1. AON network is shown below. The number of errors/incompatibilities in this Situation. The optimistic time, most likely time and pessimistic time is shown in
network is. the PERT network below.
a. 1 b. 2 c. 3 d. 4
10. if event B-C was finished at normal condition, solve for the completion of
the project in days.
a. 17.83 b. 18.67 c. 17 d. 21
2. Find the total float for activity 2-4 in the network shown. 11. Determine the minimum duration of the project.
a. 3 b. 2 c. 1 d. 0 a. 14 b. 17 c. 17.83 d. 18.67
12. What is the probability that the project will be completed on schedule.
a. 67.5% b. 60.5% c. 50% d. 79.7%
ans. 32.54%
4. which of the following gives the required weight of the gravel in kg.
a. 26,800 b. 28,500 c. 22,400 d. 32,500
Situation. The following are the activities for the construction of a residential
house, giving the nodes of the Network Diagram/CPM, time duration and cost
(in pesos) for a normal and an accelerated program:
7. Determine the activity that is the most cost effective in converting to the
accelerated program.
a. A b. H c. B d. J
8. If the budget for the project is 103,700. Compute the reduction in the number
of days to complete the project compared to the normal program.
a. 6 b. 3 c. 4 d. 5