DAILY PROJECT REPORT FORM No.

: DPR-01

THE DESIGN, SUPPLY AND BUILD OF MAUN WASTEWATER DATE 21-Sep-22


PROJECT:
TREATMENT PLANTS (MAUN EAST AND MAUN WEST) DAY
SUN MON TUE WED THU FRI SAT SUN
CONTRACT NO. WUC 036 (2021) √
CLIENT: WATER UTILITIES CORPORATION Bright Sun Cloudy Warm Windy Hot Cold
WEATHER
CONTRACTOR: CHINA JIANGSU INTERNATIONAL BOTSWANA/ EZRA & EZRA CONSTRUCTION JV √
ENGINEER: DNK ASSOCIATES/ HAAS JOINT VENTURE Station Applicable
RAINFALL
Contract Amount Commence- 21-Sep (mm)
Completion Progress
(Pula) ment Contract Elapsed 08.00 hrs 14.00 hrs 17.00 hrs
TEMP. (0C)
792,901,262.32 8/2/2022 1/23/2024 540 30
LOCATION: MAUN EAST SITE CAMP
CONTRACTOR'S RESOURCES FOR THE PROJECT
CONSTRUCTION ACTIVITIES (including description, location and status of works in progress)
HUMAN RESOURCES MAJOR PLANT & EQUIPMENT
NUMBER NUMBER 1. Site camp residential construction involving erection and welding of structural steel framework, wall cladding using
DESIGNATION DESCRIPTION
PR OS WK ST ibr roofing sheets
Site Agent 1 Dozer 2. Plastering for the ablution block- internal
Site Engineer 2 Grader 1 3. Construction of workshop inspection pit- Brickwork (2nd pit)
General Foreman 1 Loader 1 4. Rehabilitation of borrow pit road from site camp i.e spreading, mixing and compacting gravel on the road
Sectional Foreman 7 Excavator 1
Surveyor 1 Roller 1
Quantity Surveyor 2 Compactor/7ton 1
Technician TLB Loader/Exc. 1
Sen. Support Staff Concrete Mixer 1
3
Plant Operator/ Truck 8 Tipper - 20m 1
Vehicle Driver 2 Water Bowser 2 1
Skilled Labourer 11 Water pumps
Unskilled Labourer 16 Welding mach. 3
SHE Officer 1 Small dumper 4

PR = Present, OS = On Site, WK = Working, ST = Standing


MATERIALS ON SITE

1. 209cu.m of 19mm concrete stones


2. 7cu.m of crusher sand
3. 6 layers of Ref 193 mesh
4. 18cu.m of pit sand
5. 18 Pallets of cement
6. 7 Pallets of clay bricks

VISITORS
NAME ORGANISATION REMARKS

INSPECTION / TESTING / INVESTIGATION REPORT (including any site


problems encountered and steps taken)

INSTRUCTION / INFORMATION
REQUESTED BY CONTRACTOR: FROM CLIENT:

ISSUED TO CONTRACTOR: FROM ENGINEER:

SIGNED BY: ON BEHALF OF CONTRACTOR ON BEHALF OF ENGINEER


NAME: KEABETSWE MASALILA NAME:

SIGNATURE: SIGNATURE:
DESIGNATION: PROJECT ENGINEER DESIGNATION: