Professional Documents
Culture Documents
: 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 1 of 76
CONTENTS.
2. OVERALL WORKRESPONSIBILITY
4. MATERIAL HANDLING
8. NDE
11. REFERENCE
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 3 of 76
Field Piping
1) PWHT PWHT
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 4 of 76
2) Hardness Test
Pressure-Test
2. Overall Work Responsibility
1) Work Sequence
Planing &
Preparation
3) Procedure
a)DIC QA Standard Procedure
b) DIC QC Standard Procedure
3) Procedure
4. Material Handling
1) Work Sequence
Protect Flange
Spool End
Transportation
to Site
Storing/Install
at Site
a) Identification stamping shall be done only with a roundness or interrupted dot die. Stainless
steel shall not be marked by stamping, but may be marked using a Vibra-Etch tools.
b) Paints or inks may be used for marking of pipe, but those marking materials to be used for
stainless steel pipe shall be certified and conformed to the chemical composition
acceptance criteria indicated in Project Specification or relevant code.
c) Care shall be taken while stamping to assure that the maximum depth of identification does
not infringe on minimum wall thickness of the pipe.
d) For field modification, the material identification shall be maintained for all cut length (except
for Scrap), of stainless and alloy, carbon steel pipe, by the craftsman doing the work and
shall be verified by QC engineer.
e) Material considered to be scrap shall be so designated by writing the word “SCRAP” in large
letter on it and shall be transferred to a segregated area.
a) Lifting of material during the transfer, fabrication and installation, Nylon Sling shall be
used for the lifting of stainless steel piping or pipe spools.
b) All of the valve shall be protected with end cap under the storage condition.
c) All openings of pipe and pipe spool shall be protected with temporary cover during
storage and transfer
4) Temporary Attachment
1) Due care shall be taken in the transportation of materials, equipment and others to be used in
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 13 of 76
the field. All obstructions such as, foundation, trenchs, etc. shall be reviewed and sufficient
countermeasures shall be taken against these obstructions to prevent the material &
equipments from damage.
2) All work shall be scheduled in a proper manner, so as to prevent interruption in the work or
damage to other existing facilities. Contractor shall explain his detailed transportation plan,
including arrangement of guy-wire, installation of transporting facilities or materials, to
Client's personnel in charge and obtain the approval.
1) Sufficient protecting means shall be taken not to allow sand or other foreign matters go into
inside of pipes and other piping materials.
2) Protection Materials
a) Warning Tape or Fence
b) Wooden Pallet
c) Wooden Timber
d) End Cap
1) Work Sequence
Sub-Pipe Rack
Note 1: I= Inspection, R= Reporting results of Inspection, Examination or Test, D= Document Review, (W)= Random or
Partial Witness, W= Witness
Note 2: QC= Quality Control, PS= Pipe Shop, FP= Field Piping
1) Reference Documents:
a) Piping Plan/ISO Dwg
-Weld Joint Number (SW or FW)
-Spool Length
-Spool Number
-Tag Number
-Material Class
-Type of Support
-Handle Direction
-Flow Direction
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 16 of 76
-Maintenance Spacer
-Location and Position for Pipe Lines
2) Installation
a)Measurement for the determination of required design position and the erected variation
from those positions may be made from local area reference coordinates and elevations.
b) Where variations from theoretical position occur, if the variations are within the
specified tolerances and the limitations, the system shall be considered to be erected as
designed.
c)Position variations beyond these tolerances shall be disposed after engineering review
by the authorized personnel responsible for engineering design.
d) Specified slope requirements for drainage shall be maintained as a minimum design
requirement for a system.
e)Position variations shall be considered and limited by the effect of the variations on the
location of high point vents and low point drains.
3) Threaded Connection
1) Reference Documents:
a) ISO Dwg
b) Approved Tag Index as per Piping Class
c) P & ID Dwg
d) Pressure test & Flushing Scheme
2) Flanged Connection
a) Flange joint for process lines shall be tightened in accordance with the gasket
manufacturer's recommended torque values.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 17 of 76
b)Gaskets for all joints shall be of such inside dimensions that no portions will project
into the ports of valves, pipe or fittings.
c) For each type and pressure rating of gasket, Piping Engineer shall receive the
recommended torque values to be used for joining the flanges from the gasket
manufacture.
d)Temporary gaskets may be used for leak testing.
e) Temporary gaskets shall be replaced with permanent gaskets.
f) Permanent gaskets shall be installed in dry condition.
