows: V̇ 2
İ SC = , (5)
Ż SC
Step 1: Measure the voltages and currents in the
power system during normal load variation such as a change V̇ 2 V̇ ∗2
Ṗ SC = . (6)
in load power consumption. Ż ∗
SC
Step 2: Estimate the back impedance using several
sets of measured data. The load impedance can be found from Eqs. (3) and (4), and
Step 3: Calculate the short circuit currents using the thus if the back impedance Zsys of the equivalent system as
estimated back impedance and the measured data. seen from measurement point 1 can be found, then the short
circuit current at measurement point 2 can be found. The
two estimation methods for finding the back impedance are
Let us consider the configuration in Fig. 1 for a case
described below.
in which measurements are taken at two adjacent points in
a power system in order to incorporate the phase measure-
ments at multiple points using the PMU, together with the
2.2 Methods of estimation of back impedance
concept of a reference phasor, which will be described later.
V1 and V2 are the bus voltages at measurement points 1 and
We formulated a method [5] based on the method of
2; I1 and I2 are the line currents at measurement points 1 and
LS and a method [7] based on the covariance for the basic
2; and ZL1 and ZL2 are the load impedances at measurement
model shown in Fig. 1, then performed evaluations using
points 1 and 2. Let Zsys be the back impedance in the source
the analog simulator testing described later.
side equivalent system as seen from measurement point 1,
and let VG be the voltage source behind Zsys . We wish to (1) Estimation Method Based on LS [5]
find the short circuit currents at the measurement points 2.
From Eq. (1), the relationship between VG , Zsys and
The impedance Zline between the two points is assumed to
the measured data at measurement point 1 is given by
be known. The relationship between the voltage, current,
and impedance in this case is given by Eq. (1). The voltage, V̇ 1 = V̇ G − Ż sys İ 1 . (7)
45
If V̇ 1 = u + jw, İ 1 = g + jh, V̇ G = Vgr + jVgi , and Ż G =
Rsys + jXsys , then relationship (7) can be represented as
follows:
⎡Vgr ⎤
[ ] [ ] ⎢ ⎥
u 1 0 −g h ⎢Vgi ⎥
= ⎢ ⎥. (8)
w 0 1 −h −g ⎢Rsys ⎥
⎢X ⎥
⎣ sys ⎦
If the measured voltage and current phasor are assigned to
u, w, g, and h, and if y = Xθ is set in Eq. (8), the canonical Fig. 2. Experimental setup.
equation for the method of LS is
XT Xθ = XT y, (9)
where 2.3 Analog simulator tests
⎡Vgr ⎤
[ ] [ ] ⎢V ⎥ We verified the basic method described above by
u 1 0 −g h
y= = ⎢ gi ⎥ , using an analog simulator. Figure 2 shows the test circuit
w 0 1 −h −g ⎢Rsys ⎥
⎢X ⎥ of the analog simulator.
⎣ sys ⎦ In the analog simulator tests, we measured the volt-
The solution of Eq. (9), namely, the estimated back age and current waveforms (instantaneous values) and eval-
impedance and voltage behind it, can be obtained by using uated the basic principle while varying the system con-
figuration, including the location of the load (impedance
load/induction machine), the presence or absence of an
θ̂ = (XT X)−1 XT y. (10)
intermediate load, the presence or absence of a generator
In the estimation calculations, Zsys is found once for a for distributed power generation, and the magnitude of the
data set of multiple measurements measured at the different back impedance, and also changing the method of applying
time. For one Zsys from Eq. (2), the short circuit impedance the load fluctuations.
is found from load impedances ZL1 and ZL2 for multiple The load fluctuations necessary to estimate the back
(N) measurements, and the N short circuit currents are then impedance were generated by changing the impedance load
found using the short circuit impedance and the voltage V2 manually over the measurement period (18 s).
at measurement point 2 from Eq. (5). Measurements were taken and recorded with a sam-
This method is referred to later as the method of LS. pling period of 10,000 Hz for the instantaneous values, and
(2) Estimation Method Based on Covariance [7] were converted to phasor with sampling period of 240 Hz.
