Petroleum Development Oman L.L.C.

Plant Lifecycle Information Plan


(Handover and As-Built Documentation)

Document ID SP-1131

Document Type Specification

Security Restricted

Discipline Project Engineering

Owner Julian Masters UEP

Issue Date April 2018

Revision 6.0

This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part of this document
may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form by any means
(electronic, mechanical, reprographic recording or otherwise) without prior written consent of the owner.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

I Authorized For Issue – April 2018

Page 2 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

II Revision History
The following are brief revision summary of this document. Details of all revisions prior to these
are held on file by the issuing department.

Revision Date Originator Checker Reviewers Scope /


No. Remarks
Revision 6.0 Apr-18 Kingsley Chime Maulana, Andre CTP34 Brockman, Anna Updated to
UEOI41 Chukwuma, Chinonso UOP21; incorporate
UEOI12 Patrick Liesker outcome of
Morowei, Ebikpogba UEP5; Bulushi, FRD2, address
UEOI23 Yousuf UOI1; EORD delivery,
Parthasarathy, Yahyaee, Ali Tier1
Veeraraghavan UEOI14 UOI2; Campbell, Dependency
Mistry, Daxesh UEOI13 Ian UOP6 Matrix and PLIP
Paramasivan, Suresh doctype
Kumar UEOI15 rationalization
Patel, Amitkumar
UEOI46; Bhayani,
Kaushikkumar UEOI43;
Lawatia, Ali UEOI11

Page 3 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

TABLE OF CONTENT
I Authorized For Issue – April 2018........................................................................................ 2
II Revision History ................................................................................................................... 3
1 INTRODUCTION ............................................................................................................................ 5
1.1 Purpose ................................................................................................................................... 5
1.2 Changes to this Specification ......................................................................................... 5
1.3 Step-out Approval ................................................................................................................ 5
1.4 Scope ....................................................................................................................................... 5
1.5 Definitions ............................................................................................................................... 6
1.6 Abbreviations ......................................................................................................................... 6
1.7 Related CMF Business Control Documents ............................................................. 7
2 GENERAL REQUIREMENT ...................................................................................................... 8
3 PROJECT HANDOVER DELIVERABLES REQUIREMENT ........................................ 9
3.1 Master Information Deliverables .................................................................................... 9
3.2 Critical Documents & Data ............................................................................................... 9
3.3 Manufacturers (Vendor) Record Book (MRB) .......................................................... 9
3.4 Plant Operating Manual ..................................................................................................11
3.5 Commissioning Work Packs .........................................................................................11
3.6 Project Change Control ...................................................................................................12
3.7 Document Classification .................................................................................................12
3.8 Storage of Information .....................................................................................................12
3.9 Master Information Retrieval and Control ................................................................12
3.10 Pre-Start-up Audit (PSUA) Documentation .............................................................12
3.11 As-Building and TA Approval ........................................................................................12
3.12 Quality Assurance .............................................................................................................13
3.13 IM Kick-off Form .................................................................................................................13
3.14 Engineering and Operations Reference Document (EORD) ...........................13
3.15 Early Tie-in/Scope Handover ........................................................................................13
3.16 Tier1 Critical Documentation Modification Dependency ....................................13
4 ROLES AND RESPONSIBILITIES........................................................................................16
4.1 Project Engineer/Manager .............................................................................................16
4.2 Project Discipline Engineer ............................................................................................16
4.3 IM Delivery Lead ................................................................................................................16
4.4 Contractor .............................................................................................................................16
5 PLIP TEMPLATE DESCRIPTION .........................................................................................17
6 NAMES OF DISCIPLINE SUPPORT ENGINEER ..........................................................20
7 APPENDICES ................................................................................................................................22
Appendix 1: Plant Lifecycle Information Plan (Template) ............................................22
Appendix 2: MRB Document Type Handover Format Definition ...............................22
Appendix 3: IM Kick-off Form ..................................................................................................22
Appendix 4: User Feedback Form .........................................................................................22
Appendix 5: MRB Document/Drawing Hanover ...............................................................22
Appendix 6: MRB File Handover Template........................................................................22