3) Orifices Installation
a) The internal surface of pipe at the orifice location shall smooth, straight, and free
from scale, pits, or holes, reamer or holes, reamer or rifting, bumps, or other
irregularities.
b) The orifice and orifices flanges requires special handling flange surfaces and orifice
plates to protect from scratch or dent during installation.
c) The orifice plates may be replaced with dummy orifice plates during flushing.
d) After flushing, the dummy orifice plate shall be removed and the regular orifice plate
shall be installed.
e) The orifice plate shall be aligned and installed correctly with regards to direction of
flow.
Specialty items such as steam traps strainers; expansion joints shall be installed according
to the manufacturer's instructions.
5) Valve Installation
a) Prior to welding, the position of valve seat and disc shall be checked and maintained
in accordance with the manufacturer's instructions
b) Care shall be taken to prevent any arc strike between seat and disc.
c) If necessary, valve accessories should be dismantled to avoid the damage during pipe
installation period.
d) Direction of flow stamped on the body shall be consistent with the system flow.
e) Slings or chains shall never be placed around the handwheel, valve stem or limit
switch parts.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 18 of 76
f) Nylon slings may be placed around the handwheel or stem housing of large valve for
the purpose of balancing during rigging operations provided that no direct weight is
transmitted to this part.
g) Prior to installation and final closure, the interior of the valve shall be checked as
thoroughly as possible without disassembly to verify the cleanliness condition.
h) When handling or supporting the valve, care shall be taken to prevent damage to the
valve or its appurtenances (hand-wheels, drains, vents, etc...)
i) Temporary Gaskets shall be used for Pressure Test & Flushing
-Control Valve
-Check Valve (See Flow Direction)
-Orifice Plate
-Strainer Flange & Temp. Wire Mesh
-In line Instruments
-Corrosion Coupon
-Equipment Flange
-Temporary Spacer & Blind
-Vent & Drain Flange
1) Work Sequence
Alignment/Fit-up
Preheating
(If Required)
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 19 of 76
Welding
Postheating
(If Required)
Welding SSP-3P-001
SSP-3P-007
1. Welding Procedure QCP-710-20 ITP-WE-01A/B I I/R QC
2. Procedure Qualification QCP-710-22 ITP-WE-03A/B I I/R QC
3. Welder Qualification QCP-710-23 ITP-WE-04 I/R W QC
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 20 of 76
Reference Procedure:QCP-710-10/20/21/22/23
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 21 of 76
6.1.1 Cutting
1) Thermal cutting can be performed by arc cutting or oxygen gas cutting method.
a) Material shall be cut to shape and size by mechanical means such as machining,
shearing, grinding, or by gas cutting, the cut surface shall be ground to bright metal.
b) When low alloy steel is cut by thermal means, at least 1/16 inch(1.6㎜) shall be
removed by grinding.
a) Austenitic Stainless Steel material shall be cut by mechanical means, sawing, abrasive
disc, arc air gouging process or plasma arc cutting.
b) When arc air gouging is used for rough cutting, all remaining slag, scale or oxides
shall be removed by machining or grinding the cut end to sound metal.
c) No flame cutting in allowed
d) Power grinding wheels high speed cutting wheels and or brushes, which have been
used for carbon steel, shall not be used for the fabrication or installation of stainless
steel piping.
4) Carbon Steel
6.1.2 Beveling
FIRST, WELD THE PART 1 * AND FINISH OFF WELD SURFACE WITH GRINDER AND
THEN WELD PART 2*.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 23 of 76
1) Clamps, welded clips, tack welds, or other appropriate means shall be used to properly
align the joint for welding.
2) Welded attachments used for fit-up shall be compatible with the base materials.
3) Preheating for welding of temporary attachments shall be in accordance with the
applicable WPS.
4) After completing fabrication, attachments shall be removed flush with the base metal
without encroaching on the required minimum wall thickness.
5) Breaking does not permit removal of attachments.
6) PT shall examine all areas from which temporary attachments have been removed or MT
after the surface has been restored.
7) Any defects found shall be removed by additional grinding and rewelding, if necessary.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 24 of 76
1) The following steps should be followed for verification of the socket gap.
2) Before tacking and welding, the distance between the scribe line and the end of socket
depth shall be at least 1/16 inch but not greater than 1/8 inch.
Cx
1.5mm(1/16in) Approx. gap before Welding
ASME B31.3 Fig.328.5.2C Minimum Welding Dimensions for Socket Welding Components
other than Flanges
1) Preheating
a) Preheat shall be proceeded without interruption. If a weld is not completed and
preheats is specified, then the weld must be preheated again before recommencing
welding.
b) In principal, minimum preheat and interpass temperature for materials of various P-
No. shall be as specified in Attachment 1.
c) For welding of the dissimilar ferritic steels having different preheating temperatures,
the higher temperature shall be applied.
d) For welding a ferritic steel to an austenitic stainless steel, preheating shall be applied
only to the ferritic steel.
e) Preheating shall be uniformly carried out using a propane gas burner or electric
heating coils. For welding of P-No. 4 or 5 materials, which have large diameter and
heavy thickness, heating with electric heating coil is recommendable.
f) The preheating zone shall extend at least 25㎜ beyond each edge of the weld.
g) Preheat temperature shall be checked by use of temperature indicating crayons,
thermocouple or other suitable means at least 25㎜ beyond each edge of the weld.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 25 of 76
2) Post-heating
a) The Purpose of post-heating is to prevent delayed cracking due to the diffusible
hydrogen penetrated into the weld during welding.
b) Unless other wise specified, post-heating shall be carried out in accordance with the
Qualified Welding Procedure Specification, right after welding for min. 0.5 minutes
per 1㎜ in thickness of the welds(min. 5 minutes and max. 30 minutes) within the
temperature range of 300-400 C, then the weld shall be cooled slowly by the use of
insulation material.
c) Width of heating zone, heating method and check method of heating temperature shall
be the same as for preheating.
6.3 Tack-Welding
1) Tack welds shall have the same quality requirements as the final welds.
2) Qualified welders using qualified welding procedure shall make tack weld.
3) When tack welds are to become part of the finished weld, they shall be visually examined
and defective tack welds removed.
Main purposes of this WELDING MATERIAL CONTROL are to protect from mis-use of
electrodes and welding rods and to provide the welder with conditioned electrodes and
welding rods for the sound welds. Construction Contractor shall submit the detailed
procedure to the CMC considering the type and quantity of welding materials to be used for
construction.
Drying Condition
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 26 of 76
No.
Austenitic Type
Lime-Titania E308/308L-15/16
Steel E309-15/16
9% Nickel Lime Type SFA ENiCrFe-12 200-250 60 100-150
Steel 5.11
Fused Type — — 150-350 60 150-350 For
Submerged
Fluxes Bonded Type — — 200-300 60 200-300 Arc Welding
Note:*Manufacturer’s specified drying condition different from the above table may be proposed
By Construction
6.4 Welding
1) Qualified WPS based on PQR shall be provided in accordance with the applicable Codes,
Standards and project specifications prior to any production welding.
2) WPS / PQR and Welder Performance Qualification Test made in accordance with the
requirements of 1962 edition or any later edition of ASME Code section IX or ASME B31
Code for pressure piping may be used without requalification of WPS / PQR.
3) Production welding shall be only performed by the qualified welder who have
demonstrated their welding ability determined satisfactory in accordance with the approved
WPS and project specifications.
4) The WPS or PQR and RWPQT may be submitted to the Customer for his approval, if
required.
5) For inter-company procedures or inter-organization, if both company or organizations are
same corporate or single organizational structure who are both following this quality /
technical procedures, the WPS, PQR and/or welders shall be allowed to be used without
requalification in both company or organization.
6) Prior to preparation of WPS or welding procedures, the followings shall be considered to
meet the specific requirements.
a) Compatibility of weld metal and base material.
b) Metallurgical properties and desired mechanical properties.
c) PWHT or other heat treatment.
d) Service requirements and welder's ability.
1) Welding work will be performed in accordance with the flow chart of welding work.
2) For process control of the alloy and special line class, welding activity will be inspected
based on welding inspection record.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 30 of 76
Visual and RT No
(if req'd)
Yes
Yes
Qualify WPS
Yes
Yes
R.T or Bend No
Test
Yes
2) All pipe, storage tank and structural steel shall be welded using one or a combination of the
following methods.
a) Shielded Metal Arc Welding (SMAW)
b) Gas Tungsten Arc Welding (GTAW)
c) Gas Metal Arc welding (GMAW)
3) The welding of butt welds in carbon or low alloy steel pipe with a wall thickness of 3/4 inch
(19㎜) or greater may only be interrupted provided a minimum of at least 3/8 inch(9.5㎜)
thickness of weld deposit or 25% of welding groove, whichever is greater, is filled.