Because the slow load fluctuations were generated artifi-
The method of Ref. [7] is extended to find results cially in the analog simulator, we performed evaluations at
for the measured data from two points. Assuming that the estimation periods from 2.4 Hz to 24 Hz.
fluctuations of VG and ZL1 are uncorrelated and that the Figure 3 shows an example of the test results. Figure
fluctuations of VG and ZL2 are likewise uncorrelated, Zsys 3(a) shows the changes in the load current applied; it was
can be found from Eq. (11) by using the covariance of the varied slowly by hand from 0.4 p.u. to 1.2 p.u. for 17 s,
measured data. The derivation of this equation is given in then restored to 0.6 p.u. at about 18 s. Figure 3(b) shows
the Appendix. the voltage in Bus 1. It can be seen that after a discontin-
( ) ( )∗
V̇ ∗ Ċ − Ċ V1 I2 − İ 1 − İ 2 Ċ V1 V1 uous change due to switching of CB1, voltage fluctuates
̇Zsys = (1 V1 I1) ( ) , (11) as the load varies. Figures 3(c) and (d) give the results of
∗
İ 1 − İ 2 Ċ ∗ − V̇ ∗ Ċ I I − Ċ I I
V1 I1 1 1 1 1 1 estimating the short circuit current using 10 phasor values
where in a calculation interval of 4.8 Hz, and plots the changes of
∑N ̇ − X)
̇ ⋅ (Ẏ k − Y)
̇ ∗
the median over time for 18 s. The criterion values used to
k=1 (Xk
Ċ XY = δXδ
̇ Ẏ ∗ = . (12) evaluate the estimation method were found by performing
N three-phase short circuit tests in each system configura-
In the estimation calculations, N values of Zsys are found tions, and are shown in the figures by a heavy line.
for one data set consisting of multiple (N) measurements From Fig. 3, it can be seen that short circuit currents
measured at different times, and N short circuit currents can can be obtained in accordance with the change in the back
be obtained. impedance by switching CB1. However, estimation results
This method is referred to below as the covariance for about 4 s just after the change in the state of CB1
method (CV). include significant error because a data set used for the
46
erence phasor, and used filtering to remove outliers, thus
improving estimation accuracy.
47
surement time and the voltage phase at multiple points.
The vertical axis represents time, and the horizontal axis
represents the phase angle. Δt is the sampling period for
the phasor quantities. ΔT is the measurement period, and
5 s of data were collected every 3 min in the measurements
described here. Thus there are periods in which no data
were collected (2 min 55 s).
In order to maintain the uniformity of the reference
phasor in the data set for estimation at multiple points in
addition to eliminating phase changes due to frequency
fluctuations in the residual phase change due to load fluc-
tuations, the phase angles of the phasor quantities were
corrected using the process below.
(1) Elimination of Effects due to Frequency Fluctu-
Fig. 4. System frequency effect removal algorithm. ations
[Color figure can be viewed in the online issue, which is Both phase changes (a) due to load fluctuations and
available at wileyonlinelibrary.com.] phase changes (b) due to frequency fluctuations appeared in
the phases angles of the phasor quantities at the measure-
If relations (A.10) and (A.11) can be assumed to hold in ment points. Among these, phase changes due to frequency
Eq. (16) as altered by the time difference, then Zsys can be fluctuations (b) have also been included in the phase at each
found from measurement point, and consequently if the phase changes
( ) ( )∗
V̇ ∗1 Ḋ V1 I1 − Ḋ V1 I2 − İ 1 − İ 2 Ḋ V1 V1 due to frequency fluctuations (b) in the multiple measure-
Ż sys = ( )∗ ( ) . (17) ment point are eliminated, then only the phase changes due
İ 1 − İ 2 Ḋ ∗V I − V̇ ∗1 Ḋ I1 I1 − Ḋ I1 I2 to load fluctuations (a) will remain. As can be seen from
1 1
Fig. 4, subtracting the phase angle at point S from those of
This method is referred to as the time difference covariance points A and B for each phasor calculation period so that the
method (dCV). phase change due to frequency fluctuations can be removed
by using the point S as a reference.
3.2 Correction of measured data by means of (2) Maintenance of Uniformity of the Reference
reference phasor Phasor
Phase uniformity can be maintained by selecting one
In preliminary experiments we found that the phase
instant in time at one of the measurement points as the
changes associated with system frequency fluctuations af-
reference phasor. In Fig. 5, the phase angle at time t0 at
fected the accuracy of the estimation method. Thus we con-
point A with the effects of frequency fluctuations removed
sidered a method of correcting the phasor values at multiple
is used as the reference, and by subtracting that from the
phase points by using a reference phasor.
phase angle at each measurement point and each instant,
Figures 4 and 5 show the relation between the mea-
uniformity of the reference phasor is maintained.
48
Fig. 8. Field measurement and data processing.
Fig. 6. Relation between standard deviation of
measurements (voltage) and estimation results. [Color
figure can be viewed in the online issue, which is available
of satellite GPS signals. Phase measurements of the voltage
at wileyonlinelibrary.com.]
and current (three-phase components each) were made at
substations A and B.
The fundamental objective was to estimate the short
circuit currents using measured phasor values. In order to
analyze the data in detail, instantaneous data were also
collected. At the measurement locations, a primary file of
the instantaneous current and voltage values was produced
in the PMU, and was converted to a CSV file by the personal
computers used for data collection. The process of estimat-
ing the phasor changes and short circuit currents described
later was performed offline using the CSV file. The process
is illustrated in Fig. 8.
Fig. 7. Field test system. [Color figure can be viewed in The instantaneous values were collected for 5 s every
the online issue, which is available at 3 min. The sampling period of the instantaneous values was
wileyonlinelibrary.com.] 5760 Hz, and the sampling period for the phasor values
was 60 Hz. The phasor values (positive phase components)
during these periods of 5 s (=300 points) were used as the
dard deviation of the data set for estimation decreases, the data set for estimation.
estimation results tend to deviate more. Thus we decided
that when the standard deviation of a data set for estimation
is below a threshold set ahead of time (the average value for 4.2 Verification results
1 day in Fig. 6), that data set is to be ignored in estimation.
We plan to evaluate a filtering process as a counter- Figures 9 to 11 show the temporal changes (24 h)
measure against the effects of changing back impedance in the estimates of the short circuit current at substation B
when starting and stopping generator or switching trans- using the measured data at a real substation. Each plotted
mission lines. point is the median of the estimation results (300 every 5 s)
for each data set.
Figure 9 shows the estimation results of the basic
4. Verification by Field Testing method based on the conventional method. However, be-
cause the estimation accuracy without reference phase cor-
4.1 Verification system rection was so poor, reference phase correction was added.
Figure 10 shows a case in which the improved method was
For the measurements at each substation, we installed used, and Fig. 11 shows a case in which filtering to remove
PMUs (Toshiba NCT 2000; referred to as “NCT” below) outliers was added.
at substation A (measurement point 1) and substation B The reference values used to evaluate the short circuit
(measurement point 2), as can be seen in Fig. 7, and used currents were found by offline system analysis reflecting the
personal computers for data collection. We then measured operational state of the system during the measurements. In
the 77-kV bus voltage and the line current. At substation the figures, the reference values of the short circuit currents
A, we measured the 154-kV bus voltage for the purpose of (triangles) at two representative times (5:00 and 14:30) and
the phase correction described in Section 3.2. The phasor the maximum short circuit current during operation (line)
values of the NCT can be measured accurately by reception are shown.
49
Fig. 11. Estimation results by and dLS and dCV methods
(with correction/without filtering). [Color figure can be
viewed in the online issue, which is available at
wileyonlinelibrary.com.]
Fig. 9. Estimation results by LS and CV methods (with As the threshold for eliminating outliers, we used
correction/without filtering). [Color figure can be viewed the daily average value of the standard deviation of
in the online issue, which is available at the time difference data set for the voltage phasor
wileyonlinelibrary.com.] value.
