You are on page 1of 12

Journal of Engineering for Gas Turbines and Power.

Received July 21, 2022;


Accepted manuscript posted September 03, 2022. doi:10.1115/1.4055495
Copyright (c) 2022 by ASME

GAS TURBINE COMBINED CYCLE RANGE ENHANCER - PART 2: PERFORMANCE


DEMONSTRATION

AUTHORS

Downloaded from http://asmedigitalcollection.asme.org/gasturbinespower/article-pdf/doi/10.1115/1.4055495/6914221/gtp-22-1419.pdf by National Institute of Technology Kurukshetra user on 08 September 2022
Tommaso Reboli - Università degli Studi di Genova, TPG, Genova, Italy – tommaso.reboli@edu.unige.it
Marco Ferrando - Università degli Studi di Genova TPG, Genova, Italy – marco.ferrando@edu.unige.it
Lorenzo Gini - Università degli Studi di Genova, TPG, Genova, Italy – lorenzo.gini@edu.unige.it
Luca Mantelli - Università degli Studi di Genova, TPG, Genova, Italy – luca.mantelli@edu.unige.it

d
Alessandro Sorce - Università degli Studi di Genova, TPG, Genova, Italy – alessandro.sorce@unige.it

ite
Alberto Traverso - Università degli Studi di Genova, TPG, Genova, Italy – alberto.traverso@unige.it

ABSTRACT MEL Minimum Environmental Load

ed
In the current energy scenario, gas turbine combined cycles OEM Original Equipment Manufacturer
(GTCCs) are considered key drivers for the transition towards PID Proportional Integral Derivative control

py
fossil-free energy production. However, to meet this goal, they PLC Programmable Logic Control
must be able to cope with rapid changes of power request, and PLCS Physic Level Control System
to extend their operating range beyond the limits imposed by the SF Scale Factor

Co
environmental conditions in which they operate. SP Set Point
The European H2020 project PUMPHEAT [1] aims at SOC State Of Charge
achieving this goal thanks to the integration of the GTCC with a TES Thermal Energy Storage
heat pump (HP) and a thermal energy storage (TES). To study

ot
this setup, a dedicated cyber-physical facility was built at the Symbols
University of Genova laboratories, Italy. α specific air consumption
tN
The plant includes physical hardware, such as a 100kWel ṁ mass flow
micro gas turbine, (mGT), a 10 kWel HP and a 180 kWh change n shaft speed [RPM]
phase material-based TES. These real devices are up-scaled P Power
rip

thanks to performance maps and real-time dynamic models to SF Scale Factor


emulate a full-scale heavy duty 400 MW GTCC with a cyber-
physical approach. The control system determines the optimal Subscripts
sc

configuration of the whole plant and the operative point of the C compressor
real devices to minimize the mismatch with a real electric power el electric
demand curve. in inlet
nu

Different operative configurations are tested: one for max maximum


reducing the power production of the plant below the minimum min minimum
Ma

environmental load (MEL) and two for augmenting the plant out outlet
maximum power at certain ambient conditions. th thermal
From the analysis of these tests it is possible to verify the
effectiveness of the proposed concept and to characterize the 1. INTRODUCTION
ed

transient behavior of the real components. Increasing the flexibility and operative range of gas turbine
combined cycles (GTCCs) is crucial to make this technology
NOMENCLATURE more competitive in the current energy market, which is
pt

Acronyms characterized by a high number of non-dispatchable renewable


ARL Auxiliary Resistive Load energy sources. It will also reduce the environmental impact of
ce

COND Condenser GTCCs and will allow them to have a key role in the transition
COP Coefficient of Performance towards fossil-free energy generation.
EVA Evaporator Different methods to increase maximum production were
Ac

GT Gas Turbine introduced by previous studies. They can be classified as inlet air
GTCC Gas Turbine Combined Cycle cooling methods, combustion improvement methods or
HP Heat Pump combustion chamber injection systems (e.g. steam or humid air
HTF Heat Transfer Fluid injection [2]). More details regarding these solutions can be
IGV Inlet Guide Vanes found in the first part of this study [3].
INT Intake Heat Exchanger This work analyzes a range enhancing solution designed for
mGT micro Gas Turbine a GTCC following only the electrical market requests. This
MPC Model Predictive Control solution is called “Power Oriented” and its aim is to enhance the

GTP-22-1419 Reboli 1
Journal of Engineering for Gas Turbines and Power. Received July 21, 2022;
Accepted manuscript posted September 03, 2022. doi:10.1115/1.4055495
Copyright (c) 2022 by ASME

operative range of the GTCC through inlet conditioning via a and real-time models. All these activities are described in the first
heat-pump (HP) and a cold thermal energy storage (TES) [4]. part of this study [3]. The second part of the study introduces the
The HP can be used for both increasing and decreasing the control strategies implemented on the main physical equipment
compressor inlet air, while the TES can only be used for cooling. of the plant, the scale-up approach adopted, and the experimental

Downloaded from http://asmedigitalcollection.asme.org/gasturbinespower/article-pdf/doi/10.1115/1.4055495/6914221/gtp-22-1419.pdf by National Institute of Technology Kurukshetra user on 08 September 2022
Relying on a TES is an effective solution to decouple the results of the cyber-physical system.
utilization on the refrigeration system from the consumption of
electric power during peak periods, i.e. when the price is higher.
An advanced control system was developed to regulate the
integrated conditioning system and fully exploit the power plant

d
capacity [5]. The control system determines the activation of HP
and TES to optimize the economic profitability of the plant. If

ite
the power output of the GTCC must be increased, inlet cooling
with the TES is always the best solution, requiring no

ed
consumption of electric power. Therefore, the activation of the
HP for inlet cooling is evaluated only when the TES is empty.
The control system considers both effects of inlet heating to

py
determine the activation of this configuration. In fact, the HP can
be used at the same time to reduce the minimum environmental
load (MEL) of the plant and to charge the TES.

