You are on page 1of 10

Available online at www.sciencedirect.

com

International Journal of Project Management 27 (2009) 522–531


www.elsevier.com/locate/ijproman

Cost escalation and schedule delays in road construction


projects in Zambia
Chabota Kaliba *, Mundia Muya, Kanyuka Mumba
Department of Civil and Environmental Engineering, School of Engineering, The University of Zambia, P.O. Box 32379, Lusaka, Zambia

Received 27 November 2007; received in revised form 30 June 2008; accepted 3 July 2008

Abstract

The wealth of any nation is gauged by its performance in infrastructure provision through its construction industry. The construction
industry is large, volatile, and requires tremendous capital outlays. For developing economies, road construction constitutes a major
component of the construction industry. This means that much of the national budget on infrastructure development is channelled to
road construction projects. The aim of the study reported in this paper was to identify causes and effects of cost escalation and schedule
delays in road construction projects. Using a detailed literature review, structured interviews and questionnaire surveys, the results of the
study confirmed the prevalence of cost escalation and schedule delays in road construction projects in Zambia. The study established that
bad or inclement weather due to heavy rains and floods, scope changes, environmental protection and mitigation costs, schedule delay,
strikes, technical challenges, inflation and local government pressures were the major causes of cost escalation in Zambia’s road construc-
tion projects. On the other hand, delayed payments, financial processes and difficulties on the part of contractors and clients, contract
modification, economic problems, materials procurement, changes in drawings, staffing problems, equipment unavailability, poor super-
vision, construction mistakes, poor coordination on site, changes in specifications and labour disputes and strikes were found to be the
major causes of schedule delays in road construction projects. Appropriate project management practices are thus required to curb the
causes and effects of cost escalation and schedule delays in road construction projects.
Ó 2008 Elsevier Ltd and IPMA. All rights reserved.

Keywords: Cost escalation; Schedule delays; Road construction industry; Zambia

1. Introduction According to Ahmed et al. [1], delays on construction


projects are a universal phenomenon and road construc-
Cost and schedule overruns can occur due to a wide tion projects are no exception. They are usually accompa-
range of causes on various types of projects. If project costs nied by cost overruns. These have a debilitating effect on
or schedules exceed their planned targets, client satisfaction clients, contractors, and consultants in terms of growth in
would be compromised. The funding profile would no adversarial relationships, mistrust, litigation, arbitration,
longer match the budget requirement and further slippage cash-flow problems, and a general feeling of trepidation
in schedule could result. The resulting effects would be det- towards each other [1]. This problem is not unique to devel-
rimental especially in the case of developing countries oped countries but is also experienced in most of the devel-
whose wealth measure is greatly dependant on their perfor- oping economies too. The Hindu [26], an e-paper, carried
mance in infrastructure provision through the construction an article that indicated that construction projects in India
industry, especially on road construction projects which were prone to delays and cost escalation, causing contrac-
constitute a major component of the industry. tors to back out of the some projects.
Major causes and effects of cost escalation and schedule
*
Corresponding author. Tel.: +260 977619877. delays on road construction projects in Zambia are
E-mail address: cjicax@yahoo.co.uk (C. Kaliba). outlined.

0263-7863/$34.00 Ó 2008 Elsevier Ltd and IPMA. All rights reserved.


doi:10.1016/j.ijproman.2008.07.003
C. Kaliba et al. / International Journal of Project Management 27 (2009) 522–531 523

In the bid to improve the economy, the Government of Accountability Office [8], found that 77% of highway pro-
Zambia has over the past years spent a lot of resources on jects in the USA experienced cost escalation. Flyvbjerg
road construction projects. For example, US$ 118.7 million et al. [7] also concluded that nine out of every ten construc-
was spent on road projects in 2005, US$ 227 million in tion projects experienced cost escalation. Most of the cost
2006 and US$197 million in 2007 [9–11]. However, many escalation is said to occur before construction begins.
road projects were rarely completed within the planned Among the many factors identified, GAO/RCED [8] spe-
time and cost as can be seen in Table 1, leading to loss of cifically noted three:
revenue due to cost escalation and schedule delays. As a
result of its overriding importance for both the client in  initial estimates were preliminary and not designed to be
terms of performance and the contractor in terms of reliable predictors of project costs;
money, time is the source of frequent disputes and claims  initial estimates were modified to reflect more detailed
leading to lawsuits [1], leading to more expenses and reve- plans and specifications as a project is designed; and
nue losses by the parties involved.  a project’s costs were affected by among other things,
inflation and changes in scope to accommodate eco-
2. Cost escalation nomic considerations that occurs over time as a project
is designed and built.
Cost escalation refers to the increase in the amount of
money required to construct a road project over and above Other studies [5,17–21,25] identified cost escalation to be
the original budgeted amount. In the India Infrastructure a result of problems such as delay in land acquisition, unex-
Report, Datta [5] described cost escalation as a ubiquitous pected problems in supply of raw materials, illegal
problem in government projects. Cost escalation occurs encroachment on land even during project implementation,
when actual costs exceed previously estimated values [16]. or due to internal problems in government organisations. It
Schexnayder et al. [25] and Merewitz [18] endeavoured has further been noted that delays between the planning
to find some of the reasons that lead to cost escalation stage and actual implementation of especially large infra-
and categorized them into two broad groups: uncontrolla- structure projects is an ubiquitous problem resulting in cost
ble and controllable factors. escalation and failure to meet the demands as the construc-
In a study to identify factors that cause inaccuracies in tion completion horizon is reached even before the comple-
cost estimates of highway projects, the Government tion of the project [5].

Table 1
Performance of selected projects in Zambia
Name of Start date Original finish Revised Original contract sum Final contract sum (US Remarks
project date finish date (US $’ million) $’ million)
1 Nyimba- October October 2004 July 2005 4.90 5.88 Beyond budget,
Katete 2003 beyond schedule
2 Lusaka- January July 2005 On-going 24.25 25.33 Beyond budget,
Mongu 2003 beyond schedule
3 Kasama- October November Nil 35.00 Beyond schedule
Luwingu 2001 2003
4 Mpika- June 2001 December Nil 2.38 Beyond schedule
Kasama 2002
5 Mpika-Muwele June 2001 December Nil 1.30 Failure to commence
2001
6 Kashikishi- June 2001 January 2003 Nil 37.50 Incomplete work
Lunchinda
7 Chambeshi- February August 2001 Nil 1.35 Failure to commence
Chinkobo 2001
8 Isoka- December March 2002 August 2002 4.00 5.50 Beyond budget,
Muyombe 2000 beyond schedule
9 Chinsali- April 1999 July 2000 November 2.00 2.00 Beyond schedule
Nakonde 2000
10 Mpika- March March 2000 November 1.95 1.95 Beyond schedule
Chinsali 1999 2000
11 Mutanda- February February December 3.84 6.45 Beyond budget,
Kasempa 1997 1999 2000 beyond schedule
12 Choma- November February Nil 2.50 8.60 Beyond budget,
Namwala 1994 1998 incomplete work
13 Luanshya- November January 1997 December 2.53 3.63 Beyond budget,
Mpongwe 1994 2001 beyond schedule
Source: Projects progress report [23] and projects progress report [24].
524 C. Kaliba et al. / International Journal of Project Management 27 (2009) 522–531