A comparison of Figs. 9 and 10 clearly shows
that the estimation accuracy is greatly improved by us-
ing the time differences of the phasor values. Compari-
son of Figs. 10 and 11 shows that the variance of the
estimates is greatly improved by adding processing to
remove outliers. Thus, using the time difference of the
phasor quantities, we confirmed the effectiveness of the
proposed method of correcting the estimated data by us-
ing a reference phasor and adding filtering to remove
outliers.
5. Conclusions
50
REFERENCES Approximating microscopic fluctuations in Eq. (A.1) by
a first-order Taylor expansion when the fluctuations are
1. Price E. Practical considerations for implementing wide sufficiently small, we obtain
area monitoring, protection and control, IEEE 59th An-
nual Conference for Protective Relay Engineers, 2006. δV̇ G δİ δV̇ 1 δİ
− V̇ G 1 − δŻ sys = − V̇ 1 1 .
2. Adamiak MG, Apostolov AP, Begovic MM, Henville İ 1 İ 2 İ 1 İ 2
1 1
CF, Martin KE, Michel GL, Phadke AG, Thorp JS. Wide
area protection. technology and infrastructures, IEEE Thus, the microscopic fluctuations on the system side
Trans Power Delivery 2006;21(2). are
3. Phadke AG, Volskis H, Menezes de Moraes R, Bi T,
Nayak RN, Schgal YK, Sen S, Sattinger W, Martı́nez δV̇ G δV̇ 1 ( ) δİ 1
E, Samuelsson O, Novosel D, Madani V, Kulikov YA. − δŻ sys = + V̇ G − V̇ 1 . (A.7)
İ 1 İ 1 İ 2
The wide world of wide-area measurement. IEEE Power 1
Energy Mag 2008;6(5):52–65. The fluctuations in Eq. (A.5) (load 1) are
4. Xu W, Ahmed EE, Zhang X, Liu X. Measurement of
( )
network harmonic impedances: practical implementa- δV̇ 1 δ İ 1 − İ 2
tion issues and their solutions. IEEE Trans Power De- δŻ L1 = ̇
− V1 ( )2 . (A.8)
İ 1 − İ 2 İ 1 − İ 2
livery 2002;17(1).
5. Vu K, Begovic MM, Novosel D, Saha MM. Use of lo- The first-order fluctuations in Eq. (A.6) (load 2) are
cal measurements to estimate voltage-stability margin.
δV̇ 2 δİ
IEEE Trans Power Syst 1999;14(3). δŻ L2 = − V̇ 2 2 . (A.9)
6. Arefifar SA, Xu W. Online tracking of power sys- İ 2 İ 22
tem impedance parameters and field experiences. IEEE
Trans Power Delivery 2009;24(4). Because the fluctuations on the system side and the
7. Srinivasan K, Lafond C, Jutras R. Short-circuit cur- load side are separate, the relation between V̇ G , Ż sys , Ż L1 ,
rent estimation from measurement of voltage and cur- and Ż L2 is assumed to take the form of Eqs. (A.10) and
rent during disturbances. IEEE Trans Industr Appl (A.11).
1997;33(4). • Fluctuations of V̇ G and Ż L1 uncorrelated:
51
( )
V̇ ∗1 Ċ V1 I1 − Ċ V1 I2 Thus, we obtain for VG and Zsys
− ( )∗2 V̇ G − V̇ 1
İ 1 İ 1 − İ 2
( )( ) V̇ ∗1 (Ċ V1 I1 − Ċ V1 I1 ) − (İ 1 − İ 2 )∗ Ċ V1 V1
V̇ ∗1 V̇ G − V̇ 1 Ċ I1 I1 − Ċ I1 I2 =
(İ 1 −İ 2 )∗ Ċ V I V̇ ∗1 (Ċ I I −Ċ I I )
,
− ( )∗2 (A.12) İ 1
1 1
− 1 1
İ 1
1 2
İ 2 İ 1 − İ 2
1
(A.13)
( )
Ċ ∗V = Ċ I1 V1 .
