You are on page 1of 14

IPA18-585-F

PROCEEDINGS, INDONESIAN PETROLEUM ASSOCIATION


Forty-Second Annual Convention & Exhibition, May 2018

NEW LIQUID OVERFLOW HANDLING SYSTEM TO PREVENT PROCESS TANK FIRES

Reza Looyeh*
Adi Kristanto*
Gordon Chu*
Dwi Firman Nugraha*

ABSTRACT Protection, Overfill Prevention, Water Seal Box,


Horizontal P-Trap Spool
During the investigation of a recent process tank fire,
it was determined that hydrocarbon gas was released INTRODUCTION
through the malfunctioning and poor integrity of the
tank liquid overflow handling system. This allowed Background
gas to freely flow through the water seal system and
into the below grade open drain. As per current industry practice, process and storage
tanks are generally equipped with an externally
Several corrective actions were put in place and a connected liquid overflow handling system. The
significantly improved overall water seal design was liquid overflow handling system is considered as an
successfully developed and safely executed in the additional layer of protection in case process tank
field to address all critical tanks exhibiting constant level control(s) fail to prevent overfills during a
and/or intermittent gas release. This improved normal or abnormal operating condition and other
design, which uses the existing water seal system, overfill protective safeguards (if exist, whether
consists of a new upright elbow/horizontal P-trap automatic or with operator’s intervention) do not
spool with its highest point above the water seal function as intended.
system to keep the water level at that elevation and
provide a complete sealing. Overfill is a critical safety hazard which can result in
the loss of tank fluid and potentially major incidents
A second design concept was also proposed and if the fluid is flammable or environmentally
executed for these liquid overflow handling systems sensitive. In fact, overfills have been the main cause
where the water seals have integrity issues due to of serious incidents in the process industries for
their design. This design replaces the entire liquid decades. Roos & Myers (2015) reported that the
overflow handling system from the tank overflow spills of hazardous products may exceed 100,000
nozzle all the way to below grade open drain and it annually across the world and then indicated that
is fully inspectable by conventional methods. The majority of these spills are related to tank overfill
design uses a double elbow/horizontal P-trap upside- incidents. It is critical to know that overfills do not
down spool to hold the water for sufficient head to happen randomly, and therefore, they are predictable
seal the gas from exiting the tank while allowing and thereby preventable.
liquid overflow discharging into the open drain.
With stringent legislations and regulations coming
This paper aims to provide a detail sequence of into force nationally and internationally, safety
technical development, lessons learned and design expectations are rapidly increasing especially where
concepts and intends to provide doable there exist major consequences for process incidents.
recommendations for swift corrective actions of It is therefore difficult for the process industry to
existing aboveground process and storage tank maintain compliance because methodologies that
overflow handling systems in oil and gas industry were deemed acceptable in the past may not conform
while proposing a new design for inclusion into the to the newer and more stringent requirements. Thus,
applicable codes and standards. process industry is moving towards “zero is
achievable” concept, and, the goal to achieve zero
Keywords: Process Tank, Storage Tank, Liquid tank overfills should be within the reach to protect
Overflow Handling System, Process Fires, Overfill life and health, protect environment, protect process

* Chevron Pacific Indonesia


plant assets, comply with regulations and  inspection, testing, and preventive
legislations, improve public relations, assume maintenance (ITPM)
corporate social responsibility, increase operation
efficiency and minimize financial and legal risks.  optimization of the work place and safe
operating practices and protocols, emergency
Liquid Overflow Handling System procedures, and, operator training and
competency
A tank overflow handling system generally consists
of a down-comer pipe, a water seal box and an  equipment and system selection and
outgoing pipe which discharges into a below grade installation
open drain trench. The water seal box component
also has a second critical function; this is to maintain  management of change (MOC) programs
a back pressure and prevent the gas (in the vapor relative to tank overfill protection and
space of the process tank) to exit through the prevention
outgoing pipe. This is achieved by the extended
down-comer pipe immersing into the water content
 inclusion of current technology and practices
inside the fully enclosed seal box to form a seal
related to process control and automated safety
system preventing the gas to escape (Figure 1).
instrumented systems.
There is limited literature available on the subject;
most of focuses have been on the robustness and And, therefore, a robust prevention may only be
functionality of overfill protection and safeguards for achieved by ensuring that all of the above elements
both process and storage tanks especially following are in place and working properly as intended.
the Buncefield major incident occurred in 2005 and
the subsequent investigation report issued by Buncefield Major Incident Investigation Board
Buncefield Major Incident Investigation Board in report (2007) made its key reference to the
2007. Since then the focus of new build process and management of fire and explosion hazards by
storage tanks have been on devising flawless overfill applying methodologies to identify, evaluate, and
protection safeguards (with several layers of control the hazards involved in the processing and
protection) to eliminate a need for a liquid overflow handling of flammable and combustible liquids.
handling system. To the best of authors’ knowledge, They categorized hazards, but not limiting to,
relevant codes and standards such as API Standard preparation, separation, purification, and change of
650 (2016), ANSI/API Standard 2350 (2012), API state, energy content, or composition. Overall, they
Standard 2000 (2014) and NFPA 30 (2018) also came up with several recommendations for the
make very little reference to the liquid overflow operations involving flammable and combustible
handling system, its integrity and functionality and liquids and indicated that such operations shall be
the potential scenarios/risks for failure and/or major reviewed to ensure that fire and explosion hazards
incidents. are addressed by fire prevention, fire control, and
emergency action plans. Since then, many operating
While NFPA 30 (2018) provides fundamental and sites have updated existing and/or developed new
critical safeguards required for the storage, handling, safe operating procedures to incorporate the
and use of flammable and combustible liquids, Buncefield recommendations and ensure their
ANSI/API 2350 (2012) provides more focuses on aboveground process and storage tank overfill
protection and prevention with the latter being the protection and prevention systems are in place and
most basic level of protection. This standard functioning.
comprise minimum overfill (and damage) prevention
practices for aboveground storage tanks that receive Verma and Self (2014) did a comprehensive
flammable and combustible liquids. And, although assessment of all research and investigation work
this standard came into force in 1987 for the first done in past two decades on tank overfill protection
time, it made little reference to aboveground process and prevention and published their research work in
and storage tanks equipped with liquid overflow 2014. In their paper they indicated that in addition to
handling systems. With operations considered as the overflow of hazardous fluids, overfill may
primary overfill protection/prevention safeguard, encompass fluids that are safe to discharge to the
careful consideration has also been given to: atmospheric drains e.g. through a liquid overflow
handling system. Furthermore, with risk assessment
 safety and environmental protection quoted as being the key element in an overfill
management system to develop a robust tank control safeguards inspected, verified and validated on a
system, they assessed two configurations: (a) Fluids regular basis to ensure they are fit for continued
safe to release to atmosphere, and, (b) Fluids not safe service as a reliable layer of protection.
to release to atmosphere; the former to include an
overflow handling system and the latter without one. Objectives
They assessed both configurations in detail with
several overfill scenarios and although made some This paper is therefore aimed to provide a detail
reference to tank integrity but made no reference to sequence of technical development, lessons
the integrity of the overflow handling system learned and design concepts and intended to
especially those with a water seal box. provide field doable recommendations for swift
corrective actions and/or repairs for the existing
With brief review of literature as described above aboveground process and storage tank overflow
and considering that many of process and storage handling systems in oil and gas industry while
tanks built prior to 2000, and currently in service, are proposing a new design for inclusion into the
still equipped with overflow handling system, it is applicable codes and standards. Although, the
recognized that there is still a gap in industry on how structural support of the overflow handling system
to safely operate these tanks understanding of high and design of appropriate pipe supports are
risks associated with failure of such systems during included, the paper does not address shell stiffness
an overflow scenario. and stability around the overflow nozzle and box
at the top of the shell.
During the investigation of a recent process tank
incident, it was determined that the gas, which DESIGN METHODS
escaped the tank and caused the tank fire, was
through the malfunctioning and poor integrity of Several corrective actions were put in place and a
liquid overflow handling system allowing gas to significantly improved design of liquid overflow
freely flow into the down-comer pipe bypassing the handling system was successfully developed to
water seal from within the box and then flow further address all critical cases with constant gas release.
into the outgoing pipe and the trench eventually. This improved design (hereafter “Alternative 1”),
Subsequent and detailed field inspection revealed which uses the existing water seal box, consists of
that the extended down-comer pipe inside the seal a new upright elbow/horizontal P-trap spool with
box above the water level was excessively corroded its highest point above the seal box to keep the
with several pin holes and therefore not providing water level at that elevation and a new pipe
adequate sealing (Figure 2). Further inspection of all support. This design eliminates the dependency on
process tanks in the operator’s facilities identified the extended pipe inside the seal box to provide
several failed water seal boxes resulting to the release sealing and is applicable for all seal boxes with
of the explosive gas to the hazardous classified areas acceptable mechanical integrity (Figure 3).
either constantly or intermittently.
The key design, operational and construction reasons
The asset integrity ITPM plan for overflow handling for using design Alternative 1 are:
system is normally performed as part the piping’s
ITPM (and not tank’s) and includes visual checks  Existing overflow handling line and water seal
and some random UT testing on the down-comer box were examined fully using UT inspection
pipe near the top of the seal box and/or the outgoing method and found to be in good shape with no
pipe. Neither of these inspection methods produce integrity issues or concerns
any data related to the integrity of the pipe inside the
seal box. Although there exist other inspection  Existing water seal box outlet (outgoing pipe)
methods such as radiography or borescope etc., they has an existing bolted flange allowing the field
also have limitations due to the size, accuracy and execution to be performed with minimal field
accessibility in the classified hazardous areas. It was work and no hot work activity in classified
thus noted that the old overflow handling system hazardous areas
design (which includes extended down-comer pipe
into the seal box) would have not allowed for  This design relies on horizontal P-trap to provide
thorough inspection of the internal sections unless an the water seal and not the seal box, and, it is fully
intrusive inspection method was used. This was then inspectable by the conventional methods such as
considered a deficiency issue from the past tank Ultrasonic Testing (UT)
design when we did not think about the need to make
 It uses the existing overflow line and seal box inspectable by the conventional methods such
minimizing time and duration of the field as UT inspection
execution while minimizing exposure risk to
the crew and the asset, production impact and  It ensures there is always an 8 inches of water
material acquisition/usage column exists to seal the gas

