Sub-Contract Particulars Form

Enquiry Number : 11705


Enquiry Title : Metro West Phase 1B Highways and Bridges
Location : Portbury, Pill & Bristol
ELR : 9 Sites - see site location document for addresses
Chainage :
OS Grid reference :
VOP of Fixed Price : Fixed Price
Main Conditions of Contract : NEC4
Design - March 2024; Highways - April Duration of Main
Anticipated Start Date : 2025; Bridges July 2024
TBC
Contract :
Prices Required by : 17th of November 2023
Trade : Masonry Repairs

North Somerset Council requires a contractor to deliver the design and construction of works to upgrade highways
and bridges as part of the MetroWest Phase 1B project. The overall objective of MetroWest Phase 1B is to re-open
the Portishead rail line and provide an hourly service between Portishead and Bristol Temple Meads, with new
stations at Portishead and Pill. The Project will connect 50,000 residents to the rail network and forms part of a wider
MetroWest programme to deliver strategic enhancements to the local rail network. The highway and bridge works
comprise of two works packages –

Package 1 is the highways scope which includes detailed design and construction. It covers 5 sites – Winterstoke
Road, Bristol; Pill Memorial Club; Underbanks, Pill; Avon Road, Pill;Monmouth Road, Pill

Package 2 is the bridges scope which includes construction only. It covers 4 sites – Sheepway (Portbury Common);
Brief description of the works Old Station Road(Portbury Station); Royal Portbury Dock; Marsh Lane
required:
The successful bidder will be asked to enter into 3 separate contracts covering the two packages:

Delivery of Package 1 - Highway Scope is brought about through the deployment of a 2 Stage approach –

Stage 1 – NEC4 Professional Services Contract (June 2017) (including January 2023 amendments) main Option A
for completing the detailed design and ancillary services (the “Stage 1 PSC”)
Stage 2 – NEC4 Engineering Construction Contract (June 2017) (including January 2023 amendments) main Option
A for construction (the “Stage 2 ECC”).

Delivery of Package 2 - Bridges Scope will be delivered through an NEC4 Engineering Construction Contract (June
2017) (including January 2023 amendments) main Option A for construction.

Bill Pages : item :

Please refer to document Metro West Bridges - BoQ AMCO 23.10.23 for quantities

Invitation to Tender : 1. Sheepway Bridge - Removal of vegetation and ivy from bridge; extend masonry parapet wall to1.8m high; Rake Out and
repoint Arch; Remove loose material and replace on arch; Remove loose material and replace on wing walls/parapets; Rake out
and repoint wing walls/parapets/abutments;Mortar patch on Abutments; recasing wing walls; Pin and grout arch soffit

2. Portbury Station Overbridge - Removal of vegetation and ivy from bridge; extend masonry parapet wall to1.8m high; Rake
Out and repoint and stitch Arch; Remove loose material and replace on wing walls/parapets; Rake out and repoint wing
walls/parapets/abutments; Rake Out and repoint and stitch on Abutments; Pin and grout arch soffit

3. Marsh Lane Bridge - Removal of vegetation and ivy from bridge; extend masonry parapet wall to1.8m high; Rake Out and
repoint and stitch Arch; Remove loose material and replace on wing walls/parapets; Rake out and repoint wing
walls/parapets/abutments; Rake Out and repoint Abutments; Pin and grout arch soffit

Please advise on access requirements for each structure

Preambles : Working hours 07:30am - 18:00pm Weekdays. Saturday working permitted if required.
Rates to include all OH&P with Prelims priced separately
AMCO will provide all welfare and security
The Sub-contractor may insert additional items as he sees fit to assist in the preparation of his Tender.
The client for this project is North Somerset Council - the sub-contractor must adhere to their policies and procedures
For Technical Information – Meilir Williams – Meilir.williams@amcogiffen.co.uk – Mobile: 07823789107

Specification :

Drawings : See appendix 5 for all drawings


NR-CIV-SD-101B
CIVSD104_B
CIVSD105_B
Nr-CIV-SD-106B
CIVSD107_B
CIVSD116_B

Other : Metro West - Site Locations


Metro West Site Photos
Appendix 5 - ​Package 2 ECC Scope - Bridge Repair Works
Metro West Bridges - BoQ AMCO 23.10.23

Mandatory Enclosures: