Professional Documents
Culture Documents
Reza Looyeh*
Adi Kristanto*
Gordon Chu*
Dwi Firman Nugraha*
It ensures the liquid level is always 8 inches It has an external water injection point to
above the seal box providing a complete water ensure the pipe is water full at all time
seal and enabling routine inspection and
maintenance It has a draining point which allows flushing
the pipe if the water is contaminated or to
It uses the existing small-bore water supply monitor the water level
from the bottom of the tank to ensure the
horizontal P-trap pipe is water full at all time It should also be noted that both design alternatives
(once installed) benefit from daily operator routine
A second design (hereafter “Alternative 2”) was also duty and checklist (ORDC) checks to ensure the
developed for those liquid overflow handling system is fully functional and provide a complete
systems where the seal boxes have integrity issues seal.
and are not fit for continued service. This design
replaces the entire overflow handling system from EXECUTION PROCESSES
the tank overflow nozzle flange all the way to the
trench. The design uses a double elbow/horizontal Since these improved designs have different weight
P-trap upside-down to hold the water for sufficient loads and center of gravities compared to those of the
head and back pressure to seal the gas from exiting existing systems, it is critical that they have adequate
the tank while allowing liquid overflow discharging anchors/pipe support(s) to ensure maintaining the
into the trench and it also has new pipe supports mechanical integrity of the overflow handling system
(Figure 4). as well as the integrity of tank shell during a worst-
case scenario of turbulent overflow or a seismic
The key design, operational and construction reasons event. Such scenarios may also impose longitudinal
for using design Alternative 2 are: moments, lateral forces and moments, and torsion,
and therefore, anchors and pipe supports should be
Existing overflow handling line and water designed to not only take vertical loads but prevent
seal box were examined fully using UT lateral movements resulted from turbulent overfilled
inspection and found to have substantial liquid travelling rapidly through overflow handling
integrity issues either thinned below system or seismic events and prevent moments
minimum wall thickness or already leaking imposed on the tank overflow nozzle or shell.
due to pin holes
In addition to the requirements to perform process
Existing water seal box outlet (outgoing hazard analysis (PHA) and risk assessments to
pipe) has no available bolted flange encompass all possible abnormal events, each design
connection and therefore fabricating the alternative requires pipe stress analysis to be
entire overflow with double horizontal P- performed for all load cases to identify the maximum
traps is done on the shop floor with no or stresses at the tank shell overflow nozzle and in the
minimal field construction work and no field overflow handling system. Then, suitable anchors
hot work activity in classified hazardous and/or pipe support(s), either the existing standard
areas designs or new fit-for-purpose design(s), should be
used or developed to ensure all stresses will remain
Replaces the entire system from tank within allowable limits as per code requirements and
overflow flange to the trench minimizing industry best practices.
time and duration of the field execution
while minimizing exposure risk to the crew Installing a (small bore) pipe connection to
and the asset and production impact drain/flush out the water from seal box/P-trap pipe in
case of an overflow event (or as part of ORDC) and
This design relies on the double horizontal P- installing a fill line to replace the product collected
trap to provide water seal and it is fully (drained) from the seal box/P-trap pipe with (fresh)
water, are critical parts of both proposed design Figure 10 shows two field pictures taken before the
Alternatives 1 and 2. This is to: repair and after the design Alternative 2 was installed
for a process clarifier tank. As can be seen, the first
account for an overflow event when occurs; in option (shown in Figure 8) has been used to complete
this case the water will be replaced with this repair and replacement. Some field cutting work
stagnant product inside the seal box/P-trap was performed in the field to minimize the size of
pipe which likely to have gas vapor content to lifted pipes and minimize the potential of damaging
be released to atmosphere. Thus, a refill line the nearby pipework. No other hot work was
would become critical and should be used performed during this construction work. The work
during ORDC or following an overflow event included dismantling of the entire overflow handling
to replace the product content with (fresh) system, installation of a double horizontal P-trap
water pipework, fabrication of a new anchor support (at the
drain end) and another pipe support (under the down-
ensure regular replacement of the stagnant comer pipe), and finally, the civil work associated
water in the seal box/P-trap pipe, which may with the installation of the new pipe supports.
become a medium for bacteria growth and Although not shown, surrounded by other nearby
accelerated corrosion, with (fresh) water, is pipework, accurate and several field measurements,
performed in an acceptable interval as part of several and detail constructability reviews,
the ORDC. appropriate isolation plan and detail lifting plan were
the key elements to complete this repair and
RESULTS replacement work safely, reliably and successfully.
