Professional Documents
Culture Documents
Chapter
116
The Scottish Office, Edinburgh, UK
four-storey building (overall footprint ~50×250m) is of Architecture during Robert Matthew’s tenure as Head,
penetrated by a series of covered atria and open had joined the firm in the mid-1960s following a couple
courtyards along its length. It is workplace to nearly of years working with Doxiadis in Greece. He was quite
1500 civil servants from Scottish Office Departments clear that the National Farmers Union Building was ‘the
such as Education and Industry, Development, and model for Victoria Quay’ (Duncan, 1998), in terms, for
Agriculture Environment and Fisheries. example, of its energy strategy, even though there were
significant differences between the clients involved and
The designers the environmental technologies employed. Leading the
design for these technologies was engineer Drew Elliot,
The principal design services (architecture, mechanical and who had worked with several major Edinburgh-based
electrical engineering, structural and civil engineering) for consulting engineers before arriving at RMJM’s
the new building were provided by the Edinburgh office of multidisciplinary office in 1975.
RMJM Scotland Ltd. Formed in 1956 as an architectural Specialist consulting on the thermal performance of the
practice, with offices in Edinburgh and London, it had de- building was provided by ABACUS Simulations Ltd of the
veloped into a multidisciplinary practice by the early 1970s. University of Strathclyde’s Department of Architecture and
One of the firm’s earliest major projects, of particular in- Building Science.
terest to this writer was, of course, New Zealand House
in London, completed in 1963.
Project background and the design
Over the years, according to one previous chairman of
process
the Edinburgh office (Richards, 1996), four main threads
have run through the firm’s output.These include an inter- The poor condition of its main accommodation in New St
est in the entire process of planning and construction, and Andrew’s House, Edinburgh—with its sealed façade,
a significant involvement in work outside the UK; but more airconditioning and widespread use of asbestos—and the
importantly from the point of view of this book, ‘a search projected high cost of refurbishing, provided the catalyst
for architectural order, that is to say systematic and inte- for The Scottish Office to seek a new building for its fu-
grated qualities in their [buildings] appearance’, and ‘an ture needs. Following an appraisal of options that involved
emphasis on green technology’. These latter are well ex- a developer-led competition, the proposal by developer
emplified by such projects as the Hereford and Worcester Victoria Quay Ltd for a RMJM-designed building on a
County Council Headquarters (1979) and the National brownfield dockside site in nearby Leith won the day from
Farmers Union Mutual and Avon Insurance Group Head- an eventual shortlist of five.
quarters (1984) as well as The Scottish Office and the later This move enabled The Scottish Office to give up the
Glaxo-Wellcome Headquarters (1997) (see Chapter 16). lease of three Edinburgh city centre buildings, thus making
None of the Edinburgh design team had been involved some useful running cost savings, and there was a reason-
in these earlier projects south of the border, but as long- able expectation that the new building, which was not to
serving members of the practice they were well steeped be air-conditioned, would produce energy cost savings.
in the RMJM ethos—part of which it promotes by state- Located at the highish latitude of 56°N, and with 1% de-
ments such as ‘Energy efficiency and sustainable design sign temperatures of around –4 and 20.4°C (ASHRAE,
for a high quality of internal environment is achieved, not 1997:26.50–1) though 24°C was used for design purposes
by spending more on energy and equipment but by engi- (Jones and Field, 1996), natural ventilation might reason-
neering the building itself to produce comfortable ably be expected to be satisfactory. Nevertheless, the de-
conditions for the user’ (RMJM, 1998). Architect Mick veloper, ever mindful of future sub-divisions or changes in
Duncan, a graduate of the Edinburgh University School lessee, specified that the building design be sufficiently
117
The Architectural Expression of Environmental Control Systems
flexible for comfort cooling to be added at a later date if comfort air-conditioning, but revised that view when it
required. became clear that the tenant did not want this in general
The overall objective was ‘to create a building that was office space and after reviewing the design and operation
energy efficient and avoided the use of airconditioning of the National Farmers Union building. However, the
wherever possible—concentrating instead on using natu- developer wanted the building to be capable of being
ral lighting and ventilation, the use of thermal mass for air-conditioned too, so it was necessary to ensure that
free cooling, mixed-mode ventilation to optimise summer adequate plant space and distribution routes were in-
and winter climate conditions, and a building envelope corporated in the design. This was accomplished by
which optimises on insulation but controls solar heat gains’ having good-sized central plant rooms, well-organised
(Duncan, 1995).The project is also said to have taken ‘into vertical distribution routes, and a 450mm false floor, a
account embodied energy from component manufacture, depth judged adequate for accommodating chilled water
building assembly and maintenance for the first time’ pipe runs and fan coil units (say) if required at a later
(Knevitt, 1997:34). date.
