Capital Project Delivery

Stages & Gates


Kick-Off

Overview & Processes

Portlandoregon.gov/transportation 1
Today’s Agenda

1. Introductions
2. Capital Project Delivery Stages & Gates
3. Controls Team Support
4. Next Steps
5. Q&A

Portlandoregon.gov/transportation 2
Capital Project Delivery Task Force

Engineering Services
Wendy Cawley
Jason Shepard
Brenda Strombo

PPP
Denver Igarta
Mauricio Leclerc
Sheila Parrott
Steven Szigethy

Portlandoregon.gov/transportation 3
The Path to Today….

Portlandoregon.gov/transportation 4
Recent Capital Delivery Improvement Activities
Process Second Series Small Cap Task Force
Improvement e-Builder of Group Improvement Wraps Up
Begins Launched Sessions Effort

Apr – Jun ‘18 Oct – Dec ‘18

Nov ‘16 – Mar ‘18 July – Sept ‘18 Jan – Apr ‘19

First Series of Controls Task Force


Group Sessions Committee Kicks Off
Launched

Portlandoregon.gov/transportation 5
Identified Solutions (Summer ‘18)
Early PM and Engineering Project scope
engagement Design part of the approved before
of external planning and project design phase as
stakeholders development stages part of chartering

Stronger
Clear understanding of
Engineering
the project manager
Services Design
role throughout the
role with external
project lifecycle
contracting

Add’l support Standard change Improved


to assist with management process communications
managing for scope, schedule, between PM &
business and budget changes EOR/Design Manager
functions

Mutual agreement between Consistent performance


PM & EOR/Design Manager management process to
on scope, schedule, and track if we met expected
budget changes outcomes

Portlandoregon.gov/transportation 6
Stages & Gates

Portlandoregon.gov/transportation 7
Initial Conversation…..
Overall Process

• Inconsistent change management process


• PIP resources are insufficient
• Overall capacity issues, resulting in staff overburdening

Planning & Project


Development Engineering & Design Construction Closeout

• Chartering process • Need clarification • Require better • No retroactive


had no “teeth” of roles & coordination with analysis to drive
responsibilities MO on improvements
• No shared with Engineering scheduling &
understanding or groups work planning
commitment on
when projects get • Opportunity to • Evaluate current
done across groups clarify stamping on-call services to
requirements on build capacity
• No set prioritization simpler MO jobs
• No meaningful
metrics established
to track performance

Portlandoregon.gov/transportation 8
Resulted in
Shared Commitment
Capital Project Delivery

Collectively
agreed to
implement a
scalable stage-
gate process for
all capital
projects

Portlandoregon.gov/transportation 9
The Identified Solution: Stages & Gates

STAGES GATES

Comprised of unique, predefined At each Gate, project investment criteria


activities that are performed cross- are used to evaluate projects objectively,
functional, concurrently, and iteratively to individually, and cross-functionality to
optimize project scope, design, and yield effective Go/No-Go decisions
impact
• 1 – Program / Project Planning
• 2 – Project Development
• 3 – Engineering & Design
• 4 – Construction
• 5 – Closeout
• 6 – Operationalize

Portlandoregon.gov/transportation 10
The Stages & Lead Divisions

Planning, Lead: Transportation Planning Division

Overall
Project Development, Lead: Transportation Planning Division
Project
Management
(Scope, Engineering and Design, Lead: Engineering Services
Schedule,
Budget), Construction, Lead: Engineering Services
Lead: Capital
Delivery
Division Closeout, Lead: Capital Delivery Division

Operationalize, Lead: MO (Asset) & OSIP (Perf. Improvement)

Portlandoregon.gov/transportation 11
STAGE 1: Planning GATE
• Approved Policy Scan
LEAD: Transportation Planning Division • Project Concept & Alternative
• Approved Project Development Funding
Purpose: Define project’s purpose, need, public & Staffing Resource Plan
involvement, and relation to the Transportation
Systems Plan (TSP) and/or adopted plan.

1. Conduct policy scan within PBOT 6. Refine project scope and affirm goals,
needs, and criteria
2. Engage and begin coordination with other
bureaus to identify leverage opportunities 7. Define solution(s) and complete evaluating
alternatives (includes identifying and
3. Request and identify multi-disciplinary team assessing alternatives, feasibility, planning-
level cost estimates, and trade-offs)
4. Develop the public involvement plan (e.g.,
external stakeholders identified and 8. Reach consensus on preferred concept,
engagement level defined) estimate, and alternative

5. Conduct the public involvement plan 9. Formal approval of concept and alternative
(ongoing) (ex., approval of pre-charter/definition
checklist or council approval)
GATE
STAGE 2: Project Development • Approved Project Definition
LEAD: Transportation Planning Division • Approved Engineer’s Estimate Report
• Approved Design & Construction Funding
Purpose: Finalize project scope, schedule, and and Staffing Resource Plans
budget and approve the Project Charter.*

1. Identify capital project manager and multi- 6. Confirm proposed scope, schedule, and
disciplinary team budget meets stated objective and policy
goals
2. Refine public involvement plan and continue
public involvement as necessary 7. Develop engineer’s estimate report (e.g.,
order of magnitude)
3. Define performance metrics aligned with PBOT
strategic plan when the project is operationalized 8. Identify other closely related projects and
continue coordination
4. Define project encouragement strategy
9. Develop Design & Construction Funding and
5. Conduct preliminary engineering (e.g., develop Staffing Resource Plans
typical section concept, coordinated with traffic
analysis)

*E-Builder will auto-generate the Project Charter with content from the approved Project Definition Checklist.
GATE
STAGE 3: Engineering & Design • Change Management Summary
LEAD: Engineering Services • Bid Book (100% Plans, Specs, & Estimate,
including all required reports and permits)
• ROW Certification
Purpose: Finalize Plans, Specifications, & • Approved Construction Funding
Estimate (PS&E) and project funding and be • Council Ordinance for Authority to Bid
construction ready. • Council Ordinance to Award
• Signed Construction Contract
1. Confirm project management, engineering, and design 9. Obtain required permits & other regulatory approvals
team members
10. Complete ROW process and certification for federally
2. Review and confirm approved Project Charter (e.g., funded projects
review goals, scope, schedule, budget, environmental
assessment needs and permit requirements, risk 11. Complete change management summary
assessment, and identification of cost drivers)
12. Prepare bid package and council docs
3. Continue public engagement and notifications
13. Obtain Authority to Bid
4. Complete survey
14. Submit to Procurement
5. Conduct appropriate level environment impact
assessment based on the project type 15. Complete bid analysis & issue recommendation to
award
6. Design engineering (30% - 60% - 95% - Final)
16. Transmit necessary plans and design files to Survey
7. Finalize project funding
17. Obtain Council approval of Bid Award
8. Conduct outreach and notification to utilities and
partner agencies
STAGE 4: Construction GATE
• Certification of Substantial Completion
LEAD: Engineering Services Issued
Purpose: Construct the project per the
PS&E.
1. Hold transition meeting between Design Team 8. Perform inspections in the field (ongoing)
(PM / EOR / CM) and Construction Team
9. Generate progress payments from inspection
2. Establish construction management roles and reports
responsibilities
10. Document and retain all approved change-
3. Review and approve the contractor-required related documentation
submittals according to City of Portland standard
Construction Specifications 11. Review and approve additional required
contractor submittals
4. Hold Pre-Con meeting
12. Complete final reconciliation of quantities
5. Issue Notice to Proceed
13. Reach consensus on substantial completion;
6. Continue public engagement and notification of issue punch list
upcoming construction activities

7. Start project-specific encouragement work for the


promotion of new assets
STAGE 5: Closeout GATE
• As-Builts Completed and Mapped
LEAD: Capital Delivery Division • Final Project Memo
• Final Financial Accounting Closeout
Purpose: Closeout construction activities and Package to Procurement
complete project documentation.

1. Ensure all Quality and Quantity 6. Complete closeout package for


documentation is on file as established by procurement and notify accounting for
the PBOT Quality Control Plan capitalization purposes

2. Request and receive external agency 7. Complete as-builts, asset mapping, and
approval as needed (ODOT requirement) archiving

3. Complete punch list inspection and issue 8. Continue project-based encouragement


resolution
9. Complete Final Project Memo
4. Receive documentation from contractor
(i.e., ARC, CMOs, warranties) 10. Complete new asset transfer to
maintenance (e.g., deliver Final Project
5. Issue Certificate of Completion Report & as-builts to MO)

11. Complete final accounting


STAGE 6: Operationalize GATE
• Performance Evaluation
LEADS: MO & OSIP • Documentation for Ongoing
Maintenance Activities and Investments
Purpose: Complete warranty period, complete
knowledge transfer, and conduct performance
evaluation.

1. Complete warranty inspection and plant 5. Mitigation of unanticipated project impacts


establishment
6. Complete project performance evaluation
2. Ensure contractor resolves identified
warranty and mitigation of deficiencies 7. Incorporate findings into ongoing project
issues planning activities

3. Release warranty bond 8. Inform appropriate ongoing maintenance


activities and investments
4. Collect post-project data identified in Data
Collection Strategy
Gate Review Process
The initial review process will be managed in e-Builder and vetted by the
following reviewers. The Controls Team will also be involved in reviewing
and ensuring compliance with PBOT’s delivery standards

Stage Gate Gate Keepers


Project Development PPP Division Managers
Engineering & Design Engineering Services Managers
Construction Engineering Services Managers
Closeout Capital Delivery Division Manager
Operationalize Multiple Division Managers (PPP,
MO, and Business Services)

Portlandoregon.gov/transportation 18
Roles & Responsibilities

Portlandoregon.gov/transportation 19
SPIRAL: The new RACI

The Task Force modified


the existing engineering
roles & responsibility
model by adding a
“Supportive” role

They also identified lead


& support tasks for each
primary role (planner,
project manager,
supervising engineer,
and construction
manager)

Portlandoregon.gov/transportation 20
Bolded & Boxed = Lead Person Red-Boxed = Gate Owner
Planner – Roles & Responsibilities Bolded = Supports or Provides Input

Project Engineering &


Planning Development Design Construction Closeout Operationalize
• Conduct policy scan • Identify capital project • Confirm PM, • Hold internal transition • File all Quality & • Complete warranty
• Engage and begin manager and multi- engineering, & design meeting Quantity inspection & plant
coordination with other disciplinary team team members • Establish construction documentation establishment
bureaus to identify • Refine PIP and continue • Review & confirm management roles and • Request & receive • Ensure contractor
leverage opportunities public involvement as approved Project responsibilities external agency resolves identified
• Request multi- necessary Charter • Review and approve approval warranty and
disciplinary team • Define performance • Continue public
the contractor-required • Complete punch list mitigation of
• Develop initial Public metrics engagement and
submittals inspection & issue deficiencies issues
Involvement Plan (PIP) • Define project notifications
• Conduct the PIP • Complete survey • Hold pre-con meeting resolution • Release warranty
encouragement strategy
• Refine project scope • Conduct environment • Issue Notice to Proceed • Receive contractor bond
• Conduct preliminary
and affirm goals, needs, impact assessment (NTP) documentation • Collect post-project
engineering
and criteria • Confirm proposed • Design engineering (30% • Continue PIP and notify • Issue Certification of data identified in
• Define solution(s) & scope, schedule, and - 60% - 95% - Final) impacted public Completion Data Collection
complete evaluating budget meets stated • Finalize project funding • Start project-specific • Complete closeout Strategy
alternatives objective and policy • Conduct outreach and encouragement work package & notify • Mitigation of
• Reach consensus on goals notification to utilities Perform field accounting unanticipated project
preferred concept, • Develop engineer’s and partner agencies inspections • Complete as-builts, impacts
estimate and alternative estimate report • Obtain required permits • Generate progress asset mapping, & • Complete
• Formal approval of • Identify other closely & other regulatory payments archiving performance
concept and alternative related projects and approvals • Document & retain • Continue project- evaluation
continue coordination • Complete ROW process specific
change-related • Incorporate findings
• Develop Design & and certification encouragement work
documentation into ongoing planning
Construction Funding • Prepare Change • Complete Final Project
• Review & approve activities
and Staffing Resource Management Summary
required contractor Memo • Inform appropriate
Plans • Complete council
submittals • Complete new asset ongoing maintenance
approval & procurement
processes • Reach substantial transfer to activities and
• Transmit necessary completion; issue maintenance investments
plans & design files to punch list • Complete final
Survey accounting

GATE DELIVERABLES
• Policy Scan • Project Definition • Change Mgmt. Summary • Certification of • As-Builts Completed & • Performance Evaluation
• Concept Plan / Project • Engineer’s Estimate • Bid Book Substantial Mapped Documentation
Summary Report • ROW Certification Completion Issued • Final Project Memo • Documentation for
• Project Dev Funding & • Approved Design & • Approved Construction • Final Financial Accounting Ongoing Maintenance
Staffing Resource Plan Construction Funding and Funding Closeout Package to Activities and
Staffing Resource Plans • Council Ordinances Procurement Investments
• Signed Construction
Contract
Bolded & Boxed = Lead Person Red-Boxed = Gate Owner
Project Manager – Roles & Responsibilities Bolded = Supports or Provides Input

Project Engineering &


Planning Development Design Construction Closeout Operationalize
• Conduct policy scan • Identify capital project • Confirm PM, • Hold internal transition • File all Quality & • Complete warranty
• Engage and begin manager and multi- engineering, & design meeting Quantity inspection & plant
coordination with other disciplinary team team members • Establish construction documentation establishment
bureaus to identify • Refine PIP and continue • Review & confirm management roles and • Request & receive • Ensure contractor
leverage opportunities public involvement as approved Project responsibilities external agency resolves identified
• Request and identify necessary Charter • Review and approve approval warranty and
multi-disciplinary team • Define performance • Continue public
the contractor-required • Complete punch list mitigation of
• Develop initial Public metrics engagement and
submittals inspection & issue deficiencies issues
Involvement Plan (PIP) • Define project notifications
• Conduct the PIP encouragement strategy • Complete survey • Hold pre-con meeting resolution • Release warranty
• Refine project scope • Conduct preliminary • Conduct environment • Issue Notice to Proceed • Receive contractor bond
and affirm goals, needs, engineering impact assessment (NTP) documentation • Collect post-project
and criteria • Confirm proposed • Design engineering (30% • Continue PIP and notify • Issue Certification of data identified in
• Define solution(s) & scope, schedule, and - 60% - 95% - Final) impacted public Completion Data Collection
complete evaluating budget meets stated • Finalize project funding • Start project-specific • Complete closeout Strategy
alternatives objective and policy • Conduct outreach and encouragement work package & notify • Mitigation of
• Reach consensus on goals notification to utilities • Perform field accounting unanticipated project
preferred concept, • Develop engineer’s and partner agencies inspections • Complete as-builts, impacts
estimate and estimate report • Obtain required permits • Generate progress asset mapping, & • Complete
alternative • Identify other closely & other regulatory payments archiving performance
• Formal approval of related projects and approvals • Document & retain • Continue project- evaluation
concept and alternative continue coordination • Complete ROW process specific
change-related • Incorporate findings
• Develop Design & and certification encouragement work
documentation into ongoing planning
Construction Funding • Prepare Change • Complete Final Project
• Review & approve activities
and Staffing Resource Management Summary
required contractor Memo • Inform appropriate
Plans • Complete council
submittals • Complete new asset ongoing maintenance
approval & procurement
processes • Reach substantial transfer to activities and
• Transmit necessary completion; issue maintenance investments
plans & design files to punch list • Complete final
Survey accounting

GATE DELIVERABLES
• Policy Scan • Project Definition • Change Mgmt. Summary • Certification of • As-Builts Completed & • Performance Evaluation
• Concept Plan / Project • Engineer’s Estimate • Bid Book Substantial Mapped Documentation
Summary Report • ROW Certification Completion Issued • Final Project Memo • Documentation for
• Project Dev Funding & • Approved Design & • Approved Construction • Final Financial Accounting Ongoing Maintenance
Staffing Resource Plan Construction Funding and Funding Closeout Package to Activities and
Staffing Resource Plans • Council Ordinances Procurement Investments
• Signed Construction
Contract
Bolded & Boxed = Lead Person Red-Boxed = Gate Owner
Supervising Engineer – Roles & Responsibilities Bolded = Supports or Provides Input

Project Engineering &


Planning Development Design Construction Closeout Operationalize
• Conduct policy scan • Identify capital project • Confirm PM, • Hold internal transition • File all Quality & • Complete warranty
• Engage and begin manager and multi- engineering, & design meeting Quantity inspection & plant
coordination with other disciplinary team team members • Establish construction documentation establishment
bureaus to identify • Refine PIP and continue • Review & confirm management roles and • Request & receive • Ensure contractor
leverage opportunities public involvement as approved Project responsibilities external agency resolves identified
• Request and identify necessary Charter • Review and approve approval warranty and
multi-disciplinary team • Define performance • Continue public
the contractor-required • Complete punch list mitigation of
• Develop initial Public metrics engagement and
submittals inspection & issue deficiencies issues
Involvement Plan (PIP) • Define project notifications
• Conduct the PIP encouragement • Complete survey • Hold pre-con meeting resolution • Release warranty
• Refine project scope strategy • Conduct environment • Issue Notice to Proceed • Receive contractor bond
and affirm goals, needs, • Conduct preliminary impact assessment (NTP) documentation • Collect post-project
and criteria engineering • Design engineering (30% • Continue PIP and notify • Issue Certification of data identified in
• Define solution(s) & • Confirm proposed - 60% - 95% - Final) impacted public Completion Data Collection
complete evaluating scope, schedule, and • Finalize project funding • Start project-specific • Complete closeout Strategy
alternatives budget meets stated • Conduct outreach and encouragement work package & notify • Mitigation of
• Reach consensus on objective and policy notification to utilities Perform field accounting unanticipated project
preferred concept, goals and partner agencies inspections • Complete as-builts, impacts
estimate and alternative • Develop engineer’s • Obtain required permits • Generate progress asset mapping, & • Complete
• Formal approval of estimate report & other regulatory payments archiving performance
concept and alternative • Identify other closely approvals • Document & retain • Continue project- evaluation
related projects and • Complete ROW process specific
change-related • Incorporate findings
continue coordination and certification encouragement work
documentation into ongoing planning
• Develop Design & • Prepare Change • Complete Final Project
• Review & approve activities
Construction Funding Management Summary
required contractor Memo • Inform appropriate
and Staffing Resource • Complete council
submittals • Complete new asset ongoing maintenance
Plans approval & procurement
processes • Reach substantial transfer to activities and
• Transmit necessary plans completion; issue maintenance investments
& design files to Survey punch list • Complete final
accounting

GATE DELIVERABLES
• Policy Scan • Project Definition • Change Mgmt. Summary • Certification of • As-Builts Completed & • Performance Evaluation
• Concept Plan / Project • Engineer’s Estimate • Bid Book Substantial Mapped Documentation
Summary Report • ROW Certification Completion Issued • Final Project Memo • Documentation for
• Project Dev Funding & • Approved Design & • Approved Construction • Final Financial Accounting Ongoing Maintenance
Staffing Resource Plan Construction Funding and Funding Closeout Package to Activities and
Staffing Resource Plans • Council Ordinances Procurement Investments
• Signed Construction
Contract
Construction Manager – Roles & Responsibilities Bolded & Boxed = Lead Person
Bolded = Supports or Provides Input
Red-Boxed = Gate Owner

Project Engineering &


Planning Development Design Construction Closeout Operationalize
• Conduct policy scan • Identify capital project • Confirm PM, • Hold internal transition • File all Quality & • Complete warranty
• Engage and begin manager and multi- engineering, & design meeting Quantity inspection & plant
coordination with other disciplinary team team members • Establish construction documentation establishment
bureaus to identify • Refine PIP and continue • Review & confirm management roles and • Request & receive • Ensure contractor
leverage opportunities public involvement as approved Project responsibilities external agency resolves identified
• Request and identify necessary Charter • Review and approve the approval warranty and
multi-disciplinary team • Define performance • Continue public
contractor-required • Complete punch list mitigation of
resources metrics engagement and
submittals inspection & issue deficiencies issues
• Develop initial Public • Define project notifications
Involvement Plan (PIP) encouragement • Complete survey • Hold pre-con meeting resolution • Release warranty
• Conduct the PIP strategy • Conduct environment • Issue Notice to Proceed • Receive contractor bond
• Refine project scope • Conduct preliminary impact assessment (NTP) documentation • Collect post-project
and affirm goals, needs, engineering • Design engineering (30% • Continue PIP and notify • Issue Certification of data identified in
and criteria • Confirm proposed - 60% - 95% - Final) impacted public Completion Data Collection
• Define solution(s) & scope, schedule, and • Finalize project funding • Start project-specific • Complete closeout Strategy
complete evaluating budget meets stated • Conduct outreach and encouragement work package & notify • Mitigation of
alternatives objective and policy notification to utilities Perform field accounting unanticipated project
• Reach consensus on goals and partner agencies inspections • Complete as-builts, impacts
preferred concept, • Develop engineer’s • Obtain required permits • Generate progress asset mapping, & • Complete
estimate and estimate report & other regulatory payments archiving performance
alternative • Identify other closely approvals • Document & retain • Continue project- evaluation
• Formal approval of related projects and • Complete ROW process specific
change-related • Incorporate findings
concept and alternative continue coordination and certification encouragement work
documentation into ongoing planning
• Develop Design & • Prepare Change • Complete Final Project
• Review & approve activities
Construction Funding Management Summary
required contractor Memo • Inform appropriate
and Staffing Resource • Complete council
submittals • Complete new asset ongoing maintenance
Plans approval & procurement
processes • Reach substantial transfer to activities and
• Transmit necessary completion; issue punch maintenance investments
plans & design files to list • Complete final
Survey accounting