3 C-0.5Mo steel
4 1 1/4Cr-0.5Mo steel
5 2 1/4Cr-Mo 5Cr-0.5Mo
225
241
1) Work Sequence
Inspection
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 34 of 76
Note 1: I= Inspection, R= Reporting results of Inspection, Examination or Test, D= Document Review, (W)=Random or
Partial Witness, W= Witness
Note 2: QC= Quality Control, PS= Pipe Shop, FP= Field Piping
1) General
2) Definition
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 35 of 76
a) Pipe supports are those elements used to carry the weight of piping, contents,
insulation, and other loads as defined in the Power Piping Code, ASME B31.1 and
this specification.
b) Hanger or those elements : carry the load from above with the supporting members
being mainly in tension.
c) Support or those elements: carry the load from below with the supporting members
being mainly in compression.
d) Restraint or those elements: control or limit movement of the piping or any
combination of these support functions.
e) Cold setting: the indicator position or point to indicate blue sticker marked “C” on the
indicator scale when the plant is shut-down. This setting load is same as dead load
which consists of the weight of the piping components, insulation, protective lining
and coating, and other superimposed permanent loads.
f) Hot setting : the indicator position or point to indicate red sticker marked “H” on the
indicator scale when the plant is operation. This setting load is equal to the live load,
as determined by weight balance calculations plus thermal expansion load.
g) Travel stop : this device will lock the hanger against upward or downward movement
for temporary conditions of underload or overload, such as may exist during
hydrostatic test or chemical clean-out.
3) Spring Hangers
a) Spring hanger pin shall be removed only when the supported lines are ready for
start-up condition.
b) After plant has started operation, check the spring hanger position whether it is at
hot load position and confirm any excess variation from design load.
Pipe supports which is located at high elevation may be prefabricated at shop under
supervision of piping field engineer. Piping field engineer will designate exact
dimension of above mentioned pipe supports for it's prefabrication.
5) Materials
Materials and hardware for use in pipe support works shall comply with the requirements
of applicable Codes and Standards, if required.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 36 of 76
8. Nondestructive Examination
Direct Visual
Examination
5 Minutes Drying
Install Electromagnetic
Yoke
Demagnetization
Record Acceptance
Film Review
1) Remote visual examination may have to be substituted for direct visual examination using
such aids as mirrors, telescopes, fibreoptics, or cameras, provide that such systems can be
shown to have a resolution capability at least equivalent to that obtainable by direct visual
examination.
8.2.1 Pre-cleaning
1) Check that the surface to be examined and adjacent areas within 1 inch shall be through
washed with precleaner in such a manner those foreign materials and contaminants are
removed.
2) Check that the examination surface shall be wiped dry with lint free cloths or absorbent
papers, allowing a minimum of 5 minutes for complete evaporation.
8.2.4 Drying
Check that the surface shall be completely dried, prior to application of the developer, for 5
minutes of drying time.
8.2.6 Post-cleaning
1) Check that post-cleaning is necessary in those cases where residual penetrant or developer
could interfere with subsequent processing or with service requirement.
2) If post removal is necessary, that it be carried out as promptly as possible after
examination so that it does not fix on the part.
8.2.9 Records
1) Reports shall be prepared and furnish to the Customer, shall be filed for the period
required as per Quality Records Procedure unless otherwise stated by the Customer.
2) Examination condition and interpretation shall be recorded on the report form attached to
this procedure.
8.3.1 Equipment
1) AC electromagnetic yokes should have a lifting force of at least 4.5Kg(10 1bs) and DC
yokes 18Kg(40 1bs) at the maximum pole spacing where they will be used.
2) If used, prod type electrical equipment shall be used with a pole spacing 76 - 203mm(3 to
8inches) and the magnetizing current shall be applied in accordance with the requirement
of ASME Code, Sec. V, Art. 7.
8.3.2 Material
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 44 of 76
Wet magnetic particles shall be utilized as the testing medium. The color selected shall
provide adequate contrast with the surface being examined.
8.3.3 Calibration
1) The applicable block described below shall be used to verify proper operation of the
electromagnetic yoke.
