Professional Documents
Culture Documents
1150-41-004
Project No: 1150
Sheet 1 of 40
Bergen Engines India Private Limited Revision 0
A Rolls-Royce Power Systems Company
CONFIDENCE CEMENT
01 X 5.6MW GAS BASED POWER PALNT
Contents
1 DOCUMENT REVISION HISTORY ......................................................................................................... 5
2 INTRODUCTION ...................................................................................................................................... 6
3 SCOPE ..................................................................................................................................................... 6
4 PRE COMMISSIONING ........................................................................................................................... 6
4.1 CIRCUIT BREAKER ................................................................................................................................. 7
4.1.1 Preliminary Checks: ........................................................................................................................7
4.2 CURRENT TRANSFORMER ................................................................................................................... 7
4.2.1 Preliminary Checks: ........................................................................................................................7
4.3 VOLTAGE TRANSFORMER .................................................................................................................... 7
4.3.1 Preliminary Checks: ........................................................................................................................7
4.4 ISOLATOR ............................................................................................................................................... 8
4.4.1 Preliminary Checks: ........................................................................................................................8
4.5 LIGHTNING ARRESTER ......................................................................................................................... 8
4.5.1 Preliminary Checks: ........................................................................................................................8
4.6 HIGH VOLTAGE, MEDIUM VOLTAGE AND LOW VOLTAGE SWITCH GEAR ....................................... 8
4.6.1 Preliminary Checks: ........................................................................................................................8
4.7 BATTERY AND BATTERY CHARGER .................................................................................................... 9
4.7.1 Preliminary Checks: ........................................................................................................................9
Battery: 9
Battery Charger: .................................................................................................................................................9
4.8 BUS DUCT ............................................................................................................................................... 9
4.8.1 Preliminary Checks: ........................................................................................................................9
4.9 MOTOR CONTROL CENTRE, POWER/ LIGHTING DISTRIBUTION BOARD, UPS ............................10
4.9.1 Preliminary Check: ....................................................................................................................... 10
4.10 EMC (ELECTROMAGNETIC COMPATIBILITY) ................................................................................................10
4.10.1 No EMC immunity or emission tests are required on final assemblies if the following
conditions are fulfilled: ..................................................................................................................................... 10
4.10.2 Tests for EMC .............................................................................................................................. 10
4.11 CONTROL & RELAY PANEL, SYNCHRONISING PANEL, NGR CT & PT PANEL ...............................13
4.11.1 Preliminary Checks: ..................................................................................................................... 13
4.12 METERS .................................................................................................................................................13
4.12.1 Preliminary Checks: ..................................................................................................................... 13
4.13 CABLES .................................................................................................................................................13
4.13.1 Preliminary Checks: ..................................................................................................................... 13
4.14 MOTORS ................................................................................................................................................13
4.14.1 Pre-commissioning checks: ......................................................................................................... 13
4.15 EARTHING SYSTEM .............................................................................................................................14
4.15.1 Pre-commissioning Inspection and Checks ................................................................................. 14
GENERAL CHECK ................................................................................................................................................14
EARTHING ELECTRODES......................................................................................................................................14
EARTH CONTINUITY STRIPS AND EARTHING CONDUCTORS......................................................................................14
CONNECTIONS AND JOINTS..................................................................................................................................15
4.16 TRANSFORMER ....................................................................................................................................15
4.16.1 Pre-commissioning checks: ......................................................................................................... 15
4.16.2 General Checks: .......................................................................................................................... 16
REVISION:
AUTHOR P.R.
CHECKED
(Mech.)
CHECKED
04.09.2020 Issued for Preliminary
(Elect.)
2 INTRODUCTION
This specification defines the minimum requirement for Electrical Installation in a Gas
Based engine installation.
3 SCOPE
The scope of supply shall include but not limited to the following items:-
4 PRE COMMISSIONING
Before a utility will connect an installation to its supply network, strict pre-commissioning
electrical tests and visual inspections by the site engineer / site manager, must be
satisfied.
These tests are made according to local (governmental and/or institutional) regulations,
which may differ slightly from one country to another. The principles of all such
regulations however, are common, and are based on the observance of rigorous safety
rules in the design and realization of the installation.
IEC 60364-6 and related standards included in this technical specification are based on
an international consensus for such tests, intended to cover all the safety measures and
approved installation practices normally required for industrial electrical installation.
The pre-commissioning electrical tests and visual-inspection checks for installations are
as follows:
After verification and testing an initial report must be provided including records of
inspection, records of circuits tested together with the test result and possible repairs or
improvements of the installation.
• Review the test certificate. Discrepancy, if any, shall be brought into notice of
engineer / site-in-charge.
4.4 ISOLATOR
4.4.1 Preliminary Checks:
• Check nameplate details according to specification.
• Check for physical damage. Inform concerned engineer immediately if damage
occurred to any instrument / part during transit
• Assemble all spare parts supplied loose at the time of dispatch and make assembly.
• Check tightness of all bolts, clamps and connecting terminals.
• Check cleanliness of insulators.
• Insulation resistance of each pole.
• Manual and electrical operation and interlocks.
• Contract resistance of each pole / gap between male and female contacts.
• Continuity of earth connections of structures and operating handle.
• Clearances in open and closed positions.
• Carryout preliminary checks and alignments as per the manufacturer’s instruction
manuals.
• Review the test certificates. Discrepancy, if any, shall be brought into notice of
engineer / site-in-charge.
4.6 HIGH VOLTAGE, MEDIUM VOLTAGE AND LOW VOLTAGE SWITCH GEAR
4.6.1 Preliminary Checks:
• Check details of equipment / components according to specification / data sheet.
• Check for physical damage. Inform concerned engineer immediately if damage
occurred to any instrument / part during transit
• Check tightness of all bolts, clamps and connecting terminals.
• Check continuity of earthing system.
• Assemble all parts of the switchgear which have been sent loose at the time of
despatch from the switchgear factory.
• Carryout preliminary checks as per the manufacturer’s instruction manuals.
• Remove packing’s provided at the time of dispatch to arrest the movements inside
relays and Meters.
©2020 Rolls-Royce plc
The information in this document is the property of Bergen Engines India Private Limited - A Rolls-Royce Power Systems Company. The document
is not to be copied or communicated to any third party or used for the purpose of manufacture without prior permission. Such copyright must not be
infringed, and the document must be treated as private and confidential
Doc. No. 1150-41-004
Project No: 1150
Sheet 9 of 40
Bergen Engines India Private Limited Revision 0
A Rolls-Royce Power Systems Company
• Dust shall be wiped from the terminals of equipment, Bus-bar supports, contact
surfaces of relays, breakers, contactors etc. and entire interior of the
switchgear/panels shall be cleaned, if necessary by the use of vacuum cleaner.
• Review the test certificates of all equipment/instruments/components provided by
individual manufacturer and forwarded by panel manufacturer along with panel.
Discrepancy, if any, shall be brought into notice of engineer / site-in-charge.
Battery Charger:
• Check nameplate details according to specification / data sheet.
• Check for physical damage. Inform concerned engineer immediately if damage
occurred to any instrument / part during transit
• Check connection.
• Functional check of auxiliary devices, such as alarms, indicating lamps etc.
• Insulation resistance test of all circuits.
• Check continuity of earthing system.
• Dust shall be wiped out from terminals, contacts, equipment etc. by vacuum cleaner.
• Carryout preliminary checks as per the manufacturer’s instruction manuals.
• Review the test certificates of all equipment / instruments / components provided by
individual manufacturer and forwarded by panel manufacturer along with panel.
Discrepancy, if any, shall be brought into notice of engineer / site-in-charge.
4.11 CONTROL & RELAY PANEL, SYNCHRONISING PANEL, NGR CT & PT PANEL
4.11.1 Preliminary Checks:
• Check name plate details of every associated equipment according to specification /
data sheet.
• Check for physical damage and inform concerned engineer if there is damage to
any instrument / part during transit.
• Check tightness of all bolts, clamps and connecting terminals.
• Check continuity of earthing system.
• Carryout preliminary checks as per the manufacturer’s instruction manuals.
• Remove packing’s provided at the time of dispatch to arrest the movements inside
relays and meters.
• Review the test certificates of all equipment/instruments/ components provided by
individual manufacturer and forwarded by panel manufacturer alongwith panel.
Discrepancy, if any, shall be brought into notice of engineer / Site - in - charge.
