Document ID SP-1131
Security Restricted
Revision 6.0
This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any part of this document
may be disclosed to others or reproduced, stored in a retrieval system, or transmitted in any form by any means
(electronic, mechanical, reprographic recording or otherwise) without prior written consent of the owner.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
Page 2 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
II Revision History
The following are brief revision summary of this document. Details of all revisions prior to these
are held on file by the issuing department.
Page 3 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
TABLE OF CONTENT
I Authorized For Issue – April 2018........................................................................................ 2
II Revision History ................................................................................................................... 3
1 INTRODUCTION ............................................................................................................................ 5
1.1 Purpose ................................................................................................................................... 5
1.2 Changes to this Specification ......................................................................................... 5
1.3 Step-out Approval ................................................................................................................ 5
1.4 Scope ....................................................................................................................................... 5
1.5 Definitions ............................................................................................................................... 6
1.6 Abbreviations ......................................................................................................................... 6
1.7 Related CMF Business Control Documents ............................................................. 7
2 GENERAL REQUIREMENT ...................................................................................................... 8
3 PROJECT HANDOVER DELIVERABLES REQUIREMENT ........................................ 9
3.1 Master Information Deliverables .................................................................................... 9
3.2 Critical Documents & Data ............................................................................................... 9
3.3 Manufacturers (Vendor) Record Book (MRB) .......................................................... 9
3.4 Plant Operating Manual ..................................................................................................11
3.5 Commissioning Work Packs .........................................................................................11
3.6 Project Change Control ...................................................................................................12
3.7 Document Classification .................................................................................................12
3.8 Storage of Information .....................................................................................................12
3.9 Master Information Retrieval and Control ................................................................12
3.10 Pre-Start-up Audit (PSUA) Documentation .............................................................12
3.11 As-Building and TA Approval ........................................................................................12
3.12 Quality Assurance .............................................................................................................13
3.13 IM Kick-off Form .................................................................................................................13
3.14 Engineering and Operations Reference Document (EORD) ...........................13
3.15 Early Tie-in/Scope Handover ........................................................................................13
3.16 Tier1 Critical Documentation Modification Dependency ....................................13
4 ROLES AND RESPONSIBILITIES........................................................................................16
4.1 Project Engineer/Manager .............................................................................................16
4.2 Project Discipline Engineer ............................................................................................16
4.3 IM Delivery Lead ................................................................................................................16
4.4 Contractor .............................................................................................................................16
5 PLIP TEMPLATE DESCRIPTION .........................................................................................17
6 NAMES OF DISCIPLINE SUPPORT ENGINEER ..........................................................20
7 APPENDICES ................................................................................................................................22
Appendix 1: Plant Lifecycle Information Plan (Template) ............................................22
Appendix 2: MRB Document Type Handover Format Definition ...............................22
Appendix 3: IM Kick-off Form ..................................................................................................22
Appendix 4: User Feedback Form .........................................................................................22
Appendix 5: MRB Document/Drawing Hanover ...............................................................22
Appendix 6: MRB File Handover Template........................................................................22
Page 4 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
Page 5 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
1 INTRODUCTION
Project records, documents, drawings and business process data (for CIMS, SAP, EDW, etc), are critical
to safe Operation and Maintenance of PDO’s Assets. This document brings the deliverable requirements
for Asset Lifecycle Information Management into one place. It is applicable for all PDO assets and
projects no matter which contracting strategy is pursued.
The Plant Lifecycle Information Plan (PLIP) is the standard PDO document reference library that
describes ‘What’ information shall be developed by a project and their distribution. It contains generic
listing of Information deliverables requirements (drawing, data, records and documents) to be developed
during project, and what is to be handed over to support Operations. It provides means of ensuring
deliverables completeness and delivery of all Critical Documentation that are essential for Asset
Operations lifecycle as required in CP-115.
1.1 Purpose
Every new or modified Asset will either produce new information deliverables or modify existing ones.