 It ensures the liquid level is always 8 inches  It has an external water injection point to
above the seal box providing a complete water ensure the pipe is water full at all time
seal and enabling routine inspection and
maintenance  It has a draining point which allows flushing
the pipe if the water is contaminated or to
 It uses the existing small-bore water supply monitor the water level
from the bottom of the tank to ensure the
horizontal P-trap pipe is water full at all time It should also be noted that both design alternatives
(once installed) benefit from daily operator routine
A second design (hereafter “Alternative 2”) was also duty and checklist (ORDC) checks to ensure the
developed for those liquid overflow handling system is fully functional and provide a complete
systems where the seal boxes have integrity issues seal.
and are not fit for continued service. This design
replaces the entire overflow handling system from EXECUTION PROCESSES
the tank overflow nozzle flange all the way to the
trench. The design uses a double elbow/horizontal Since these improved designs have different weight
P-trap upside-down to hold the water for sufficient loads and center of gravities compared to those of the
head and back pressure to seal the gas from exiting existing systems, it is critical that they have adequate
the tank while allowing liquid overflow discharging anchors/pipe support(s) to ensure maintaining the
into the trench and it also has new pipe supports mechanical integrity of the overflow handling system
(Figure 4). as well as the integrity of tank shell during a worst-
case scenario of turbulent overflow or a seismic
The key design, operational and construction reasons event. Such scenarios may also impose longitudinal
for using design Alternative 2 are: moments, lateral forces and moments, and torsion,
and therefore, anchors and pipe supports should be
 Existing overflow handling line and water designed to not only take vertical loads but prevent
seal box were examined fully using UT lateral movements resulted from turbulent overfilled
inspection and found to have substantial liquid travelling rapidly through overflow handling
integrity issues either thinned below system or seismic events and prevent moments
minimum wall thickness or already leaking imposed on the tank overflow nozzle or shell.
due to pin holes
In addition to the requirements to perform process
 Existing water seal box outlet (outgoing hazard analysis (PHA) and risk assessments to
pipe) has no available bolted flange encompass all possible abnormal events, each design
connection and therefore fabricating the alternative requires pipe stress analysis to be
entire overflow with double horizontal P- performed for all load cases to identify the maximum
traps is done on the shop floor with no or stresses at the tank shell overflow nozzle and in the
minimal field construction work and no field overflow handling system. Then, suitable anchors
hot work activity in classified hazardous and/or pipe support(s), either the existing standard
areas designs or new fit-for-purpose design(s), should be
used or developed to ensure all stresses will remain
 Replaces the entire system from tank within allowable limits as per code requirements and
overflow flange to the trench minimizing industry best practices.
time and duration of the field execution
while minimizing exposure risk to the crew Installing a (small bore) pipe connection to
and the asset and production impact drain/flush out the water from seal box/P-trap pipe in
case of an overflow event (or as part of ORDC) and
 This design relies on the double horizontal P- installing a fill line to replace the product collected
trap to provide water seal and it is fully (drained) from the seal box/P-trap pipe with (fresh)
water, are critical parts of both proposed design Figure 10 shows two field pictures taken before the
Alternatives 1 and 2. This is to: repair and after the design Alternative 2 was installed
for a process clarifier tank. As can be seen, the first
 account for an overflow event when occurs; in option (shown in Figure 8) has been used to complete
this case the water will be replaced with this repair and replacement. Some field cutting work
stagnant product inside the seal box/P-trap was performed in the field to minimize the size of
pipe which likely to have gas vapor content to lifted pipes and minimize the potential of damaging
be released to atmosphere. Thus, a refill line the nearby pipework. No other hot work was
would become critical and should be used performed during this construction work. The work
during ORDC or following an overflow event included dismantling of the entire overflow handling
to replace the product content with (fresh) system, installation of a double horizontal P-trap
water pipework, fabrication of a new anchor support (at the
drain end) and another pipe support (under the down-
 ensure regular replacement of the stagnant comer pipe), and finally, the civil work associated
water in the seal box/P-trap pipe, which may with the installation of the new pipe supports.
become a medium for bacteria growth and Although not shown, surrounded by other nearby
accelerated corrosion, with (fresh) water, is pipework, accurate and several field measurements,
performed in an acceptable interval as part of several and detail constructability reviews,
the ORDC. appropriate isolation plan and detail lifting plan were
the key elements to complete this repair and
RESULTS replacement work safely, reliably and successfully.
Field Repairs Quality control and quality assurance (QA/QC) were
part of the MOC process during early field
Figure 5 depicts one (sample) design out of 5 measurements, drawing development and approval,
possible options for the design Alternative 1 to material selection and suitability assessment, shop
account for differences in all existing overflow fabrication work and finally during and after the
handling systems which require repairing using this completion of the installation. Each repaired
design alternative. Other 4 options are shown in overflow handling system was then filled with
Figure 6. adequate water, put back into service and finally
tested with gas detector during normal operation to
Figure 7 shows two field pictures taken before the ensure there is a zero presence of gas while the tanks
repair and after the design Alternative 1 was are functioning. The gas measurement and
installed for a process wash tank. As can be seen, monitoring and water level checks are part of the
the first option (shown in Figure 5) has been used operation daily ORDC in line with safe operating
to complete this repair. No hot work was procedure.
performed in the field but the work included
outgoing pipe dismantling, horizontal P-trap Lessons Learned
installation using bolted flange, fabrication of a
second pipe support and finally the civil work Although this repair and replacement work is
associated with the installation of this second pipe normally presumed as a routine construction work, it
support. Although not shown, due to connectivity is critical to consider the operations’ constraints,
and proximity of other pipework near this tank, equipment age and asset integrity, constructability
accurate and several field measurements, detail challenges due to equipment and pipework
constructability review, appropriate isolation plan congestion and complexity surrounding the repair
and detail lifting plan were the key elements to area, isolation plan, lifting sequence and QA/QC to
complete this repair safely, reliably and ensure no impact to the continuous operation while
successfully. conducting the work successfully incident and injury
free. It is thus important to have a detailed MOC
Figure 8 depicts one (sample) design out of 5 process from early stage of design work to the field
possible options for the design Alternative 2 to execution and handover to operations to include (but
account for differences in all existing overflow not limited to) field survey, appropriate issue of
handling systems which require repairing using drawings for construction, constructability
this design alternative for replacement of the entire review(s), development of engineering/construction
overflow handling system. Other 4 options are work packs, pipe stress analysis for the worst case
shown in Figure 9. scenario(s), design of non-standard pipe supports,
isolation plan, lifting and handling plan, handling CONCLUSIONS & RECOMMENDATIONS
of field changes during execution, permitting,
inspection, functional reviews, QA/QC, pre-start Overfill protection and prevention are the keys in
up safety review (PSSR) etc. providing and maintaining safe, reliable and
continuous operations for the aboveground process
Some of our key lessons learned for this repair and storage tanks. Although the current industry
work are highlighted below: focus is on flawless overfill protection and
safeguards, the tank incident statistics over the past
 A robust MOC process would allow several decades suggest that overfills are still the
development of work from early stage to cause of many process industry incidents especially
execution and put back in service. Frequent for in-service older tanks in which several layers of
audit of the MOC and appropriate functional overfill and overflow protection may not be in place
reviews by all relevant engineering or they may be in place but not functioning.
discipline would ensure the quality and
A recent process tank fire investigation determined
appropriateness of the MOC
that hydrocarbon gas was released through the
 Several field surveys and measurements and malfunctioning and poor integrity of the tank liquid
constructability reviews are key to ensuring overflow handling system allowing gas to freely flow
accuracy of the work before execution into the overflow line and through the water seal
system to the below grade open drain, subsequently.
