You are on page 1of 4

PROCESS OWNER: Supervisor DEPARTMENT: Survey

TASK − To cut and create Seismic Lines as directed by


Surveyor

− Be conversant with Project Technical


Parameters and Environmental Guidelines.

− Ensure you have been trained in the use of


machete

− Implement safe handling and swinging of


machete to avoid cuts on the body

− Cut shrubs to the bare ground and avoid


sharp edges cuts.

− Ensure machete head is in grip of hands to


avoid being flung.

− Ensure you are donned in required PPE while


carrying out lines cutting.

− Watch out for snakes, bees while cutting and


assume safe position

− Use probing stick while walking through


swamp

− Ensure you are trained in the use of probe


stick while walking in swamp

− Ensure you are within reach while cutting


lines. Be in view of cleaners

− Ensure your feet are well positioned to gain


good balance while cutting

− Participate in daily tool box meeting

− Participate in RIR system

− Implement line trekking procedure

− Adopt buddy system on lines.

− Ensure you are guided by HSE Policy of IDSL


whilst in employment

− Ensure lines are cleaned to avoid trip hazards

− Mark out hazards spots to warn those coming


behind

FREQUENCY Duration of project


JOB HAZARD − Hostile Communities
ANALYSIS
− Wild Animals/Environmental Conditions.

− Road Traffic Hazards.

− Provisional sleeping conditions.

SKILL SET − Minimum 1 year as survey helper.

− Machete handling.

TOOLS & EQUIPMENT Coverall,Safety-boots,Machete,Shin-


guard,Hand-gloves,Eye-goggles and Hard-hat.
PPE’S REQUIRED Coverall,Safety-boots,Machete,Shin-
guard,Hand-gloves,Eye-goggles and Hard-hat.
DAD WORK PROCEDURE FOR ALL SECTIONS

Edition: Revision 2
Date of Issue: June. 2019
Next Revision before: June. 2023
NG01013215
DAD WORK PLAN
Page

Approval By: D.M. TARIAH


(MD -IDSL)
Signature: