Professional Documents
Culture Documents
at
HAFIZ CONSTRUCTION CO. PVT. LTD.
B.E (Civil)
July-August,2022
SUBMITTED BY
NAME(S): LATEEF UR REHMAN WANI
UNIVERSITY ROLL NO.(s): 191206022
1|Page
TITLE PAGE
CONSTRUCTION OF ADIJAN BRIDGE AT KULGAM
MUNAWARABAD, SRINAGAR(J&K)190001
of
By
191206022
2|Page
Table of Contents
ACKNOWLEDGEMENT……………………………………………………………
INTRODUCTION…………………………………………………………………....
EXECUTIVE SUMMARY…………………………………………………………..
CONSTRUCTION DETAILS…………………………………………………….…
1. BRIDGE MEMBERS…………………………………….………………….
2. BRIDGE MATERIALS………………………………..…………………….
3. TRUSS ……………………………………………………………………....
4. BRIDGE BEARING…………………………………………………………
5. DECK REINFORCEMENT…………………………………………..……..
6. CRASH BARRIER…………………………………………………..............
7. WATER CEMENT RATIO……………………………………………...…..
8. GIRDER BRIDGES………………………………………………………….
9. FORMWORK………………………………………………………………..
10. TRUSS CONNECTIONS…………………………………………………....
11. DECK CONCREATING………………………………………………….....
SELF-EVALUTAION……………………………………………………………….
CONCLUSION………………………………………………………………………
3|Page
ACKOWLEDGEMENT
I also would like to thank all the people that worked along with me with their patience
and openness they created an enjoyable environment.
It is indeed with the great sense of pleasure and immense sense of gratitude that I
I am highly indebted to Director Prof. ANKUR GUPTA for the facilities provided to
I would like to thank my Head of the Department Dr. ARVIND DEWANGAN for his
constructive criticism throughout my internship.
I would like to thank college internship coordinator SALMAN RABBANI for their
support and advices.
(191206022)
4|Page
INTRODUCTION
Directors of Hafiz Construction Company Private Limited are Feroz Ahmad Hafiz,
Farooq Ahmad Hafiz and Tariq Ahmad Hafiz.
5|Page
EXECUTIVE SUMMARY
6|Page
GEOLOGICAL INFORMATION OF THE REGION
1. Location;
The village Adijan Devsar is located in Kulgam Tehsil of Kulgam District in
the Union Territory of Jammu and Kashmir in India. It is governed by Adigan
Dewsar Gram Panchayat. It comes under D.h Pora Community Development
Block. The nearest town is Kulgam, which is about 8 kilometers away from
Adijan Devsar.
The village is connected by public bus services. Private buses services are
available for the village. There is a railway station more than 10 kms away from
the village.
Total area of Adijan Devsar is 267.1 Hectares as per the data available
Total sown/agricultural area is 97.5 ha. About 97.5 ha is irrigated area. About
7|Page
bounded by Reasi, Ramban & Rajouuri Districts in the South and South west
though separated by mighty and majestic mountainous range of Pirpanjal acting
as a massive topographic physical protection. The District has road connectivity
with its neighboring districts like Shopain, Pulwama, Anantnag and Ramban
etc, besides being linked with far flung areas of the district by a dependable road
network. Nallah Veshav, which drains from northern face of Pir Panjal, is the
main left bank tributary of river Jehlum and traverses through District Kulgam.
Before confluence of Veshu with the Jehlum, it gets broken off into a number
of channels providing drinking water facilities to vast population of the district
and irrigation facilities to huge tracks of the agricultural land of the district.
On the first day, I was familiarized with the basics of bridge constructions. I visited the
site with the concerned on time and he briefed me about the basics of constructing a
bridge.
The major steps that are involved in the planning for bridge construction are:
2. Traffic Assessment
3. Location study
8|Page
5. Preliminary Engineering a) Developing plans b) Preliminary design and costing c)
Evaluation of alternatives, risk analysis, and final choice
7. Implementation
The decision of having a new bridge in an area is taken as a part of development of the
society. This facilitates the feasibility of linking the cities and towns, which gain more
importance in the overall growth of a nation. Their need is studied based on the socio-
economic viabilities.
An assessment of the traffic type and its quantum is necessary to decide the following
factors:
While having a location study and fixing the location of the bridge, it is very essential
to consider the need and the location of cross drainage works if any. The cross-
drainage work is said to have 15 to 20 % of the overall project cost if it must be
9|Page
implemented. Hence before choosing the alignment for bridge construction, it is
necessary to determine all the possible CD works and its effect. The following factors
are considered reliable in fixing the location of the bridge.
Other than the above-specified conditions, the major river crossings of the bridge
construction should satisfy the following conditions:
a)River regime
The river upstream must be straight. If there is bend in the downstream, it must be
avoided. The river in the reach must be free from whirls, excess current due to eddies.
The channel in reach must is narrow and well defined. The river regime should have
unerodable banks that are firm. If there are no unerodable banks, over gorging, guide
banks in dry locations also must be provided.
b) Approaches
During floods, the approaches must be secure from flood attacks or any major spills.
High expensive approach construction must be avoided. It is recommended to pass
through built-up areas, or high hills or through major basin or religious structures. The
approaches have a reasonable proximity to the main road. It should not let construction
of costly connecting link. The ideal approach will avoid the construction under water
that is highly costly and uneconomical. They should help in a way to bring lesser
maintenance to the whole system, hence increasing the life period of the bridges.
This is a pre-feasibility study, which studies the entire reach of the river, that must be
crossed; to find out best and suitable position for bridge location. The factors each site
satisfies are taken as lists and each is analyzed individually, from which the best
consideration is chosen. The final number of feasible sites must be refined down to
10 | P a g e
three or four, this can be done only by going in detail of each site and refining the most
suitable ones. During this stage, maps are used to locate theses feasible sites. The direct
assessment of the site is made to understand the location features (local criteria),
studying the existing and growth of traffic with the help of surveys, knowing
information from the people residing, simple routes and short cuts in the area, river flow
and its spread are also studied. A feasibility study on the economy of cost, the duration
of construction, the sources of resources are also assessed. Now the whole information
is gathered and a comparison is made. Based on the discussion and refinement, the best
feasible site for implementation is chosen.
This stage of planning can be called as a techno-economic feasibility study. Here, the
technical details related to the bridge construction is studied in a detailed manner, to
bring all possible alternatives to proceed the construction. Mainly it is found that the
total cost of the project is plus or minus 15% of the cost that is estimated at this stage
of planning. To process the technical study, minimum level of field study and
measurements, the location study, and related parameters must be done.
This study carried out at the bridge construction site should bring the following
tabulated content details:
This stage is the final stage of planning in the bridge construction, before the
commencement of the construction work. Full investigation from the roots is taken
and documented. The investigations conducted are:
11 | P a g e
Ground survey
Soil exploration- foundation details
Hydrological data
Model studies and analysis
3)BRIDGE DESIGNS
Bridges are designed to handle tension and compression in a variety of ways depending
on their use and location.
TYPES OF BRIDGES
FIG. 1
12 | P a g e
1)Suspension bridges:
Cables hung from vertical suspenders support the bridge deck while piers balance
compression.
FIG. 2
2)Truss bridge:
The superstructure consists of diagonal chords or beams that carry tension and
compression throughout the structure.
FIG.3
13 | P a g e
3)Arch bridges:
A steel, stone or concrete arch balances compression and serves as a wind bracer.
FIG. 4
4) Cantilever Bridge:
Cantilever bridges use sets of upper chords to carry tension and lower chords to handle
compression.
FIG. 5
14 | P a g e
4)COMPONENTS OF BRIDGE
DECK
ABUTMENT
PILE
PIER
GIRDER
RAIL TRACK
Acquire Land
Choose a Technical Consultant and a Design Professional
Prepare the Building Plan
Prepare Estimate
Interview Contractors
Get your Permits
Construction Phase
Site clearance
Excavation
Foundation
15 | P a g e
Realization of the piles
FIG. 6
16 | P a g e
Realization of soles
FIG. 7
17 | P a g e
Realization of the support (piles and abutment)
Realization of the apron
The deck of the bridge is a very important element technically there are several types
of aprons according to the types of bridges and according to the method of realization.
FIG. 8
18 | P a g e
CONSTRUCTION DETAILS
1)Bridge members
The bridge members are divided into two major categories: the superstructure and the
substructure.
a)Superstructure
The superstructure is the upper portion of the bridge above the beam seats where you
drive or walk. Members include:
Beams
Bearings
Curbs
Deck
Deck wearing surface
Floor beams
Girders
Parapets
Sidewalks
Traffic barriers
Trusses
b)Substructure
The substructure is under the superstructure and supports all of the bridge loads.
Members include:
Abutments
Backwalls
Beam seats
Cheek walls
Footings
Piers
Piles
Wingwalls
19 | P a g e
FIG. 9
2)Bridge materials
Some of the main materials found on a bridge are steel, concrete, stone and asphalt.
Other materials include iron, timber, aluminum, rubber and other joint materials.
Below is a description of some typical uses for these materials in a bridge.
a)Concrete
Concrete is commonly used for many bridge superstructure members such as decks,
pre-stressed concrete beams, curbs, sidewalks and parapets (side traffic barrier walls).
It is used extensively in new construction for the entire abutment, including the
footings, stem (main front wall), wingwalls, cheek walls, backwalls, endwalls (for
traffic barrier connection), beam seats, and the piers with similar members. It can also
be used for cast-in-place or precast concrete piles to support the abutments and piers.
Cements used in construction can be characterized as being either hydraulic or non-
hydraulic. Hydraulic cements (e.g., Portland cement) harden because of hydration, a
chemical reaction between the anhydrous cement powder and water. Thus, they can
harden underwater or when constantly exposed to wet weather. The chemical reaction
20 | P a g e
results in hydrates that are not very water-soluble and so are quite durable in water.
Non-hydraulic cements do not harden underwater; for example, slaked limes harden by
reaction with atmospheric carbon dioxide. The most important uses of cement are as an
ingredient in the production of mortar in masonry, and of concrete, a combination of
cement and an aggregate to form a strong building material. Non-hydraulic cement such
as slaked limes (calcium hydroxide mixed with water), harden due to the reaction of
carbonation in presence of the carbon dioxide naturally present in the air. Calcium oxide
is produced by lime calcination at temperatures above 825 °C (1,517 °F) for about 10
hours at atmospheric pressure:
The calcium oxide is then spent mixing it to water to make slaked lime:
Once the water in excess from the slaked lime is completely evaporated (this
process
This reaction takes a significant amount of time because the partial pressure of
carbon dioxide in the air is small. The reaction of carbonation requires the air be in
contact with the dry cement, hence, for this reason the slaked lime is a non-hydraulic
cement and cannot be used under water.
CONCLUSION
Cement is a binder substance that sets and hardens independently and can bind other
material together. Cement used in constructions is characterized as hydraulic or Non
Hydraulic. Hydraulic cement harden because of hydration , chemical directions .
The most important use of cement is the production of mortar and concrete.
21 | P a g e
CONCRETE
1.cement
2. fine aggregates
3. coarse aggregates
4. water
5. admixtures
2.Proportioning of materials,
3.Mixing,
4.Transporting,
22 | P a g e
FIG . 9
b)Steel
Steel is commonly used in the bridge superstructure for armoring expansion joints,
beams, bearings, floor beams, girders, reinforcing bars in concrete, traffic barriers and
trusses. It is used in the substructure for the reinforcing bars in concrete, armoring for
expansion joints, anchor bolts, etc. It is also used for piles to support the abutments and
piers.
c)Stone
Stone was commonly used for building the abutments and piers in the 1940s and earlier.
This is particularly true where local field stone was readily available. Many spectacular
stone arch bridges were built for the B&O railroad system in the 1800s. In Harford
County, the remains of some MA & PA Railroad bridge abutments and piers are still
standing.
d)Asphalt
Asphalt is the material that has been used extensively for the wearing surfaces on
corrugated metal decks, timber decks and concrete decks in Harford County.
e)Iron
Iron was used typically in beams and trusses that were built before 1900. Steel
23 | P a g e
replaced iron because it has more tensile strength than iron and is less brittle. There
are almost no uses for iron in today’s bridge designs.
f)Timber
Timber is used for several decks and traffic barriers in Harford County. It is also used
for the beams on one bridge and the abutments and piles on another bridge.
g) Aluminium
h)Rubber
Rubber and synthetic rubber products are used for bearings and for expansion joint
material.
TRUSS
24 | P a g e
TYPES OF TRUSSES
Pratt Truss
Warren Truss
K Truss
Howe Truss
Fink Truss
Gambrel Truss
FIG .10
25 | P a g e
BRIDGE BEARING
Rocker bearings
Rocker bearings have curved surfaces that allow rocking. As the bridge expands, the
bearing rocks to allow movement in the horizontal direction. Rocker bearings are
primarily made of steel. Rocker bearings tend to be used for highway bridges.
26 | P a g e
FIG .11
Elastomeric bearings
Elastomeric bridge bearings are the most popular type of bridge bearing used today.
They are made of rubber and do not have any moving parts, because the rubber itself
allows movement in the bridge. Elastomeric bearings can be made at a low cost, and do
not need to be maintained, like other forms of bearings that have moving parts and are
made of metal. Elastomeric bearings can be reinforced with steel to make them stronger
if needed.
27 | P a g e
FIG . 12
Sliding bearings
Sliding bearings have both a flat sliding surface to allow horizontal movement and a
spherical surface to allow rotation. Although they used to be made of metal, sliding
bearings now tend to be made of Teflon.
FIG . 13
28 | P a g e
Spherical bearings
As the name suggests, spherical bearings are in the shape of a sphere. These bearings
only allow rotation, and prevent movement in the horizontal and vertical directions.
FIG .14
29 | P a g e
Deck Reinforcement
The reinforcement in the bridge deck must be defined to properly perform engineering
evaluations of the bridge.
As = (Area of individual bar/spacing + lump sum area per unit length) X (Tributary
width of deck)
Primary Reinforcement
The primary longitudinal reinforcement runs the full length of the bridge. The
reinforcement can be described with a bar size and spacing AND a lump sum area per
unit length. If both bar spacing and lump sum input is provided, they are added together
for the total amount of reinforcement. For example, if the top mat is defined with #6
bars at 18” and 0.18 in2/ft, the total reinforcement will be 0.44in2/1.5ft + 0.18in2/ft =
0.473in2/ft.
Supplemental Reinforcement
30 | P a g e
FIG . 15
CRASH BARRIER
Crash barriers are designed to withstand the impact of vehicles of certain weights at
certain angle while traveling at the specified speed. They are expected to guide the
vehicle back on the road while keeping the level of damage to vehicle as well as to the
barriers within acceptable limits. Ideally a crash barrier should present a continuous
smooth face to an impacting vehicle, so that the vehicle is redirected, without
overturning, to a course that is nearly parallel to the barrier face and with a lateral
deceleration, which is tolerable to the motorist. To achieve these aims the vehicle must
be redirected without rotation about both its horizontal or vertical axis (that is, without
‘spinning out’ or overturning), and the rate of lateral deceleration must be such as to
cause the minimum risk of injury to the passengers.
According to the IRC (6-2000) the crash barriers shall be provided at the following
locations:
31 | P a g e
1. For bridges without foot paths, concrete crash barriers shall be provided at the edge
of the carriageway.
2. The type design for the crash barriers may be adopted as per IRC:5. The design
loading for the barriers shall be as per Clause 209.7 of IRC:6.
3. For bridges with foot paths, pedestrian railing shall be provided on the outer side of
footpath.
4. The railings of existing bridges shall be replaced by crash barriers, where specified
in Schedule-B of the Concession Agreement.
FIG .16
32 | P a g e
FIG . 17
33 | P a g e
WATER CEMENT RATIO
According to the water – cement ratio law given by Abram as a result of many
experiments, the strength of well compacted concrete with good workability is
dependent only on the ratio. The lower water content produces stiff paste having greater
binding property and hence the lowering the water-cement ratio within certain limits
results in the increased strength. Similarly, the higher water content increases the
workability, but lower the strength of concrete.
The optimum water-cement ratio for the concrete of required compressive strength is
decided from graphs and expressions developed from various experiments. Amount
of water less than the optimum water decreases the strength and about 10% less may be
insufficient to ensure complete setting of cement. An increase of 10% above the
optimum may decrease the strength approximately by 15% while an increase in 50%
may decrease the strength to one-half. According to Abram’s Law water-cement law,
lesser the water-cement ratio in a workable mix greater will be the strength. If water
cement ratio is less than 0.4 to 0.5, complete hydration will not be secured. Some
practical values of water cement ratio for structure reinforced concrete
Water cement ratios in the range of 0.40 to 0.60 are typically used. For higher strength
concrete, lower w/c ratios are necessary, along with a plasticizer to increase
flowability. (0.38 w/c ratio for mix design of 1:0.75:1.5)
GIRDER BRIDGES
A girder bridge is a bridge that uses girders as the means of supporting its deck. The
two most common types of modern steel girder bridges are plate and box.
