Tugas Besar 2
Hitunglah besar biaya operasi pada tugas besar sesuai dengan instruksi yang telah dijelaskan
pada pertemuan tatap muka ke-2.
Jawaban:
A. Loading Cost
➢ Coal Reverse = 3.728.900 ton
➢ Waste = 45.950.200 bcm
➢ Loading cost for coal = USD 1,73 per ton
= USD (1,73 x 3.728.900) per ton
= USD 6.450.997 per ton
➢ Loading cost for waste = USD 1,56 per bcm
= USD (1,56 x 45.950.200) per bcm
= USD 71.682.312 Per bcm
B. Contract
➢ The coal hauling distance = 5,50 km
➢ The waste hauling distance = 1,00 km
➢ The actual coal distance = 6.350 m = 6,35 km
➢ The actual coal distance = 1.710 m = 1,71 km
C. Overdistance
• Coal = (6,35 - 5,50) km = 0,85 km
• Waste = (1,71 – 1,00) km = 0,71 km
D. Cost Hauling
➢ Coal = USD (5 + (0.1 x last digit of student ID) per km
= USD (5 + (0.1 x 2) per km
= USD 5,2 per km
= USD (5,2 x 5.50)
= USD 28,6
➢ Waste = USD (1,00 + (0.1 x the last digit of student ID)) per km
= USD (1,00 + (0.1 x 2) per km
= USD 1,2 per km
= USD (1,2 x 1,00)
= USD 1,2
E. Cost Overhaul
➢ Coal = USD 0,14 Per ton per km
= USD (O,14 x 3.728.900 x 0,85)
= USD 443.739,1
➢ Waste = USD 0,31 Per bcm per km
= USD (O,31 x 45.950.200 x 0,71)
= USD 10.113.639,02
F. Fuel Cost
➢ Coal = USD 0,58 per liter per ton
= USD (0,58 x 1 x 3.728.900)
= USD 2.162.762
➢ Waste = USD 0,82 per liter per bcm
= USD (0,82 x 1 x 45.950.200)
= USD 37.679.164
G. Fuel Cost for Overdistance
➢ Coal = USD 0.05 per liter per ton per km
= USD (0,05 x 1 x 3.728.900 x 0,85)
= USD 158.478,25
➢ Waste = USD 0,28 per liter per bcm per km
= USD (0,28 x 1 x 45.950.200 x 0,71)
= USD 9.134.899,76
The general and administration cost is calculated as 35% of total production cost.
Production Cost = USD(Total (Coal Processing + Coal Hauling + Coal Barging +
Transhipment))
= (Total (1.566.138 + 906.122,9835 + 5.667.928+ 7.681.534))
= USD 15.821.722,9835
The general and administration cost = 35% x USD 15.819.601,4835
= USD 5.537.603,0442