Professional Documents
Culture Documents
BEFORE
Sri R.Rajamani,
Ex- Commissionerof Railway Safety,
Flat No. 3, Ram Priya AE – 172,
11th Main Road, Ana Nagar,
Chennai – 600040.
………….Presiding Arbitrator
Sri S.R.Chaudhuri,
Retd. General Manager,
East Coast Railway,
EE-118, Flat No. 6,
Salt Lake City, Sector – II,
Kolkata – 700091.
……………………Arbitrator
AND
Project of KMRCL”
AND
BETWEEN
Kolkata – 700017.
…………..
Claimant
-VS-
~3~
…….Respond
ent
not only a resourceful contractor, but also possess all modern plants
~4~
nature.
length for each station on East-West Metro Project of KMRCL” from the
(Copy annexed and marked “C-1” at page no. 1 of volume no II) had
conditions but not all the conditions and called upon the Claimant to
work was Rs.53,09,23,842.00 (Rupees fifty three crore nine lac twenty
three thousand eight hundred and forty two only). In the letter of
for mobilization was allowed from the date of letter of acceptance before
no II).
three rows with one row along the central median of the road and
level slab and platform slab together with stair cases and other
mm;
Claimant. The Claimant once upon called upon the Respondent for
Respondent’s letter dated 14-08-2009 (C-7 colly). The said letter was
wherein the Claimant submitted the first revision of the Base Line
~9~
inputs from the Respondent. As such, the said revised Base Line
the Respondent vide its letter dated 24-08-2009 (C-7 colly) had stated
that the revised Base Line Programme shows the time for completion
more than twenty three months, when the time stipulated for
requested the Claimant to revise the programme, keeping the time limit
incorporating in the Base Line Schedule. Since both the parties were in
approved GAD and AFC drawings for working piles relating to all the
three station locations so that the Claimant could submit the said work
~ 10 ~
detail work programme against the said contract only upon receipt of
approved GAD and AFC drawings for working piles for all the three
Claimant however submitted the said three month work programme for
the other package i.e. EWS-2 (R) since AFC drawings for working piles
were partially available for the said project. The Claimant submitted
the second revision of Base Line Programme with its letter dated 09-02-
2010.
part of the Respondent and the work was completed in all respects by
appear from the said completion certificate that extension of time was
damages.
plant and other activities. The Claimant had offered rebate for
allot land at Salt Lake as per the agreed terms of the contract.
both the parties herein and upon such visit the Claimant was
b) Block – HC, Sector – III, Salt Lake, beside ‘Police Abasan’ &
Institute of Homeopathy.
c) Block – GE, Sector – III, Salt Lake, near Girl’s Hostel & Water
iii) The Claimant vide letter dated 12-06-2009 (Copy annexed and
time. This in turn spells out that the Claimant had to remobilize
almost in the midst of the project and this has grossly affected
Respondent.
that GTS bench mark, temporary bench marks and three control
given to the Contractor at the start of the project. The Base Line
stipulate under ‘Activity ID No. 12’ that the survey station points
and follow ups, the Claimant could get the control points only on
Clause no. 4.11 of GCC supplemented with Sl. No. 2 of SCC clearly
receive the AFC drawings for test pile(s) by 10th June 2009. However,
the same was issued by the Respondent only on 14th September 2009,
for Test Piles despite the Claimant’s repeated requests had delayed
volume no II).
station:-
~ 16 ~
after a delay of 198 days from the date of handing over of such
was also changed from 13.80m to 17.10m and due to the same
diversion work at the said station location and also delayed the
2010.
iv) It is further submitted that the Claimant was issued the drawings
February 2010 and the Claimant had commenced the piling work
volume no II).