GATE DELIVERABLES
• Policy Scan • Project Definition • Change Mgmt. Summary • Certification of • As-Builts Completed & • Performance Evaluation
• Concept Plan / Project • Engineer’s Estimate • Bid Book Substantial Mapped Documentation
Summary Report • ROW Certification Completion Issued • Final Project Memo • Documentation for
• Project Dev Funding & • Approved Design & • Approved Construction • Final Financial Accounting Ongoing Maintenance
Staffing Resource Plan Construction Funding and Funding Closeout Package to Activities and
Staffing Resource Plans • Council Ordinances Procurement Investments
• Signed Construction
Contract
Capital Controls Team
Support & Oversight

Portlandoregon.gov/transportation 25
Capital Controls Team and Support
Support staff with business functions Standard Change Management Process

Help with Performance


Management Tracking Data gathering, analytics and
reporting

Project Controls is the gathering of data, management of the data and the processes used to predict,
understand and influence the time and cost outcomes of a project or program in a constructive manner. This
happens through the communication of information in formats that assist effective management and decision
making.

What do we do?
• Here to help guide project staff through the stages and gates process and deliverables
• Enforce standards for overall processes and documentation
• Identify areas to be highlighted within the standard project delivery process for improvement
• Provide a place for staff feedback to inform process improvement
• Help create reports and dashboards to facilitate the use of project delivery data

Portlandoregon.gov/transportation 26
Reminder: Scope, Schedule, Budget Change (SSBC) Requests

Starting now, all


SSBCs need to
be formally
submitted in e-
Builder. In mid-
June, the
Controls
Committee will
begin to review
the SSBC
Dashboard
biweekly.

Portlandoregon.gov/transportation 27
What’s Next?

Portlandoregon.gov/transportation 28
Next Steps: Jump In!
Summer ‘19: Winter ‘20: Review
Complete Initial Rollout
Provide Feedback & Support Materials &
by June 10th
Refine Processes Participate in Retro

Know the stages Participate in Review the initial


Learn your role feedback surveys project delivery
Check out e-Builder Review e-Builder manual & supporting
to: communications to reference materials
• Review your learn about Participate in the
projects’ current improvements retrospective to
stages Attend the update at share findings,
• Review the current the CIP Budget Kick- showcase
gate deliverable off improvements, and
templates identify next set of
Submit SSBC improvements
Requests in e-Builder

Portlandoregon.gov/transportation 29
Where to go for help

Group / Division Capital Controls & e-Builder


PPP Controls Team
Kristin Hull PBOT.e-builder@portlandoregon.gov
kristin.hull@portlandoregon.gov Alicia Gruber, Controls Manager
Millicent Williams Aaron Kaufman, Analyst
millicent.williams@portlandoregon.gov
How to access e-Builder: Send an email to the
Engineering Services address above! The Controls Team will set up
Eva Huntsinger your account & can also provide training
eva.Huntsinger@portlandoregon.gov www.e-builder.net
Todd Liles
todd.liles@portlandoregon.gov
Jason Shepard
jason.shepard@portlandoregon.gov

Portlandoregon.gov/transportation 30
Capital Project Delivery
STAGES & GATES
Project Engineering &
Planning Development Design Construction Closeout Operationalize
Define project’s Finalize project Finalize Plans, Construct the Closeout Complete
purpose, need, scope, schedule, Specifications, & project per the construction warranty
public and budget and Estimate (PS&E) PS&E activities and period,
involvement, approve the and project complete complete
and relation to Project Charter funding and be project knowledge
the TSP and/or construction documentation transfer, and
adopted plan ready
conduct
performance
evaluation

GATE DELIVERABLES
• Policy Scan • Project • Change • Certification of • Closeout package • Performance
• Concept Plan / Definition Management Substantial • As-Builts Evaluation
Project Engineer’s Summary Completion Completed & Documentation
Summary Estimate Report • Bid Book Issued Mapped • Documentation
• Project Dev • Design & • ROW • Final Project for Ongoing
Funding & Construction Certification Memo Maintenance
Staffing Funding and • Approved
• Final Financial Activities and
Resource Plan Staffing Construction
Accounting Investments
Resource Plans Funding
• Council Closeout Package
Ordinances
• Signed
Construction
Contract