Field Repairs Quality control and quality assurance (QA/QC) were
part of the MOC process during early field
Figure 5 depicts one (sample) design out of 5 measurements, drawing development and approval,
possible options for the design Alternative 1 to material selection and suitability assessment, shop
account for differences in all existing overflow fabrication work and finally during and after the
handling systems which require repairing using this completion of the installation. Each repaired
design alternative. Other 4 options are shown in overflow handling system was then filled with
Figure 6. adequate water, put back into service and finally
tested with gas detector during normal operation to
Figure 7 shows two field pictures taken before the ensure there is a zero presence of gas while the tanks
repair and after the design Alternative 1 was are functioning. The gas measurement and
installed for a process wash tank. As can be seen, monitoring and water level checks are part of the
the first option (shown in Figure 5) has been used operation daily ORDC in line with safe operating
to complete this repair. No hot work was procedure.
performed in the field but the work included
outgoing pipe dismantling, horizontal P-trap Lessons Learned
installation using bolted flange, fabrication of a
second pipe support and finally the civil work Although this repair and replacement work is
associated with the installation of this second pipe normally presumed as a routine construction work, it
support. Although not shown, due to connectivity is critical to consider the operations’ constraints,
and proximity of other pipework near this tank, equipment age and asset integrity, constructability
accurate and several field measurements, detail challenges due to equipment and pipework
constructability review, appropriate isolation plan congestion and complexity surrounding the repair
and detail lifting plan were the key elements to area, isolation plan, lifting sequence and QA/QC to
complete this repair safely, reliably and ensure no impact to the continuous operation while
successfully. conducting the work successfully incident and injury
free. It is thus important to have a detailed MOC
Figure 8 depicts one (sample) design out of 5 process from early stage of design work to the field
possible options for the design Alternative 2 to execution and handover to operations to include (but
account for differences in all existing overflow not limited to) field survey, appropriate issue of
handling systems which require repairing using drawings for construction, constructability
this design alternative for replacement of the entire review(s), development of engineering/construction
overflow handling system. Other 4 options are work packs, pipe stress analysis for the worst case
shown in Figure 9. scenario(s), design of non-standard pipe supports,
isolation plan, lifting and handling plan, handling CONCLUSIONS & RECOMMENDATIONS
of field changes during execution, permitting,
inspection, functional reviews, QA/QC, pre-start Overfill protection and prevention are the keys in
up safety review (PSSR) etc. providing and maintaining safe, reliable and
continuous operations for the aboveground process
Some of our key lessons learned for this repair and storage tanks. Although the current industry
work are highlighted below: focus is on flawless overfill protection and
safeguards, the tank incident statistics over the past
A robust MOC process would allow several decades suggest that overfills are still the
development of work from early stage to cause of many process industry incidents especially
execution and put back in service. Frequent for in-service older tanks in which several layers of
audit of the MOC and appropriate functional overfill and overflow protection may not be in place
reviews by all relevant engineering or they may be in place but not functioning.
discipline would ensure the quality and
A recent process tank fire investigation determined
appropriateness of the MOC
that hydrocarbon gas was released through the
Several field surveys and measurements and malfunctioning and poor integrity of the tank liquid
constructability reviews are key to ensuring overflow handling system allowing gas to freely flow
accuracy of the work before execution into the overflow line and through the water seal
system to the below grade open drain, subsequently.