Factors that lead to cost escalation are said to include delay included approval of working drawings, delays in
among others: the size of the project; project scope enlarge- payments to contractors and the resulting cash-flow prob-
ment; inflation; length of time to complete the project; lems during construction, design changes, conflicts in work
incompleteness of preliminary engineering and quantity schedules of subcontractors, slow decision making and
surveys; engineering uncertainties; exogenous delays; com- executive bureaucracy in the clients’ organisations, design
plexities of administrative structures; and inexperience of errors, labour shortage and inadequate labour skills.
administrative personnel [18]. Cost escalation is further Promkuntong and Ogunlana [22] concluded that the
compounded by factors such as project location, project problems of the construction industry in developing econ-
conditions, environmental mitigation costs, suspension of omies could be nested in three layers:
works, strikes, poor coordination on site, expiry of bid,
local government pressures, political discontinuity and  shortages or inadequacies in industry infrastructure,
transportation problems [14,21,25]. mainly supply of resources;
Studies by the Rand Corporation to address the ques-  problems caused by clients and consultants; and
tion of what steps could be taken to minimise cost and  incompetence of contractors.
schedule risks suggest that factors such as remote sites, fail-
ure to plan for adequate manpower, poor understanding of
local labour practices, and changing or unclear labour reg- 4. The need to improve management of road construction
ulations can lead to cost escalation [19,20]. These studies projects
also indicate that poor management would cause cost esca-
lation but stress that poor project execution caused by In an effort to improve the Zambian economy and in
management deficiencies is usually not the primary driver keeping with the Millennium Development Goal Number
of project cost escalation [19,20]. Mansfield et al. [17] 8, Target 14 which focuses at assisting landlocked low-
showed that the major factors that cause cost escalation income developing countries like Zambia to meet their spe-
were poor contract management, improper planning, inac- cial development needs and to help them overcome the
curate estimating, and overall price fluctuations. impediments of geography by improving their transit trans-
port systems, the Government of Zambia in its 2006
3. Schedule delays national budget allocated an equivalent of US $227 million
towards roads [10]. Fig. 1 shows the country data and loca-
Schedule delay refers to a situation where a construction tion of Zambia in Africa.
project does not come to completion within the planned per- In its Fifth National Development Plan (FNDP) run-
iod. Time is an integral part of every plan a company devel- ning from 2006 to 2010, the Zambian Government further
ops for performing contract work. There is a relationship stressed the need for strengthening economic infrastructure
between the schedule, the scope of work, and project condi- as one of the critical vehicles for the realization of the
tions. Changes to any one or more of the above three can plan’s objectives. During the FNDP, it was planned that
affect the compensation level and time of completion [1]. roads in a maintainable condition should improve from
Construction projects frequently experience schedule 51% in 2005 to 90% by 2010. Spending on rural feeder
delays. Various factors affect completion periods of pro- roads, in particular, was to be enhanced so as to widen
jects. It has been argued that it is necessary to create aware- market access on a large scale. The FNDP targeted to raise
ness of causes of project schedule delays, their frequency, spending on road infrastructure to at least 2.0% of Gross
and the extent to which they can adversely affect project Domestic Product (GDP) during the planned period [12].
delivery [6]. According to Ahmed et al. [1], delays can be While it was noble to allocate so much resources to the
grouped in the following four broad categories depending road sector, it has been argued that the Government would
on how they operate contractually: continue to put taxpayers’ money in a ‘bottomless pit’ if
there was no proper management of road projects [4].
 non-excusable delays; From available information [23,24], there seems to be a
 non-compensable excusable delays; consistent pattern of projects costing more than budgeted
 compensable excusable delays; and for, taking longer than planned or even being terminated
 concurrent delays. before commencement or during implementation as dem-
onstrated by a selected list of projects in Table 1. The por-
Mansfield et al. [17] showed that the most significant trayed situation is a source of concern and needs urgent
factors affecting construction schedules were financing measures to address it.
and payment for completed works, poor contract manage- Improved management of roads would only be demon-
ment, changes in site conditions, shortage of materials, and strated when projects of desired quality would be delivered
improper planning. Ahmed et al. [1], Al-Moumani [2], within their scheduled period and costs. From the foregoing
Kumaraswamy and Chan [15] and Assaf et al. [3] agreed discourse, there are a wide range of views on the causes of
on most of the causes of schedule delays in the construction schedule delays and cost escalation regarding engineering
industry and concluded that the most significant causes of and construction projects. Some are attributable to a single
C. Kaliba et al. / International Journal of Project Management 27 (2009) 522–531 525

