TA.

2022

RENCANA ANGGARAN BIAYA (RAB)

LOKASI KEG. :SDN 8 MIMBAAN KEGIATAN : PERBAIKAN ATAP PENUTUP KANTOR

KECAMATAN :PANJI SUMBER DANA :

HARGA SAT. TOTAL HARGA


NO. URAIAN PEKERJAAN VOLUME SATUAN
( Rp ) ( Rp )
1 2 3 4 5 6

A BAHAN
1 GRC board 3 mm ( 120 x 240cm ) 9.00 lembar 93,500.00 841,500.00
2 Listplank polos 0,8 x 200 x 3000 2.00 lembar 71,500.00 143,000.00
3 Genteng kodok 250.00 buah 3,850.00 962,500.00
4 Kayu kaso borneo 4 x 6, 4meter 12.00 batang 44,000.00 528,000.00
5 Cat tembok 7.00 kg 66,000.00 462,000.00
6 Plamir tembok 8.00 kg 55,000.00 440,000.00
7 Paku kayu 5cm 4.00 kg 27,500.00 110,000.00
8 Corong talang lubang pembuangan air kotak persegi, 8 1.00 buah 209,000.00 209,000.00
9 Paku 1cm -2,5 cm 3.00 kg 27,500.00 82,500.00
10 - -
11 - -
12 - -
13 - -
14 - -
15 - -
16 - -
17 - -
18 - -
19 - -
20 - -
21 - -
22 - -
23 - -
24 - -
Sub Total A) 3,778,500.00

B PERALATAN & ALAT PELINDUNG DIRI


1 Kuas 4" 2.00 buah 18,150.00 36,300.00
2 Kuas 3" 2.00 buah 17,600.00 35,200.00
3 - -
4 - -
5 - -
Sub Total B) 71,500.00

C UPAH
1 Pekerja 7.00 OH 75,000.00 525,000.00
2 Tukang 7.00 OH 90,000.00 630,000.00
3 Mandor - -
Sub Total C) 1,155,000.00

JUMLAH TOTAL (A+B+C) 5,005,000.00

Kepala Sekolah Bendahara

….......................................... …..........................................
TA. 2022

RENCANA ANGGARAN BIAYA (RAB)

LOKASI KEG. :SDN 8 MIMBAAN KEGIATAN : PENGECATAN LAPANGAN

KECAMATAN :PANJI SUMBER DANA :

HARGA SAT. TOTAL HARGA


NO. URAIAN PEKERJAAN VOLUME SATUAN
( Rp ) ( Rp )
1 2 3 4 5 6

A BAHAN
1 Cat genteng 70.00 kg 60,500.00 4,235,000.00
2 Cat kayu 3.50 kg 88,000.00 308,000.00
3 Thiner 7.00 liter 30,800.00 215,600.00
4 - -
5 - -
6 - -
7 - -
8 - -
9 - -
10 - -
11 - -
12 - -
13 - -
14 - -
Sub Total A) 4,758,600.00

B PERALATAN & ALAT PELINDUNG DIRI


1 Kuas 4" 8.00 18,150.00 145,200.00
2 - -
3 - -
4 - -
5 - -
6 - -
7 - -
8 - -
Sub Total B) 145,200.00

C UPAH
1 Pekerja 10.00 OH 75,000.00 750,000.00
2 Tukang 10.00 OH 90,000.00 900,000.00
3 Mandor - -
Sub Total C) 1,650,000.00

JUMLAH TOTAL (A+B+C) 6,553,800.00

Kepala Sekolah Bendahara

….......................................... …..........................................
TA. 2022

RENCANA ANGGARAN BIAYA (RAB)

LOKASI KEG. :SDN 8 MIMBAAN KEGIATAN : PERBAIKAN ATAP PENUTUP

KECAMATAN :PANJI SUMBER DANA :