The purpose of this specification is to specify information requirements (records, drawings, business
process data and documents), that may be developed or modified and delivered at the end of a project.
It shall be used to set project deliverable expectation in SELECT (Basis for Design), DEFINE (FEED),
EXECUTE (Detailed Design and Construction) and OPERATE (modifications) phases.
The PCAP (DCAF) deliverables requirement is mapped in the PLIP so that it serves as the primary
source of information deliverables that shall be scaled by the project delivery team to produce a project
specific DDR.
Refer to requirement in DEP 82.00.10.30-Gen: Engineering Information Specification (EIS), section 3.3
Classification of Documents.
1.2 Changes to this Specification
The Owner of this document is the CFDH, Engineering Project Delivery (UEP) and the custodian is the
manager of Engineering and Operations Information (UOI). Users of this Document who identify
inaccuracy or ambiguity should utilize the “User Feedback Page” provided in the Appendix 4 to notify the
Custodian or his/her delegate, and request changes be initiated.
1.3 Step-out Approval
Should compliance be considered inappropriate, then step out approval must be obtained from the
Document Custodian in accordance with approved Change Control system prior to any changes or
activities associated with the specification being carried out.
1.4 Scope
The Information set contained in appendix 1 is a generic list of Information requirements from which a
project specific DDR shall be developed. The PLIP template readily filters into PDO deliverables
distribution requirement (DDM), final handover deliverables, and Critical Documentation requirement
(required for Operating Integrity).
All Operations activities that change the plant shall also modify corresponding Information in line with the
modification Dependency Matrix of section 3.15 to reflect the change. The "default values" in the template
came originally from 3 sources:
Reference tables in DEP 82.00.10.30-Gen Engineering Information Specifications,
Data from previous projects
Existing discipline documents
These have been validated by the respective discipline CFDHs.
Page 6 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
1.5 Definitions
Deliverable(s) Product(s) of an activity (ies) or undertaking(s). The product can be a
document, data, drawing, record or just an activity.
DCAF Discipline Control and Assurance Framework: specifies the TA level
required to review and approve discipline control deliverables.
Electronic Electronic file created by scanning or direct rendition through software.
Image
Document Manuals, drawing, reports, datasheet, etc
Information Documents, 3D Model, Engineering Data and Business process data
deliverables (E-SPIR; SAP-PM, CIMS, EDW, etc)
IM Kickoff Form Template populated to request existing data to be issued for a project
work. It contains concurrent modification and dependency declaration
by the PE.
Livelink PDO corporate EDMS.
Compound Multiple files (maybe containing independent files), which are delivered
Document as a single document, e.g. MRBs
Contractor A party to a Contract with PDO.
1.6 Abbreviations
AFC Approved for Construction
AFD Approved for Design
AIC Asset Information Center
AI-PSM Asset Integrity – Process Safety Management
CCMS Certification and Completion Management System
CMMS Computerized Maintenance Management System
DDR Document Deliverables Register
DDM Document Distribution Matrix
EDS Engineering Design System
EDMS Electronic Document Management System
EIS Engineering Information Specification
EOIM Engineering and Operations Information Management
EORD Engineering and Operations Reference Documents
FCP Facility Change Proposal
IFR Issued for Review
IM Information Management
IOM Installation, Operation and Maintenance Manual
ITT Invitation To Tender
MRB Manufacturers Record Book
PCAP Project Control and Assurance Plan
PCC Project Close-out Certificate
PE Project Engineer
PLIP Plant Lifecycle Information Plan
PLN SP-2065 document status that indicates a document is planned for development
in project, will change to IFR document is created.
Page 7 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
Page 8 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
2 GENERAL REQUIREMENT
Plant Lifecycle Information Plan (PLIP) appendix 1 is the PDO’s information reference library (document,
drawings and data) of all information that could be generated in projects. It shall be referenced by project
delivery team to select information deliverables scope for the project. The deliverables selected becomes
the project specific DDR.