6. Structured interviews

The structured interviews were preliminary in nature


and design and were targeted at respondents from consult-
ing and construction firms, financing institutions and
implementing agencies. The structure of the interview ques-
tions was based on information gathered from literature
review and was intended to identify challenges that finan-
ciers, consultants, implementing agencies and contractors
face in implementing road projects in Zambian. The inter-
views were also aimed at obtaining all possible factors that
would cause cost escalation and schedule delays in road
construction projects in Zambia so as to have them
included in the main questionnaire survey.
Ten respondents, randomly selected from a cross-section
of organisations in the road sector, were interviewed. Zam-
bia is a relatively small low-income developing country as
earlier seen in Fig. 1. The construction industry is equally
small. There are three major governmental client ministries
in Zambia with a number of implementation wings and
quasi-government agencies, 15 consulting firms, and 40
main contractors in Category R, Grades 1 to 4 registered
with the National Council for Construction in the Zambian
Fig. 1. Country data and location of Zambia in Africa.
road construction sector. The sample size, though small,
encompassed the key players in the Zambian road sector
party, others can be ascribed to several quarters, and many and helped in providing preliminary insights into the chal-
relate more to systemic faults or deficiencies rather than to a lenges faced by the road sector in which the government is
group or groups of people. Successful execution of con- almost the sole client. The preliminary issues from the
struction projects and keeping them within estimated cost interviews fed into the information utilised in the construc-
and prescribed schedules depend on a methodology that tion of the wider questionnaire survey described later in the
requires sound engineering judgment [13]. This calls for paper.
employment of effective project management techniques.
Despite the high number of studies [1–3,6,14,15,17– 6.1. Information from the interviews
22,25] on causes of cost escalation and schedule delays in
construction projects, little or no research has been under- 6.1.1. Overview of projects handled by interviewees
taken in Africa in general and Zambia in particular to Information on the projects the interviewees had been
address the identified challenges. Additionally, most of involved with in the past five years was captured. Mainly,
the reported studies relate to the construction industry in questions relating to the number of projects undertaken,
general, and the building sector in particular, and as such contract values, and the extent to which the projects had
would not highlight some of the major causes of cost esca- satisfied the objectives of budget, schedule and perfor-
lation and schedule delays in road construction projects. mance requirements were posed.
The studies also are predominantly from developed coun- All the interviewees indicated that they had been
tries and would not highlight clearly the factors that would involved with not less than five projects in their work expe-
affect the road construction sector in developing countries. rience. Further, the value of contracts managed by the
The fact that there is no literature of similar studies con- interviewees ranged from USD 25,000 to USD
ducted in Zambia suggests that little attention has been 50,000,000. These values indicate that the magnitude of
paid to this area of investigation in the past. the resources that the Government and other financing
agencies inject into the sector is quite significant. It is,
5. Research methods therefore, imperative that the resources are utilised effi-
ciently and effectively through good project management.
This paper presents findings of a study carried out from
February 2006 to February 2007 on the major causes and 6.1.2. Budget overruns
effects of cost escalation and schedule delays in road con- From the experience of the interviewees, budget over-
struction projects in Zambia. The data was collected using runs on projects were a common occurrence; four of the
structured interviews and questionnaires surveys, literature interviewees indicated that ‘Many’ projects they had been
review and case studies of road construction projects in the involved in had suffered budget overruns, three stated that
country. ‘Quite a few’ projects had budget overruns, while another
526 C. Kaliba et al. / International Journal of Project Management 27 (2009) 522–531

three believed that the number of projects that had experi- interviewees pointed out that all other project objectives
enced budget overruns was ‘Negligible’. were seriously compromised because of this single factor.
With the above responses, it was quite clear that this Three indicated that ‘Contractors’ incompetence’ contrib-
subject needed to be explored further. The need for further uted to poor project performance; two stated that ‘Poor
exploration was especially highlighted from the facts pre- project supervision’ contributed to many projects failing
sented in Table 1. Interviewees indicated that in some to meet desired objectives; and one singled out ‘Sudden
cases, funding was so erratic that claims owing to delayed change or increase in the scope of works’ contributory to
payments, interest and standing time by contractors projects failing to meet desired objectives.
formed a significant part of the final total project cost. These results correlated with most of the factors identi-
Due to delayed payments, project durations increased fied in the literature review. The results showed the serious-
and costs escalated. It was also pointed out that due to ness of the impact that these risks could have on project
political and other influences; the scope of works on most outcomes. Quite often, these factors, while occurring sepa-
government-funded projects could be increased without rately or jointly have caused serious implementation prob-
due regard to budgetary, schedule and other constraints. lems on road projects in Zambia.
Budget overruns, if not controlled, have the potential to
adversely affect the completion of projects. Stringent man- 6.1.5. Prevalence of projects failing to meet objectives
agement of the various risks that can adversely impact on For an overview of the extent or magnitude of the prob-
increased project costs is thus paramount. lem of road projects facing implementation difficulties,
interviewees were asked to rate the frequency of projects
6.1.3. Schedule overruns failing to meet budgetary, schedule and design require-
Results showed that a significant number of projects ments. Three out of ten interviewees rated the prevalence
were not completed within schedule. Six of the interviewees as ‘High’, four indicated that the prevalence as ‘Medium’,
indicated that ‘Many’ projects they were involved in had while three rated the frequency as ‘Low’.
schedule overruns, three believed that ‘Quite a few’ projects It was quite evident from the interviews that many pro-
had schedule overruns, while one stated that the number of jects, especially solely government-funded projects, fre-
projects with schedule overruns was ‘Negligible’. quently failed to meet the objectives of cost, time and
The literature reviewed showed that completing projects quality. It seemed these problems were so widespread that
within time is one of the biggest challenges facing the con- it was almost an accepted norm for this to occur on govern-
struction industry. If risks are not managed well, schedule ment-financed projects. Some of the reasons advanced
overruns are likely to occur. Many risks, apart from included the sanctioning of road projects for political expe-
increasing costs, have the tendency to disrupt works, caus- dience without proper analysis or evaluation of the ade-
ing delays and hence prolonging the duration of a project. quacy of resources or justification of the projects.
From the interviews, it was clear that schedule overrun Kasama-Luwingu and Kashikishi-Lunchinda Projects were
risks were significantly high on road projects in Zambia. good examples cited. The findings from the interviews were
Insights from the interviewees showed that due to funding, vital input into the questionnaire survey.
design, and unplanned increases in scopes of works, some
projects suffered protracted durations. Some of these sche- 7. Questionnaire survey
dule overruns were so severe that they could increase the
original project durations two, three or even four fold as The questionnaire survey, which was designed to deter-
evidenced from the information in Table 1 in which pro- mine the major causes and effects of cost escalation and
jects such as Luanshya-Mpongwe, Kasama-Luwingu and schedule delays in road projects, was targeted at 60 partic-
Kashikishi-Lunchinda roads severely exceeded original ipants using the disproportionate stratified sampling tech-
project durations. nique. To ensure that the findings of the survey included
all possible factors that would cause cost escalation and
6.1.4. Key factors that contribute to projects failing to meet schedule delays in road construction projects in Zambia,
desired objectives the sample was disproportionately stratified so as so have
It was necessary to identify the most important factors represent the views of contractors, consultants and clients
that contributed to some projects falling short of the equally. The response rate for the questionnaire survey
desired objectives of cost, time and quality. From their was 43%, 70% of which was shared equally between con-
own experiences, interviewees were requested to pick out tractors and consultants while clients had 30%
from a given list, factors they considered most significant representation.
in contributing to projects failing to meet desired
objectives. 7.1. Profile of questionnaire respondents
Four of the interviewees believed that ‘Poor or erratic
funding’ contributed most to poor project outcomes. Some The academic qualifications of the questionnaire survey
explained that this was more characteristic with projects respondents were assessed. As shown in Fig. 2, out of 26
that were fully government-financed. In fact, most of the participants 27% of the respondents had a diploma in engi-
C. Kaliba et al. / International Journal of Project Management 27 (2009) 522–531 527

