Safety Checklist

OIL RIGS

Site: -------------
Project: -------------
Date: -------------
Team Member: -------------

PPE & GENERAL Regularly scheduled meetings of the crew


SAFETY
Weekly safety meeting

Pre-Job safety meeting held

Safety equipment available

The crew wears proper clothing

Hard hats used by the crew

Safety gloves used by the crew

Eye protection used by the crew (if it is essential.)

Hard toed shoes used by the crew

Fall protection used when required

Respiratory protection used when required

Hearing protection used when required

No Smoking rules observed

First Aid Kit are available on site

Communications equipment work correctly

Critical Equipment periodically inspected & tested

Page:01/10
source: OSHA
Safety Checklist
OIL RIGS

Site: -------------
Project: -------------
Date: -------------
Team Member: -------------

PPE & GENERAL Smoking or open flames not permitted within 20 ft


SAFETY of compressed gases are used or stored

Flammable liquids not stored within 50 ft of


wellbore

Adequate lighting installed

COMMENTS:

Page:02/10
source: OSHA
Safety Checklist
OIL RIGS

Site: -------------
Project: -------------
Date: -------------
Team Member: -------------

MATERIAL Material Handling Equipment


HANDLING (forklift/Winch/Mobile crane) operators trained
EQUIPMENT and certified.

Correct type of Fork Lift, etc in use for the location

Equipment inspected prior to use (daily)

Equipment stability during movement or lifting

COMMENTS:

Page:03/10
source: OSHA
Safety Checklist
OIL RIGS

Site: -------------
Project: -------------
Date: -------------
Team Member: -------------

FIRE Adequate number of fire extinguishers available


PROTECTION
Fire extinguishers properly charged

Fire extinguishers with equipped with gauges

Fire extinguishers properly located and in/at their


assigned locations.

Flare lines should be as long as practical and


straight as possible and securely anchored.

Flare area, if present, is clear of combustibles

Flare Lines & Flare Stack location based on


prevailing wind direction.

Welding work performed safely

Engines within 100 feet of the well have spark and


heat arrester, or water, on all engine exhausts

All engines located approx 100 ft from the well or


gas source, if possible

COMMENTS:

Page:04/10
source: OSHA
Safety Checklist
OIL RIGS

Site: -------------
Project: -------------
Date: -------------
Team Member: -------------

PIPE RACK Ends of pipe racks properly chocked


AREA
Spacers used to separate layers of pipe

Layers of pipe properly chocked

Pipe rack catwalk in good condition

Stairs with handrails provided

V-door slide in good condition

Pipe stops used on V-door slide in good condition

Pipe tubs and bridles in good condition

Derrick stand and ladder in good condition

Dead end of drilling line anchored

Employees not permitted on top of pipe

Adequate lighting provided

Approved lighting installed

General housekeeping

COMMENTS:

Page:05/10
source: OSHA
Safety Checklist
OIL RIGS

Site: -------------
Project: -------------
Date: -------------
Team Member: -------------

DERRICK & Derrick/A-Frame assembly pins in place


SUBSTRUCTURE
Assembly pins secured with keepers

Substructure assembly pins in place

Substructure assembly pins secured with keepers

Fall lane of derrick clear

Condition of derrick ladder

Climb assist device available

Climb assist device used by derrickman.

Climb assist device in good condition

Full body harness with lanyard available

Full body harness w/ lanyard in good condition

Fall protection devices in use

Derrick/Tubing boards in good condition

Guardrails installed on outside of derrick board

Pipe fingers in good condition

Finger board in good condition

Page:06/10
source: OSHA
Safety Checklist
OIL RIGS

Site: -------------
Project: -------------
Date: -------------
Team Member: -------------

DERRICK & Derrick board walk around platform in good


SUBSTRUCTURE condition, if available

Latch dog visually inspected prior to loading


derrick

Finger board safety cable attached

Derrick hydraulic system free of leaks

Booms and boom lines in good condition

Adequate lighting provided

Approved lighting for the location installed

Derrick emergency escape line installed

Rotary beams and all braces are in good condition

COMMENTS:

Page:07/10
source: OSHA
Safety Checklist
OIL RIGS

Site: -------------
Project: -------------
Date: -------------
Team Member: -------------

DRILL FLOOR Rotary/rig floor level and in good condition


AREA
Kelly bushing guard used

Controls adequate if guard not used

Rotary chain drive guarded

All unused floor holes covered

Drawworks operator at or near controls while in


operation

Pipe slips & Dies in good condition

Racking floor area in good condition

V-door gate or chain provided and in place

Air/hydraulic hoist line in good condition


□ near driller □ opposite driller

Air/hydraulic hoist line properly guarded


□ near driller □ opposite driller

Spinning chain in good condition

Handling winch & tail chain grade 8 & tagged

Overrunning clutch in good condition

Page:08/10
source: OSHA
Safety Checklist
OIL RIGS

Site: -------------
Project: -------------
Date: -------------
Team Member: -------------

DRILL FLOOR Adequate lighting provided


AREA
General housekeeping

Minimum 2 exits from drill floor doghouse

Drill floor doghouse doors installed properly

First aid kit available in drill floor doghouse

The rig floor is in a orderly manner and free of


objects that could cause slipping or tripping
hazards or hinder rapid egress.

Guardrails installed along open edges of drill floor

COMMENTS:

Page:09/10
source: OSHA
Safety Checklist
OIL RIGS

Site: -------------
Project: -------------
Date: -------------
Team Member: -------------

HAND TOOLS Makeup and breakout tongs in good condition

Tong body & jaws in good condition

Tong safety handle pins secured

Tong die keeper used

Tong snubbing lines in good condition

Tong snubbing line clamps in good condition

Tong vertical support line clamps in good


condition

Tong positioner in good condition

Tong motion controlled

Condition of tong jerk line(s)

Cleanliness of hand tools

Plugs of electrical extension cords in good


condition

COMMENTS:

Page:10/10
source: OSHA