The PLIP has predefined distribution list for each deliverable, which may be customized for a project
specific scope. The project shall produce a project specific DDM from the predefined list in PLIP.
The project engineer/manager shall notify the IM team, with the individual per discipline, who will carry
out the discipline review/approval and the IM team will update DDM.
The project will develop/modify deliverables in line with PR-1666 - Engineering and Operations
Document, Drawing and Data Control Procedure, and on completion of project, handover the IM
deliverables electronically to the project IM focal point.
The project shall follow SP-2122: E&O IM Specifications, for deliverables handover and assurance
requirements. The IM team shall deliver the Business process data to application owners for publishing
as required by SP-2142: Engineering Project Data Specification.
The project team shall follow PR-1150: Project Close-out Procedure for the successful project delivery,
facility handover to Asset team and closeout.
Page 9 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
Page 10 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
Page 11 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
Page 12 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
Page 13 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
At the end of commissioning, the RLMU drawings shall be signed by both the contractor and the PDO
commissioning engineer (or representative at site), to confirm consistency of RLMU with the actual
constructed work, refer to PR-1666.
For example, a project modification that changes existing asset documentation like PEFS shall evaluate
other existing documentation for impact (HAZOP Report, Operation HSSE Case, MRB, POM
Safeguarding Memorandum, Variable Table, etc), in line with the Dependency matrix below (even with no
Page 14 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
impact). The IM Delivery team will verify compliance as part of Information Deliverables Handover
Assurance Review.
Where change impacted the following information deliverables: HAZOP Report, Safeguarding
Memorandum and POM, the master file shall be retrieved from AIC and updated as part of the project
delivery activities. Addendum will not be accepted without step out; the addendum numbering will be
same with master file as shown below:
PLAN OPERATING MANUAL FOR MARMUL MAIN PRODUCTION
STATION PLAN
MAR-24-104332-OA-4811-00001-0000
ADDENDUM TO POM FOR MARMUL MAIN PRODUCTION
STATION PLAN (Installation of Gas Compressor)
MAR-24-104332-OA-4811-00002-0000
Follow PR-1666: Engineering and Operations Document, Drawing and Data Control procedure during
Information development, modification or field hardcopy management.
Page 15 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Apr-18
Page 15 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation)
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18
Page 16 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18
INFORMATION
DESCRIPTION POSSIBLE TITLES_
Additional description of document types No action
AND_TYPE_DESCRIPTION
Page 17 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18
Document Security Classification per PDO guidelines Discipline Lead to verify the
SECURITY_CLASSIFICATION (Unrestricted, Restricted, Confidential, Most Confidential) --- default value (specified by IM
various handling procedures are required team).
Related objects of the Document to facilitate navigation from the
Discipline Lead to verify the
object to the documents. An object can be an Asset type (in
RELATED_OBJECTS default value (specified by IM
Plant Asset Hierarchy --- Site, Plant, Process_Unit, Equipment,
team).
Tag, Model_Parts) or other Document such as a Purchase Order.
Format of the Information (Document or Data) to be delivered Discipline Lead to verify the
BASIC DURING_PROJECT_FORMAT during the project for eview/approval/information (Paper, MS default value (specified by IM
DOCUMENT Word, MS Excel, MS Access, Adobe Acrobat, AutoCAD, etc.) team).
PROPERTIES Format of the Information (Document or Data) to be delivered Discipline Lead to verify the
AFTER_PROJECT_FORMAT during handover to Operation (Paper, MS Word, MS Excel, MS default value (specified by IM
Access, Adobe Acrobat, AutoCAD, etc.) team).
With respect to project scope, identify from the Critical
REQUIRE_FIELD_CONTROLLE PE verifies from Operations,
Documentation list of CP-115, which Information is required to be
D_HARDCOPY default values (Yes or No).
physically available in the field for Operations of the facility.
Categorization/value of the Information (Document or Data) for Discipline Lead to verify the
AFTER_PROJECT_CATEGORY PDO after handover from project to operation (Essential, Legal, default value (specified by IM
Desirable) --- different requirements on repository and retention team).
Discipline Lead to verify the
Based on PDO document group retention guidelines (asset life, 2
RETENTION_PERIOD default value (specified by IM
yrs, etc).
team).
Critical Information (document and data) deliverables as defined Discipline Lead to verify the
CRITICAL_ DOCUMENTATION in CP-115: Operation of Surface Product Flow Asset. This is default value (specified by IM
the minimum deliverables that is required for Operating Integrity. Team).
Discipline Lead to verify the
Document is a deliverable of PCAP (Project Control and
DCAF Control (Identification default value (specified by IM
Assurance Plan). Those "Yes" deliverables subject to PCAP
DOCUMENT Number) team) against the latest signed
requirement.
PCAP-discipline list.
DELIVERY
(SELECT) REQ_FOR_ Will the Information (documents & data) be delivered as part of Discipline Lead to verify the
REQUIRED CONCEPT SELECTION the concept selection? default values (Yes or No).
PER PROJECT
(DEFINE) REQ_FOR_ PROJECT Will the Information (documents & data) be delivered as part of Discipline Lead to verify the
PHASE _ SPECIFICATION/FEED the project specification package (FEED)? default values (Yes or No).
(EXECUTE) REQ_FOR_
Will the Information (documents & data) be delivered as part of Discipline Lead to verify the
DETAILED DESIGN AND
the detailed design package? default values (Yes or No).
CONSTRUCTION
(OPERATE) REQ_FOR_ PSUA_ Will the Information (documents & data) be required to support Discipline Lead to verify the
Page 18 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18
COMMISIONING AND PSUA, Pre-commissioning and Commissioning/Start-up default values (Yes or No).
OPERATION (Flawless start-up initiative)?
REQUIRED_FOR_FINAL_HAND Will the Information (documents & data) be required as part of the Discipline Lead to verify the
OVER handover package to PDO? default values (Yes or No).
Will the Information (documents & data) deliver as As-built (ASB) Discipline Lead to verify the
REQUIRED_HANDOVER_
or Certified FINAL (revision of information not requiring As- default values (ASB, FINAL or
STATUS (ASB or FINAL)
Building)? If value is no, then information not required. No).
This field was left blank to allow project customization in line with
project strategy. It should be populated as part of MDR
REQUIRE_PDO_REVIEW/APPR development, to capture PDO's review requirements on Discipline Lead to specify or
OVAL documents produced by others (contractor / suppliers) per the verify the default values.
Document Type: IFR=Issue For Review; IFA=Issue For
Approval; IFI=Issue For Information; No=No review required.
Resource typically a
Highlights document types in which RLMUs may be generated. At
commissioning Engineer but
the end of project, PDO focal point shall check As-Built produced
OTHERS FINAL RED-LINE CHECKING the Project Engineer to agree
against “RLMU”, to confirm that As-Built produced is a true
resource with Operations if
reflection of constructed works.
different
Who is the final owner/status of the deliverable after handover?
Typically, ownership of Critical Documentations is with the Asset Discipline Lead to specify or
FINAL OWNER/STATUS
Manager, while other deliverables are stored electronically in a verify the default values.
secured EDMS location for future reference.
COMMENT General comments from IM team or Discipline Lead
Page 19 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18
Page 20 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18
Page 21 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19
The controlled version of this CMF Document resides online in Livelink®. Printed copies are UNCONTROLLED.
Petroleum Development Oman LLC Revision: 6.0
Effective: Mar-18
7 APPENDICES
Appendix 1: Plant Lifecycle Information Plan (Template)
Appendix 2: MRB Document Type Handover Format Definition
Appendix 3: IM Kick-off Form
Appendix 4: User Feedback Form
Appendix 5: MRB Document/Drawing Hanover
Appendix 6: MRB File Handover Template
Page 22 of 23 SP-1131: Plant Lifecycle Information Plan (Handover and As-Built Documentation) Printed: 18/09/19