60 Weighted opinion averages of each cause of cost escala-


tion and schedule delays in road construction project were
determined to assess their perceived significance. The aver-
50
age weighted perceived significance was then computed
using the formula below:
Percent of respondents

40 4
P
F i Ri
1
WA ¼  14  100%
30
4 P
Fi
1

where WA is the average weighted perceived significance;


20
Ri is the response type on the Likert scale, i ranging from
1 to 4 on the Likert scale; Fi is the frequency or total num-
10 ber of respondents choosing response type i on the Likert
Dip in Eng BEng Msc in Eng scale, with i ranging from 1 to 4 as earlier described.
Academic qualification As an example, WA, the average weighted perceived sig-
Fig. 2. Academic qualifications of the respondents. nificance was computed as follows:
1
 
ðF 1  R1 þ F 2  R2 þ F 3  R3 þ F 4  R4 Þ
WA ¼ 
4 ðF 1 þ F 2 þ F 3 þ F 4 Þ
 100%
30
It is note worthy that the possible values of average
weighted perceived significance, WA, ranged from 25% to
Percent of respondents

20
100% because each factor identified through literature or
interviews had some level of significance that would not
amount to zero. The factors whose WA score was 50%
and above were categorized as major factors that cause cost
10
escalation and schedule delays in road construction pro-
jects in Zambia.
0
5 years or less 11 to 15 years
9. Major causes of cost escalation in road construction
6 to 10 years 16 years or more projects
Working experience in road construction industry
Results of questionnaire surveys showed that there were
Fig. 3. Working experience in road construction industry.
eight major causes of cost escalations that predominantly
affect road construction projects in Zambia. From Fig. 4,
neering, 50% had a bachelor’s degree in civil engineering bad weather, mainly heavy rainfall and floods, scored the
while 23% had a masters of science in engineering. highest weighted average of 73%. It was followed by scope
Fig. 3 shows that 31% of the respondents had worked in changes which scored 63% and environmental protection
the construction industry for more than sixteen years, 23% and mitigation cost which scored 61%. Schedule delay
for eleven to sixteen years, 27% for six to ten years while scored 54% while strikes had 52%. The others were local
the rest had worked for five years or less. government pressures, technical challenges and inflation
The profile and experience of the respondents suggest which all scored 50%.
sufficient exposure to make the information acquired
reliable. 10. Responsibility and category of major causes of cost
escalation
8. Analysis and discussion of questionnaire survey results
The major causes of cost escalation were categorized as
A questionnaire survey was used to further investigate shown in Table 2, which indicates that clients were respon-
the findings of the interviews and test the extent to which sible for most of the major causes of cost escalation. Four
the results could be generalised. Participants of the ques- of the major causes of cost escalation were solely attributed
tionnaire survey were asked to rate the causes of cost esca- to clients. Contractors bore responsibility for two whilst
lation and schedule overruns with respect to their sharing one with consultants. Bad or inclement weather
significance on a Likert scale ranging from 1 to 4, where had shared responsibility by the parties involved.
1 = not significant, 2 = slightly significant, 3 = significant It was also noted that most of the causes of cost escala-
and 4 = very significant. tion were controllable. Only inclement weather and infla-
528 C. Kaliba et al. / International Journal of Project Management 27 (2009) 522–531