Page 4 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

Page 5 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

1 INTRODUCTION
Project records, documents, drawings and business process data (for CIMS, SAP, EDW, etc), are critical
to safe Operation and Maintenance of PDO’s Assets. This document brings the deliverable requirements
for Asset Lifecycle Information Management into one place. It is applicable for all PDO assets and
projects no matter which contracting strategy is pursued.
The Plant Lifecycle Information Plan (PLIP) is the standard PDO document reference library that
describes ‘What’ information shall be developed by a project and their distribution. It contains generic
listing of Information deliverables requirements (drawing, data, records and documents) to be developed
during project, and what is to be handed over to support Operations. It provides means of ensuring
deliverables completeness and delivery of all Critical Documentation that are essential for Asset
Operations lifecycle as required in CP-115.
1.1 Purpose
Every new or modified Asset will either produce new information deliverables or modify existing ones.
The purpose of this specification is to specify information requirements (records, drawings, business
process data and documents), that may be developed or modified and delivered at the end of a project.
It shall be used to set project deliverable expectation in SELECT (Basis for Design), DEFINE (FEED),
EXECUTE (Detailed Design and Construction) and OPERATE (modifications) phases.
The PCAP (DCAF) deliverables requirement is mapped in the PLIP so that it serves as the primary
source of information deliverables that shall be scaled by the project delivery team to produce a project
specific DDR.
Refer to requirement in DEP 82.00.10.30-Gen: Engineering Information Specification (EIS), section 3.3
Classification of Documents.
1.2 Changes to this Specification
The Owner of this document is the CFDH, Engineering Project Delivery (UEP) and the custodian is the
manager of Engineering and Operations Information (UOI). Users of this Document who identify
inaccuracy or ambiguity should utilize the “User Feedback Page” provided in the Appendix 4 to notify the
Custodian or his/her delegate, and request changes be initiated.
1.3 Step-out Approval
Should compliance be considered inappropriate, then step out approval must be obtained from the
Document Custodian in accordance with approved Change Control system prior to any changes or
activities associated with the specification being carried out.
1.4 Scope
The Information set contained in appendix 1 is a generic list of Information requirements from which a
project specific DDR shall be developed. The PLIP template readily filters into PDO deliverables
distribution requirement (DDM), final handover deliverables, and Critical Documentation requirement
(required for Operating Integrity).
All Operations activities that change the plant shall also modify corresponding Information in line with the
modification Dependency Matrix of section 3.15 to reflect the change. The "default values" in the template
came originally from 3 sources:
 Reference tables in DEP 82.00.10.30-Gen Engineering Information Specifications,
 Data from previous projects
 Existing discipline documents
These have been validated by the respective discipline CFDHs.

Page 6 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

1.5 Definitions
Deliverable(s) Product(s) of an activity (ies) or undertaking(s). The product can be a
document, data, drawing, record or just an activity.
DCAF Discipline Control and Assurance Framework: specifies the TA level
required to review and approve discipline control deliverables.
Electronic Electronic file created by scanning or direct rendition through software.
Image
Document Manuals, drawing, reports, datasheet, etc
Information Documents, 3D Model, Engineering Data and Business process data
deliverables (E-SPIR; SAP-PM, CIMS, EDW, etc)
IM Kickoff Form Template populated to request existing data to be issued for a project
work. It contains concurrent modification and dependency declaration
by the PE.
Livelink PDO corporate EDMS.
Compound Multiple files (maybe containing independent files), which are delivered
Document as a single document, e.g. MRBs
Contractor A party to a Contract with PDO.

1.6 Abbreviations
AFC Approved for Construction
AFD Approved for Design
AIC Asset Information Center
AI-PSM Asset Integrity – Process Safety Management
CCMS Certification and Completion Management System
CMMS Computerized Maintenance Management System
DDR Document Deliverables Register
DDM Document Distribution Matrix
EDS Engineering Design System
EDMS Electronic Document Management System
EIS Engineering Information Specification
EOIM Engineering and Operations Information Management
EORD Engineering and Operations Reference Documents
FCP Facility Change Proposal
IFR Issued for Review
IM Information Management
IOM Installation, Operation and Maintenance Manual
ITT Invitation To Tender
MRB Manufacturers Record Book
PCAP Project Control and Assurance Plan
PCC Project Close-out Certificate
PE Project Engineer
PLIP Plant Lifecycle Information Plan
PLN SP-2065 document status that indicates a document is planned for development
in project, will change to IFR document is created.

Page 7 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

SoF Statement of Fitness


PIN Project Initiation Note
POM Plant Operating Manual
PDMS Plant Design Management System
PSUA Pre-Start-up Audit
RLMU Redline Mark-up Drawings
TA Technical Authority
VDRL Vendor Document Requirements Listing: listing showing specific Document
requirement relating to the equipment being supplied or manufactured.
WP Work Package; a group of activities that are considered as one unit from the
planning perspective.
1.7 Related CMF Business Control Documents
The related CMF Documents can be retrieved from the CMF Business Control Portal.
1 CP-102: Data and Document Management Code of Practice
2 CP-115: Operation of Surface Product Flow Assets
3 CP-117: Project Engineering Code of Practice
4 CP-223: Opportunity Realization Code of Practice
5 SP-1074: Preparation of Plant Operation Manuals
6 SP-1131: Handover & As-Built Documentation (Plant Lifecycle Information Plan)
7 SP-1134: General Specification for Detailed Engineering of Oil & Gas Facilities
8 SP-2065: Document Management In Engineering Projects and Operations
9 SP-2113: Specification for Commissioning and Start-Up
10 SP-2122: E&O Information Management Specification
11 SP-2142: Engineering Project Data Specification
12 SP-2144: Engineering Project IM SoW
13 PR-1052: Preparation and Updating of Station Plant Operating Manuals
14 PR-1150: Project Close-out Procedure
15 PR-1159: Commissioning Procedure
16 PR-1169: Initial Start-Up Procedure
17 PR-1247: Project Management of Change Procedure
18 PR-1358: Concept Engineering in Select Phase (DG3) Procedure
19 PR-1666: E & O Document, Drawing and Data Management Procedure
20 PR-1692: PDO Document Retention Procedure
21 PR-2066: Deviation from Standard and Procedure
22 PR-2117: Engineering Project Data Control Procedure
23 PR-2160: Pre Start-up Audit Procedure
24 DEP 82.00.10.30-GEN (Engineering Information Specification) February 2012

Page 8 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

2 GENERAL REQUIREMENT
Plant Lifecycle Information Plan (PLIP) appendix 1 is the PDO’s information reference library (document,
drawings and data) of all information that could be generated in projects. It shall be referenced by project
delivery team to select information deliverables scope for the project. The deliverables selected becomes
the project specific DDR.

The PLIP has predefined distribution list for each deliverable, which may be customized for a project
specific scope. The project shall produce a project specific DDM from the predefined list in PLIP.

The project engineer/manager shall notify the IM team, with the individual per discipline, who will carry
out the discipline review/approval and the IM team will update DDM.

The project will develop/modify deliverables in line with PR-1666 - Engineering and Operations
Document, Drawing and Data Control Procedure, and on completion of project, handover the IM
deliverables electronically to the project IM focal point.

The project shall follow SP-2122: E&O IM Specifications, for deliverables handover and assurance
requirements. The IM team shall deliver the Business process data to application owners for publishing
as required by SP-2142: Engineering Project Data Specification.

The project team shall follow PR-1150: Project Close-out Procedure for the successful project delivery,
facility handover to Asset team and closeout.

Page 9 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

3 PROJECT HANDOVER DELIVERABLES REQUIREMENT


When a project is completed, it is the responsibility of the Project delivery team to ensure delivery of both
completed Physical Asset as well as the Information Asset to Operations in line with PR-1150: Project
Close-Out Procedure.
Final Master Information to be delivered to PDO shall be as specified in the project specific DDR:
 The Contractor shall deliver to PDO (AIC), complete final handover package electronically as
specified in project scope specific DDR
 Operating Integrity IM team (UOI2) shall prepare and deliver Tier1 Critical Documentation to the
Field
 The Master Hardcopy delivered to the field shall be received by the OI Coordinator (OXO16x) who
will sign the transmittal, stamp/sign the deliverables received and deliver them to the station
 Information retention shall be in line with CP-102: Corporate Document Management – CoP and
PR-1692: PDO Document Retention Procedure
3.1 Master Information Deliverables
Master information comprises of: As-Built drawings like PEFS, Certified Final Document like POM, 3D
model files and Business Process data for systems (SAP-PM, CCMS, CIMS, EDW, etc). They shall be
delivered as applicable to data system custodian in line with SP-2142 and SP-1131.
These information deliverables are developed or modified during projects or operations as a result of new
Asset development or modification of existing Assets (no matter how small the modification may be).
3.2 Critical Documents & Data
Tier 1 and 2 Critical Documentation: As-Built drawing, Certified Final document, and Data (business
process data like SAP-PM, etc), are as defined in CP-115 - Operation of Surface Product Flow Assets -
CoP, as the minimum Master Information deliverables that shall be delivered to Operations at the end of
an Engineering project.
Only Tier 1 Critical Documentation shall be produced in hardcopy format and maintained at the station to
support Asset operation, refer to PR-1666 for detailed lifecycle management procedure.
3.3 Manufacturers (Vendor) Record Book (MRB)
MRB concept is PDO means of delivering VDRL records (drawings, datasheets, etc) defined in project to
be delivered as part of equipment procurement.
During project handover, MRB shall be delivered to AIC for publishing in the E&O IM Portal along with
other project information deliverables. Follow appendix 2 for MRB doctype handover format definition.
The procurer (PDO or Contractor) shall customize the VDRL template in SP-2065 - Document
Management in Engineering Projects - Appendix 3 for relevant documentation required to support
operation and maintenance of the equipment. The MRB shall be delivered in electronic format with only
one clean master hardcopy delivered and maintained in the Field.

