Planned Cumulative
Balance Achvd till Previous Planned for Sep-22 Planned for Oct-22 Planned for Nov-22 Achieved This Cummulative %
Sr. No Item Description Unit Total Scope This Month Achieved Today Achieved as on Remarks
Scope Month (Aug-22) Month Sep-22 Achieved
(Sep-22) W1 W2 W3 W4 T W1 W2 W3 W4 T W1 W2 W3 W4 T date
A ELEVATED VIADUCT WORK
1 Piling Nos 88 28 60 8 2 2 2 2 8 3 3 3 3 12 3 3 3 3 12 60 68% P17-P20 utility trenching done
3 Pier Nos 21 21
C ELEVATED RAMP
1 Excavation Rmt 309 277 32 500 500 1000 500 500 1000 32 10% Ramp area dewatering wip
E UG STATION WORK
1 Secant Pile Nos 615 412 200 100 100 110 110 3 203 33% SP-324, 343 & HP-276 concrete done
a Hard Pile Nos 308 230 77 65 15 20 15 15 65 20 10 20 20 70 20 10 20 20 70 1 1 78 25% Flood wall 18 m concrete done
b Soft Pile Nos 307 182 123 35 10 5 10 10 35 10 10 10 10 40 10 10 10 10 40 2 2 125 41% Capping beam 25 m concrete done
c Caping Beam Rmt 518 402 91 50 20 10 10 10 50 10 10 10 10 40 10 10 10 10 40 25 25 116 22% 15 trip muck disposal
c Excavation cum 35000 32986 2014 6000 1000 2000 1000 2000 6000 1000 2000 1000 2000 6000 1000 2000 1000 2000 6000 2014 6%
G UG STATION (LS+SB)
1 Secant Pile Nos 852 412 437 100 100 110 110 3 440 52%
H CASTING ELEMENTS
Tunnel Ring segments Nos 2935 2914 21 80 20 20 20 20 80 25 25 25 25 100 30 30 30 30 120 21 1%
I Critical Isue