2) A calibration block of a ferromagnetic material weighting a minimum 4.5 Kg(10 1bs)
shall be used to confirm the lifting power of AC magnetizing current, at the max. pole
spacing
3) A calibration block of a ferromagnetic material weighting a minimum 18 Kg(40 1bs) shall
be used to confirm the lifting power of DC magnetizing current, at the max. pole spacing.
1) Surface preparation
The surface being examined shall be clean and dry and shall be free from oil sand, loose rust,
loose scale. Thin paint must be removed at points where electrical contact is to be made.
2) Method
a) The electromagnetic yoke shall be applied twice in each testing area. The second testing
shall be conducted with the lines of magnetic flux approximately at right angles to the
first application. Overlap shall be sufficient to ensure the entire testing area is covered.
b) The magnetic particle shall be applied by either spraying or flowing it over the areas to
be tested.
c) The adequacy of magnetic field shall be demonstrated by field indicators. The operation
shall also use field indicators during testing to verify the adequacy of magnetic field.
d) All examinations shall be conducted using the "continuous method". The
electromagnetic yoke shall remain activated during the application and removal of
excess material
e) Variable electromagnetic yoke pole spacing shall be a maximum of 203mm(8 in)
measured on the material surface between the centerline of the poles.
3) Post-examination cleaning
Examination personnel shall conduct post-cleaning for removal of testing medium.
4) Demagnetization
When residual magnetism in the part could interfere with subsequent processing or usage, the
part shall be demagnetized any time after completion of the examination.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 45 of 76
8.3.6 Records
Examination condition and interpretation shall be recorded on the report form attached to this
procedure.
1) Equipment
a) The following equipment or equivalent shall be utilized for this examination.
b) The equipment shall be of the pulse-echo type.
c) The equipment shall generate receive and present the relevant pulses on a CRT in the
frequency range from 1 to 6 MHz.
d) The horizontal linearity shall be within ±5% of full screen height over the range of 10%
to 100% of full screen height.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 46 of 76
e) The equipment shall have a calibrated gain control adjustable in discrete 1 or 2 dB steps
over a range of at least 60 dB. The accuracy of the gain control settings shall be within
±1 dB.
2) Search unit
a) Straight beam techniques
-Normal size of 1/2" x 1/2" or 1" x 1" search units with nominal frequencies of 2 or
2.25 MHz are utilized for this examination.
b) Angle beam techniques
-Projection angle of 45 deg, 60 deg,70 deg search units with nominal frequencies of 2 or 2.25
MHz are utilized for this examination.
3) Calibration block
Test equipment shall be calibrated using reference calibration blocks fabricated from
material that is acoustically similar to that being inspected and standard calibration blocks
to be used are as following:
a) IIW : standard calibration block
b) IOW : beam profile block
c) Standard thickness calibration block
8.4.2 Couplant
Couplant shall be water washable such as glycerine or deionized water with or without wetting
agent.
deg ±2 deg and 60 deg ±2 deg shear wave in the examination material.
1) Surface preparation
The surface from which scanning is to be achieved should be cleaned to remove all scale
or coating to assure continuous coupling during the examination.
2) Basic measurement
a) The thickness of each member from which is to be achieved should be determined and
recorded for use in the flow location determinations.
b) The entire area from which scanning is to be achieved should be examined by the
longitudinal wave technique to assure freedom from laminations or other laminar type
defects which could interfere with sound wave propagation.
a) Scanning
The weld shall be examined by moving the search unit progressively along and across a
sufficient contact area so as to scan the entire weld.
b) Sensitivity level
When possible, scanning shall be performed at a minimum gain setting of twice (6 dB)
the initial reference level. Evaluation of discontinuities shall be done with the gain
control set at the reference level.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 48 of 76
a) Scanning
The weld shall be scanned using the lowest numbered leg possible within the constraints
of avoiding interference between the transducer wedge and the weld bead.
b) Sensitivity level
The reference level sensitivity for monitoring discontinuities is the initial reference
response corrected for distance by the DAC curve. When possible, scanning shall be
performed at a gain setting of two times (6 dB) the reference level sensitivity.
All indications which procedure a response greater than 20% of the reference level shall be
investigated to the extent that the operator can determine the shape, identity and location of all
such reflectors and evaluate than in terms of the acceptance standards.
8.4.6 Records
1) A report from which clear identified the work and the area of examination shall be
completed by the ultrasonic examiner at the time of examination.
2) Examination condition and interpretation shall be recorded on the report form attached to
this procedure.
All X-ray devices shall be calibrated at least every three months by comparing the difference
of densities between two sequence radiographs gained at each calibration shooting.
8.5.3 Materials
1) Film
Radiographs shall be made using in accordance with ASME Code, Sec. V.
2) Intensifying screen
A front and back lead intensifying screen shall be used in accordance with the referencing
codes and shall be in direct contact with the film.
3) Film cassette
The film cassette shall be firmly fixed and maintained as closely as practical against the surface
of the component during exposure.
1) System of identification
A system shall be used to produce permanent identification on the radiograph traceable to the
contract, component, weld or weld seam or part numbers, as appropriate. In addition, the
manufacturer's symbol or name and the date of the radiograph shall be plainly and
permanently included on the radiograph. in any case, this information shall not obscure the
area of interest.
2) Location markers
Location markers, which are to appear as radiographic images on the film, shall be placed
on the part -not on the exposure holder/cassette- and their locations shall be marked on the
surface of the part being radiographed or on a map in a manner permitting the area of
interest on a radiograph to be accurately located on the part, and providing evidence on the
radiograph that the required coverage of the region being examined has been obtained.
Location markers shall be placed in accordance with the referencing codes.
1) Selection
The thickness on which the penetrameter is based is the nominal single wall thickness plus
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 50 of 76
2) Placement
a) For welds, a source side penetrameter shall be placed adjacent to the weld seam.
For materials other than welds, a source side penetrameter shall be placed in the area of
interest.
b) He penetrameter shall be placed on the film side of the part, and a lead letter "F" at least as
high as the identification number shall be placed adjacent to the penetrameter.
3) Number
a) One penetrameter shall be used for each radiograph.
b) If the requirements are met by using more than one penetrameter, one shall be
representative of the lightest area of interest and the other the darkest area of interest.
The transmitted film density through the radiographic image of the body of the appropriate
penetrameter and the area of interest shall be followed in accordance with the applicable
codes and project specifications.
Interpretation may be accomplished using either single or composite viewing. Acceptance shall
be as the referencing codes or project specifications.
1) Work Sequence
Radiographic
Examination
Accepted R/T
Hardness Test
1) Heating element made of nichrome wire shall be wrapped on the full length of the weld to
be heat-treated, on the width of at least two(2) inches from the each side of the weld.
2) Heating element shall be wrapped on its full length and width by the insulation material
made of glass wool or ceramic fiber.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 53 of 76
3) The connection of a heating element (coil) and a cable shall be wrapped by asbestos cloth
and fixed by a friction tape for safety.
9.1.1 Heating
1) Heating for PWHT shall be made by the electric machine which produces the energy from
the electric resistance of nichrome wire (heating element).
2) Heating rate shall be max. 200℃ per hour and in accordance with the qualified Welding
Procedure Specification.
3) The temperature and time for each weld shall be automatically recorded on chart by
electric machine. And the required number and location of thermocouples to record the
temperature and time are as follows.
1) The hardness limits in Attachment 2 shall be applied to both the weld and heat affected zone.
2) Hardness tests of heat affected zone shall be made at a point as near as practicable from the
edge of the weld.
3) The weld to be tested shall be flat finished by grinding and removed the impurities.
4) The hardness of the weld and heat affected zone shall be tested by one point per one weld
which performed the PWHT.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 54 of 76
5) The hardness shall be obtained by portable hardness tester in BRINELL HARDNESS value
or equivalent.
1) Preheating temperature
2) Post Weld Heat Treatment
3) Work Flow of PWHT
4) Inspection Requisition Sheet for “PWHT”
5) Instruction of PWHT Work
6) Record of Heat Treatment
7) Log Sheet of PWHT
10-1. 중점 관리 ITEM
SEC. I, Shop prefabrication 참조
Description 문 제 점 조치 사례
Description 문 제 점 조치 사례
절감과 회사 경쟁력 강화
10 Bolts & Nuts 초기에 Bolts 자재 조달이 늦어져 다른 초기부터 Bolts & Nut를 Expedite를 하여
Size를 임시 설치 후 Replace가 제대로 추가 Replace 문제를 극소화 하고, 임시
되지 않음. 설치는 반드시 기록으로 혼선 방지 및
입고된 자재는 Piping Material Class 별로
Color Code 적용 후 현장 불출.