Page 10 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

3.3.1 MRB File Handover Template


Follow below structure of appendix 6, for MRB file handover template, which shows the actual
equipment records produced for the equipment and their reference document numbers. During operation,
MRB records shall be retrieved by searching the E&O IM Portal using FLOC or Tag number. The FLOC-
Tag-Document reference table delivered as part of EDW shall retain the link between equipments and
associated MRB documentation.

3.3.2 MRB Document/Multiple Drawing Handover


Each VDRL doctype in MRB shall be delivered separately, doctype by doctype. Where the doctype is
document (e.g. datasheet, installation manual, etc), or a drawing with multiple sheets (e.g. PEFS, etc),
the structure below of appendix 5 shall be applied in delivering the MRB electronically.

Page 11 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

3.4 Plant Operating Manual


The Plant Operating Manual (POM) contains or refers to document types like PEFS (a distinct document
with identification number). These document types shall not be added or inserted (as picture or object)
directly on the POM but shall be referenced, indexed and hyperlinked from POM to the original location of
the master drawing. This will maintain single master location of information, and allow modification to take
place independently on the referenced information.
For each modification project, an assessment of impact on the existing POM shall be undertaken in line
with section 3.16, and where impact is identified, it shall be made directly to the master POM held by AIC,
rather than creating an addendum file (see section 3.16 for addendum requirements). The Contractor
shall update the POM in accordance with the following Specifications and Procedures:
 SP-1074: Preparation of Plant Operation Manuals Specification
 PR-1052: Preparation and Updating of Station Plant Operating Manuals.
 PR-1666: Engineering and Operations Document, Drawing and Data Control Procedure.
The POM shall be delivered in electronic format, fully indexed with hyperlink of the original location of any
document referenced in the POM and with only one clean master hardcopy delivered and maintained
in the Field.
3.5 Commissioning Work Packs
On completion of the construction, pre-commissioning / commissioning and handover of the project, all
Construction, Fabrication and Commissioning deliverables (CCMS punch lists, check sheets, test sheets,
quality dossier, handover certificates, etc), associated with works on the facilities shall be assembled,
delivered, retained and archived electronically in AIC in the appropriate work parks. The work packs shall
be signed off by all parties as detailed on the individual sheets and certificates. For more details refer to:
 SP-2113: Specification for Commissioning and Start-Up (Key Principles)
 GU-623: Project Completion Management System CMS Guideline

Page 12 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

3.6 Project Change Control


Notification and approval documents relating to: changes / variances in Basis for Design, Front End
Design Deliverables, Project Specification, Budget Proposals / RFAs, Detailed Design (AFC drawings
and documentation) and selected Standards shall be held in the project workspace and form part of the
handover to AIC.
Reference should be made to PR-1247: Project Management of Change Procedure and PR-1153: Field
Trouble Reporting Procedure for more information.
3.7 Document Classification
This standard defines document types and assigns numeric classification codes (refer appendix 1) to
each type, to aid their reference and retrieval from IM system.
3.8 Storage of Information
Electronic version of Master Information delivered at the end of a project shall be stored and maintained
centrally in AIC while hardcopies of Tier 1 Critical Documentation and MRBs shall be delivered to the
respective Field. Project hardcopy information required shall be delivered to AIC (central archive).
Similarly, the Design Integrity IM Team shall handover the archive location of project workspace to AIC
for archiving; refer to PR-1666.

3.9 Master Information Retrieval and Control


Master Information required for Operating, Maintenance and Design Integrity is controlled electronically in
AIC, and becomes uncontrolled when printed unless stamped with “Controlled Hardcopy” and wet
signed, or printed with watermark, etc.
During a project, construction deliverables in hardcopy shall be printed from the project IM system and
signed by the IM focal point of the party that made the print to confirm the source of printing. Any other
printed hardcopy or electronic version residing elsewhere is uncontrolled.
Information required for reference or to support activities (PIN, Integrity and FCP of existing asset) shall
be retrieved from AIC IM Portal system.

3.10 Pre-Start-up Audit (PSUA) Documentation


Documents identified in the project DDR as “REQUIRED_FOR_FINAL_HANDOVER” shall be available in
their final form prior to the PSUA. This requirement recognizes that certain drawings may still be in RLMU
state; As-Built drawings may still be outstanding.
The project IM Lead shall demonstrate that information deliverables handover assurance review has
been undertaken on a project before progressing with PSUA activities.
Refer to PR-2160: Pre Start-up Audit Procedure for general requirement and guidance for PSUA.

3.11 As-Building and TA Approval


TA review/approvals are required during detailed design and engineering leading to AFC deliverables.
Any change to the AFC package requires appropriate TA approval before being implemented.

Page 13 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

At the end of commissioning, the RLMU drawings shall be signed by both the contractor and the PDO
commissioning engineer (or representative at site), to confirm consistency of RLMU with the actual
constructed work, refer to PR-1666.

3.12 Quality Assurance


The contractor shall have an approved checking and approval process in place (as a part of its ISO9000
system), which is implemented and supported by regular assurance /quality checks.
This will ensure that the information deliverables are reviewed and checked internally before they are
delivered to PDO.

3.13 IM Kick-off Form


The project shall utilize the IM Kick-off Form (appendix 3):
 To request for existing information required for project execution
 To confirm the impact of project on concurrent project or FCP
 To request for allocation of Tags

3.14 Engineering and Operations Reference Document (EORD)


Revised EORD framework for delivering information required for Operations and future modification of
Facility would no longer be produced in the traditional form (binder of selected facility documentation).
Each EORD information deliverable doctypes shall be selected from the PLIP of appendix 1 and included
as part project information deliverable scope in the DDR, which will be delivered and published in the
E&O IM Portal at the end of the project. EORD documentation like PEFS, etc shall be retrieved directly
from the master source, E&O IM Portal.
The Plant Operating Envelopes has been included in the PLIP as a critical document, which shall be
developed and delivered as part of project information delivery published in the E&O IM Portal.
3.15 Early Tie-in/Scope Handover
When a project needs to deliver part of the overall scope, like early Tie-in scope, etc, they shall also
deliver associated handover information. Where any of the information delivered from the early scope is
required to continue the project work, they shall retrieve it from AIC for reference and checkout for As-
Building accordingly.
Early scope delivery shall be identified and RAMZ Subproject ID created:
 Information deliverables associated with the scope identified and delivered to AIC
 Closeout undertaken in AutoPCC for relevant deliverables
3.16 Tier1 Critical Documentation Modification Dependency
The dependency matrix provides the standard for proper IM scoping and clear guideline to the project
team, to ensure that Asset changes will evaluate documents shown on matrix for impact.

For example, a project modification that changes existing asset documentation like PEFS shall evaluate
other existing documentation for impact (HAZOP Report, Operation HSSE Case, MRB, POM
Safeguarding Memorandum, Variable Table, etc), in line with the Dependency matrix below (even with no
Page 14 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

impact). The IM Delivery team will verify compliance as part of Information Deliverables Handover
Assurance Review.

Where change impacted the following information deliverables: HAZOP Report, Safeguarding
Memorandum and POM, the master file shall be retrieved from AIC and updated as part of the project
delivery activities. Addendum will not be accepted without step out; the addendum numbering will be
same with master file as shown below:
PLAN OPERATING MANUAL FOR MARMUL MAIN PRODUCTION
STATION PLAN
MAR-24-104332-OA-4811-00001-0000
ADDENDUM TO POM FOR MARMUL MAIN PRODUCTION
STATION PLAN (Installation of Gas Compressor)
MAR-24-104332-OA-4811-00002-0000

Follow PR-1666: Engineering and Operations Document, Drawing and Data Control procedure during
Information development, modification or field hardcopy management.

