You are on page 1of 1

Gabcikovo-Nagymaros Case (1997) ICJ In September 1997, the International Court of

justice held that:


Gabcikovo Nagymaros Dam Construction
Case
Slovakia, as successor to Czechoslovakia,
became a party to the Treaty from January
In 1977, Hungary and Czechoslovakia signed a
1993
treaty to construct a dam.
In 1989, Hungary abandoned the project, but
Czechoslovakia continued construction work. That impossibility is not a valid ground to
terminate the Treaty, as Hungary's failure to
In May 1992, Hungary notified Czechoslovakia
carry out the construction work compromised
that it was terminating the Treaty.
the Treaty's performance, and that Hungary
could not use the Necessity's defense, as it
could not prove that its decision was made in
Five months later, Czechoslovakia diverted the response to a situation of imminent danger to
river's waters into a bypass canal which the environment.
caused environmental harm.

The Court also held that the collapse of


In January 1993, Slovakia became an communism and the reduced economic
independent Country. benefits, did not radically transform Hungary's
obligations, as the change of circumstance
must be fundamental and unforeseen,
Hungary claimed that Czechoslovakia's
unilateral construction activities constituted a
material breach, and that the Treaty became And that Hungary did not act in good faith in
impossible to perform, because implementing it suspending the project as it was not entitled to
would cause serious environmental harm. abandon it. However, Czechoslovakia was in
Consequently, it argued that under the Vienna material breach when it diverted the river's
Convention, an essential object of the Treaty waters.
had been destroyed.

lastly, the ICJ held that Hungary and Slovakia


In addition, Hungary invoked the defense of must negotiate in good faith to ensure the
Necessity to justify its decision to abandon achievements of the Treaty, and that unless
construction work, and that Necessity is a the Parties otherwise agree, a joint operation
recognized defense to State responsibility. regime must be established following the
Treaty; And that Hungary shall compensate
Slovakia for the damage resulted from its
Hungary also argued that it was entitled to abandonment of works, while Slovakia shall
terminate the Treaty, as there had been a pay Hungary for the damage it has sustained.
fundamental change of circumstances since
the Treaty was concluded, as the Treaty's
obligations had been changed by the collapse
of communism, and the reduced economic
benefits linked with the project.

You might also like