80%
70%

Weighted Average
60%
50%
40%
30%
20%
10%
0%
Bad Scope Env Schedule Strikes Technical Inflation Local govt
weather changes protection delay challenges pressures
&
mitigation
costs
Causes of cost escalation

Fig. 4. Major causes of cost escalation in road projects and their ranking in Zambia.

Table 2 weighted average percentage of occurrence as shown in


Responsibility and category of the major cause of cost escalation Fig. 5.
Causes of cost escalation Responsibility (who Category of
bares the cost?) factor 13. Responsibility and category of the major causes of
Bad weather Shared Uncontrollable schedule delays
Inflation Client Uncontrollable
Schedule delay Contractor Controllable Table 3 indicates that clients were responsible for six of
Scope changes Client Controllable the major causes of schedule delay. The other six were
Local government pressures Client Controllable
Strikes Contractor Controllable
attributed to contractors while two to consultants. As
Technical challenges Contractor and Controllable can be seen from Table 3, 50% of the major causes of sche-
consultant dule delay were compensable events thus the need to keep
Environmental protection and Client Controllable the occurrence of such factors to a minimum so that pro-
mitigation costs jects could be executed within budget.

tion were uncontrollable and as such the problem of cost 14. Effects of schedule delays
escalation could be minimised.
The major effects of schedule delays in road construction
11. Effects of cost escalation projects were identified to be poor quality of end product,
project extension, litigation, and cost overruns.
The study established that project delay, poor quality,
project extension, project abandonment, litigation and cost 15. Conclusions
overruns were the effects of cost escalation. These effects
could adversely affect the national economy if left In an effort to improve the Zambian economy and in
unchecked. keeping with the Millennium Development Goal Number
8, Target 14 which focuses on assisting landlocked develop-
12. Major causes of schedule delays ing countries like Zambia to meet their special development
needs and to help them overcome the impediments of geog-
Delayed payment was found to be the number one cause raphy by improving their transit transport systems, a lot of
of schedule delays in the Zambian road construction indus- investments has been channelled into road construction
try with 75% as its weighted average percentage of occur- projects. Despite substantial investment in road projects,
rence. It was followed by protracted financial processes in improvements in the performance of the sector are signifi-
client organisations and financial difficulties that accom- cantly impeded by cost escalation and schedule delays
pany the delayed release of funds by client organisations experienced on many projects.
which had 67% and 60% respectively. Contract modifica- The study found bad or inclement weather due to heavy
tion was ranked forth at 57% while economic hardships rains and the resulting floods to be the number one cause for
were ranked as the fifth major cause of schedule delays cost escalation. It was followed by scope changes, environ-
56% weighted average score. Material procurement and mental protection and mitigation costs. Schedule delays,
changes in drawings both scored 55%. Staffing problems, strikes, local government pressures, technical challenges
equipment unavailability, poor supervision, construction and inflation were also found to be major contributors to
mistakes, poor coordination on site and changes in specifi- cost escalation. On the other hand, delayed payments were
cations all scored 53% while labour disputes were least found to be the number one cause of schedule delays in the
among the major causes of schedule delays with 50% Zambian road construction industry. It was followed by the
C. Kaliba et al. / International Journal of Project Management 27 (2009) 522–531 529

Fig. 5. Major causes of schedule delay in road projects and their ranking in Zambia.