Page 15 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18

3.16.1 Modification Dependency Matrix

Page 15 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18

4 ROLES AND RESPONSIBILITIES


4.1 Project Engineer/Manager
Accountable for ensuring that project information deliverables are selected from PLIP at the beginning
of the project (FEED/Detail Design). S/he shall:
 Ensure that where project modifies existing asset documentation like PEFS, the impact on
other existing documentation is assessed in line with section 3.17.1 dependency matrix
 Endorse the project specific DDM for implementation
 Ensure that project information deliverables are not kept or managed elsewhere, that all DDR
deliverables are managed and available in the document management system
4.2 Project Discipline Engineer
 Ensure that the DDR produced by contractor, contains correct discipline deliverables in line
with project scope
 Update DDM template from PLIP with any additional project distribution and send to IM Team
 Review and approve discipline deliverables in DDR, as required in DDM
4.3 IM Delivery Lead
 Ensure that DDR and DDM are finalized as part of project initiation, and that DDR deliverables
are planned with status PLN, tracked and reported using the document management system
 Provides electronic reference copy of the master information, including identification of any
other project using the same master.
 Ensure project engineer evaluates impact of existing asset information modification like PEFS
on other data system like SAP, POM, in line with the dependency matrix of 3.17.1.
 Work with PDO partners developing or modifying information to ensure adequate internal
review and approval.
 Ensure that information specified in a project DDR is developed and delivered, ensuring that
information deliverables meets specification for handover AIC.
 Conduct information deliverables handover assurance review in line with project assurance
plan and archive electronic location of project information.
4.4 Contractor
 Agree IM resource with IM Delivery Lead before assigning responsibility for all or part of
information management activities.
 Produce a project specific DDR from the PLIP template of appendix 1, as part of project
initiation and kick-off and agree with PDO discipline focal point
 Update DDR with associated plan showing key information development milestone dates
(Issued for Review and Approved for Design/Construction). These milestones shall be
measured and reported as agreed with the IM Delivery Lead as one of the project KPIs.
 Ensure adequate internal checking and approval of information before delivering to PDO.
 Deliver information deliverables to IM Delivery Lead as contained in DDR.
 Ensure that where project modifies existing asset documentation like PEFS, the impact on
other existing documentation is assessed in line with the modification dependency matrix

Page 16 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18

5 PLIP TEMPLATE DESCRIPTION


COLUMN NAME DESCRIPTION / CLARIFICATION ACTIONS REQUIRED
The party who will produce the document --- either a PDO entity
ORIGINATOR Discipline Lead to specify
or 3rd party or Contractor or Supplier.
The name of the PDO team member who is responsible for the
PROJECT FOCAL POINT Discipline Lead to specify
SOURCE document (prepares or reviews or approves).
Discipline Lead to verify what
Standard "Discipline Code - Discipline name" as defined in is selected by IM team and to
DISCIPLINE_CODE
DEP82.00.10.30-Gen Engineering Information Specifications. consult with IM team if it
should be changed.
Discipline Lead to verify the
INFORMATION REQUIRED A typical title, type or category of documents and data to be
default value (listed by IM
(DOCUMENT & DATA) delivered at various stages through the project lifecycle.
team).

Standard "Discipline-Document Type Code + Name" and


DOCUMENT_TYPE_NAME "Descriptions" defined in DEP82.00.10.30-Gen Engineering
Discipline Lead to verify the
Information Specifications. Standard classification on document
default value (specified by IM
types facilitates document repository in EDMS (standard folder
team).
DOCUMENT_TYPE_ structure in Livelink) and to make cross reference to the Record
CODE Management requirements (e.g. retention).

INFORMATION
DESCRIPTION POSSIBLE TITLES_
Additional description of document types No action
AND_TYPE_DESCRIPTION

Discipline Lead to specify or


verify the default values.
Preferably to refer to a DEP or
Reference to DEP or other samples/examples which define
a Project Specification. As the
REFERENCES minimum requirements or level of details regarding the technical
minimum, the Discipline Lead
contents of the Document.
should be able of providing a
sample/example from previous
projects.
Notes to describe specific project requirements or clarifications Discipline Lead to add specific
PROJECT SPECIFIC NOTES
on the information (document or data) listed. special notes

Page 17 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18

Document Security Classification per PDO guidelines Discipline Lead to verify the
SECURITY_CLASSIFICATION (Unrestricted, Restricted, Confidential, Most Confidential) --- default value (specified by IM
various handling procedures are required team).
Related objects of the Document to facilitate navigation from the
Discipline Lead to verify the
object to the documents. An object can be an Asset type (in
RELATED_OBJECTS default value (specified by IM
Plant Asset Hierarchy --- Site, Plant, Process_Unit, Equipment,
team).
Tag, Model_Parts) or other Document such as a Purchase Order.
Format of the Information (Document or Data) to be delivered Discipline Lead to verify the
BASIC DURING_PROJECT_FORMAT during the project for eview/approval/information (Paper, MS default value (specified by IM
DOCUMENT Word, MS Excel, MS Access, Adobe Acrobat, AutoCAD, etc.) team).
PROPERTIES Format of the Information (Document or Data) to be delivered Discipline Lead to verify the
AFTER_PROJECT_FORMAT during handover to Operation (Paper, MS Word, MS Excel, MS default value (specified by IM
Access, Adobe Acrobat, AutoCAD, etc.) team).
With respect to project scope, identify from the Critical
REQUIRE_FIELD_CONTROLLE PE verifies from Operations,
Documentation list of CP-115, which Information is required to be
D_HARDCOPY default values (Yes or No).
physically available in the field for Operations of the facility.
Categorization/value of the Information (Document or Data) for Discipline Lead to verify the
AFTER_PROJECT_CATEGORY PDO after handover from project to operation (Essential, Legal, default value (specified by IM
Desirable) --- different requirements on repository and retention team).
Discipline Lead to verify the
Based on PDO document group retention guidelines (asset life, 2
RETENTION_PERIOD default value (specified by IM
yrs, etc).
team).
Critical Information (document and data) deliverables as defined Discipline Lead to verify the
CRITICAL_ DOCUMENTATION in CP-115: Operation of Surface Product Flow Asset. This is default value (specified by IM
the minimum deliverables that is required for Operating Integrity. Team).
Discipline Lead to verify the
Document is a deliverable of PCAP (Project Control and
DCAF Control (Identification default value (specified by IM
Assurance Plan). Those "Yes" deliverables subject to PCAP
DOCUMENT Number) team) against the latest signed
requirement.
PCAP-discipline list.
DELIVERY
(SELECT) REQ_FOR_ Will the Information (documents & data) be delivered as part of Discipline Lead to verify the
REQUIRED CONCEPT SELECTION the concept selection? default values (Yes or No).
PER PROJECT
(DEFINE) REQ_FOR_ PROJECT Will the Information (documents & data) be delivered as part of Discipline Lead to verify the
PHASE _ SPECIFICATION/FEED the project specification package (FEED)? default values (Yes or No).
(EXECUTE) REQ_FOR_
Will the Information (documents & data) be delivered as part of Discipline Lead to verify the
DETAILED DESIGN AND
the detailed design package? default values (Yes or No).
CONSTRUCTION
(OPERATE) REQ_FOR_ PSUA_ Will the Information (documents & data) be required to support Discipline Lead to verify the

Page 18 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18

COMMISIONING AND PSUA, Pre-commissioning and Commissioning/Start-up default values (Yes or No).
OPERATION (Flawless start-up initiative)?
REQUIRED_FOR_FINAL_HAND Will the Information (documents & data) be required as part of the Discipline Lead to verify the
OVER handover package to PDO? default values (Yes or No).
Will the Information (documents & data) deliver as As-built (ASB) Discipline Lead to verify the
REQUIRED_HANDOVER_
or Certified FINAL (revision of information not requiring As- default values (ASB, FINAL or
STATUS (ASB or FINAL)
Building)? If value is no, then information not required. No).
This field was left blank to allow project customization in line with
project strategy. It should be populated as part of MDR
REQUIRE_PDO_REVIEW/APPR development, to capture PDO's review requirements on Discipline Lead to specify or
OVAL documents produced by others (contractor / suppliers) per the verify the default values.
Document Type: IFR=Issue For Review; IFA=Issue For
Approval; IFI=Issue For Information; No=No review required.
Resource typically a
Highlights document types in which RLMUs may be generated. At
commissioning Engineer but
the end of project, PDO focal point shall check As-Built produced
OTHERS FINAL RED-LINE CHECKING the Project Engineer to agree
against “RLMU”, to confirm that As-Built produced is a true
resource with Operations if
reflection of constructed works.
different
Who is the final owner/status of the deliverable after handover?
Typically, ownership of Critical Documentations is with the Asset Discipline Lead to specify or
FINAL OWNER/STATUS
Manager, while other deliverables are stored electronically in a verify the default values.
secured EDMS location for future reference.
COMMENT General comments from IM team or Discipline Lead

Page 19 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18

6 NAMES OF DISCIPLINE SUPPORT ENGINEER


The names of respective discipline engineer assigned to support the project scope (full time or part time) are as follows:

DISCIPLINE LEAD (Focal


Remar
Point in PDO Project
DISCIPLIN k
Team)
E DISCIPLINE DESCRIPTION
Defin Detaile
_CODE Execut
e- d
e
FEED Design
Management and Project execution plan, basis of design, organization, authorities.
AA
Project Engineering Integrated plans such as those for Pre-Commissioning.
BA Construction Construction- and fabrication-related information. Also, installation and
transportation specifications.
CB Architectural All buildings: including interior design and structure.
CG Geotechnical / Soil properties, shallow hazards, piles, suction piles, anchors, mud
Foundation mats.
CI Infrastructure Onshore: Roads, drainage, sewering, fences, etc.
CS Structures All major structures (steel and concrete) also vessels, ships, jackets,
topside modules, floating production systems.
EA Electrical Design and application of circuitry and equipment for power generation
and distribution, machine control.
FA Cost and Planning Integrated project cost, schedule, budget estimating and tracking.
HE Environmental Environment-related topics.
HH Health Human and animal health.
HP Security Prevention of espionage, sabotage, intellectual property leakage, attack
or unauthorized handling.
HS Safety Technical Safety-related topics.
HX HSE&S General To use if Health, Safety, Environment and Security document cannot be
assigned to one of the other HSE&S document types (i.e. not
Environmental, Health, Safety, Security. Also for Hazard Management).
IC IC Process control For Process Control and Optimization discipline related deliverables.
& Optimization. Distributed control systems, PLCs, process control logic

Page 20 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18

IN Instrumentation Instruments and instrument systems


JA Information Content management, Data, Document and Knowledge management,
Management Procedures, Specifications, Standards.
KA Information IT Infrastructure, hardware, software, applications
Technology
LA Pipelines Line pipe, stability, hydraulics, installation, commissioning.
MP Piping Pipe, flanges, fittings, valves, pipe supports, stress analysis.
MH HVAC Heating, Ventilation and Air-conditioning.
MR Rotating Equipment Compressors, pumps turbines, etc.
MS Mechanical - Static Vessels, furnaces, boilers, tanks, etc.
MX Mechanical Other Use only when the other Mechanical disciplines cannot be used (i.e. not
HVAC, Mechanical - Static, Piping, Rotating Equipment)
NA Engineering The branch of engineering that deals with equipment reliability.
Maintenance
OA Operations Readiness for production, marine, subsea, logistics, supply base,
shutdown, etc.
PF Fluid Flow Includes all issues important to maintaining the flow of oil and gas from
Assurance reservoir to receiving facilities.
PX Process Other Use only when the other Process disciplines cannot be used (i.e. not
Fluid Flow and Assurance, Process Operational Turnaround Support,
Process Technology)
QA Quality Assurance Includes formal review of designs, problem identification, corrective
actions to remedy any deficiencies and evaluation of actions taken.
RA Materials and Materials, corrosion and coating issues across multiple disciplines.
Corrosion
TA Telecommunication Radio communication, satellite and Cable communication, etc.
ZT Production Everything related to Production Technology
Technology
ZP Petrophysics. Everything related to Petrophysics
ZR Reservoir Everything related to Reservoir Engineering
Engineering
ZV Vendor All equipment deliverables
ZW Well Engineering Everything related to oil and gas wells.

Page 21 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18

7 APPENDICES
Appendix 1: Plant Lifecycle Information Plan (Template)
Appendix 2: MRB Document Type Handover Format Definition
Appendix 3: IM Kick-off Form
Appendix 4: User Feedback Form
Appendix 5: MRB Document/Drawing Hanover
Appendix 6: MRB File Handover Template

Page 22 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.