~ 18 ~
Sector V station:
ii) Similarly, as per the base line programme, pile cap drawing for
iii)As per the base line programme (C-7) pile cap drawings
but the same were handed over to the Claimant as late as on 29-
of volume no II)
ii) Similarly, as per the base line programme, the Respondent was
of volume no II)
the AFC drawings for Pier Caps pertaining to Central Park station
13th July 2009. However, Pier Cap drawings were issued only on
~ 21 ~
10th June 2010, i.e. after a delay of 332 days from the baseline
2nd stage casting of hammer head after casting of 1 st stage, till the
the 1st stage casting of the common pier cap at P130 (i.e. K2 pier)
II).
~ 22 ~
but the same were made over to the Claimant on 04-05-2010 i.e.
Karunamoyee station:
Claimant could not have proceed with the sub structure (Pile
October, 2010. However, the AFC drawing for cut-out details were
control and fire control wiring etc., were also issued to the
Claimant on 3rd October, 2010 and the same in turn had delayed
~ 24 ~
casting of stage-1 of track slab for the Central Park station. Even
at this stage the Claimant was kept waiting for AFC drawing(s) for
playground area and the same called for a fresh round of review
further delay and for the best interest of the project from Grid No.
of volume no II)
programme.
~ 26 ~
19,750 RM. Hence the scope for piling works was increased by
per the received AFC drawings, 137 nos piles, 22 nos pile caps
Moreover, the length and width of the concourse area was also
Quantity
Revised
Sl. Item Stipulated in
Station Quantity % Variation
No. Description the BoQ
(RM.)
(RM.)
Provision for
further increase in
scope of work for
4 Piling 1795.38
construction of
entry structures at
various stations.
* Considering BoQ quantity for each Station = Total BoQ Quantity/3 = 10,500 RM./3 = 3500.000 RM.
~ 29 ~
GCC the Respondent was obliged to acquire and provide land for
fronts inside Sech Bhavan and Bikash Bhavan (for Grid No. 1 &
2) } to the Claimant.
Claimant.
iv) The Claimant had completed installation of all 129 nos. piles on
volume no II).
piling work on Grid No. 1 & 2 (inside the Bikash Bhavan premises):-
The Claimant had installed 20 nos. piles on Grid No. 1 & 2, which
depot side could be resumed only on 20th September, 2010 upon grant
station:
piles on Grid No. 3 was made available to the Claimant only upon
authority from onwards 25th May, 2010. In this regard the Claimant
~ 32 ~
available piles the Claimant could install only 11 nos. piles owing to
balance 11 nos. piles on Karunamoyee bus depot side had not been
correspondences:-
of volume no II).
~ 33 ~
4:
Grid No-4 from onwards 04-09-2010 for 6 nos. piles out of total
the 2nd piling rig was rendered idle at the said station location.
10-09-2010 and then only the 2nd rotary piling rig for pile boring
location..
volume no II).
filling work before the monsoon of Year 2010: As per tender stage
the E.D. canal and the Claimant had envisaged construction of those
pile caps adopting localized filling inside the canal. However, the
numbers of pile caps inside the canal were increased to 22 nos. i.e. by
3.67 times than the tender stage consideration. In addition to this, the
individual pile cap sizes also got increased with minimum number of
piles in any singular group being four and the largest group is having
caps and piers inside the E.D. Canal at the proposed Sector-V station
location called for filling of entire width of E.D canal for an approximate
NP3 pipes for the said length to maintain dry weather canal water flow.
~ 35 ~
Upon completion of entire piling works falling under Grid 1 & 2 inside
inside the E.D. canal in view of the ensuing monsoon of Year 2010.
Accordingly, the Claimant had reinstated the canal before the onset of
monsoon. Nonetheless, to construct the pile caps and piers inside the
once again fill up the canal post monsoon to commence the sheet piling
work and also reinstate the canal once again upon completion of work.
In view of the above, repeated filling and excavation work inside the
execution phase at the said station location, delayed the work in its
entirety.
correspondences:-
05.10.2010.