• Dust shall be wiped out from terminals, contacts, equipment etc. by vacuum cleaner.
4.12 METERS
4.12.1 Preliminary Checks:
• Check name plate details according to specification / data sheet.
• Physical check for any damage and inform concerned engineer if damage occurred
to any meter during transit.
• Megger all insulated portions.
• Check C.T. and V.T. connections with particular reference to their polarities for
power type meters.
• Carryout preliminary checks as per the manufacturers’ instruction manuals.
4.13 CABLES
4.13.1 Preliminary Checks:
• Check details as per specification / data sheet / drum schedule.
• Check for physical damage and inform concerned engineer if damage occurred to
any cable / cable drum during transit.
• Check cables are dispatched as per drum schedule, if any. Also check length and
size are as per drum schedule.
4.14 MOTORS
4.14.1 Pre-commissioning checks:
• Check equipment for free movement of rotor, Check lubrication and for any other
mechanical defects.
• Check stop push button is providing with facility with the approved cable schedule.
• Check the size of cable for conformity with the approved cable schedule.
• Check whether duplicate earthing is provided for the body of the motor from
diametrically opposite sides. Check the size of the earthing conductor for adequacy.
Also check the earth lead terminations and connections for
• Socketing of the earth lead ends (if round conductor)
• Proper surface contact.
• Removal of the paint of the body of the equipment
• Tinning of copper flats at termination
• Effectiveness of bolting.
• Check the rating of switch, back-up fuses and setting of overload relay provided in
starter panel / MCC for respective sizes of motors.
• Check commutators, slip rings, brushes, brush-holders etc. for satisfactory
conditions.
General Check
• Check whether the earthing layout is as per the scheme approved by the
department of Electrical Inspectorate.
• Check whether the number of plate electrodes / pipe electrodes and spacing
between them are as per the approved scheme / drawings.
• Measure earth resistance of each electrode separately insulating the same from
station grid as well as from other earth electrodes. If a number of earth electrodes
are interconnected with one another, combined earth resistance shall also be
measured. The earth resistance of each electrode and / or a group of electrodes
shall not exceed 1.0 ohm.
• Carryout line earth loop impedance test. The loop comprises the conductor from the
point of fault, back to the supply transformer, the path through transformer winding,
the earthed neutral point of the transformer and path from that point to the point of
fault through the earthing system.
• Continuity test for earth continuity conductors with ELV tester.
• All test results shall be recorded for future reference
Earthing Electrodes
• Check whether all earth electrode terminals are visible and numbered
• Check size and material of earth electrode (Plate or pipe) is as per approved
scheme/ drawings.
• Check the construction of earth electrode/station is as per approved
scheme/drawings/ IEEE-80/BS-7430
• Check the size of earth mat of sub-stations with designed values (spread of earth
mat, mesh size, conductor size, size of riser, depth of laying etc.)
• Check whether all the earth electrodes are interconnected to form a closed mesh.
• Check whether duplicate earthing of adequate size is provided for equipment rated
415V and above. However, all equipment located in hazardous areas shall have
duplicate earthing connections with adequate size conductors.
• Check whether duplicate earthing is provided for the neutral of the transformers and
generators. There shall be one direct connection from each neutral to a separate
earth electrode interconnecting the earthing strip.
• Check whether the bottom of each high voltage bushing is earthed using strip.
• Check whether outdoor CT, PT breaker units, isolators, lightning arresters etc. are
directly earthed to the risers of the earthing mat / earthing grid.
4.16 TRANSFORMER
4.16.1 Pre-commissioning checks:
• Check nameplate details with the specifications / Data sheet.
• Check for any physical damage, in particular of bushings. Inform concerned
engineer / Site - in-charge immediately if damage occurred to any instrument / Part
during transit.
• Check cleanliness of bushings, oil level in the bushings if sealed bushings are used.
Release air from bushings if air release plugs are provided.
• Assemble all parts of transformer which have been removed and sent loose at the
time of dispatch from factory. Finally check fittings and accessories as per approved
drawings.
• Oil leakage particularly along the welds if the transformer is dispatched filled with oil
or reduction in pressure of inert gas if the transformer is dispatched gas filled. When
the transformer is dispatched gas filled, the temperature and the pressure at the
time of gas filling is marked on a tag. The temperature and pressure should be
checked to ascertain whether there was any leakage of atmospheric air into the tank
during transit. In case of leakage it is possible that the winding may have absorbed
moisture and the transformer will have to be dried out. If the pressure is positive and
varies with the temperature of the surrounding air, the seal can be taken to be
effective.
