Technical Operation and Engineering Department

First Bay
POWER CORPORATION DAILY ACTIVITIES
Date: August 01, 2022
Technical Operations
I. Meter Readers (7:00am -5:00pm)
Work Description Location Remarks
Meter Reading Cupang 401 / 402, Sinala 202, Magalang-galang, San Pedro, Sampaguita completed
Statement of Account
Malindig completed
(SOA Deliveries)
 
II. Line Crew (8:00am - 5:00pm)
Crew A, B & C
(7 manpower and 2 Work Description Work Order No. Location Remarks
casual)
Work Order: Interconnection of
Substation 1 and Substation 2 (section 1 - Balayong-Manghinao
    on-going
from Balayong to Manghinao Bridge) for Proper
Feeder 2
1. Cable pulling of new span 3 wire #4/0
       
PACSR primary lines.
Crew D (2 manpower) Dispatch Customers Name Location Remarks
Blk 29 Lot 8 Lynville
    1. New Connection Hernandez, Nora Alcayde
Residences, As-is
completed
Dela Cruz, Charle Magne
    2. Temporary Connection Karlo Aranas
Grand Villa, Balayong completed
    3. Reconnection Evangeline Ilao Cupang completed
    Routinary Activity:        
Inspection of substation and recording of Substation (Taño Rd,
       
operational data. Manghinao Proper)
             
Regular OT - 3 manpower
Routinary Activity:        
(5pm - 10pm)
Inspection of substation and recording of Substation (Taño Rd,
       
operational data. Manghinao Proper)
Crew D (2 manpower)
Routinary Activity:        
10:00pm - 8:00am
Inspection of substation and recording of Substation (Taño Rd,
       
operational data. Manghinao Proper)

TOTAL NO. OF REPLACED KWH METER:


Today To Date
0 17,725
TOTAL CUSTOMER TO DATE:
New Connection
A. Residential   B. Commercial  
Total
Today To Date Today To Date
2 8,879 0 1,289 9,872
Total Consumer 23,901 Total Consumer 2,263 25,872