Co
Based on a previous study by Sorce et al. [6], the integrated
inlet conditioning system is expected to increase the operation
flexibility of GTCC in terms of:
FIGURE 1 - MAIN CONTENTS OF THE 1ST AND 2ND PARTS OF THIS

ot
1) power augmentation (+14% during TES discharging); STUDY.
2) minimum environmental load reduction (-16%);
3) off-design efficiency enhancement (ca. +1%).
tN
These activities are presented in this article. A test of about
To assess the performance of the GTCC range enhancer on 8 hours is run on the cyber-physical system, activating all the
a real system, and to test the control system in a possible configurations of the plant. Each configuration is
hardware-in-the-loop setup, a cyber-physical test-rig facility was analyzed separately, in order to highlight the performance of the
rip

built in the laboratory of the Thermochemical Power Group different components (mGT, HP, TES), critical issues and
(TPG) of the University of Genoa. This facility is composed by possible improvements. Therefore, the results shown in this
two main parts: real hardware and real-time simulation software. article can be considered as a validation of the overall GTCC
sc

These two parts constitute a cyber-physical emulator of a GTCC, range enhancer concept and its four-level control system.
coupled with a heavy duty HP and an industrial cold TES.
nu

Cyber-physical systems are widely used in academia to 2. TEST-RIG AND EXPERIMENTAL CAMPAIGN
study complex, expensive and large energy systems in a DESIGN
laboratory environment [7]–[9]. In fact, beside the savings in
Ma

equipment costs, the installation of a cyber-physical system 2.1. Cyber-Physical system description
speeds up the development and deployment of innovative power The PUMP-HEAT project aims at studying and developing
plants, encouraging private and public investment, and innovative solutions to increase the flexibility of GTCCs and
substantially reducing the risk of failure [10]. extend their operative range. Within this framework, the TPG of
ed

The real hardware, the simulation software and the control the University of Genoa, installed an innovative combined cycle
system of the Power Oriented cyberphysical system are emulator plant to study these solutions. This facility was
described in details in the first part of this study [3]. This article designed to study the impact of compressor inlet conditioning,
pt

focuses on the experimental campaign carried out on the test-rig considering the integration of the GTCC with a HP, which can
facility. The system is operated in various operating conditions, be used for heating or cooling, and with a cold TES [1].
ce

making it possible to analyze the performance of the GTCC The test rig facility, shown in Figure 2, represents the
range enahancer and its control system. The article also provides physical hardware of a cyber-physical full-scale plant, as
described in the first part of this study [3]. The top part of Figure
Ac

additional information regarding the scale-up approach adopted


to integrate the system and the low-level control strategies 3 shows the real-time software simulating the GTCC, also
regulating the real devices. highlighting the data connection points with the laboratory
facility.
1.1. Scope of work The lower part of Figure 3 shows the main real devices of
The research activities on the GTCC range enhancer were the emulator plant:
organized in two main parts, as shown in Figure 1. The first part - Turbec T100 micro gas turbine (mGT), equipped with inlet
includes definition of different operating conditions, installation conditioning heat exchanger (INT)
of the experimental setup, and development of control system - 10 kWel HP using butane as working fluid

GTP-22-1419 Reboli 2
Journal of Engineering for Gas Turbines and Power. Received July 21, 2022;
Accepted manuscript posted September 03, 2022. doi:10.1115/1.4055495
Copyright (c) 2022 by ASME

- 180 kWh cold TES. The GTCC plant can operate in four different
A dedicated hydraulic circuit connects the plant configurations. To simplify the definition of the plant operation,
components. This circuit is equipped with many three-way each configuration is identified by a FLAG parameter, which can
valves, which can be set-up in different configurations to test the have a value between 1 and 4:

Downloaded from http://asmedigitalcollection.asme.org/gasturbinespower/article-pdf/doi/10.1115/1.4055495/6914221/gtp-22-1419.pdf by National Institute of Technology Kurukshetra user on 08 September 2022
system while emulating various operating conditions.
• Normal operation – FLAG 1 - In this configuration, the HP
is turned off and the TES does not exchange any heat flux with
the other components. It is the standard operating condition of
the plant, and it is set when the GTCC can easily follow the
electric power demand.

d
• Continuous Cooling – FLAG 2 - In this configuration, the HP

ite
is used to cool down the compressor inlet air, while the TES
does not exchange any heat flux with the other components.

ed
The reduction of air temperature increases the GTCC power
output, increasing its maximum achievable power and making
it easier to follow fast load increases.

py
• TES Discharge – FLAG 3 - In this configuration, the HP is
turned off and the TES is used to cool down the compressor

Co
inlet air. Similarly to Continuous Cooling, the reduction of air
temperature increases the GTCC power output, increasing its
maximum achievable power and making it easier to follow fast
load increases.

ot
FIGURE 2 – THE GTCC RANGE ENHANCER TEST-RIG INSTALLED IN
THE TPG LABORATORY. • TES Charge – FLAG 4 - In this configuration, the HP is used
tN
to warm up the compressor inlet air, while charging the cold
TES. The increase of air temperature decreases the GTCC
power output, reducing its minimum achievable power and
rip

enhancing its power ramping capabilities.


The GTCC is regulated by a 4-levels control architecture,
designed to condition the compressor inlet air temperature and
sc

generate the desired electrical power. The first 3 levels of the


control system were implemented on Matlab-Simulink and
integrated with a real-time dynamic model of the GTCC, while
nu

to fourth level, named physical level control system (PLCS), was


developed in NI Labview [3].
Ma

2.2. Operative strategies


2.2.1. mGT operating range
When experimental test-rig and dynamic model are linked
ed

in cyber-physical configuration, the T100 mGT is scaled up to


emulate the heavy-duty GT of the Iren Energia GTCC 2GT,
Moncalieri, Italy. Reboli et al. [11] have already presented
pt

relationships and similarities between the off-design


performance of GT and mGT. In normal operating conditions,
ce

both mGT and GT control fuel consumption and air mass flow
to regulate the generated power. The mGT control system
Ac

intervenes on the rotational speed (n) to modify air mass flow


and electric power, while the heavy-duty GT, running at fixed
speed, uses an inlet guide vane (IGV). At n/nmax equal to 100%
and 78%, the mGT reaches respectively the maximum (100%)
and minimum (38%) dimensionless load. Eqs. (1) and (2),
obtained with the mGT exhaust temperature (TT,out) set equal to
FIGURE 3 – TEST-RIG LAYOUT AND REAL-TIME MODEL. 645°C, show how the actual power values are influenced by the
compressor inlet temperature TC,in (Figure 4).

GTP-22-1419 Reboli 3
Journal of Engineering for Gas Turbines and Power. Received July 21, 2022;
Accepted manuscript posted September 03, 2022. doi:10.1115/1.4055495
Copyright (c) 2022 by ASME

Downloaded from http://asmedigitalcollection.asme.org/gasturbinespower/article-pdf/doi/10.1115/1.4055495/6914221/gtp-22-1419.pdf by National Institute of Technology Kurukshetra user on 08 September 2022
n/nmax = 100%

d
ite
n/nmax = 78%

ed
py
FIGURE 5 – CONTROL LOGICS OF THE HEAT PUMP.
FIGURE 4 – ELECTRICAL POWER OUTPUT OF THE MGT T100 AT
MINIMUM (N/NMAX = 78%) AND MAXIMUM (N/NMAX = 100%) LOAD, AS

Co
A FUNCTION OF TC,IN. Depending on the configuration of the plant, there are different
ways to vary the evaporator thermal load (and TEVA,out):
𝑃𝑒𝑙,𝑚𝐺𝑇,𝑚𝑎𝑥 = −1.2 · 𝑇𝐶,𝑖𝑛 + 110 (1) • TES Charge (FLAG 4): in this case the PLCS changes the
HTF mass flow by varying the pump P3 speed through a

ot
𝑃𝑒𝑙,𝑚𝐺𝑇,𝑚𝑖𝑛 = −0.8 · 𝑇𝐶,𝑖𝑛 + 53.7 (2) dedicated PID (in this configuration the pump P3 is the
actuator).
tN
For each compressor inlet temperature, the Pel,MGT has been • Continuous Cooling (FLAG 2): in this case the HTF mass
scaled up, through dimensionless power load, to the power of a flow that passes through the HP EVA is constant. The PLCS
heavy duty GT, which off-design performance have been acts on the regulating valve RV_2, which is the actuator for
rip

confirmed by the original equipment manufacturer (OEM) [11] this configuration. In this way, only a fraction of the mass
[6]. This operation is integrated in the cyber-physical setup using flow goes through the INT, which is the thermal load of the
Matlab-Simulink linear lookup tables. circuit. The remaining mass flow is bypassed. In this case the
sc

physical parameter that is controlled is the HP EVA inlet


2.2.2. HP control strategy
temperature, which directly influences the thermal load of the
As already introduced in [3], the HP is equipped with a HP and consequently the absorbed electric power.
nu

programmable logic controller (PLC) which has three different


control logics: 2.2.3. TES control strategy
- expansion valve: regulated to keep a constant temperature at The TES is one of the key components of the system. A
Ma

the evaporator stable control of the thermal power delivered to the INT is
- three-way valve: controlled to maintain the superheat of butane fundamental to follow the thermal power setpoint (SP)
leaving the evaporator to a proper level, before entering the determined by the control system in TES Discharge
configuration (FLAG 3). In fact, in FLAG 3 the HP is turned off,
ed

compressor
- compressor speed: controlled to match the evaporator outlet and the TES is directly connected to the INT through a dedicated
temperature setpoint on the heat transfer fluid (HTF) side circuit where the HTF is moved by the pump P3 (see Figure 3).
pt

(TEVA,out). As already anticipated in the first part of this study [3], the
The compressor speed is responsible for the electric power power provided by the TES is regulated by varying the HTF
mass flow, controlling the speed of the pump P3. Due to its high
ce

absorbed by the HP and, consequently, for the cold thermal


power generated, but it is not possible to directly control the HP thermal capacitance, the TES reacts to flow variations with a
electric power. However, the electric power can be indirectly behavior that can be well approximated by a second-order
Ac

controlled, varying the evaporator thermal load and letting the system. Consequently, it was necessary to dedicate a specific
HP regulate the compressor speed to maintain the HTF leaving activity to properly tune the related PID. In Figure 6 it is possible
the evaporator at a proper temperature. to observe the response of the system to step variations of the
Figure 5 shows how PLCS and HP PLC are integrated with control variable u, which represents the pump P3 speed.
the test-rig.

GTP-22-1419 Reboli 4
Journal of Engineering for Gas Turbines and Power. Received July 21, 2022;
Accepted manuscript posted September 03, 2022. doi:10.1115/1.4055495
Copyright (c) 2022 by ASME

of the GT, due to the lack of blade cooling, resulting in a different


specific air consumption. The SFth, which is computed according
to Eq. (3), is implemented into the cyber-physical system.

Downloaded from http://asmedigitalcollection.asme.org/gasturbinespower/article-pdf/doi/10.1115/1.4055495/6914221/gtp-22-1419.pdf by National Institute of Technology Kurukshetra user on 08 September 2022
𝑃𝑒𝑙,𝐺𝑇 𝛼𝐺𝑇 𝑚̇𝑎𝑖𝑟,𝑚𝐺𝑇,𝐶 𝑀𝑊𝑡ℎ
𝑆𝐹𝑡ℎ = ∙ ∙ = 0.555 (3)
𝑃𝑒𝑙,𝑚𝐺𝑇 𝛼𝑚𝐺𝑇 𝑚̇𝑎𝑖𝑟,𝑚𝐺𝑇,𝑡𝑜𝑡 𝑘𝑊𝑡ℎ
Where:
𝑃𝑒𝑙,𝐺𝑇 = 268 𝑀𝑊 GT nominal electric power

d
𝑃𝑒𝑙,𝑚𝐺𝑇 = 100 𝑘𝑊 mGT nominal electric power

ite
FIGURE 6 – RESPONSE OF THE PTES TO MULTIPLE STEP VARIATIONS 𝑚̇𝑎𝑖𝑟,𝐺𝑇 𝑘𝑔𝑎𝑖𝑟
OF PUMP P3 SPEED. 𝛼𝐺𝑇 = = 2.5 GT specific air consumption
𝑃𝑒𝑙,𝐺𝑇 𝑠 ∙ 𝑀𝑊

ed
The absolute value of PTES grows with the increase of mass 𝑚̇𝑎𝑖𝑟,𝑚𝐺𝑇 𝑘𝑔𝑎𝑖𝑟
flow. However, since the cold energy is leaving the storage in 𝛼𝑚𝐺𝑇 = =8 mGT specific air consumption

py
this configuration, the values of PTES are negative. It can be noted 𝑃𝑒𝑙,𝑚𝐺𝑇 𝑠 ∙ 𝑘𝑊
that, before reaching a steady condition, the thermal power trend 𝑘𝑔
shows a wide overshoot, making the tuning of the PID controller 𝑚̇𝑎𝑖𝑟,𝑚𝐺𝑇,𝐶 = 0.8 Air mass flow elaborated by

Co
more difficult. The overshoot occurs because the flow rate 𝑠 the mGT compressor
variation is almost instantaneous, while temperature variations 𝑘𝑔 Total air mass flow elaborated
require a longer time. The power varies greatly at first, due to the 𝑚̇𝑎𝑖𝑟,𝑚𝐺𝑇,𝑡𝑜𝑡 = 1.2
𝑠 by the mGT
sudden change in flow rate, and then stabilizes as soon as the

ot
thermal transient is complete. To evaluate the accuracy of the scale-up, a balance-of-plant
The problem of PID calibration was addressed modelling was performed, considering TES Charge, TES Discharge and
tN
the TES as a second order transfer function in Matlab-Simulink, Continuous Cooling. The electrical power of the HP and the
and designing the PID according to the pole placement method thermal power of the TES were set to be consistent with those
[12]. After implementing the PID on the real plant, its parameters obtainable in the laboratory, assuming to perform a complete
rip

were adjusted to optimize the performance of the controller. charge and discharge of the TES.
Figure 7 shows the good tracking capabilities of the PID on It must be underlined that the thermal losses for the full-
the TES, while changing the thermal power setpoint with scale plant were assumed to be equal to 10%, both for the cold
sc

multiple step variations. and the hot circuit. This value exceeds the expected one for
industrial applications, but it was set for consistency with the
nu

ones observed on the test-rig, as explained in [3].


Table 1, Table 2 and Table 3 show the results of this
assessment, where the blue cells indicate the assumption, while
Ma

the main outcomes of the analysis are highlighted in red.

TABLE 1 – TES CHARGE SCALE-UP ANALYSIS.

avg Pel HP 8,5 kW


ed

COP HP 1,7 -
Pth cold HP (to TES) 14,0 kW
Laboratory
pt

Pth TES 11,5 kW


TES Charging time 3 h
ce

FIGURE 7 – RESPONSE OF THE CONTROLLED TES TO MULTIPLE STEP TES final SOC 19,2 %
CHANGES OF THERMAL POWER SETPOINT.
Pel HP 3,0 MW
COP HP 2,5 -
Ac

2.3. Scale-up analysis Cyber-


As already described in the first part of this study [3], all Pth cold HP (to TES) 7,4 MW
physical
the physical elements are scaled up to a real GTCC plant. The Pth TES 6,7 MW
GTCC
10kWel HP is scaled up to a 3.5 MWel HP, in accordance with Charging time TES 3 h
the analysis by Mantilla et al. [13]. All the heat flows provided TES final SOC 100,1 %
to the INT are scaled up through a thermal scale factor (SFth),
which considers the characteristics of the mGT and GT in terms
of electric power and specific air consumption α. In fact, the
mGT needs to keep the TIT at a lower temperature than the one

GTP-22-1419 Reboli 5
Journal of Engineering for Gas Turbines and Power. Received July 21, 2022;
Accepted manuscript posted September 03, 2022. doi:10.1115/1.4055495
Copyright (c) 2022 by ASME

TABLE 2 – TES DISCHARGE SCALE-UP ANALYSIS. of Continuous Cooling (FLAG 2). This scenario made it
avg Pth TES (to INT) 11,5 kW possible to experiment all the possible operative conditions and
to test all the control system functions.
Pth INT 11,0 kW
Laboratory The test was designed to verify that all the possible
Discharge time TES 3 h

Downloaded from http://asmedigitalcollection.asme.org/gasturbinespower/article-pdf/doi/10.1115/1.4055495/6914221/gtp-22-1419.pdf by National Institute of Technology Kurukshetra user on 08 September 2022
configurations of the plant are activated in the proper way,
final SOC TES 0 %
validating its operating capabilities, and improving its load
Pth TES (to INT) 6,7 MW following features during intra-day adjustments, while
Cyber-
Pth INT 6,1 MW optimizing the HP operation.
physical
Discharge time TES 3 h
GTCC 3. HARDWARE IN THE LOOP RESULTS

d
TES final SOC 0,1 %
To demonstrate the potential of the GTCC range extender,

ite
an 8 hour long test was designed and carried out on the test-rig.
TABLE 3 – CONTINUOUS COOLING SCALE-UP ANALYSIS. All the measurements and uncertainties were evaluated relying
avg Pel HP 8,5 kW on the experimental setup described in the first part of this study

ed
COP HP 1,7 - [3]. In this section the whole test scenario is described, and the
Laboratory effect of each different configuration is analyzed in details.
Pth cold HP (to INT) 14,0 kW
Figure 8 shows the full test, in terms of electric power

py
Pth cold INT 12,2 kW
Pel HP 3,0 MW demand, net electric power produced, scheduled and operative
COP HP 2,5 - configuration (FLAGS).
Cyber-

Co
The test starts with minimum power demand and the plant
physical Pth cold HP (to INT) 7,4 MW
running under FLAG 1, where the GT is operated with no inlet
GTCC Pth INT 6,8 MW
conditioning. Due to a decrease of electric power demand, the
COP scale factor 1,5 -
control system changes the plant operation to FLAG 4, activating

ot
the HP. The HP condenser is connected to the INT heat
These tables show that the assumptions regarding TES exchanger to heat up the compressor intake, and effectively
capacity and HP nominal power are consistent with the expected
tN
reduce the minimum load. Figure 9 shows the variation of
performance of the GTCC range enhancer. electrical power absorbed by the HP, highlighting the
In fact, assuming Pel,HP = 8.5 kW in TES Charge mode and responsiveness of the controller. During FLAG 4, the TES stores
Pth TES =11.5 kW in TES Discharge mode, 20 MWh are
rip

the cold energy generated by the HP; consequently, its SOC


sufficient to ensure around 3 hours of autonomy. increases (Figure 10). FLAG 4 is active from 0.5 h to 2.5 h.
As indicated in At the end of the TES Charge, the HP is switched off and the
Table 3, assuming to scale up the HP to 3.5 MWel implies a
sc

system is brought to full power, with a loading ramp performed


COP scale factor equal to 1.5. This means that the full-scale HP entirely with no inlet conditioning, i.e., in FLAG 1. When
should have a better performance compared to the laboratory- maximum power is reached at 3.5 h, FLAG 1 is maintained for a
nu

scale one. In particular, its COP should vary between 2 and 3, further 0.75 h. Then, the control system activates TES Discharge
depending on the condenser temperature and the HP load. (FLAG 3) at time 4.25 h. This phase demonstrates how the
This assumption is perfectly coherent for a scale-up towards maximum power output of the GTCC can be increased by
Ma

an industrial application. In fact, as already described in [3], the exploiting the cold energy that was previously stored in the TES.
performance of the laboratory HP is not good enough to be Figure 10 shows the trend of thermal power provided by the TES
considered for installation in a full-scale industrial plant. and its SOC.
ed

When the TES is fully discharged (after 6.25 h), the FLAG
2.4. Experimental campaign design automatically changes from 3 to 2, activating Continuous
A typical day of operation (1st of April 2021) was selected Cooling configuration and turning on the HP (Figure 9). FLAG
pt

to test the GTCC range enhancer. This day is characterised by 2 is a backup configuration, which can be used when the power
significant ambient temperature changes and a GTCC load demand is still high, but the TES is empty. This can be better
variation from minimum to maximum. The ambient temperature
ce

understood looking at Figure 8, where the operative FLAG is not


trend forecasted by the scheduler (i.e., the high-level controller consistent anymore with the scheduled FLAG. FLAG 2 is
described in [3]), had a very similar trend to the one measured in maintained until the end of the test.
Ac

the laboratory during the actual test day. Figure 11 shows the direct impact of the FLAGS 4-3-2 in
The scheduler defined an optimal operation baseline terms of inlet conditioning, highlighting the temperature increase
including normal operation (FLAG 1), TES Charge (FLAG 4) and decrease with respect to the ambient temperature.
and TES Discharge (FLAG 3). However, the initial state of Figure 12 shows the different power contributions of the
charge (SOC) of the TES was set lower to the scheduled one, in GTCC, displaying separately the power generated by the gas
order to cause its complete discharge and trigger the activation turbine and by the components of the steam bottoming cycle.

GTP-22-1419 Reboli 6
Journal of Engineering for Gas Turbines and Power. Received July 21, 2022;
Accepted manuscript posted September 03, 2022. doi:10.1115/1.4055495
Copyright (c) 2022 by ASME

Downloaded from http://asmedigitalcollection.asme.org/gasturbinespower/article-pdf/doi/10.1115/1.4055495/6914221/gtp-22-1419.pdf by National Institute of Technology Kurukshetra user on 08 September 2022
d
ite
ed
py
FIGURE 8 – GTCC ELECTRIC POWER TRENDS DURING THE FULL DAY TEST.

Co
ot
tN
rip
sc
nu
Ma

FIGURE 9 – HP ELECTRIC LOAD TREND DURING THE FULL DAY TEST.


ed
pt
ce
Ac

FIGURE 10 – TES THERMAL POWER TRENDS DURING THE FULL DAY TEST.

GTP-22-1419 Reboli 7
Journal of Engineering for Gas Turbines and Power. Received July 21, 2022;
Accepted manuscript posted September 03, 2022. doi:10.1115/1.4055495
Copyright (c) 2022 by ASME

Downloaded from http://asmedigitalcollection.asme.org/gasturbinespower/article-pdf/doi/10.1115/1.4055495/6914221/gtp-22-1419.pdf by National Institute of Technology Kurukshetra user on 08 September 2022
d
ite
ed
py
FIGURE 11 – COMPARISON BETWEEN AMBIENT TEMPERATURE AND COMPRESSOR INLET TEMPERATURE.

Co
ot
tN
rip
sc
nu
Ma

FIGURE 12 – EMULATED GTCC POWER SHARE DURING THE FULL DAY TEST.

3.1. TES Charge – FLAG 4 analysis the HP to charge the TES occurs when the price of electrical
As already introduced in the previous section, the first part energy is low, with minimum effect on the economic profitability
of the plant.
ed

of the test, between 0 h and 2.5 h, was designed to validate the


range extension potential below the minimum environmental Figure 13 shows a detail of the first hours of this test. During
limit by turning on the HP to warm-up the compressor inlet. This the first 30 minutes, the plant was operated at minimum load,
pt

is a very efficient configuration because all the energy flows around 206-207 MW, in accordance to [3].
converge for the same purpose, i.e., to reduce the GTCC load, At 0.5 h, the electric power demand is reduced, and the
ce

and there are no parasitic effects as in the case of Continuous control system changes plant configuration accordingly,
Cooling (see Section 3.3). switching from FLAG 1 to FLAG 4. The transition between
In fact, the heat flow leaving the condenser is introduced FLAGs took some time because it was necessary to turn on
Ac

into the cycle, reducing the GT specific power, and consequently valves, activate circulation pumps (around 2 minutes) and turn
the GT load, while the electric power absorbed by the HP on the HP, which is the most critical and time-demanding
contributes to a further reduction of the net power of the plant. process, requiring 12-15 minutes. In fact, before considering the
Moreover, the cold energy produced by the HP is not wasted, but FLAG 4 configuration as fully operative, the HP must reach a
stored in form of latent heat into the TES. Since the condenser is regulating condition, i.e., it is necessary to wait for the
connected to INT, the ambient temperature indirectly influences evaporator to reach -6°C and then to activate the dedicated PID
its temperature (and thus its pressure), affecting the COP of the (described in the first part of this study [3]).
HP. However, the additional consumption of electric power by

GTP-22-1419 Reboli 8
Journal of Engineering for Gas Turbines and Power. Received July 21, 2022;
Accepted manuscript posted September 03, 2022. doi:10.1115/1.4055495
Copyright (c) 2022 by ASME

Downloaded from http://asmedigitalcollection.asme.org/gasturbinespower/article-pdf/doi/10.1115/1.4055495/6914221/gtp-22-1419.pdf by National Institute of Technology Kurukshetra user on 08 September 2022
d
ite
ed
FIGURE 13 - NET POWER PRODUCED WITH SETPOINT AND GT INLET
TEMPERATURE DURING FLAG 4
FIGURE 15 - TES SOC AND THERMAL POWER DURING FLAG 4.

py
This start-up process can be analyzed in Figure 14, where
Moreover, as explained in Section 2.2.1, the minimum load curve
all the mismatches between HP electric load setpoint and the real
of the test-rig mGT was identified as the set of the operative

Co
HP load are concentrated between 0.5 h and 0.7 h, during a
points where the mGT internal controller switches from a
period of ~15 minutes corresponding to the configuration change
constant speed logic to a TT,out constant logic. Therefore, varying
and the HP start-up ramp. Except for this first part, the HP
the inlet temperature when the turbomachinery is close to this
indirect controller described in [3] works properly and allows the

ot
condition, the mGT changes for some minutes its control logic.
HP to follow the load adequately, as shown in Figure 14.
Consequently, there are some sudden changes of the net power
Figure 15 shows the thermal power trend and the SOC of the
generated by the mGT, which can be observed at 1.1 h, 1.4 h, 1.8
tN
TES. As explained in Section 2.2.2, the variation of electrical
h, 2.1 h in Figure 13. A possible way to avoid such disturbances
power required by the HP is controlled indirectly by varying the
would be to operate the mGT far from its lower limit.
HTF flow rate. For this reason, the power absorbed by the TES
From 1 h to 2.2 h, the mismatch between power demand and
rip

shows some oscillations, which are related to the flow rate


power produced by the GTCC had an average value of 0.715%
variations made by the PID. The SOC grows linearly by about
(relative to power demand). The mismatch between HP set point
60% in this first phase, and it is not significantly affected by
and HP electric load was instead equal to 1.24% (relative to HP
sc

thermal power fluctuations.


set point).
nu

3.2. TES Discharge – FLAG 3 analysis


The TES Discharge phase is used to increase the maximum
power output of the combined cycle, in order to exploit the cold
Ma

thermal energy previously stored in the TES. As shown in Figure


16, right after 3.5 h, the system is operating under FLAG 1 and
the GT is working at maximum load. In this condition, the GTCC
is generating an electric power of 376 MW, in agreement with
ed

[3]. At time 4.25 h, the electric power demand increases, and the
FLAG is changed from 1 to 3. This is possible because the TES
pt

is not fully discharged, otherwise FLAG 2 would have been set.


The start-up phase of the TES power control goes up to about
4.5 h, taking about 15 minutes, as shown in Figure 17. The
ce

control takes quite a long time to increase the power provided by


the TES because it reacts to changes in the HTF flow rate as a
Ac

FIGURE 14 - HP ELECTRIC LOAD AND ITS SETPOINT DURING FLAG 4. second order system, as explained in Section 2.2.3. At 4.5 h the
PID parameters were deliberately changed to make the control
The hot thermal power generated at the HP condenser is unstable, resulting in power fluctuations. This procedure was
transferred to the GT intake. The effect of temperature increase done to evaluate the influence of these oscillations on the plant
at the GT inlet is clearly visible in Figure 13, where the power production. As shown in Figure 16, the fluctuations do not
temperature increases from -20°C to -32°C. It can be noted that lead to changes in the power output of the combined cycle,
the plant was not able to perfectly match the demand. This is probably because they are damped by the large thermal
caused by the thermal capacitance of the physical components, capacitance of the INT exchanger and its hydraulic circuit.
in particular of the INT heat exchanger.

GTP-22-1419 Reboli 9
Journal of Engineering for Gas Turbines and Power. Received July 21, 2022;
Accepted manuscript posted September 03, 2022. doi:10.1115/1.4055495
Copyright (c) 2022 by ASME

required by the HP itself and the fact that the entire auxiliary
resistive load (ARL) circuit must be pre-cooled. Since only one
circulation pump (P3) is used to regulate TES and HP evaporator
load, it was not possible to turn on the HP and let the ARL circuit

Downloaded from http://asmedigitalcollection.asme.org/gasturbinespower/article-pdf/doi/10.1115/1.4055495/6914221/gtp-22-1419.pdf by National Institute of Technology Kurukshetra user on 08 September 2022
reached the proper temperature before stopping draining cold
energy from the TES. A possible upgrade to overcome this limit
could be to include an additional circulating pump to serve
exclusively the TES, in order to uncouple these two operative
conditions (HP startup and TES Discharge)”.

d
In this configuration, the ARL is used as a thermal buffer,
as explained in the first part of this study [3]. During this start-

ite
up phase, the HTF flow rate to the INT exchanger is zero and the
HP is set to maximum power to speed up the cooling of the ARL

ed
circuit. As shown in Figure 19, during this period, the GTCC
FIGURE 16 - NET POWER PRODUCED WITH SETPOINT AND maximum power returns to its nominal value. Shortly after 6.5
COMPRESSOR INLET TEMPERATURE DURING FLAG 3. h, the flow to the INT starts growing, cooling the air entering the

py
GT. The cooling transient of the INT ends approximately at 6.75
h. When the HP is at maximum power, the power output of the
combined cycle is less stable. This behavior is related to the

Co
physics of the system described in Section 2.2.2. In Continuous
Cooling, a large variation of flow rate to the INT is required to
change the outlet temperature of the HP evaporator. To reduce

ot
the HP load, the flow rate to the INT is reduced to almost zero,
resulting in a temperature increase at the INT. To increase the HP
load, the flow rate to the INT is increased significantly, causing
tN
a temperature reduction at the INT. This process causes the small
fluctuations in GT inlet temperature and generated power shown
in Figure 19. For higher ambient temperatures, a smaller flow
rip

rate variation would probably be required to achieve a similar


variation in the HTF temperature at the evaporator outlet.
Figure 19 clearly shows that, regardless of these
sc

FIGURE 17 – TES SOC, TES THERMAL POWER SETPOINT AND fluctuations, the power generated by the GTCC does not vary
THERMAL POWER RELEASED DURING FLAG 3. significantly, remaining always around 390MW, while the HP
nu

power changes (Figure 18). In fact, both the electrical power


At 4.7 h the parameters of the controller were reset to their absorbed by the HP and the power generated by the GT increase
original values, and the TES power demand was again followed or decrease at the same time, causing minimum variations of the
Ma

with good accuracy, showing only a small lag due to the GTCC power output. The increase of COP when the HP is
complexity of the TES system. Figure 16 also shows the large running at low power (i.e. low rotation speed, as described in [3])
temperature reduction at the GT caused by the cold thermal should also be considered.
power released by the TES. The compressor inlet temperature
ed

drops from 22°C in FLAG 1 to 14-16°C in FLAG 3, depending


on the power required at the TES. The TES Discharge phase ends
at 6.25 h, as soon as the minimum TES Charge level is reached
pt

(Figure 17). From 4.8 h to 6.2 h (after the initial TES power
oscillations) the mismatch between power demand and power
ce

produced by the GTCC had an average value of 0.19% (relative


to power demand). The average mismatch between TES thermal
power and its set point was instead equal to 3.4% (relative to TES
Ac

thermal power set point).


3.3. Continuous Cooling – FLAG 2 analysis
The Continuous Cooling phase is activated when the power
demand is still high, but the TES is empty. In fact, this phase
starts exactly at the end of the TES Discharge (6.25 h). As visible
in Figure 8 and shown in Figure 18, the start-up of the HP takes
approximately 15-20 minutes, because of the technical time FIGURE 18 - ACTUAL HP ELECTRIC LOAD AND ITS SETPOINT
DURING FLAG 2.

GTP-22-1419 Reboli 10
Journal of Engineering for Gas Turbines and Power. Received July 21, 2022;
Accepted manuscript posted September 03, 2022. doi:10.1115/1.4055495
Copyright (c) 2022 by ASME

TABLE 4 – EFFECT OF THE INLET HEATING+TES CHARGING AT


MINIMUM LOAD.
Inlet Heating +
Business as usual
TES Charge

Downloaded from http://asmedigitalcollection.asme.org/gasturbinespower/article-pdf/doi/10.1115/1.4055495/6914221/gtp-22-1419.pdf by National Institute of Technology Kurukshetra user on 08 September 2022
Compressor intake
20.9 32.1
temperature [°C]
Net power [MWel] 205.5 190.4 (-7.4%)
Fuel consumption [kg/s] 8.5 8.1 (-4.7%)

d
Global efficiency [%] 50.4 49.0 (-2.7%)

ite
4.2. Inlet cooling

ed
The effect of the intake cooling is shown in Table 5. Also in
FIGURE 19 - NET POWER PRODUCED WITH SETPOINT AND this case, the percentage difference with the business-as-usual
COMPRESSOR INLET TEMPERATURE DURING FLAG 2. configuration is displayed between brackets for each specific

py
parameter. Thanks to the reduction of intake temperature, the
In fact, this phenomenon is reason why the heat output at the GTCC can generate an extra 17.5MW during TES discharge.
evaporator does not vary significantly and so does the When the HP is used for inlet cooling instead, the extra

Co
temperature at the GT inlet. The GT inlet temperature goes from production is equal to 13.4 MW, with an auxiliary systems
21°C to 12-13°C in this configuration, then remains consumption of 2.2 MW. As already explained, the variation of
approximately constant throughout the duration of the FLAG, the HP set point and load does not affect the net power produced
despite the change in HP load.

ot
by the plant. Consequently, a good operative strategy would be
An effective strategy for adopting Continuous Cooling to keep the HP at minimum load in Continuous Cooling mode.
could be to operate the HP at a fixed point, corresponding to its
tN
highest COP. However, it is possible that heat pumps with a TABLE 5 – EFFECT OF TES DISCHARGE AND OF CONTINUOS
wider operating range may give better results in regulation. COOLING AT MAXIMUM LOAD.
From 6.8 h to 8.2 h, the mismatch between power demand Inlet cooling
rip

and power produced by the GTCC had an average value of Business


Continuous
as usual TES Discharge
0.52% (relative to power demand). The average mismatch Cooling
between HP set point and HP electric load was instead equal to Compressor intake
sc

21.2/ 20 13.8 12.9


1.1% (relative to HP set point). temperature [°C]
Net power [Mwel] 377.0 394.5 (+4.6%) 390.4 (+3.6%)
Fuel consumption
nu

4. COMPARISON WITH BUSINESS AS USUAL 13.9 14.5 (+3.9%) 14.5 (+3.9%)


This section shows a comparison between the performance of a [kg/s]
Global efficiency
GTCC with and without the range enhancer proposed in this 56.3 56.7 (+0.7%) 56.1 (-0.4%)
[%]
Ma

article. All the parameters are compared for inlet heating (TES
Charge – FLAG 4), inlet cooling (TES Discharge – FLAG 3) and
This impacts directly on the global efficiency of the GTCC,
continuous cooling – FLAG 2).
which gains 0.4 percentage points during TES discharge and
4.1. Inlet heating loses 0.6 percentage points in Continuous Cooling.
ed

In Figure 13, it is possible to observe the effect of inlet


heating comparing the behavior of the system before 0.5 h and 5. CONCLUSIONS
pt

between 1 h and 2 h. Inlet heating lowers the GTCC minimum The cyber-physical GTCC emulator introduced in [3] was
environmental load and reduces its fuel consumption (-4.7%). successfully operated in various conditions, and its performance
ce

When the price of electrical energy is low, this has a double was deeply analyzed. Relying on scale-up equations, it was
beneficial effect, reducing the variable costs of the plant and its possible to create a relationship between the behavior of the
pollution emission [6]. devices in the laboratory (mGT, HP and TES) with the
Ac

Making an estimate of the different effects contributing to components of a simulated heavy-duty plant. The integration of
the minimum load reduction, about 80% is caused by inlet the real components with a dynamic model of the bottoming
heating, while the remaining 20% is related to the power cycle made it possible to emulate a full GTCC in a laboratory
consumption of the HP (3 MWel on average). environment and to test the range enhancer on it.
Table 4 shows the comparison between the performance of The experimental campaign, which was designed to activate
the plant without and with inlet conditioning. The percentage all the possible plant configurations, showed the effectiveness of
difference with the business-as-usual configuration is displayed the proposed four-levels control system. The proper FLAGs
between brackets for each specific parameter. were scheduled for all the test duration, reducing the compressor

GTP-22-1419 Reboli 11
Journal of Engineering for Gas Turbines and Power. Received July 21, 2022;
Accepted manuscript posted September 03, 2022. doi:10.1115/1.4055495
Copyright (c) 2022 by ASME

intake temperature to increase the maximum power generation doi: 10.1115/GT2015-43159.


of the plant, while heating the intake when it was necessary to [3] T. Reboli, M. Ferrando, L. Mantelli, L. Gini, and et al.,
reduce the minimum environmental load of the GTCC. The “Gas Turbine Combined Cycle Range Enhancer - Part 1:
control system also showed good adaptability to the current Cyber-physical setup (to be published),” in ASME Turbo

Downloaded from http://asmedigitalcollection.asme.org/gasturbinespower/article-pdf/doi/10.1115/1.4055495/6914221/gtp-22-1419.pdf by National Institute of Technology Kurukshetra user on 08 September 2022
operative conditions, switching from TES discharge to inlet Expo 2022, 2022, pp. 1–14.
cooling in case of fully discharged TES. [4] B. Zalba, J. M. Marín, L. F. Cabeza, and H. Mehling,
The GTCC range extender developed for the PUMP-HEAT “Review on thermal energy storage with phase change:
project could be easily adapted to other systems. In fact, it is Materials, heat transfer analysis and applications,” Appl.
regulated by an independent control system, and it requires Therm. Eng., vol. 23, no. 3, pp. 251–283, Feb. 2003, doi:

d
minimum alterations of the pre-existent components. Thanks to 10.1016/S1359-4311(02)00192-8.
these features, it could be tailored both for GTCCs and GTs, [5] V. G. Gkoutzamanis, A. I. K. , Anastasia N.

ite
being included in the layout of new plants or integrated with Chatziangelidou, Theofilos G. Efstathiadis, and J. N. W.
existing facilities to improve their flexibility and provide a C. Alberto Traverso, “THERMAL ENERGY

ed
competitive advantage on the energy market. STORAGE FOR GAS TURBINE POWER
The cyber-physical approach for the emulation of GTCCs AUGMENTATION,” GPPS Conf., pp. 1–11, 2019.
could be adopted by other researchers, making it possible to [6] A. Sorce, A. Giugno, D. Marino, S. Piola, and R.

py
study heavy duty plants in a laboratory environment. Hopefully Guedez, “Analysis of a Combined Cycle Exploiting Inlet
this will help the development of technological solutions and Conditioning Technologies for Power Modulation,”
control strategies aimed at increasing the flexibility of GTCCs, Proc. ASME Turbo Expo, vol. 3, Nov. 2019, doi:

Co
making them a key element towards decarbonization. 10.1115/GT2019-91541.
Analyzing the results presented for this study, and [7] J. Duquette, D. O’Sullivan, S. Ceballos, and R. Alcorn,
conducting additional experiments, it will be possible to “Design and Construction of an Experimental Wave

ot
characterize the real behavior of the devices installed in the Energy Device Emulator Test Rig,” 2009.
laboratory, in particular mGT, HP and TES. The dynamic model [8] J. Agrawal and M. Aware, “Photovoltaic system
will be then calibrated on the available data, in order to minimize emulator,” PEDES 2012 - IEEE Int. Conf. Power
tN
the error between simulations and experimental tests. For this Electron. Drives Energy Syst., 2012, doi:
purpose, it will be necessary to determine the exact time 10.1109/PEDES.2012.6484360.
constants of the main physical phenomena and to accurately [9] S. Tan, W. Z. Song, S. Yothment, J. Yang, and L. Tong,
rip

model the effect of the various inlet conditioning strategies on “ScorePlus: An integrated scalable cyber-physical
the turbomachinery. Thanks to the high accuracy of the model, it experiment environment for Smart Grid,” 2015 12th
will be possible to test the plant and its control system also in a Annu. IEEE Int. Conf. Sensing, Commun. Networking,
sc

a model-in-the-loop setup. In this way, the performance of the SECON 2015, pp. 381–389, Nov. 2015, doi:
plant will be easily evaluated on multiple scenarios, providing a 10.1109/SAHCN.2015.7338338.
nu

more deep understanding of the GTCC range enhancer. [10] D. Tucker, P. Pezzini, and K. M. Bryden, “Cyber-
Physical Systems: A New Paradigm for Energy
Technology Development,” Jun. 2018, doi:
ACKNOWLEDGEMENTS
Ma

10.1115/POWER2018-7315.
This project has received funding from
[11] T. Reboli, I. Rossi, A. Traverso, and G. Torelli, “A
the European Union's Horizon 2020 research
guideline to link the off-design performance of a micro-
and innovation programme under grant
gas turbine to a heavy-duty gas turbine in a test rig that
ed

agreement No 764706, PUMP-HEAT.


aim to investigate flexibility of GTCC,” E3S Web Conf.,
The authors devote a special acknowledgement to Iacopo
vol. 238, p. 05003, Feb. 2021, doi:
Rossi and Yutaka Watanabe for the help provided on the
10.1051/E3SCONF/202123805003.
pt

development of control systems and dynamic models.


[12] E. Lerma, R. Costa-Castelló, R. Griñó, and C. Sanchis,
The authors devote a special acknowledgement also to the
“Duino-Based Learning (DBL) in Control Engineering
ce

project partners MAYEKAWA Europe NV, i-TES Srl and SIT


Courses,” IEEE Int. Conf. Emerg. Technol. Fact. Autom.
Technologies Srl for having provided equipment and advise for
ETFA, vol. 2019-September, pp. 798–803, Sep. 2019,
the new laboratory realization.
Ac

doi: 10.1109/ETFA.2019.8869451.
[13] W. Mantilla, R. Guédez, J. García, and A. Sorce, “Short-
term optimization of a combined cycle power plant
REFERENCES integrated with an inlet air conditioning unit,” in
[1] Pump-Heat Project, “D4 . 6 – ‘ Validation results in Proceedings of the ASME Turbo Expo, 2020, vol. 5, doi:
Energy -Hub of MPC with cold thermal storage ,’” 2021. 10.1115/GT2020-15162.
[2] M. A. Ancona, M. Bianchi, F. Melino, and A. Peretto,
“Power Augmentation Technologies: Part I — Literature
Review,” Proc. ASME Turbo Expo, vol. 3, Aug. 2015,

GTP-22-1419 Reboli 12

You might also like