 Lifting and handling plan should include Several corrective actions were put in place
detail sequence of dismantling as well as including detail inspections and ORDC, and, two
sequence of installation in line with design alternatives were proposed, i.e. Alternative 1
constructability review recommendations – and Alternative 2, and implemented in the field
This may include crews of different safely and successfully. While Alternative 1 uses the
expertise which may need to work existing water seal box with a horizontal P-trap
concurrently to achieve the intent of the addition to maintain a water seal, Alternative 2
construction work replaces the entire overflow handling system with a
double horizontal P-trap pipe. The former is used for
 QA/QC, PSSR, completion of as build overflow lines which have good integrity and the
documentation are key final stages before latter is proposed where the inspection has identified
closing an MOC some integrity issues. Both designs are fully
inspectable by the conventional methods such as UT
 Detail and accurate planning and scheduling inspection.
of the work order is critical to ensure
appropriate completion of the entire work The results of this work have been shared widely
scope within the planned schedule through industry alerts and this paper intended to
further share detail sequence of technical
 Visual and random UT inspection may not be development, lessons learned and design concepts
adequate as part of an ITPM to confirm good accordingly. Doable recommendations for
integrity of a tank overflow handling system. corrective actions of existing aboveground process
More intrusive inspection methods such as and storage tank overflow handling systems have
borescope through hot tapping or other been proposed and the results of field execution have
technologies may need to be used to better been provided to allow other operators to implement
evaluate the conditions of internal sections appropriate corrective actions accordingly. And
e.g. the extended down-comer pipe inside finally, it has been proposed to develop appropriate
the seal box. amendment(s) to the applicable codes and standards
to ensure awareness while helping to eliminate or
minimize future incidents associated with any
 Details of this work can be the source of
overflow handling system failure.
discussion during code committee meeting
and for the assessment what needs to be ACKNOLEDGEMENTS
changed in the current code for better and
wider appropriate awareness and action The authors would like to thank PT. Chevron Pacific
across oil and gas industry. Indonesia for permission to publish this work. They
would also like to thank the working team
including engineering and technical authroity, API Standard 2000, 2014, Venting Atmospheric and
operations, infrastructure maintenance, field Low-pressure Storage Tanks, American Petroleum
engineering, technical services and contractor Institue.
teams who work efficiently to complete the field
remedial work safely, successfully and incident Buncefield Major Incident Investigation Board,
free. 2007, Recommendations on the design and operation
of fuel storage sites.
REFERENCES NFPA 30, 2018, Flammable and Combustible
Liquids Code, National Fire Protection Association.
ANSI/API Standard 2350, 2012, Overfill
Protection for Storage Tanks in Petroleum Roos, C-J, Myers, P. E., 2015, The Engineer’s Guide
Facilities, American Petroleum Institue. to Overfill Prevention, Emerson Process
Management.
API Standard 650, 2016, Welded Tanks for Oil
Verma, S. and Self, F., 2014, Design Options for
Storage, American Petroleum Institute.
Overfill Protection for Aboveground Storage Tanks:
Proceedings of American Institue of Chemical
Engineers, 10th Global Congress on Process Safety.
Figure 1 - Hydrocarbon Processing Tank with Liquid Overflow Handling System

Figure 2 - Pin Hole Failure Inside Water Seal Box Allowing Methane Gas to Freely Escape the Seal System
and Release into Atmosphere
Figure 3 - Tank Liquid Overflow Handling System with Improved Horizontal P-Trap Pipe Spool and Existing
Water Seal Box

Figure 4 - Tank Overflow Handling System with Improved Double Horizontal P-Traps Without a Water Seal
Box
Figure 5 - Sample Option of Design Alternative 1 with Improved Horizontal P-Trap Pipe Spool and Existing
Water Seal Box
Figure 6 - Four Other Sample Options of Design Alternative 1 with Improved Horizontal P-trap Pipe Spool
and Existing Water Seal Box
Figure 7 - Wash Tank Overflow Handling System; (a) Original System Before Repair, (b) Improved System
After Repair Using Design Alternative 1

Figure 8 - Sample Option of Design Alternative 2 with Improved Double Horizontal P-Traps Without a Water
Seal Box
Figure 9 - Four Other Sample Options of Design Alternative 2 with Improved Double Horizontal P-Traps
Without a Water Seal Box
Figure 10 - Clarifier Tank Overflow Handling System; (a) Original System Before Repair, (b) Improved
System After Repair Using Design Alternative 2

You might also like