Professional Documents
Culture Documents
FOR
At
APPLICANT CONSULTANT
Punjab Chemicals and Crop
Eco Chem Sales & Services
Protection Ltd
Village: Kolimajra & Samalheri, Office Floor, Ashoka Pavilion - A
P.O. Lalru, Tehsil.: Dera Bassi, New Civil Road, Surat, 395001
Dist.: SAS Nagar Punjab - 140501. NABET/EIA/1720/RA 051
E-Mail: pharmainfo@punjabchemicals.com E-mail: eco@ecoshripad.com
Tel No.: +91 -1762-275210 / 506998 Tel No. +91 261 2231630
Prefeasibility Report M/s Punjab Chemical and Crop Protection Ltd.
Contents
1.0 EXECUTIVE SUMMARY ....................................................................................................... 1
2.0 INTRODUCTION OF PROPOSED PROJECT AND THE PROPONENT .............................. 3
2.1 Project Proponent.............................................................................................................. 3
2.2 Nature of the project .......................................................................................................... 3
2.3 Need of the Project............................................................................................................ 3
3.0 PROJECT DESCRIPTION .................................................................................................... 5
3.1 Type of Project .................................................................................................................. 5
3.2 Location of Project............................................................................................................. 5
3.3 Details of alternate sites considered .................................................................................. 8
3.4 Size or magnitude of operation .......................................................................................... 8
3.5 Product Description ........................................................................................................... 8
3.6 Resource Requirement.................................................................................................... 26
3.7 Quantity of waste to be generated and disposal .............................................................. 29
4.0 SITE ANALYSIS ................................................................................................................. 33
4.1 Connectivity..................................................................................................................... 33
4.2 Land Form, Land use and Land ownership...................................................................... 33
4.3 Topography ..................................................................................................................... 34
4.4 Existing Infrastructure ...................................................................................................... 34
4.5 Soil classification ............................................................................................................. 35
4.6 Climate data from secondary sources ............................................................................. 35
5.0 PLANNING BRIEF .............................................................................................................. 35
5.1 Planning Concept ............................................................................................................ 35
5.2 Land use Planning........................................................................................................... 35
5.3 Amenities/ Facilities ......................................................................................................... 36
6.0 PROPOSED INFRASTRUCTURE ...................................................................................... 36
8.1 Project Schedule ............................................................................................................. 37
8.2 Cost Estimation ............................................................................................................... 37
9.1 Financial and social benefits ........................................................................................... 38
Prefeasibility Report M/s Punjab Chemical and Crop Protection Ltd.
List of Tables
Table 1.1: Summary of the proposed project ................................................................................ 1
Table 3.1: List of products ................................................................................................................ 8
Table 3.2 Raw Material requirement............................................................................................. 26
Table 3.3 Land Use Break up of project Site .............................................................................. 27
Table 3.4: Water Consumption ...................................................................................................... 28
Table 3.2 Water consumption and waste water generation ...................................................... 29
Table 3.3 Flue gas Emission .......................................................................................................... 31
Table 3.4 Process Gas Emission .................................................................................................. 31
Table 3.5 Solid & Hazardous waste generation .......................................................................... 32
Table 4.1 Environmental Sensitivity near the project site ......................................................... 33
Table 8.1 Capital Cost Projection.................................................................................................. 37
Table 8.2 Cost of Environment Management System ............................................................... 37
Prefeasibility Report M/s Punjab Chemical and Crop Protection Ltd.
List of Figures
Figure 3.1: Google Image of Project site.............................................................................. 5
Figure 3.2: Study area Map ................................................................................................. 6
Figure 3.3: Project site Layout ............................................................................................. 7
Figure 3.4 Water Balance Diagram .................................................................................... 28
Prefeasibility Report M/s Punjab Chemical and Crop Protection Ltd.
As per the amended EIA notification-2006: proposed products are covered under the Schedule -
5(b) category- A (Pesticides industry and pesticide specific intermediates (excluding
formulations). Hence, Environmental clearance is required.
The pre-feasibility report includes a brief introduction of the company, need and justification of the
project, manufacturing process description, required and available resources, proposed
Environment Management Systems, land-use and proposed infrastructure, project schedule and
cost. Summary of the proposed project is mentioned in Table 1.1 below:
The solid, liquid and gaseous wastes from the proposed plant will be disposed-off in an
environmentally acceptable manner. Process effluents will be properly treated in adequate effluent
treatment plant and treated waste will be also send to TSDF site for further disposal.
Proper precaution will be taken and adequate green belt will be developed to keep noise level
within prescribed limit. Adequate measure has been contemplated to ensure least pollution from
the proposed project.
2.0 INTRODUCTION OF PROPOSED PROJECT AND THE PROPONENT
2.1 Project Proponent
Started in 1975 as Punjab United Pesticides & Chemicals Limited (PUPCL) has now evolved as
Punjab Chemicals and Crop Protection Limited uniting all its divisions – Agro-technical,
Pharmaceuticals, Intermediates, Chemicals & International Trading, under one roof, by a
combination of all companies into Punjab Chemicals in March 2006.
Presently, Punjab Chemicals has various state-of-the-art manufacturing sites which are located
across India and have international standards with support from its R&D strengths and
unparalleled Pilot Plant facilities, All are ISO 9001 & ISO 14001 certified. Punjab Chemicals
produces various Agro-technical, API’s, Pharmaceutical Intermediates, Phosphorous Derivatives
and Speciality Chemicals.
The overseas subsidiary- marketing company SD Ag chem (Europe), N.V., Belgium serves as
immediate supply for company products from the doorstep of Europe. Punjab Chemicals having
the ownership of the marketing registrations with the above companies is an added advantage.
List of Directors
Chairman Emeritus Ghattu Ramanna Narayan
Chairman Mukesh Dahyabhai Patel
Board Of Directors -Shalil Shashikumar Shroff, Managing Director
-Capt. Surjit Singh Chopra (Retd.)
-Vijay Dilbagh Rai
-Sheo Prasad Singh
-Aruna R Bhinge (Smt.)
-Shivshankar Shripal Tiwari
-Avtar Singh, Director (Operations & Business
Development)
Sr. V.P. (Finance) & Company Punit Kumar Abrol
Secretary
Indian Pesticides is one of the rapidly growing markets and has emerged a strong export
oriented business. Out of the present business of 180 Billion markets, the export accounts 100
billion and is steadily growing at a rate of 6.7%. This is 2.5 times more than the world market.
With the introduction of genetically modified crops in India, the consumption of Insecticides
decreased marginally. But the other sectors such as weedicides & herbicides, fungicides etc. are
rapidly growing. Punjab Chemical is focuses on the sectors of Fungicides and herbicides and
strong in export of these group molecules.
Company is always focusing on manufacturing all products locally with backward integration so
that Country will get benefits like Growth, employment, infrastructure etc. Punjab Chemical R &
D team is constantly engaged in identifying & evaluating new molecules. After a very careful
scrutiny of the developments of R & D, the company is ready to launch new intermediates as
well as several new pesticides. Company is importing only such products for which, either the
technology is not available in India or, the manufacturing cost is higher than the import cost.
With more than 50% of its raw materials being import products, coming mainly from China,
Europe & Asian sub-continent.
Proposed products manufacturing in the country will be very much economical compare to
Imports of the same and also the export of the same will earn extra revenue generation for our
county.
No alternative site study has been carried out as project will be developed adjacent to
existing agrochemical unit of Punjab Chemicals.
The land for the proposed project is already in the possession of Punjab Chemicals
as the proposed project will be developed adjacent to existing agrochemical unit.
All the infrastructure facilities are available with the existing unit of Punjab
Chemicals.
The project site has all the facility such as RCC road, water supply, effluent
disposal line, power supply, Fire and Safety Services.
The project is very well connected to National Highway no. 152 and Northern
Railways
Easy availability of infrastructure facilities.
No prime agricultural land / forest land needed to be converted for industrial use.
There is enough extra land to raise required green belt / green cover.
Area where proposed site is to be located has no history of natural calamities like
floods, cloud burst etc.
Proximity to raw material suppliers.
The human resource required for the proposed project will be easily available.
In addition to the above, the following factors within the study area have also been
considered:
There is no National Park or Wild Life Sanctuary.
There are no metropolitan cities.
There are no ecologically sensitive areas.
The company is using the latest available process technology for the production. The
manufacturing process of the product, chemical reactions, and material mass balance &
mole balance for the product are given below:
1. AZOXYSTROBIN
Chemical Reaction:
Mass Balance
MATERIAL BALANCE OF AZOXYSTROBIN
Azoxystrobin 1000
1 Chloroform 928
5 TMOF 695
8153 8153
EFFLUENT TREATMENT
26 Pot. Carbonate 565 Salt recovered after fileration 601 Land Fill
28 Methanol for Crystallization 560 Organic resudue from all recovery units 1230.5 To Incinerator
Chemical Reaction:
Material Balance:
Process:
Step-II
Methylene Aminoacetonitrile was further reacted with Sulphuric acid and methanol –water
mixture to got Amino Acetonitrile Sulphate (AANS) and by product Dimethoxy methane, ppt
product isolated by filtration. Wet product dry and packed into LDPE-HDPE bags.
Chemical Reaction:
Process:
Potassium ethyl Xanthate can be prepared by the reaction of ethanol with potassium
hydroxide and carbon disulfide.
Chemical Reaction:
Mass balance:
Sodium Isopropyl Xanthate
Process:
Sodium isopropyl Xanthate is produced by the reaction of an Iso Propyl alcohol with sodium
hydroxide and carbon disulfide.
Chemical Reaction:
Mass balance:
Potassium Isopropyl Xanthate
Process:
Potassium isopropyl Xanthate is produced by the reaction of an Iso Propyl alcohol with
Potassium hydroxide and carbon disulfide.
Chemical Reaction:
Mass balance:
Potassium Amyl Xanthate
Process:
Potassium amyl Xanthateis produced by the reaction of an Amyl alcohol with potassium
hydroxide and carbon disulfide.
Chemical Reaction:
Mass balance:
5. Asulam (Methyl Sulfanilyl Carbamate)
Process:
Raw materials Dimethyl Carbonate, Sodium Methoxide and Sulfanilamide are charged in
the reaction vessel at room temperature. Reaction mass is heated up to reflux temp of 68°C
slowly and is maintained at reflux temperature for some time. After completion of the
reaction, methanol contained in the mass is recovered by steam and vacuum distillation.
Balance mass in the reactor after removal of methanol is transferred to storage tank as
product.
Recovered Methanol along with water is sent for methanol distillation where ethanol is
purified and the waste water is sent for treatment to ETP.
Chemical Reaction:
Process flow diagram:
6. Metobromuron
Process:
Chemical Reaction:
Process flow diagram:
Mass balance:
3.6 Resource Requirement
Various resources like Raw Materials, land, utility, power, fuel, water, manpower etc. will be
utilized for carry out production activities. Simply production is converting resources into
finished product.
3.6.1 Raw material requirement
Raw material will be sourced through local market. The transportation of raw material will
be done by road trough trucks. Detailed raw material requirement along with estimated
quantity are given as below:
Table 3.2 Raw Material requirement
Quantity
# Raw Materials CAS No. Kg/MT of
TPA
Product
Azoxystrobin
1. Choloroform 67-66-3 2227.2 928
2. Sodium Methoxide 124-41-4 3792 1580
3. Acetic anhydride 108-24-7 3964.8 1652
4. 2-Coumaranone 553-86-6 1315.2 548
5. Methanol 67-56-1 1003.2 418
6. Dichlorophenol (4, 6 DCP) 120-83-2 1581.6 659
7. Toluene 108-88-3 415.2 173
8. DMF 68-12-2 151.2 63
9. Acetic acid 64-19-7 43.2 18
10. 2-cynophenol 611-20-1 885.6 369
11. Potassium carbonate 584-08-7 1356 565
12. Caustic lye (47%) 1310-73-2 5234.4 2181
Triazinone
1. Carbon disulphide 75-15-0 1533.6 426
2. Hydrazine Hydrate (80%) 7803-57-8 2646 735
3. 2-chloro ethanol 107-07-3 39.6 11
4. Sodium hydroxide (47%) 1310-73-2 6062.4 1684
5. isoamylene 513-35-9 1681.2 467
6. Formaldehyde (35%) 50-00-0 1976.4 549
7. o-xylene 95-47-6 118.8 33
8. caustic flakes 1310-73-2 3060 850
9. Sulphuric acid 7664-93-9 1983.6 551
10. Hypochlorite (12.5%) 7681-52-9 11260.8 3128
11. chlorine 7782-50-5 2872.8 798
12. HCl (35%) 7647-01-0 6984 1940
Asulam (Methyl Sulfanilyl carbamate)
1. Sulfanilamide 63-74-1 1351.68 704
2. Sodium Methoxide 124-41-4 424.32 221
3. Dimethyl carbonate 616-38-6 706.56 368
Metabromuron
1. Phynil isocyanide 622-44-6 750 500
2. Hydroxylamine sulfate 10039-54 543 362
3. Sodium hydroxide(49%) 1310-73-2 1560 1040
4. toluene 108-88-3 106.5 71
5. Etylene Dichloride (EDC) 107-06-2 45.75 30.5
6. Dimethyl Sulfide (DMS) 75-18-3 787.5 525
7. Bromine 7726-95-6 997.5 665
8. Sodium Bicarbonate 144-55-8 321 214
9. Methanol 67-56-1 121.5 81
AMINO ACETO NITRILE SULPHATE (AANS)
1. Ammonium Chloride 12125-02-
1875 1250
9
2. Formaldehyde 50-00-0 5754 3836
3. Sodium Cyanide 143-33-9 1534.5 1023
4. Sodium Hypochlorite 7681-52-9 3069 2046
5. Conc Sulphuric Acid 1108.5 739
CS2 Based 4-products-Xanthates(Either Individual or total)
1- Potassium Ethyl Xanthate
1. Ethanol 288 288
2. 30% KOH 1170 1170
3. CS2 470 470
2-Sodium Isopropyl Xanthate
1. Iso Propyl Alcohol 380 380
