Commissioning Procedure for QXEH-pumps

100-I-000019-00

This document describes the commissioning procedure for QXEH-pumps in servo drives.
This procedure must be applied in following three cases:
1. Pumps in new machines at the production plant.
2. Pumps in new machines at the end customer after filling the oil tank (only “1. Step” and “4. Step” necessary, see
Figure 1).
3. In case of a pump replacement in the field.

1 De-Airing the Pump


- See “1. Step” in Figure 1 below.
- During the de-airing the pump delivers its flow and the air directly into the tank. It must be ensured that the oil is free
from bubbles and foam before the de-airing is completed.
- Maximum outlet pressure: 15 bar.
- Maximum start viscosity of the hydraulic oil: 300 cSt (10 °C with HLP46)

2 Oil Heating
- See “4. Step” in Figure 1 below.
- By using mineral oil HLP 46 the oil heating phase of the commissioning is completed when the oil temperature reaches
35 °C. After the commissioning procedure the minimum allowable operating temperature is 25 °C.
Goal of the Commissioning Procedure is to ensure a proper Outlet Pressure
running-in for the pump w ith the respective fluid in the QXEH - Commissioning Procedure Shaft Speed
respective machine. If the required shaft speed can not be 3500
achieved, please communicate w ith Bucher Hydraulics. 7. Step, cyclic running-in
pressure level 3
- Run the pump for 45 seconds
125 with maximum set pressure of the
ma xi mum operating pressure machine at shaft speed range
700...3000 1/min.
5. Step, running-in 6. Step, cyclic running-in
pressure level 2 pressure level 2
- Run the pump for 45 - Run the pump with
100 seconds with 6 x 60 % of the maximum
60 % of the maximum pressure ramps at shaft
pressure and shaft speed 700...2500 1/min.
Outlet Pressure in %

1. Step, de-airing the pump 2. Step, running-in 3. Step, cyclic running- 4. Step, oil heating speed 700...2500

Shaft Speed [1/min]


- Fill the pump and the pressure level 1 in pressure level 1 - Run the pump with following 1/min.
75 suction line with oil. - Run the pump for 45 - Run the pump with parameters as long as oil
- Run the pump at least 2 seconds with 6 x 30 % of the maximum temperature of at least 35 C is
minutes with max. 15 bar 30 % of the maximum pressure ramps at shaft reached: 40 % of the
pressure and shaft speed > pressure at shaft speed speed 500...2000 1/min. maximum pressure, shaft
200 1/min. 500...2000 1/min. speed 500...2000 1/min.
50

25

0 0
-60 -40 -20 0 20 40 60 80 100 120 140 160 180 200 220 240 260 280 300 320 340 360 380
Tim e [s]

Figure 1. Commissioning cycle.

info.kl@bucherhydraulics.com www.bucherhydraulics.com
© 2017 by Bucher Hydraulics GmbH, D-79771 Klettgau
All rights reserved.
Data is provided for the purpose of product description only, and must not be construed as warranted characteristics in the legal
sense. The information does not relieve users from the duty of conducting their own evaluations and tests. Because the products
are subject to continual improvement, we reserve the right to amend the product specifications contained in this catalogue.
Alle Rechte vorbehalten.
Die angegebenen Daten dienen allein der Produktbeschreibung und sind nicht als zugesicherte Eigenschaften im rechtlichen Sinne
zu verstehen. Die Angaben entbinden den Anwender nicht von eigenen Beurteilungen und Prüfungen. Auf Grund kontinuierlicher
Verbesserungen der Produkte, sind Änderungen der in diesem Katalog gemachten Produktspezifikationen vorbehalten.

Bucher Hydraulics CC-DE Schutzvermerk nach ISO 16016 beachten BHKL · 01.06.2017
Änderungen vorbehalten 1/1

You might also like