Table 3 development. Delays and any cost overruns tend to unbal-


Responsibility and category of the major causes of schedule delays ance the initial cost benefit analyses conducted, considering
Causes of delay Responsibility (who leads to Type of delay much of the money used to construct the roads is borrowed
the cause?) and has to be paid back with interest. All the factors iden-
Changes in Client Excusable – tified in this study need to be carefully managed so as to
drawings compensable avoid risks that are attributable to them. This calls for
Changes in Consultant Excusable –
improved risk and project management practices by clients,
specifications compensable
Material Contractor Non-excusable contractors and consultants.
procurement Lastly, the small sample size of 26 respondents to the
Construction Contractor Non-excusable questionnaire survey poses some limitations to the extent
mistakes to which the results of the study could be generalised.
Poor supervision Consultant Non-excusable
Due to this limitation, the survey may not have identified
Equipment Contractor Non-excusable
unavailability all the possible factors that could cause cost escalation
Financial process Client Excusable – and schedule delays and their effects in road construction
compensable projects in Zambia. However, this notwithstanding, the
Financial difficulties Client Excusable – study made a significant attempt at identifying the major
compensable
causes of cost escalation and schedule delays in road con-
Delayed payments Client Excusable –
compensable struction projects in Zambia.
Economic problems Client Excusable –
compensable 16. Recommendations
Labour disputes and Contractor Non-excusable
strikes
There are no straightforward solutions to the challenges
Contract Client Excusable –
modification compensable of cost escalation and schedule delays in road construction
Staffing problems Contractor Non-excusable projects. There are, however, steps that can be taken to
Poor coordination Contractor Non-excusable minimise their causes and effects, the major one being the
on site use of efficient project management tools and practices.
For the specific factors that cause cost escalation and sche-
dule delays in road construction projects in Zambia, the
financial processes in client organisations and financial dif- following recommendations are suggested.
ficulties that accompany the delayed release of funds by cli-
ent organisations, contract modifications, and economic 16.1. Project timing and scheduling
hardships. Materials procurement, changes in drawings,
Staffing problems, equipment unavailability, poor supervi- The projects earmarked for construction should be
sion, construction mistakes, poor coordination on site, properly planned and timed in such a way that most of
changes in specifications and labour disputes were among the works can be executed in seasons of clement weather.
the major causes of schedule delays. Except for long contracts which take more than one year,
These factors combine to impede the rate of delivery of the projects should be executed between early April and
road infrastructure and consequently the rate of national early December, which is the dry season in Zambia. This
530 C. Kaliba et al. / International Journal of Project Management 27 (2009) 522–531

means that procurement processes need to be embarked on 16.5. Competent personnel


at appropriate times. Proper scheduling would also ensure
that projects do not experience significant resource Effective project implementation requires competent
bottlenecks. personnel. This would minimise errors, poor supervision
and enhance coordination on sites. Clients, Consultants
16.2. Scope definition and Contractors should ensure that they have the right per-
sonnel with the right qualifications to manage their pro-
For any project, scope needs to be well defined from jects. Where possible, construction managers need to
inception to completion. Scope changes often lead to have experience and qualifications in project or construc-
claims and at time disruption of work due to inadequate tion management so that they can effectively utilise the pro-
analysis of the project in its initial stages. Reasonable sur- ject management tools that are available.
veys that would bring to light the scope of works to be
undertaken must always be conducted. The period between 16.6. Capacity building
these surveys and award of contract should not be too long
as conditions would not remain the same for a long period Capacity building is essential for sustainable develop-
of time. It should be borne in mind that contractors tend to ment. Governments should set up deliberate schemes that
over price variations so as to cover up for any short falls in can help local contractors build their capacity by availing
their initial bids. This implies that the variations that result them credit facilities. This would ensure adequate equip-
from scope enlargements are more costly hence compound ment availability. On the other hand, deliberate policies
cost escalation. Effective scope definition is therefore indis- for personnel capacity building should also be put in place
pensable for satisfactory project delivery. by contractors, consultants and client. The benefits of such
facilities would upset the prevalent quality shortfalls and
16.3. Project costing and financing losses of time and money.