~ 36 ~
volume no II).
volume no II).
concourse area:
area {i.e. from 2627 sq.m to 5845 sq.m(122%)} as per the AFC
rig and allied machinery and man power deployed at such location.
Such embargo delayed the completion of the work in its entirety. In this
~ 38 ~
Claimant, request was made to inter alia to stop the work due to
requested to stop the work due to the ensuing Durga Puja festival
2010 to 20-10-2010.
~ 39 ~
Claimant vide letter dated 18.05.10 (copy annexed and marked “C-
25” at page no. 234 of volume no III) had intimated the Respondent
that the work had come to a standstill since 14 th May 2010 due to
The matter was also brought to the knowledge of MD, KMRCL during
works from 14th May 2010 to 05th June 2010. The Claimant once again
235 of volume no III) had inter alia stated that due to non-handing
work in such crisis period. Such letter was followed by Claimant’s letter
heads, liquid waste etc. to the Claimant. Due to the failure on the
volume no III)
etc.
10. That owing to the delays and defaults on the part of the
programme (C-7)
Station
station
11. The Claimant had applied for the second extension of time vide
grounds:-
front;
d) Non-release of payments;
f) Miscellaneous stoppages.
~ 44 ~
13. The Claimant had applied for the third and final extension of
14. The Respondent vide letter dated 14-05-2012 (C-33 colly) had
grounds based on which the extensions of time were prayed for by the
~ 45 ~
volume no III)
Board of Directors;
~ 46 ~
Managing Director;
Managing Director.
volume no III)
31-05-2012.
time were necessitated for the delays and defaults on the part of the
compilation hereunder:-
~ 47 ~
01st 1. Delay in handing 1. Central Park 03 (three) months 1. Clause 2.6 of the Notice
interim over of area for station – 617 days. i.e. up to Inviting Tender, Part –I,
EOT Claimant’s Depot. 22.04.2011 Volume 1 of the Contract
2. Delay in handing Document, regarding
over of survey control 2. Karunamoyee (01st interim EOT) Construction Depot.
points. Station - 540 days. 2. Sl. No. 8 of Special
3. Delay in issuance conditions of Contract (SCC)
of AFC drawings for adding supplement to General
Test Pile (initial pile 3. Salt Lake Sector- Conditions of Contract (GCC)
load test). V Station - 772 sub clause 4.14 on setting out.
4. Delay in issuance days. 3. Sl. No. 2 of SCC
02nd of AFC drawing for 01 (one) month supplement to GCC sub Clause
interim working piles. i.e. up to no. 4.11 (specifications and
EOT 5. Increase in scope 22.05.2011 drawings).
of works. 4. Clause 10.7 of GCC.
6. Delay due to Non (02nd interim 5. Clause 2.1 (General
availability of working EOT) Obligations of Employer) of
front. GCC.
7. Delay due to non- 6. Clause 4.20 (Right of Way
availability of AFC & facilities) of GCC.
drawing for pile caps. 7. Clause 10.3.2 of GCC.
03rd Up to 30.09.2011
8. Delay due to non- 8. Clause 10.3.3 of General
interim availability of AFC Conditions of Contract
EOT drawing for piers. (03rd interim 9. Clause 2.2 of General
9. Delay due to non- EOT) Condition of Contract.
availability of AFC 10. Clause 4.19 of General
drawings for Pier Caps. Condition of Contract.
10. Delay in issuance 11. Clause 10.6 of General
of AFC Drawings for Conditions of Contract
Superstructure 12. Clause 12.1 of General
components. Conditions of Contract
11. Miscellaneous 13. Clause 12.2 of General
01st Up to 31.12.2011
stoppages. Conditions of Contract
formal
EOT (01st formal EOT)
02nd 1. Delay due to non- 1. Central Park Up to 30.04.2012 1. Clause 2.2 of General
formal availability of final station – Condition of Contract
EOT AFC drawing for entry/ 31.03.2012. 2. Clause 4.19 of General
exit structures. Condition of Contract
2. Delay due to non- 3. Clause 4.20 of General
availability of final 2. Karunamoyee Condition of Contract
AFC drawing for Station – 4. Clause 10.3.2 of General
ancillary structures. 30.04.2012. Condition of Contract
3. Delay due to Non 5. Clause 10.3.3 of General
availability of Conditions of Contract
encroachment/ 3. Salt Lake 6. Clause 10.6 of General
~ 48 ~
Final 1. Delayed instruction for 31 days for the Up to 31.05.2012 1. Clause 10.6 of General
EOT construction of ASS/ entire work Conditions of Contract.