HARGA SAT. TOTAL HARGA


NO. URAIAN PEKERJAAN VOLUME SATUAN
( Rp ) ( Rp )
1 2 3 4 5 6

A BAHAN
1 GRC board 3 mm ( 120 x 240cm ) 5.00 lembar 93,500.00 467,500.00
2 Listplank polos 0,8 x 200 x 3000 4.00 lembar 71,500.00 286,000.00
3 Kayu kaso meranti 4 x 6, 4meter 20.00 batang 48,400.00 968,000.00
4 Kayu reng meranti 2 x 3, 4meter 100.00 batang 22,000.00 2,200,000.00
5 Cat tembok 6.00 kg 66,000.00 396,000.00
6 Plamir tembok 6.00 kg 55,000.00 330,000.00
7 Paku kayu 5cm 5.00 kg 27,500.00 137,500.00
8 Paku kayu 7cm 3.00 kg 26,400.00 79,200.00
9 Paku 1cm -2,5 cm 1.00 kg 27,500.00 27,500.00
10 Kayu kaso meranti 5 x 7, 4meter 10.00 batang 59,400.00 594,000.00
11 - -
12 - -
13 - -
14 - -
15 - -
16 - -
17 - -
18 - -
19 - -
20 - -
21 - -
22 - -
23 - -
24 - -
Sub Total A) 5,485,700.00

B PERALATAN & ALAT PELINDUNG DIRI


1 Kuas 4" 2.00 buah 18,150.00 36,300.00
2 - -
3 - -
4 - -
5 - -
Sub Total B) 36,300.00

C UPAH
1 Pekerja 20.00 OH 75,000.00 1,500,000.00
2 Tukang 20.00 OH 90,000.00 1,800,000.00
3 Mandor - -
Sub Total C) 3,300,000.00

JUMLAH TOTAL (A+B+C) 8,822,000.00

Kepala Sekolah Bendahara

….......................................... …..........................................
TA. 2022

RENCANA ANGGARAN BIAYA (RAB)

LOKASI KEG. :SDN 8 MIMBAAN KEGIATAN : PAPAN PENGUMUMAN KLS

KECAMATAN :PANJI SUMBER DANA :

HARGA SAT. TOTAL HARGA


NO. URAIAN PEKERJAAN VOLUME SATUAN
( Rp ) ( Rp )
1 2 3 4 5 6

A BAHAN
1 Besi hollow 60 x 30 x 1,5 mm, 6M 2.00 lonjor 253,000.00 506,000.00
2 Besi lis kaca ( 1 x 1 ) cm 16.00 M 15,400.00 246,400.00
3 Kaca polos 5 mm 2.00 m2 168,300.00 336,600.00
4 Triplek hard wood meranti 122 x 244cm 3mm 1.00 lembar 74,800.00 74,800.00
5 Paku rivet 3,2 mm x 11 mm,50 pcs 200.00 biji 330.00 66,000.00
6 Kunci gembok 4.00 buah 16,500.00 66,000.00
7 Lantai karpet 2.00 m2 34,650.00 69,300.00
8 Cat besi 0.50 kg 88,000.00 44,000.00
9 Thiner 1.00 liter 30,800.00 30,800.00
10 - -
11 - -
12 - -
13 - -
14 - -
Sub Total A) 1,439,900.00

B PERALATAN & ALAT PELINDUNG DIRI


1 - -
2 - -
3 - -
4 - -
5 - -
6 - -
7 - -
8 - -
Sub Total B) -

C UPAH
1 Pekerja OH 75,000.00 -
2 Tukang 8.00 OH 90,000.00 720,000.00
3 Mandor - -
Sub Total C) 720,000.00

JUMLAH TOTAL (A+B+C) 2,159,900.00

Kepala Sekolah Bendahara

….......................................... …..........................................
TA. 2022

RENCANA ANGGARAN BIAYA (RAB)

LOKASI KEG. :SDN 8 MIMBAAN KEGIATAN : JARINGAN LISTRIK 5 TITIK

KECAMATAN :PANJI SUMBER DANA :

HARGA SAT. TOTAL HARGA


NO. URAIAN PEKERJAAN VOLUME SATUAN
( Rp ) ( Rp )
1 2 3 4 5 6

A BAHAN
1 Plafond fiting 11.00 pcs 11,000.00 121,000.00
2 Saklar doble 2.00 pcs 27,500.00 55,000.00
3 Saklar sigglle 1.00 pcs 27,500.00 27,500.00
4 Lampu philips LED 5 watt 5.00 buah 57,200.00 286,000.00
5 Kabel 2 X 1,5mm 300/500 ( NYM ) 20.00 M' 16,500.00 330,000.00
6 - -
7 - -
8 - -
9 - -
10 - -
11 - -
12 - -
13 - -
14 - -
Sub Total A) 819,500.00