Lifting and handling plan should include Several corrective actions were put in place
detail sequence of dismantling as well as including detail inspections and ORDC, and, two
sequence of installation in line with design alternatives were proposed, i.e. Alternative 1
constructability review recommendations – and Alternative 2, and implemented in the field
This may include crews of different safely and successfully. While Alternative 1 uses the
expertise which may need to work existing water seal box with a horizontal P-trap
concurrently to achieve the intent of the addition to maintain a water seal, Alternative 2
construction work replaces the entire overflow handling system with a
double horizontal P-trap pipe. The former is used for
QA/QC, PSSR, completion of as build overflow lines which have good integrity and the
documentation are key final stages before latter is proposed where the inspection has identified
closing an MOC some integrity issues. Both designs are fully
inspectable by the conventional methods such as UT
Detail and accurate planning and scheduling inspection.
of the work order is critical to ensure
appropriate completion of the entire work The results of this work have been shared widely
scope within the planned schedule through industry alerts and this paper intended to
further share detail sequence of technical
Visual and random UT inspection may not be development, lessons learned and design concepts
adequate as part of an ITPM to confirm good accordingly. Doable recommendations for
integrity of a tank overflow handling system. corrective actions of existing aboveground process
More intrusive inspection methods such as and storage tank overflow handling systems have
borescope through hot tapping or other been proposed and the results of field execution have
technologies may need to be used to better been provided to allow other operators to implement
evaluate the conditions of internal sections appropriate corrective actions accordingly. And
e.g. the extended down-comer pipe inside finally, it has been proposed to develop appropriate
the seal box. amendment(s) to the applicable codes and standards
to ensure awareness while helping to eliminate or
minimize future incidents associated with any
Details of this work can be the source of
overflow handling system failure.
discussion during code committee meeting
and for the assessment what needs to be ACKNOLEDGEMENTS
changed in the current code for better and
wider appropriate awareness and action The authors would like to thank PT. Chevron Pacific
across oil and gas industry. Indonesia for permission to publish this work. They
would also like to thank the working team
including engineering and technical authroity, API Standard 2000, 2014, Venting Atmospheric and
operations, infrastructure maintenance, field Low-pressure Storage Tanks, American Petroleum
engineering, technical services and contractor Institue.
teams who work efficiently to complete the field
remedial work safely, successfully and incident Buncefield Major Incident Investigation Board,
free. 2007, Recommendations on the design and operation
of fuel storage sites.
REFERENCES NFPA 30, 2018, Flammable and Combustible
Liquids Code, National Fire Protection Association.
ANSI/API Standard 2350, 2012, Overfill
Protection for Storage Tanks in Petroleum Roos, C-J, Myers, P. E., 2015, The Engineer’s Guide
Facilities, American Petroleum Institue. to Overfill Prevention, Emerson Process
Management.
API Standard 650, 2016, Welded Tanks for Oil
Verma, S. and Self, F., 2014, Design Options for
Storage, American Petroleum Institute.
Overfill Protection for Aboveground Storage Tanks:
Proceedings of American Institue of Chemical
Engineers, 10th Global Congress on Process Safety.
Figure 1 - Hydrocarbon Processing Tank with Liquid Overflow Handling System
Figure 2 - Pin Hole Failure Inside Water Seal Box Allowing Methane Gas to Freely Escape the Seal System
and Release into Atmosphere
Figure 3 - Tank Liquid Overflow Handling System with Improved Horizontal P-Trap Pipe Spool and Existing
Water Seal Box
Figure 4 - Tank Overflow Handling System with Improved Double Horizontal P-Traps Without a Water Seal
Box
Figure 5 - Sample Option of Design Alternative 1 with Improved Horizontal P-Trap Pipe Spool and Existing
Water Seal Box
Figure 6 - Four Other Sample Options of Design Alternative 1 with Improved Horizontal P-trap Pipe Spool
and Existing Water Seal Box
Figure 7 - Wash Tank Overflow Handling System; (a) Original System Before Repair, (b) Improved System
After Repair Using Design Alternative 1
Figure 8 - Sample Option of Design Alternative 2 with Improved Double Horizontal P-Traps Without a Water
Seal Box
Figure 9 - Four Other Sample Options of Design Alternative 2 with Improved Double Horizontal P-Traps
Without a Water Seal Box
Figure 10 - Clarifier Tank Overflow Handling System; (a) Original System Before Repair, (b) Improved
System After Repair Using Design Alternative 2