Quiz 1
1. Upon completion of the construction, the said licensed architect or civil engineer shall
submit the logbook, duly signed and sealed, to the Building Official. He shall also
prepare and submit a _____________________ of the project stating that the
construction of building conforms to the provisions of this Code as well as with the
approved plans and specifications.
Certificate of Acceptance
Certificate of Mobilization
Certificate of Completion
Certificate of Retention
2. It is the length of time a material can withstand being burned which may be one-hour,
two-hours, three-hours, four-hours, etc.
Fire-resistive time period rating
Fire-resistive revolution
Fire zonings
Fire retardant
3.Any person, firm or corporation who shall violate any of the provisions of this Code
and/or commit any act hereby declared to be unlawful shall upon conviction, be
punished by a fine of _________________________________ or by both such fine and
imprisonment:
not less than twenty thousand pesos or by imprisonment of not more than twelve years
twenty-five thousand pesos or by imprisonment of not more than two years
twenty thousand pesos or by imprisonment of not more than two years
not more than twenty thousand pesos or by imprisonment of not more than two years
Building Permit
Certificate to Occupy
Certificate of Occupancy
Certificate of Completion
8.Who undertakes the final inspection, prepares corresponding fees and order of
payment, and issues the Certificate of Occupancy?
10
14
15
20
10. It deals with mandated compliances relating to the physical planning, design,
development, construction and use of socialized housing and resettlement sites, and
the pertinent dwelling units.
NBCP
NSCP 2015
Batas Pilipinas 220
BP220