Proper costing is essential in every capital project. The 16.7. Legislation and good corporate governance
initial cost estimates should be as accurate as possible.
This would allow clients to ensure that the required funds Strike and labour disputes can be controlled through the
for executing the project are sourced in good time and use of adequate and appropriate legislation. The govern-
made available when required. Cost and value engineering ment should update, enact and effectively enforce laws that
principles must be applied at all stages of the project. would ensure that the work force is not ill-treated by their
During the execution stage of the project, project manag- employers. These laws should also provide for an effective
ers should ensure that contractual obligations are dealt and proper grievance resolution procedure. This would call
with diligently within the required period. Delayed pay- for good corporate governance procedures by the client,
ments due to complex financial processes in client organ- consultant and contractors.
isations would cause financial difficulties to contractors,
and consequently cause schedule delays. Interest could Applied singularly or collectively, the suggested recom-
also be charged on delayed payments, hence inducing cost mendations are essential for improving delivery of road
escalation. Therefore, clients should ensure that they have construction projects in Zambia and other low-income
funds available for projects before they are commissioned. developing countries. It is necessary that the risks and
The engagement of the financially efficient private sector weaknesses identified in this paper are addressed if the sub-
through public private partnerships in road infrastructure stantial investments in road construction projects would
would be another alternative for funding road projects. contribute to poverty alleviation and an improved quality
On the other hand, contractors should avoid misapplying of life for the population this vital infrastructure category
project finances as this could put them in financial distress is intended to serve.
that could result in them failing to execute the works.
Advance payments should be applied on intended pur-
poses in order that project objectives of cost, time and References
quality are achieved.
[1] Ahmed S, Azher S, Castillo M, Kappagantula P. Construction delays
in Florida; an empirical study, Florida; 2002. <http://
16.4. Communication www.cm.fiu.edu/publication/Delays%20project.pdf>.
[2] Al-Moumani HA. Construction delay: a quantitative analysis. Int J
Effective communication can alleviate most of the fac- Project Manage 2000;18(1):51–9.
tors that cause cost escalation and schedule delays in road [3] Assaf S, AL-Khalil M, Al Hazmi M. Causes of delay in large building
construction projects. J Manage Eng 1995;11(2):45–50.
construction projects. Clients ought to promote team- [4] CSPR. CSPR statement on the 2006 National Budget; 2006. p. 4.
building communication processes. Project managers need [5] Datta B. Management of infrastructure projects in urban local
to deal with all project issues objectively and ensure that all bodies: case study of Kanpur Development Authority. India Infra-
communication is project issue based. structure Report; 2002. p. 207–11.
C. Kaliba et al. / International Journal of Project Management 27 (2009) 522–531 531

[6] Falqi II. Delays in project completion: a comparative study of [17] Mansfield NR, Ugwu OO, Doran T. Causes of delay and cost
construction delay factors in Saudi Arabia and the United Kingdom; overruns in Nigerian construction projects. Int J Project Manage
2004. <http://www.saedin.com/index.php?option=com_docman& 1994;12(4):254–60.
task=doc_download&gid=48&Itemid=57>. [18] Merewitz L. Cost overruns in public works. Aldine: Benefit Cost and
[7] Flyvbjerg B, Holm MS, Buhl S. Underestimating costs in public Policy Analysis Chicago; 1973. p. 227–97.
works projects, error or lie. J Am Plan Assoc 2002;68(3):279–92. [19] Merrow EW, Phillips KE, Myers CW. Understanding cost growth
[8] GAO/RCED. Transportation infrastructure managing the costs of and performance shortfalls in pioneer process plants. Santa Monica,
large-dollar highway projects, Washington, DC; 1997. CA: The Rand Corporation; 1981.
[9] Ministry of Finance and National Planning. Government Republic of [20] Merrow EW. Understanding the outcomes of megaprojects: a
Zambia 2005 Budget; 2005. quantitative analysis of very large civilian projects. Santa Monica,
[10] Ministry of Finance and National Planning. Government Republic of CA: The Rand Corporation; 1988.
Zambia 2006 Budget; 2006. [21] NAP. Completing the Big dig; managing the final stages of Boston’s
[11] Ministry of Finance and National Planning. Government Republic of Central Artery/Tunnel Project. Washington, DC: The National
Zambia 2007 Budget; 2007. Academies Press; 2003. <http://www.darwin.nap.edu/books/
[12] Ministry of Finance and National Planning. Government Republic of 0309088879/html>.
Zambia’s Fifth National Development Plan; 2006. p. 36. [22] Promkuntong K, Ogunlana ST. Construction delays in fast-growing
[13] Hancher DE, Rowing RE. Sitting highway construction contract economy: comparing Thailand with other economies. Int J Project
duration. J Constr Eng Manage 1981;107(2):169–79. Manage 1996;14(1):37–45.
[14] Hall P. Great planning disasters. USA: University of California Press; [23] Roads Department. Projects progress report; 2002.
1980. [24] Road Development Agency. Projects progress report; 2005.
[15] Kumaraswamy MM, Chan DW. Determinants of construction [25] Schexnayder C, Fiori C, Weber S. Project cost estimating; a synthesis
duration. Constr Manage Econ 1995;13(3):209–17. of highway practice, Arizona; 2003. <http://www4.trb.org/trb/
[16] Leavitt D, Ennis S, McGovern P. The cost escalation of rail projects: crp.nsf/All+Projects/NCHRP+20-7>.
using previous experience to re-evaluate the cal speed estimates. [26] The Hindu. Hit by delays and cost escalation; 2007. <http://
California high speed rail series, April working paper; 1993. www.hindunnet.com/2007/07/06/stories/2007070657310100>.

You might also like