2. 30% NaOH 835 835
3. CS2 476 476
3-Potassium isopropyl Xanthate
1. Iso Propyl Alcohol 172.5 345
2. 30% NaOH 531 1062
3. CS2 216 432
4- Potassium amyl Xanthate
1. Amyl Alcohol 313.92 436
2. 30% NaOH 658.08 914
3. CS2 267.84 372
3.6.2 Land
Punjab chemical has already acquired land of 95448 sq.m. Land document is attached as
Annexure – 1. Among the total acquired land 95448 sq.m, total existing builtup is 10436
sq.m, total existing green area is 33400 sq.m, area covered for road is 6000 sq.m .Total
3481 sq.m of land from existing un-built area i.e 45606 sq.m will be utilised for pesticide
unit. Proposed pesticide manufacturing unit will be developed in 3481 m2 area vacant land
adjacent to agrochemical plant. All the basic amenities of agrochemical plant such as Office
and Laboratory Area, Toilet Block and Others, Parking area will be utilized for proposed
unit. Construction of administration building, plant building, Raw material storage area,
finished products storage area, utility area, treatment facility, fire hydrant and other ancillary
amenities shall be undertaken within the plot area. Proposed project will be developed in
accordance with local development plan and used for industrial purpose. Bifurcation of plot
area is mentioned in Table 3.3.
Water requirement for proposed project will be 367 KLD which will be sourced through own
tube-well. Project proponent has already made to application to CGWA to obtained
permission for withdrawal of water. Bifurcation of daily water consumption during
construction and operation phase is described below in Table 3.4.
Operation Phase
Table 3.4: Water Consumption
S. Water Consumption
Particulars Remarks
No. KLD
A. Domestic 18 -
B. Industrial
1. Processing 64 For process and
pollution control
Floor/equipment 7
washing
2. Boiler 68
RO plant 10
3. Cooling 200 -
Total Industrial 349
Total (A+B) 367
C. Gardening 18 Treated water from
STP will be used
The requirement of utilities for the proposed project has been estimated based on plant
operation capacity
Boiler : 18 TPH
Cooling Tower 5 Nos. – 1000 m3/hr
Fuel:
Rice Husk – 4400 kg/h
HSD - 480 Litr/hr
Source: local Supplier
Industrial Effluent
Total industrial Waste Water Generation will be 267 KLD, out of which 187 KLD from
Process and 7 KLD from floor and container washing will be treated in ETP/MEE (12.5
m3/hr capacity) followed by ATFD. Total 50 KLD of waste water (3 KLD from the DM Plant,
10 KLD from the boiler, 30 KLD from the cooling tower with 7 KLD fresh water) will be
treated in the RO. RO rejection (10 KLD) will be taken to ETP/MEE. 40 KLD of RO
permeate will be recycled in cooling tower. 20 KLD water from the boiler will be treated in
ATFD. Total 227 KLD water (i.e. 40 KLD RO Permeate, 64 KLD ATFD condensate, 103 KLD
MEE condensate and 20 KLD boiler condensate) will be recycled. Average 55 TPD salt
from MEE will be dispose off into TSDF. Thus there will be a zero liquid discharge.
Sewage from Canteen, Amenity blocks, Administrative block, Gate complex and Time office
is collected in the septic tank through closed drains. The collected sewage from sump is
then constantly pumped into the MBBR (Moving bed biofilm reactor).MBBR is a modular
construction comprising of bar screen, collection tank, Aeration section, Sedimentation
Section,& Treated sewage holding/Transfer chamber. The treatment occurs in various
aerobic chambers. In aerobic chambers, thousands of MBBR media is fed, upon which the
bio mass grow. Water is then fed to flocculation chamber which is dosed with alum &
polyectrolyte on continuous basis at a proportional flow rate for solids removal by
sedimentation in the clarifier. The settled sludge is partially re-circulated back to aeration
tank to give a constant feed to the bacteria & balance is dried in drying beds. Clarified water
of low TDS will pass through sand & activated carbon filters. Clear water after filtration is
given to the plantation.