B PERALATAN & ALAT PELINDUNG DIRI


1 - -
2 - -
3 - -
4 - -
5 - -
6 - -
7 - -
8 - -
Sub Total B) -

C UPAH
1 Pekerja 75,000.00 -
2 Tukang 2.00 OH 90,000.00 180,000.00
3 Mandor - -
Sub Total C) 180,000.00

JUMLAH TOTAL (A+B+C) 999,500.00

Kepala Sekolah Bendahara

….......................................... …..........................................
TA. 2022

RENCANA ANGGARAN BIAYA (RAB)

LOKASI KEG. :SDN 8 MIMBAAN KEGIATAN : TIANG & LAMPU HALAMAN

KECAMATAN :PANJI SUMBER DANA :

HARGA SAT. TOTAL HARGA


NO. URAIAN PEKERJAAN VOLUME SATUAN
( Rp ) ( Rp )
1 2 3 4 5 6

A BAHAN
1 Pipa galvanis 1" x 3,20 mm, 6 M 2.00 lonjor 517,000.00 1,034,000.00
2 Kap lampu 2.00 buah 38,500.00 77,000.00
3 Kabel 2 x 1,5mm" 300/500 V ( NYM ) 20.00 m' 16,500.00 330,000.00
4 Saklar siggle 2.00 buah 27,500.00 55,000.00
5 Isolasi listrik 1.00 pcs 16,500.00 16,500.00
6 Lampu philips LED 14,5 watt 2.00 pcs 93,500.00 187,000.00
7 Cat besi 0.50 kg 88,000.00 44,000.00
8 Thiner 1.00 liter 28,600.00 28,600.00
9 Semen ( PCC ) 20.00 kg 1,870.00 37,400.00
10 Pasir 0.15 m3 220,000.00 33,000.00
11 - -
12 - -
13 - -
14 - -
Sub Total A) 1,842,500.00

B PERALATAN & ALAT PELINDUNG DIRI


1 Kuas 3" 1.00 buah 16,500.00 16,500.00
2 - -
3 - -
4 - -
5 - -
6 - -
7 - -
8 - -
Sub Total B) 16,500.00

C UPAH
1 Pekerja 3.00 OH 75,000.00 225,000.00
2 Tukang 3.00 OH 90,000.00 270,000.00
3 Mandor - -
Sub Total C) 495,000.00

JUMLAH TOTAL (A+B+C) 2,354,000.00

Kepala Sekolah Bendahara

….......................................... …..........................................
TA. 2022

RENCANA ANGGARAN BIAYA (RAB)

LOKASI KEG. :SDN 8 MIMBAAN KEGIATAN : PERBAIKAN PIPA AIR 16 M'

KECAMATAN :PANJI SUMBER DANA :

HARGA SAT. TOTAL HARGA


NO. URAIAN PEKERJAAN VOLUME SATUAN
( Rp ) ( Rp )
1 2 3 4 5 6

A BAHAN
1 Pipa + mof pvc 1" setara maspion, 6 meter 4.00 buah 91,300.00 365,200.00
2 Knee pvc 1" 6.00 buah 6,050.00 36,300.00
3 Lem pvc 0.20 kg 82,500.00 16,500.00
4 - -
5 - -
6 - -
7 - -
8 - -
9 - -
10 - -
11 - -
12 - -
13 - -
14 - -
Sub Total A) 418,000.00

B PERALATAN & ALAT PELINDUNG DIRI


1 - -
2 - -
3 - -
4 - -
5 - -
6 - -
7 - -
8 - -
Sub Total B) -

C UPAH
1 Pekerja 3.00 OH 75,000.00 225,000.00
2 Tukang 3.00 OH 90,000.00 270,000.00
3 Mandor - -
Sub Total C) 495,000.00

JUMLAH TOTAL (A+B+C) 913,000.00

Kepala Sekolah Bendahara

….......................................... …..........................................