• Drum containing transformer oil which have been dispatched separately, should be
examined carefully for leaks and any shortage should be reported.
• Check the radiator for release of air and positions of valves. Ensure that all radiator
valves. Ensure that all radiator valves are opened.
• Check the oil level in the main conservator & OLTC Conservator. The conservator
Shut-off valve in the Buchholz relay pipe line shall be in open position.
• Check the transformer is correctly installed with reference to its phasing.
• Check external connection of the transformer in accordance with diagram of
connection and phase sequence.
©2020 Rolls-Royce plc
The information in this document is the property of Bergen Engines India Private Limited - A Rolls-Royce Power Systems Company. The document
is not to be copied or communicated to any third party or used for the purpose of manufacture without prior permission. Such copyright must not be
infringed, and the document must be treated as private and confidential
Doc. No. 1150-41-004
Project No: 1150
Sheet 16 of 40
Bergen Engines India Private Limited Revision 0
A Rolls-Royce Power Systems Company
4.16.3 Terminations:
• The transformer terminal connection may be checked for the following:
• Flexibility and area of cross - section of flexible connections at bushings.
• Clearances of live jumper connections from transformer tank and accessories.
• Perfection of Crimping.
• Tinning of contact surfaces to prevent bimetallic action.
• Clearances inside cable end box
• Clearances of bus-bar trunking
• Conformity of cable end box with the relevant IP (Ingress Protection) classification.
• Correctness of cable glanding and adequacy of cable gland earthing or pig tail.
• Support of cables at termination and unsupported lengths.
4.16.5 Earthing:
Check the size of earthing conductors, tinning of contact surfaces area of contact and
seating, effectiveness of bolting, riveting, welding etc. for the earthing of the following.
• Duplicate earthing for neutral and body
• Main tank and top cover
• Fan Motors, Pumps.
• OLTC chamber
• Tap changer driving gear
• Diverter Switch
• Cable gland/Termination.
• Marshalling Box
4.16.8 Winding Temperature indicator (WTI) and oil temperature Indicator (OTI):
• Check whether thermometer pocket is filled with oil
• Check whether the connection of the CT for winding temperature indicator to the
thermometer pocket is properly made as per the instructions given on the WTI
terminal box.
• Check whether the contacts of WTI and OTI for alarm and trip are set at required
temperatures depending upon ambient temperature and loading condition. For oil
filled transformers, the maximum permissible temperature rise above the ambient
temperature is usually taken as 45°C for oil and 55°C for winding. In case of cast
resin transformers, the alarm contact of the winding temperature relay is usually
designed to operate at 140°C and trip contact at 160°C for transformer upto
1000KVA. For higher ratings, the temperatures are 160°C and 180°C respectively.
• The hottest -spot temperature rise corresponding to a winding temperature rise (by
resistance) of 55°C for a transformer with natural oil circulation is calculated as
follows;
The recommended settings of the alarm and trip contact of WTI and OTI relay are
as follows;
ALARM TRIP
WTI: 88°C 98°C
©2020 Rolls-Royce plc
The information in this document is the property of Bergen Engines India Private Limited - A Rolls-Royce Power Systems Company. The document
is not to be copied or communicated to any third party or used for the purpose of manufacture without prior permission. Such copyright must not be
infringed, and the document must be treated as private and confidential
Doc. No. 1150-41-004
Project No: 1150
Sheet 18 of 40
Bergen Engines India Private Limited Revision 0
A Rolls-Royce Power Systems Company
The above settings are based on a weighted average annual ambient temperature of
32°C as per relevant IEC/BS
Guide for loading of oil immersed transformers’. At another ambient, the temperatures
settings will have to be correspondingly changed.
Also check whether all lamps, buzzers etc. are working satisfactorily.
The insulation test reveals the condition of the insulation inside the transformer. The
insulation resistance values are affected by temperature, humidity and presence of dirt
on insulators and bushings.