The unit proposes to install 18 TPH capacity of steam boiler. Rice Husk will be used as a
fuel. 30 meters chimney will be provided to the boiler. The company also proposes to install
three numbers of D G set of 1000 kVA each capacity as stand by. 10 meters height of
chimney will be provided.
Process Gas Emission
There will be generation of Sulphur dioxide, Nitrogen oxides, HCl and SPM from the
Incinerator. Multi dust cyclone separator followed by wet scrubber and height of 30 m
chimney will be provided.
There will be generation of HCl during manufacturing of Trizinone, which will be scrubbed in
alkali scrubber. 5 m height of chimney will be provided.
Construction Phase: Noise will be generated during construction phase due to vehicular
movement, operation of construction equipment. Well maintain vehicles and construction
equipment shall be engaged to minimize the noise pollution.
Operation phase: The sources of noise pollution at site will be equipment, pumps, blowers,
DG sets (stand by) etc. General noise levels within plant are expected to remain below 75
dB (A).Use of PPEs like ear plugs and ear muffins will be made compulsory near the high
noise generation machine. Proper mitigation measures will be implemented to control the
noise to keep it within the prescribed norms.
The industry has proposed 33400 m2 area for green belt around the periphery of the plant
boundary and open space of plot. Greenbelt will help in reducing the adverse effect of noise
pollution in general.
4.0 SITE ANALYSIS
Propose project site were selected for evaluation based upon their general suitability for
industrial development. Site analysis was done to ensure that development is undertaken in
such a way that reduces negative impacts to the onsite environment and surrounding
ecosystems. Propose project site is supported by various basic infrastructure facilities i.e.
water supply, transportation, electricity supply, fuel supply etc.
4.1 Connectivity
The project is very well connected to National Highway no. 152 and Northern Railways.
The nearest Railway station is Dappar which is 1.75 km away in North direction from the
project site. Chandigarh railway station is 22 km away in North direction from the project
site The nearest airport is Chandigarh which is 19 km away in North direction from the
project site.
4.3 Topography
Proposed project site is located at Latitude: 30°30'4.96"N Longitude: 76°48'24.95"E. It has
an average elevation of 282 meters above sea level. The overall project site is located on
plain barren land devoid of any permanent and economically useful vegetation. The
topography of the proposed site for project is plain terrain. Forest, national park, eco
sensitive area, wild life sanctuary, Historical, religious and other important cultural place etc.
is not located within 10 Km periphery of the proposed project site. There will be no change
in land use/topography. Ghaggar River with its tributaries forms the main surface
hydrological feature in the area. Due to the flat topography, at many places the water
channels (locally known as choes) are dry during the inter-monsoon period but swells
during the monsoons. The protection of these floodable zones is of paramount importance
for ground water aquifers. (Source: http://pbhousing.gov.in)
The region experiences extreme weather conditions. Period of April to June experiences
hot and dry season with the maximum temperature reaching 45ºC. November to
February is subjected to cold weather and in winters the minimum temperature goes
down to about 1ºC. In Punjab, the average annual rainfall ranges from 58 cms in plains to
96 cms in sub mountain regions and decreases from North to South. The annual average
rainfall in Greater Mohali Region is 114 cm and is heavy during the monsoon season.
The monsoon season starts in the first week of July and continues till middle of
September. (Source: http://pbhousing.gov.in)
For Green Belt Development as per the layout plan, the company has already developed
33400 m2 area of green belt. The company shall also develop additional green belt along
the periphery of the proposed site and in common premises available outside the company
premises.
While selecting the plants species to be grown in the green belt zone, following points will
be taken into account:
1. Climatic condition and soil characteristics of the region.
2. The air pollution emitted by the industry – gaseous and particulate matter.
Plant interaction with both gaseous and particulate pollutants and to a great
extent absorbs them and thus, removes them from the atmosphere.
3. Characteristics of plants including shapes of crowns considered necessary
for effective absorption of pollutant gases and removal of dust particles.
4. Height of the plants should not be too high to be lethal.
5. For absorbance of gases, the duration of the foliage should be longer.
Vegetation controls soil erosion rates significantly. The decrease of water erosion rates with
increasing vegetation cover is exponential. This review reveals that the decrease in water
erosion rates with increasing root mass is also exponential. Plant species having good root
system are selected, so that soil erosion can be checked.