1 I1 V̇ G − V̇ 1
Ż sys =
By assumptions (A.10) and (A.11) we have İ 1
̇∗ ( ) (
( )∗ ( ) ( )C )∗
0 = İ 1 − İ 2 ̇CV V + İ 1 − İ 2 ∗ V̇ G − V̇ 1 V1 I1 V̇ ∗1 Ċ V1 I1 − Ċ V1 I2 − İ 1 − İ 2 Ċ V1 V1
1 1
İ 1 = ( ( ) .
( )( ) )∗
( ) V∗1 V̇ G − V̇ 1 Ċ I1 I1 − Ċ I1 I2 İ 1 − İ 2 Ċ V1 I1 − V̇ ∗1 Ċ I1 I1 − Ċ I1 I2
− V̇ ∗1 Ċ V1 I1 − Ċ V1 I2 − .
İ 1 (A.14)
Suresh Chand Verma (senior member) completed the M.E. program in electrical engineering at the Graduate School of
Engineering of Roorkee University, India, in 1986, then was employed by a power company in India. He came to Japan in 1990
and completed the doctoral program in electrical engineering at the Graduate School of Engineering of Nagoya University in
1994. Since 1994 he has been employed by the Chubu Electric Power Company, where he is affiliated with the Electric Power
Technology Laboratory. He is primarily engaged in research on the analysis and control of electric power systems (D.Eng.). He
received an IEEJ Outstanding Paper Prize in 2003. He is a member of IEEE.
Yoshiki Nakachi (member) completed the M.E. program in electrical engineering at the Graduate School of Engineering
of Musashi Institute of Technology in 1992, then joined Chubu Electric Power Company. After working in the Electric Power
Technology Laboratory of the Research and Development Division, he joined the Grid Technologies Group in the Power System
Operations Department, where he is engaged in research on the analysis, stabilization control, and voltage control of electric
power systems. He completed the latter half of the doctoral program at the Graduate School of Engineering of Nagoya Institute
of Technology in 2007 (D.Eng.). He received an IEEJ Outstanding Paper Prize in 2005. He is a member of the Institute of
Electrical Installation Engineers of Japan.
Yoshihiko Wazawa (member) received a bachelor’s degree from the Department of Electrical Engineering of Tohoku
University in 1985, then joined Chubu Electric Power. He is primarily engaged in the planning, development, and operation
of protective control devices and stabilization devices for electric power systems. He is now affiliated with the Electric Power
Technology Laboratory of the Research and Development Division.
52
AUTHORS (continued) (from left to right)
Yoko Kosaka (member) received a bachelor’s degree from the Department of Applied Physics of Nihon University in
March 1990, then joined Toshiba Corporation. She is now engaged in research and on the operation, monitoring, control, and
analysis of electric power systems at the Power and Industrial Systems R&D Center.
Takenori Kobayashi (senior member) completed the doctoral program in electrical engineering at the Graduate School
of Engineering of the University of Tokyo in 1995. He joined Toshiba in 1994. He is now engaged in engineering research on
smart grids and storage systems at the Grid Solutions Technology Office of the Transmission & Distribution Systems Division
(D.Eng.). He is a member of IEEE.
Kazuya Omata (senior member) completed the M.E. program at the Graduate School of Science of Waseda University in
1980, then joined Toshiba Corporation. He is now engaged in research on analysis, monitoring, and control systems for electric
power and energy systems at the Power and Industrial Systems R&D Center (D.Eng.). He received an IEEE/PES Paper Award
in 1992 and an IEEJ Outstanding Paper Prize in 1994.
Yoshiki Takabayashi (member) received a bachelor’s degree from the Department of Electrical Engineering of Chiba
Institute of Technology in 1982, then joined Toshiba Corporation. He is primarily engaged in system design and in the
development of monitoring and control systems for electric power grids. He is now affiliated with the Grid Solutions Technology
Office in the Transmission & Distribution Systems Division.
53