650V 500 V
1.1 KV 1000 V
3.3KV 2500 V
6.6 KV and above 5000 V
4.17 GENERATOR
During the pre-commissioning checks and tests, each component of the generator
installation is checked for proper installation and correct assembly. The electrical
connections are verified for conformity with the approved diagrams at every stage of the
installation. Pre-commissioning tests of generators include testing of the protective
devices and relays, auxiliary equipment and control circuitry.
Electrical Checks
• Verify all electrical connections to ensure that they are as per the approved electrical
schematic Diagram.
• Check the tightness of all electrical connections.
• Check the connections to the AVR. The connections should be as per the diagram
of connections and the instructions of the supplier of AVR.
• Check the power cables connections at the generator terminal box and the control
panels for proper clamping and terminations.
• Check the control cable connections for proper terminations and glanding.
• Check whether the neutral formation and neutral earthing have been done correctly.
• Check whether the Neutral Grounding Register (NGR) / Neutral Grounding
Transformer (NGT) is as per approved scheme.
• Check the voltage grade of the cable used for NGR / NGT. The voltage grade of the
cable shall be same as that for unearthed system.
• Check whether neutral switching gear is rated for the same voltage as that of the
generator.
• Check whether remote switching facility is provided for the neutral switching device.
• Check whether the frame work of NGR is insulated from its enclosure for the same
voltage as that of the generator.
• Check the connection of governor. The connection should be as per the diagram
given by manufacturer.
If the measured value of insulation resistance is less than the value indicated above it is
an indication of presence of moisture and condensation of vapour in the windings. The
windings should therefore be dried out as per the instructions of the manufacturer. The
measured values of insulation resistance may be recorded for future reference. The AVR
connections shall be removed before measuring the insulation resistance.
Polarisation Index:
(Please refer chapter for transformer)It is necessary to measure and record the
polarisation index of HV generators. Measurement of polarisation index is a conclusive
test for ascertaining the quality of insulation of HV generators. The value of insulation
resistance after 1 minute and 10 minutes of starting the measurement are measured
using HV insulation tester of appropriate voltage. The polarisation index (PI value) which
is the ratio of the 10 minute value to the 1 minute value shall be more than 2.
5 SWITCHGEAR INSTALLATION
DELIVERY, TRANSPORT AND ASSEMBLY OF ELECTRICAL SWITCHGEAR /
PANELS.
5.1 Transportation
Position during transport
Switchgear/ panels may only be transported upright. If local conditions require
transportation in a different position, it must be coordinated with the manufacturer in
advance.
Load securing
Observe the general rules and regulations for securing cargo for transport by road, rail or
sea.
Caution
The lifting eyes are designed for a single load of no more than 700kg. Thus, taking a
margin of safety into account, panels or transport units up to a maximum total mass of
2,500 kg can be lifted by the lifting eyes. The lifting eyes are not removed from the
panels also after assembly at the installation site.
Alternatively, angle irons can be bolted along the top edges of very large and heavy
panels to spread the tensile force to more points on the housing to handle heavier loads
than which the lifting eyes can do only on the corners.
These crane brackets have to be removed after the panel has been transported, for one
thing because they could obstruct the functioning of the pressure-relief dampers.
The length of the chains/belts must be such that an angle of 30 ° vertical or 60°
horizontal is not exceeded.
Switchgear/panels are factory-fitted with transport timber bolted to the bottom. These
allow the lifting and transport by lift truck, forklift or crane fork.
They are bolted through the holes for floor installation and have to be removed during
installation.
Attention
When transporting by forklift, lift truck or crane fork, the forks must go in all the way
under the Switchgear/panels. If the forks stop under the base plate, the latter can get
damaged when being lifted. In the worst case, the Switchgear/panels can tilt and fall
from the forklift, causing serious damage.
5.2 Delivery
When the switchgear/Panels are delivered, responsibilities lie on customer which
includes the following:
• Checking the delivery for completeness and integrity (e.g. also for moisture and its
adverse effects). In case of doubt, the packaging must be opened and then sealed
again properly if stored temporarily; new bags with desiccant must then be placed
in the packaging, if any were present.
• Documentation and reporting of damage and defects. If any parts are missing or
defects or transport damage is found, customer have to do the following:
• Note the relevant event or defect on the delivery note.
• Notify the relevant carrier or forwarding agent immediately, in accordance with the
applicable liability provisions.
• Always document damage by taking photographs of it.