The term "girder" is often used interchangeably with "beam" in reference to bridge
design. However, some authors define beam bridges slightly differently from girder
bridges.
A girder may be made of concrete or steel. Many shorter bridges, especially in rural
areas where they may be exposed to water overtopping and corrosion, utilize concrete
box girder. The term "girder" is typically used to refer to a steel beam. In a beam or
34 | P a g e
girder bridge, the beams themselves are the primary support for the deck, and are
responsible for transferring the load down to the foundation. Material type, shape, and
weight all affect how much weight a beam can hold. Due to the properties of the second
moment of area, the height of a girder is the most significant factor to affect its load
capacity. Longer spans, more traffic, or wider spacing of the beams will all directly
result in a deeper beam. In truss and arch-style bridges, the girders are still the main
support for the deck, but the load is transferred through the truss or arch to the
foundation. These designs allow bridges to span larger distances without requiring the
depth of the beam to increase beyond what is practical. However, with the inclusion of
a truss or arch the bridge is no longer a true girder bridge.
FIG .18
35 | P a g e
FORMWORK
Formwork is molds into which concrete or similar materials are either precast or cast-
in-place. In the context of concrete construction, the falsework supports
the shuttering molds. In specialty applications formwork may be permanently
incorporated into the final structure, adding insulation or helping reinforce the finished
structure.
Types
Formwork may be made of wood, metal, plastic, or composite materials:
36 | P a g e
5. Stay-In-Place structural formwork systems. This formwork is assembled on
site, usually out of prefabricated fiber-reinforced plastic forms. These are in the
shape of hollow tubes, and are usually used for columns and piers. The
formwork stays in place after the concrete has cured and acts as axial
and shear reinforcement, as well as serving to confine the concrete and prevent
against environmental effects, such as corrosion and freeze-thaw cycles.
DECK FORMWORK
Fig .19
On the dawn of the revival of concrete in slab structures, building techniques for the
temporary structures were derived again from masonry and carpentry. The traditional
slab formwork technique consists of supports out of lumber or young tree trunks, that
support rows of stringers assembled roughly 3 to 6 feet or 1 to 2 metres apart, depending
on thickness of slab. Between these stringers, joists are positioned roughly 12 inches
(30 cm) apart, upon which boards or plywood are placed. The stringers and joists are
usually 4 by 4 inch or 4 by 6 inch lumber. The most common imperial plywood
thickness is 3⁄4 inch and the most common metric thickness is 18 mm.
37 | P a g e
Metal beam slab formwork
Similar to the traditional method, but stringers and joist are replaced
with aluminium forming systems or steel beams and supports are replaced with metal
props. This also makes this method more systematic and reusable. Aluminum beams
are fabricated as telescoping units which allows them to span supports that are located
at varying distances apart. Telescoping aluminium beams can be used and reused in the
construction of structures of varying size.
Modular slab formwork
These systems consist of prefabricated timber, steel or aluminum beams and formwork
modules. Modules are often no larger than 3 to 6 feet or 1 to 2 metres in size. The beams
and formwork are typically set by hand and pinned, clipped, or screwed together. The
advantages of a modular system are: does not require a crane to place the formwork,
speed of construction with unskilled labour, formwork modules can be removed after
concrete sets leaving only beams in place prior to achieving design strength .
Fig .20
38 | P a g e
TRUSS CONNECTIONS
1)Riveting
FIG .21
2) Fastening,
3)Welding,
FIG .22
39 | P a g e
4)Mechanical joints,
In the real-world applications, because the mathematic models of truss members are
applied, any connections in the truss structure are assumed to be free of rotations.
However, one must ensure that the impact of rotational restraints is ignorable in contrast
to that of translational restraints. Otherwise, the element types such as bending or frame
members have to be used.
DECK CONCRETING
40 | P a g e
41 | P a g e
SELF-EVALUATION
42 | P a g e
CONCLUSION
In the end I would like to thank my college, Model Institute of Engineering and
Technology for providing me this wonderful opportunity to acquire some much
needed on-field experience. The main objective of these internship programmes
is to provide an opportunity to undergraduates to identify, observe and practice
how engineering is applicable in the real industry, it is not only to gain
experience on technical practices but also to observe management practices and
to interact with field workers. I feel like I received a lot from this internship
programme. During these six weeks, I was able to see different theoretical
aspects and methodologies. I think this internship programme laid a good
foundation for me to kickstart my career.
43 | P a g e