Professional Documents
Culture Documents
Abstract— FACTS technologies can have major positive Non-traditional enhancements are needed to accomplish the
impacts on power system reliability performance and the actual following conflicting objectives: (1) Provide additional
benefits obtained can be assessed using suitable models and transmission infeed capacity to distribution substations, (2)
practice. Emerging techniques for composite power system Not to add capacity which will raise the existing fault current
reliability evaluation mainly focus on conventional generation levels. Normally, the addition of transmission lines to a
and transmission facilities. In this paper, improvement of
substation will lower the infeed impedance and raise the fault
Reliability in composite electric power system is examined by
incorporating Unified Power Flow Controller (UPFC). Two test current levels.
systems, Reliability Test System (RTS) and Roy Billinton Test In this paper, the impact of UPFC on composite electric
System (RBTS) are considered to show major improvement in power system reliability is examined. UPFCs are employed in a
reliability. A state space reliability model of multi-module UPFC system to adjust the transmission infeed impedances and
has been developed and incorporated in the system. Load point &
therefore, increase the transmission system capacity without
System indices performances are presented to examine the
increasing the system fault current levels. Load point & system
impact of UPFC on the composite electric power system
reliability. Investigation results show a significant improvement
indices performances are presented to examine the impact of
in the Load point & system indices when utilizing UPFC. UPFC on the two test systems via 24 bus IEEE RTS and 6 bus
RBTS.
Keywords- Unified Power Flow Controller (UPFC), Load Point
Indices, System Indices, Composite Power System Reliability. II. UNIFIED POWER FLOW CONTROLLERS
A UPFC consists of two switching converters where each
I. INTRODUCTION converter is a voltage source inverter using gate turn off
System
IV. RELIABILITY INDICES RBTS RTS
Indices
Load Point Indices: BPSD 19.71 817.62
The following are the expressions [4] to determine the load BPII 0.367 2.72
point indices of the given system BPECI 331.16 2211.6
Probability of Failure = ∑ P j Pkj System Indices (SI) of 6 bus RBTS and 24 bus RTS are
j
determined for different modules (Mo) of UPFC are shown in
Frequency of Failure = ∑ Fj Pkj
j
Table 3.
Expected Load Curtailed = ∑ L kj Fj (MW ) Table 3: Comparison of System Indices of 6 bus RBTS and 24
j
bus RTS with different modules of UPFC
Expected Energy Not Supplied (EENS)
= ∑ L kj P j ∗ 8760(MWh ) SI BPSD BPII BPECI
j
Mo RBTS RTS RBTS RTS RBTS RTS
Where:
2 19.69 817.49 0.3642 2.673 331.14 2211.14
j is an outage condition in the network
Pj is the state probability of the outage event j 3 19.58 817.41 0.363 2.655 331.11 2211.02
Fj is frequency of occurrence of the outage event j 4 19.47 817.32 0.3622 2.641 331.08 2210.94
Pkj is the probability of load curtailment at bus k 5 19.39 817.25 0.3612 2.647 331.04 2210.92
during outage event j 6 19.31 817.13 0.361 2.651 330.91 2210.89
Lkj is the load curtailment at bus k during outage
7 19.26 817.11 0.359 2.562 330.69 2210.82
event j
Dkj is the duration in hours of load curtailment at bus 8 19.38 817.26 0.364 2.648 331.01 2210.91
k during outage event j. The probability of failure & EENS of the original 6 bus
RBTS is shown in Table 4 & compared with different modules
System Indices:
of UPFC is shown in Table 5 & Table 6.
Bulk Power Supply Disturbances (BPSD) = ∑ ∑ Fj
k j Table 4: Probability of Failure & EENS of 6 bus RBTS
Bulk Power Interruption Index (BPII)
Bus Probability of
∑ ∑ L kj Fj EENS
=
k j
(MW / MW − Year) No. Failure
Ls 1 0.0081547 124.64
Bulk Power Energy Curtailment Index (BPECI) (Severity 2 0.0082665 88.082
Index)
3 0.0083131 377.731
∑ ∑ 60 ∗ L kj D kj Fj 4 0.0083139 177.28
k j
= (system min)
Ls 5 0.0083145 88.86
where Ls is the total system load 6 0.0094512 288.36
Table 5: Probability of Failure for 6 bus RBTS vs Number of The reliability indices increase, as the generation capacity
Modules of UPFC and load demand increase, and the transmission system
Mo Bus No. becomes more heavily utilized. The study examines the impact
No. 1 2 3 4 5 6 of the location of UPFC device in 6 bus RBTS [4]. UPFCs
2 0.00823 0.00836 0.00814 0.00813 0.00814 0.0087 were applied to transmission lines 1 and 6 in the modified
RBTS i.e., generation capacity and load demand are at 150%
3 0.00821 0.00834 0.00816 0.00816 0.00817 0.0088
base values. The UPFC capacity was varied from 100MW to
4 0.00819 0.00833 0.00824 0.00824 0.00825 0.0089 180MW and compared with system indices which is shown in
5 0.00817 0.00831 0.00828 0.00827 0.00828 0.0090 Table 8
6 0.00815 0.00829 0.00830 0.00830 0.00830 0.0092 Table 8: System Indices for Modified 6 bus RBTS
7 0.00815 0.00826 0.00831 0.00831 0.00831 0.0094 UPFC Severity
BPSD BPII
8 0.00816 0.00829 0.00830 0.00830 0.00830 0.0091 Capacity Index
100 36.79 0.462 377.18
Table 6: Probability of EENS (MWh) for 6 bus RBTS vs
120 23.81 0.385 338.79
Number of Modules of UPFC
140 23.81 0.380 337.34
Mo Bus No.
No. 1 2 3 4 5 6 160 23.80 0.375 335.91
2 126.21 89.21 377.86 178.38 90.68 290.34 180 23.54 0.371 334.72
3 125.94 88.81 377.35 177.97 90.31 289.97 It can be observed from Table 8 & Figs. 7, 8 & 9 that the
incremental benefit in the system severity index with UPFC
4 125.54 88.39 376.94 177.69 89.81 289.34
device investment becomes relatively small after a certain
5 125.12 88.12 376.61 177.26 89.42 288.94 point
6 124.65 87.88 376.21 176.94 88.93 288.56
7 123.97 87.68 375.92 176.54 88.49 287.99
8 124.21 87.91 376.14 176.85 88.81 288.31
System Indices via BPSD, BPII, and Severity Index of 6
bus RBTS are compared with Generation Capacity & Load
Demand without using UPFC in Table 7 and with using 7
Module UPFC in Table 8.
Generation Load
Severity
Capacity Demand BPSD BPII
Index
(MW) (MW)
240 185 19.834 0.364 329.642
270 203.5 19.897 0.372 331.246 Fig. 7: BPSD vs UPFC device capacity for Modified 6 bus
300 222 20.653 0.379 333.201 RBTS
330 240.5 21.842 0.389 336.721
345 259 34.197 0.465 371.264
360 277.5 78.673 0.913 615.259