TSS building at Central 2. Clause 10.7 of General
Park station after Conditions of Contract:
demobilization of Extension of Time for
resources from site. Completion not on Contractor’s
2. Delay in handing over fault.
of AFC drawing for 3. Clause 12.1 of General
ASS/ TSS building at Conditions of Contract:
Central Park station. Authority to order.
4. Clause 12.2 of General
Conditions of Contract.
5. Clause 4.19 of General
Condition of Contract.
pages) and called upon the Respondent for payment of the amounts
18. The Respondent vide its letter dated 29-06-2013 (Copy annexed
and marked “C-35” at page no. 279 of volume no III) had disputed
annexed and marked “C-36” at page no. 282 of volume no III). The
conciliation.
19. That the Claimant vide letter dated 24-02-2014 (Copy annexed
and marked “C-37 ” at page no. 287 of volume no III) had submitted
the analysis break up for updated claims to the Conciliator. Finally, the
and marked “C-38” at page no. 345 of volume no III) had confirmed
Summary of applications
Sl. No. Description Claim amount Detailed
(Rs.) Calculation
1 Uncharted overhead cost on a/c of 77,848,210 Exhibit-I
over stay at site resulting due to (modified claim
reasons not attributable to the amt =
Contractor 2,68,65,417/-
2 Interest charges on delayed 31,776,172 Exhibit-II/1/R
payment against various withheld (modified claim
and outstanding amount as of 15th amt =
January'2014. 34,577,135)
3 Additional cost incurred, on a/c of 11,687,077 Exhibit-III
idling and/ or gross underutilization
of piling setup
4 Uncharted overhead cost incurred 2,187,899 Exhibit-IV
on a/c of frequent shifting of piling
setup due to reasons not
attributable to the Contractor
5 Additional mobilization of shuttering 9,533,654 Exhibit-V
and staging material due to change
in sequence of work
6 Extra cost incurred on account of 3,029,819 Exhibit-VI
maintenance & handling of
barricading boards beyond the
original completion period
7 Extra cost incurred towards 8,802,226 Exhibit-VII
fabrication, driving & retrieval of
additionally mobilized sheet pile
materials to facilitate construction of
pile caps inside the E.D. Canal at
Sector-V station
8 Extra cost incurred due to lesser 279,434 Exhibit-VIII
number of repetition of pier shutter
7,78,48,210.00
02-2014 (C-37) before the Conciliator. It shall appear from page 295 of
volume III that the computation has been made for both the packages
i.e. EWS – 1 (R) and EWS – 2 (R) and the Claimant had claimed for this
~ 52 ~
value of work done under the package with respect to total value of
work done for both the packages during the extended stay. The
value of work done in the extended period. The Claimant could realize
set off from the amount claimed earlier and the modified / reduced
2,68,65,417/-.
~ 53 ~
(in short ‘LOA’) dated 23-05-2009 (C-4). Accordingly, the Claimant had
from the date of issuance of the LOA. The Claimant had specifically
the works, that the said baseline program was adversely affected and
impact of the change in the agreed fact situation for turn of events
from time to time. Many of these delay events & circumstances were
documents
21.1.6 The Claimant respectfully prays that the Learned A.T. may
sixty eight lac sixty five thousand four hundred and seventeen only) as
January, 2014 and the said calculation is updated for claiming interest
till 10th December, 2015 and the updated claim amount is Rs.
and marked C-39 at page no. 346 of volume III). The Claimant
be made by the Respondent within 7 days and the balance 20% of the
certified value of work done shall be paid within 28 days from the date
escalation bills shall also be made within 28 days from the date of
21.2.4 Time and again the Claimant had put the Respondent on
volume III)
21.2.5 The Claimant had emphasized that without timely and regular
the Claimant should not be able to plough back its working capital for
Claimant should lose its creditability in the borrowing market and the
21.2.6 The delay in releasing the payment was primarily due to the long
against various technical issues, which were beyond the ambit of the
invariably been raised just 1-2 days prior to the stipulated date of
had made itself liable to pay interest to the Claimant and the Claimant
overhead cost owing to over stay at site for idle and underutilized
piling setup mobilized for the work consequent upon the delays and
delay days and movement of hydraulic piling rig is made for better
repeated occasions.
contemporaneous correspondence:-
volume III)
for pile(s) by 10th June, 2009 complying with the baseline programme.
However, AFC drawing for first initial load test pile was issued by the
first set of AFC drawing for working piles for Central Park on 31st
colly) and 29-10-2009 (C-14 colly), through which the Claimant had
recorded the initial duration of idling of piling set up for the non-
delay in issuance of AFC drawings for all the station locations and the
said AFC drawings were also issued to the Claimant in piece-meal basis
~ 62 ~
obstruction free piling front at various station locations, the piling set
up of the Claimant had remained idle at site for prolonged period and
the same was notified to the Respondent and its General Consultant
for idling of piling set up the Claimant had to resort to frequent shifting
idle for 172 available rig-days i.e. 5.73 available rig-months owing to
21.3.6 The Claimant respectfully prays that the Learned A.T. may
one crore sixteen lac eighty seven thousand and seventy seven only).
~ 63 ~
rigs one each at any of the two station locations and such rigs shall
start installation of working piles for two locations with effect from 09-
(being a line diagram depicting available working days, delay days and
~ 64 ~
21.4.1 The Claimant respectfully prays that the Learned A.T. may
one lac eighty seven thousand eight hundred and ninety nine only).
Rs.95,33,654.
95,33,654 (ninety five lac thirty three thousand six hundred and
encroachment free working areas had not been handed over as per the
situation arising out of the delays and defaults of the Respondent and
Claimant for all its losses and injuries. It is irrefutable that the
& April, 2012 and October, 2010 & August, 2011 respectively. From
perforce to incur additional cost which was not envisaged during tender
stage.
21.5.3 The Claimant respectfully prays that the Learned A.T. may
be pleased to award the said sum of Rs. 95,33,654 (ninety five lac thirty
period = Rs.30,29,819.
The Claimant craves to elaborate the said Exhibit VI during the course
of volume III). The Respondent did not dispute the factual positions
21.6.3 The Claimant respectfully prays that the Learned A.T. may
twenty six only) being the extra cost incurred towards fabrication,
Claimant craves to vividly explain the said Exhibit VII during the
construction of 6 nos. smaller sized pile caps over 6 Nos. Pile groups
with each of the groups comprising of 3-4 Nos. of piles, inside E.D.
131 piles with the largest group consisting of as many as 20 Nos. piles
inside E.D. canal area. This involved the works viz. casting, de-
Claimant had mobilized the said quantum of sheet pile materials with a
and make fit for requirement, the Claimant had to fabricate and drive
the sheet piles to facilitate construction of pile caps below canal bed
letters:-
a) dated 28-04-2011;
b) dated 03-05-2011;
c) dated 10-05-2011.
volume III)
22.7.7 The Claimant respectfully prays that the Learned A.T. may
2,79,434/- (Rupees two lac seventy nine thousand four hundred and
thirty four only) being the extra cost incurred owing to lesser number of
2014 (C-37). The Claimant craves to vividly explain the said Exhibit
maximum two types of circular piers for the subject work i.e. one type
for piers on central median and another type for piers on either side of
joint piers of diameters 1800 mm, 1600 mm, 1400 mm and 1000 mm.
nos. of uses prescribed as per Sl. No. 9.4 of preface of DSR, 2007
22.8.3 The Claimant respectfully prays that the Learned A.T. may
be pleased to award the said sum of Rs. 2,79,434/- (Rupees two lac
The Claimant craves to vividly explain the said Exhibit IX during the
yard for the work. It is submitted that cement was transported from
Km. Indian Railways had increased the railway freight w.e.f. 27th
Rs.814.40/Mt for the above rail distance. This rate was once again
page no. 481 of volume III) It may be appreciated that this increase
22.9.3 The Claimant respectfully prays that the Learned A.T. may
seventeen lac eighty five thousand one hundred and sixteen only).
94,395/- (Rupees ninety four thousand three hundred and ninety five
existing taxes and duties by the Government of India during the course
of execution of the work. Excise duty on ready mix concrete (RMC) was
01-03-2011.
volume III).
22.10.5 The Claimant respectfully prays that the Learned A.T. may
be pleased to award the said sum of Rs. 94,395/- (Rupees ninety four
part of the Respondent and the work was completed in all respects by
Government of West Bengal had introduced Entry Tax. Such tax was
applicable for almost all the construction materials at the relevant time.
the Claimant.
hereunder:-
“1. any new tax which is imposed after the due date of submission of
tender and which impacts the performance of the Contractor with
increased cost or which results in extra financial gains to the Contractor
due to decreased cost in execution of Works
2. Change in any law pertaining to work having the above said impact”
~ 78 ~
22.11.4 The Claimant respectfully prays that the Learned A.T. may
58,84,080.00
58,84,080.00 (Rupees fifty eight lac eighty four thousand and eighty
that “To the extent that full compensation for any rise or fall in costs to
~ 79 ~
the Contractor is not covered by the price variation formula, the rates in
by the terms of the contract, but in the event one of the parties to the
has a direct bearing on the work to be executed by the other party, the
party for the extra costs incurred by him as a result of failure of the
upon the delays and defaults on the part of the Respondent. The
learned A.T. may kindly appreciate that the instant contract had
should be compensated.
~ 80 ~
the Claimant had put the Respondent on notice that supply of coarse
from local suppliers at fancy price. While finalizing the price of the
tender for the said contract during the month of Mar-Apr.’2009, the
volume III)
22.12.6 The Claimant respectfully prays that the Learned A.T. may
(C-37 colly), the Claimant inter alia had brought to the notice of the
22.13.3 The Claimant respectfully prays that the Learned A.T. may
Rs. 4,24,73,904.00
thousand nine hundred and four only) for Loss of profit and unrecovered
The details for arriving at the claim amount are spelt out hereunder:-
basis----------(C=A/B)
turn over------(D=10% of C)
hindrance basis and accordingly had planned and mobilized all the
defaults on the part of the Respondent and the work was completed in
reasonable profit
not offer competitive price, since the Claimant structured its bid relying
tenders which were invited by RVNL vide notice dated 27-06-2011 for
works and copy of forwarding letter dated 17-08-2011 with which the
~ 86 ~
Claimant had submitted its tenders and those are collectively marked
accrued.
Learnned A.T. to the date of full realization of the said amount. The
Act, 1996.
conditions made part of the tender and subsequently made part of the
of which the said tender was invited and all other relevant documents
Claimant humbly prays before the Learned Arbitral Tribunal for the
following:-
graciously pleased to
and proper
And for this act of kindness, the Claimant, as in duty bound, shall ever
pray.
VERIFICATION
I, R.K. Bagri, s/o Shri Late Mohan Das Bagri, employee and
thereunder of the foregoing Statement of Claim are all true to the best
~ 90 ~
December, 2015.
_____________________
SIGNATURE