With all the key personnel in this multidisciplinary ABACUS Simulation’s task was ‘to establish the opti-
practice housed under the same roof, one might expect mum configuration of courtyard [atrium] to minimise en-
an integrated approach to design to be readily achievable. ergy consumption and to ensure comfort conditions within
Mick Duncan (1998) is well aware that ‘What we should the offices’ (EDAS, 1995). Results indicated that ‘a central
ideally do, and we don’t always do it, is that we should atrium could achieve significant energy saving over the
set the architectural and engineering and environmental winter period and should not affect the natural ventila-
parameters before we even sit down…We should all be tion of the building during the summer. It was concluded
working hand in glove. But I think there is a chemistry that the building should adopt a mixed-mode ventilation
and a personality thing there that may prevent it system to allow benefit from seasonal variations of cli-
sometimes’. Personality differences or not, the practice mate’. The simulations also ‘indicated a need to replace
makes strenuous efforts to facilitate good communication the proposed light-weight roof with a concrete structure’
between the design team members. According to Elliot (Jones and Field, 1996:16) and this was done. Even then,
(1998), ‘the intention [now fulfilled] with the design for the desire to have the structural slabs and beams exposed
the forthcoming Scottish Parliament Building project is to make use of their thermal mass could have been
to knock down the wall of my office and turn it and the thwarted by the developer’s wish to have a suspended
adjacent space into a combined architectural and ceiling—the solution was to ‘float’ ceiling panels between
engineering design studio’. the downstand ribs of the precast concrete floor units.
Duncan, influenced partly by the results of research This satisfied both requirements and had the additional
on built form emanating from the University of function of covering extract ducts and other services (Elliot,
Cambridge’s Martin Centre and partly by the design of 1995).
the National Farmers Union building, came up with the
concept of a low-rise (ideally four floors), high ground Design outcome and thermal
coverage, block, with ‘holes carved into the plans…It had environmental control systems
to be a flexible building—it had to be divisible into parts—
it had to be capable of being cellular or open as required The architect describes The Scottish Office thus:
by the occupant’.
Elliot’s involvement in the project started long before The building is classically ordered both in plan and
it became clear that The Scottish Office would tenant section [Figures 9.2 and 9.3]. A simple ladder plan
the building—he had assumed then that it would require accommodates three linked departmental blocks on
118
The Scottish Office, Edinburgh, UK
four floors, each focused round an atrium.This facili- pavilions which overlook roof terraces. Major ele-
tates close departmental working, with individual ments of plant are housed in [six] rooftop plant
identities clearly linked within the framework of a rooms. (Duncan, 1995)
single homogeneous building.The atrium in the cen-
tral block is punctuated by the entrance rotunda ris- Having determined to use a mixed-mode environmental
ing above the rest of the building. On the south façade control strategy to achieve low-energy operating costs,
[the long axis of the building runs east-west], a two- the minimum wintertime internal design temperature was
storey colonnade runs along the entire length of the set at 18.5°C, while for summertime it was predicted
building [Figure 9.4], joining the three blocks and that the inside temperature should not exceed 26°C for
providing a covered pedestrian route…First and sec- more than 105h year–1—a range of 20–24°C was speci-
ond floors provide 7800m2 of office space each, while fied for those spaces such as meeting rooms, restaurants
the third floor is designed as a series of linked glazed and computer rooms, which were equipped with full
119
The Architectural Expression of Environmental Control Systems
air-conditioning (Jones and Field, 1996:18). The installed high-level glazing—ventilation is by means of the exhaust
heating and cooling capacities are 4600 and 275kW re- air (natural and mechanical) from the surrounding offices
spectively. (Figure 9.6). In the summer, natural stack ventilation is
The mechanical ventilation system for the office areas achieved by means of low-level inlets connected to an
has a total capacity of 51m3 s–1, equivalent to two air adjacent courtyard (Plate 14) and high-level louvred open-
changes per hour, at normal fan speed, but can be in- ings at the top of the atria (Plate 15)—both inlet and
creased to 4.5 air changes for night-time cooling of the outlet systems have manually controlled motorised
building during the summer.There are 12 air-handling units dampers.
(AHUs), two in each of the six rooftop plant rooms Natural cross-ventilation of the 15m-wide office spaces
(Figures 9.2 and 9.5). Four AHUs serve each of the three is by means of conventional window openings, high-level
main blocks. These supply their air, via the underfloor hoppers on both the exterior and interior (atrium or
plenum system, to displacement outlets in the raised courtyard) façades, plus tilt-and-turn lower windows on
floors. Extract is via openings above the ‘floating’ false the exterior, all manually operated (Figure 9.7).
ceiling panels, the air being ducted out through the plenum The location of thermal mass has already been noted.
space of the floor above. The air is then recirculated or Thermal insulation of the building fabric is to a high
exhausted according to the dictates of the CO detectors, standard, with wall and roof R=~3.6 and 4.8m2.°CW–1
2
or discharged into the atriums or directly to outside respectively. Windows are generally triple-glazed, other
(Figure 9.6), as appropriate. Radiators are under the than the atrium roofs and walls which are double-glazed.
perimeter glazing. In conjunction with the thermal mass Solar heat gain to the lower two floors of the south
of the building, the ventilation system is designed to allow façade is limited by the use of the colonnade, together
secure night-time cooling. with vertical perforated shading devices (Figure 9.7).
For winter conditions, the atria are fitted with heating The two upper floors are equipped with horizontal
coils under the floor and finned heating pipes below the external louvres designed to limit this source of heat gain
120
The Scottish Office, Edinburgh, UK
121
The Architectural Expression of Environmental Control Systems
122
The Scottish Office, Edinburgh, UK
ventilation air supply points are very much in evidence thermostatic valves within comfortable reach of the oc-
(Figure 9.9), by contrast with the air-extract points hidden cupants.
above the ceiling panels. No attempt has been made to The solar shading on the south façade finds expression
disguise the perimeter radiators below the window sills, in several ways (Figure 9.6). The top of the colonnade, for
which are clearly visible inside the offices, or even from example, provides a continuous horizontal band shading
the exterior where the glazing is taken down to the floor the first floor, while the ground floor glazing is protected
(Plate 14), although these are column radiators with their by vertical perforated panels fixed proud of the surface
123
The Architectural Expression of Environmental Control Systems
124
The Scottish Office, Edinburgh, UK
125
The Architectural Expression of Environmental Control Systems
ceilings’ (Field, 1995:34) (Figures 9.8 and 9.9). Neverthe- are the same size, actually the experience in the atrium
less, the building has won several awards, including the 1996 and the courtyard is quite different. Although they have
AHS Emstar Energy Conservation Award, the 1996 Hydro exactly the same dimensions, the courtyard is somewhere
Electric Building Services Award, a couple of Urban where you want to be in a private world. The atrium is a
Regeneration/Renewal Awards and the 1996 RIAS social space and with rooms around it is a bit like a big
Regeneration Design Award, not to mention a ‘very good’ theatre’.
BREEAM rating. Elliot (1998) had concerns about the ability of the plant
With the benefit of hindsight, there are always design rooms to cope with future changes. Despite the apparent
details that the architect and engineer of any project would generosity of their size and number, those towards the
like to refine further in the light of experience in use. east end of the building where some of the specialist fa-
However, Duncan (1998) did not think that ‘we would cilities were clustered, were becoming very tight for space.
want to change anything fundamental if we were approach- He was aware that initially some adjustment had been
ing it now [i.e. three years after first occupancy]. I think needed in the placement of staff in the open plan layout to
we would still want to organise the building in the same ensure that those with a preference for fresh air were
way. I think the logic of it is fine and it has proved to be an nearer the windows than those who perceived such a situ-
enjoyable building… it seems airy and warm and all of ation as potentially drafty. He was also firmly of the opin-
that—pleasant to be in. Obviously, there are going to be ion that it was preferable to leave decisions about open-
details that one would want to refine and perfect…but ing the windows for the occupants to agree rather than
architects rarely have that opportunity because each having them controlled remotely.
project is new’. Asked about the incorporation of both At the detail level, he suggested that it would have been
enclosed atria and open courtyards, he responded, ‘I don’t climatically preferable for the atria supply air to come
think we would want to change that.Although in plan they from the shaded north side of the building rather than
126
The Scottish Office, Edinburgh, UK
the adjacent courtyard but, of course, that would have connection with the project, and who gave me such useful
had security implications in this case. With the advantage insights into the process and the outcome.
of hindsight, I have the sense that if 4.5 air changes were
rarely needed in the climate of Stratford (for the National References
Farmers Union building) then the chances of this rate of
ASHRAE (1997) ASHRAE Handbook: Fundamentals, SI Edition, Atlanta:
ventilation being needed to cope with an Edinburgh sum- ASHRAE.
mer were probably fairly remote—expectations of higher Duncan, M. (1995) ‘Architect’s account—a landmark for Leith’, Archi-
internal heat gains and global warming notwithstanding. tects’ Journal, 7:30.
——(1998) Transcript of an interview held on 20 August, Edinburgh.
EDAS (1995) ‘Victoria Quay, Edinburgh’. Case Study 13, Energy Design
Acknowledgements Advice Scheme, 6/95, Edinburgh.
Elliot, A. (1995) ‘Services engineer’s account—a landmark for Leith’,
My thanks to architect Mick Duncan for the generous Architects’ Journal, 7:32.
——(1998) Transcript of an interview held on 20 August, Edinburgh.
amount of time he took to show me around the building, Field, M. (1995) ‘Appraisal—a landmark for Leith’, Architects’ Journal, 7: 33–4
and to Building Manager Bob Collins, who accompanied Jones, D.L. and Field, J. (1996) ‘Civil services’, Building Services, 18: 14–8.
us during the visit and explained some operational mat- Knevitt, C. (1997) ‘The RMJM method’, Architects’ Journal, 12 June: 32–4.
Richards, J. (1996) ‘Themes and variations’, in RMJM 40: The First Forty
ters. In addition, I am grateful to Mick and Drew Elliot, Years, London, RMJM.
both of whom I interviewed at RMJM’s Bells Brae office in RMJM (1998) Multi-disciplinary Design [flyer], London: RMJM.
127