5.4 Assembly
5.4.1 General
Before starting the installation, the proposed switchgear room must be fully completed,
have lighting and power supply, be lockable, dry and equipped with ventilation devices.
All necessary preparations such as wall openings, conduits, etc. for the routing of power
and control cables to the switchgear must be completed.
The ground or the supporting structure (intermediate floor) must be strong enough to
support the weight of the switchgear.
Attention
When planning the room for the switchgear, sufficient distance to the ceiling must be
ensured, so that the pressure-relief dampers can be opened unobstructed in an
emergency. The ceiling height must conform to the IEC standard.
In some cases, additional measures to protect the operator at the control panel may be
required, e.g. deflector plates or discharge channels.
©2020 Rolls-Royce plc
The information in this document is the property of Bergen Engines India Private Limited - A Rolls-Royce Power Systems Company. The document
is not to be copied or communicated to any third party or used for the purpose of manufacture without prior permission. Such copyright must not be
infringed, and the document must be treated as private and confidential
Doc. No. 1150-41-004
Project No: 1150
Sheet 25 of 40
Bergen Engines India Private Limited Revision 0
A Rolls-Royce Power Systems Company
Also take note of prescribed or technically required minimum clearances to side and rear
walls in accordance with the contract documents /Statutory Requirements.
Refer to the project documents for the relevant measurements of the unit footprint.
Please refer to the individual measurements in the construction drawing for the bottom
plate relating to the order.
In an ideal situation, the base for the installation of the Switchgear / panels has been
measured before installation. Before anchoring the Switchgear / panels to the base, the
measurement log can be evaluated and, if necessary, an absolutely horizontal surface
can be created with shims for the installation of the Switchgear / panels.
When a line-up is installed, the entire surface under all Switchgear / panels / transport
units of the line-up must be uniformly level and horizontal. This is primarily the current-
free connection line-up elements to be assembled side by side; uneven surfaces will
also twist the frames causing Switchgear / panel doors to stick or not close tightly.
1st After having placed the Switchgear / panels in place by forklift or crane, align the
first panel of the line-up on the base frame according to the drawing. The
other Switchgear/ panels are placed at a short distance parallel to the first control
panel.
• The sealing material is already attached to the open side of the adjacent
panel, if the panels are intended for assembly soon.
• Rear walls, roof panels or parts may have to be removed to gain access to
screw connections if access is not possible through the doors.
When a longer storage period is envisaged, the sealing material is not pre-assembled,
but included in the delivery and must be applied on the sealing surfaces before
assembly.
• Grease the joints of bus bars with suitable grease. If necessary, pull
insulating covers over the bus bars. Install and connect the bus bars with the
included or pre-assembled fasteners.
4th Then the panels are screwed onto the bottom. Rear walls or parts may have to
be removed to gain access to screw connections if access is not possible
through the doors.
Attention
The rear walls of panels of higher internal arc classification are very heavy due to the
double plates. This needs to be taken into account during handling.
5th Finally, reinstall rear walls or other housing covers necessary for floor anchoring
where applicable.
Fig 01
Handling:
• Panels can be handled either by fork-lift or overhead cranes in an upright position
depending on where they have to be placed. Care should be taken to see that the
panels don’t topple during transportation.
• Avoid tilting of Panels.
• While transporting the panel using a forklift, ensure that the distance between the legs
of the forklift and ground is at least 12 cm.
• Limit the speed of the forklift to 10 kmph.
• Use both legs of the forklift.
• If Switchgears/Panels are to be installed at higher elevations, shift them from the
unloading spot through the opening planned in the building for this purpose. This
should be done with all safety precautions and strict supervision by trained personnel.
Fig 02
Fig 03
Receipt and handling:
In case of handling by lifting crane,
• Suspend ropes from the hook and pass them under the wooden pallet at the bottom
of the Panel.
• Centre of gravity indicators and chain marks are provided on the Panel as shown in
Figure 04.
• Use PP (Poly- propylene) ropes of minimum 1” diameter for this purpose. Choose
the diameter of the rope according to the weight of the Switchgear/Panels which is
mentioned in Packing List.
• Verify that the route from the unloading spot to the erection spot has free access.
• Unload the Panels after reaching the unloading spot.
Fig. 04
Fig. 05
In case the Panel is unpacked before reaching the site, use the lifting channel provided
at the top of the panel for easy transportation.
Fig. 06
Fig. 07
To facilitate transportation and handling, the Switchgears / Panels is split into multiple
sections / transport units (Panels). Each section is wrapped with a HDPE (High Density
Polyethylene) cover and packed in a wooden case. To arrive at the approximate overall
dimensions of the packing cases, add 300 mm to the dimensions of the respective
section
List of equipment’s and special tools for site erection and assembly
• Crane and truck for equipment shifting.
• Slings and ropes - As per requirement.
• Rolling pipes - 10 Nos.
• Channels - 10 m.
• Crowbars - 4 Nos.
• Welding machines - 1 No.
• Spanner sets - 1 Set.
(Ring & Open spanner size 13mm, 17mm, 19mm, and 24mm. Box or pipe spanner
13mm.)
For safe handling lifting angle (θ) should be greater than 45°.
(Ring & Open spanner size 13mm, 17mm, 19mm, and 24mm. Box or pipe spanner
13mm.)
For safe handling lifting angle (θ) should be greater than 45°.
5.4.6 Storage:
If Switchgears / Panels are to be commissioned at a later date, the following precautions
should be taken.
• OUTDOOR STORAGE SHOULD BE AVOIDED. Store all cases indoors, in a
clean, dry and well ventilated place where seepage of water and condensation
does not occur.
©2020 Rolls-Royce plc
The information in this document is the property of Bergen Engines India Private Limited - A Rolls-Royce Power Systems Company. The document
is not to be copied or communicated to any third party or used for the purpose of manufacture without prior permission. Such copyright must not be
infringed, and the document must be treated as private and confidential
Doc. No. 1150-41-004
Project No: 1150
Sheet 32 of 40
Bergen Engines India Private Limited Revision 0
A Rolls-Royce Power Systems Company
5.4.8 Installation:
Typical Switchgear/ Panel Front View:
5.4.9 Installation:
Tools
• Torque wrench
• Bush Ratchet
• Hydraulic jack
• Rubber mallet
• Clamps
5.4.11 Erection:
• After Switchgear / Panels have reached the installation site, unpack the panels and
move the packing material to its allocated area.
• Check if all components are in place as per the drawings and the packing list.
• Vertical sections should be shifted sequentially into the installation site for ease of
installation.
• The panels must be carried in an upright position to avoid the risk of toppling.
• Place the first TU over the base channel frames erected in the floor concrete by the
civil contractor. Check correctness of leveling (± 1 mm tolerance per meter is
allowed) and alignment of panels & proceed as per General Arrangement (GA)
Drawings.
• Maintain clearances as mentioned in GA drawings. Provide sufficient space on all
sides of the panel for personnel to work conveniently.
Fig-08
• Tack-weld or bolt the panel with the ISMC Base Channel / Base Frame.
• When bolting the panel, drill the required holes in the ISMC Base Channel / Base
Frame, so that it matches with the holes provided in the integral base Frame.
In A.C. test the current shall be of approximately sine wave form at nay frequency from
40 to 60Hz inclusive and the rms value of the applied voltage shall be as below. When
carrying out the test, voltage shall be applied and increased gradually to the full value.
The test voltage shall be maintained continuously for 5 minutes between conductors and
between each conductor and sheath without any failure.
Note: DC voltages for old cables is 1.5 times rated voltage or less depending on the age
of the cables, repair work or nature of Jointing Work carried out etc. In any case
the test voltage should not be less than the rated voltage.
5.6.1 MV cables
• All MV (3.3KV and above) Cables shall be terminated with Raychem/Equivalent Heat
Shrinkable Termination Kit. Termination kit shall be provided with elastic barrier self-
amalgamating insulating tape which will relief stress, long barrel compression type lugs
which permit more than one compression shall be provided.
• In outdoor Raychem/Equivalent kit addition to the above mentioned a pre-cast Tropolin
rain shield should be provided which offers longer creepage path.
• Non-magnetic cable glands and gland plates will be used with single core cable.
ANNEXURE – 1
Installation of Equipment, Earthing, Cable Tray, Cable Trench, Lightning Arrestor etc. should
be as per attached drawing with Annexure–1 (All the Drawings/Documents will be furnished to
successful Bidder)