11 Dissimillar Cracking Furnace의 welding Process중 [별첨 #1]Proposal대로 Client 승인을
Welding (P4+P8) Heater Coil Outlet(SUS304)와 득하여 재시공
Interconnection (Cr, Mo) 이종 금속
용접으로 Code violation 발생됨. 즉 P4
Material(Cr-Mo)는 Dissimillar Welding
후 ASME B31.3 Para 331.2에 의거 720
℃, 2HRS Holding Time으로 열처리를
실시 해야되나, Stainless Steel은
500∼800 ℃로 열처리 시행할 경우 Cr.
이 석출되는 예민화 현상(Sensitization)
이 발생하므로, 이 문제점으로 인하여
Welding이 기 완료된 Cracking Furnace
Interconnection Line (72 Joint)를 제
시공 했으며, 도면을 Revision 시켰음.
12 Welding For 영국 Paralloy 회사로 부터 공급된 Stone & Webster의 Welding Engineer,
Paralloy (Furnace) Furnace Transfer Line Paralloy(Cr 39w) Paralloy Vendor의 Welding Specialist의
Welding중 Crater Crack 및 Fine Crack 자문 및 Vendor Welder Mob. 등
발생으로 가장 어려웠던 Welding 최종적으로 Vendor 주문에 의한KEMPPI
작업이었음.<참조> Paralloy : Cast Heat 회사의(Water Cooling Type) Welding
Resisting Alloy로 Chemical Composition Machine을 구입하여 Welding Defect를
은25/35 Cr/Ni+1.2/0.1 Nb/C임. Clear 하였음.
Description 문 제 점 조치 사례
13 Status For C.S 및 일반 SUS 용접봉은 Hyundai 1)Status For Welding Rod [별첨 #3]참조.
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 57 of 76
14 Welder Project Spec.은 ASME Sec.IX에 의하여 Project Spec. 및 Code 요건에 따라(별첨
Qualification 기능 Test 를 하게되어 있으나 Client는 #4) Proposal for Welder Qualification Test
Alloy 및 SUS도 C/S와 같이 Test 시행 와 같이 시행 협의
요구(Table 참조)
15 Welding Process 배관 용접 기법은(Welding Process)중 SEC. I. Shop prefabrication
수동(Manual)용접은 많은 물량의 “Welding process 참조”
Fabrication을 위한 Shop Welding으로는
많은 인력과 시간이 소모되어 SAW
(Submerged Arc Welding)용접이 검토 (특히 Alloy 및 SUS Heavy Wall
되어야함 반영요망)
16 Support Marking Piping Plan DWG에는 Support의 Type 및 배관공사의 모든 ISO DWG은 Spool No.가
on ISO Drawing 위치가 표시되어 있으나 ISO DWG 표시되는 Shop 제작 및 설치를 위하여
상에는 표시되어 있지 않아 Hydro Test Welding Joint No. 및 Spool DWG을
Package 검토 및 Line Check시 어려움이 작성해야 된다. 현장
많았슴. 규모에 따라 다르지만 통상 ISODWG으로
Shop DWG을 작성하여Validation이
끝나면, TOC의 경우 12매 정도 Copy를
해서 Client, 해당부서 및 Subcontractor로
분배해야 되는 상황으로 볼때 품질 및
공사관리를 위하여Support Marking 은
Shop Drawing 제작 전 ISO DWG에 표시
되어야 한다.
17 Dummy & Pipe Class과 동일 재질을 사용해야 하나 Pipe Support용 자재는 Main-Contractor가
Trunnion Support 현장에서 별도 구매 시 공기에 지장이 공급하는 것이 바람직함
있음
18 Hanger & Special 현장에서 제작 불가 Fabricated Support(Tagged Items)는 Main-
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 58 of 76
Pad를 부착시켜Welding 을 완료
시켰음(약100소).
Disposition으로 R.T 및 U.T를
실시했으나 R.T는 Source 위치 및 Film
부착이 용이하지 않아 R.T Shooting
결과, Film 판독이 불분명 하였고, 또한
U.T도 Branch Pipe의 Wall Thickness가
6㎜ 미만으로 Beam 각도가 나오지
않아 시행 불가능 하였음.
24 Electric Shock by P3, P4 and P5(Alloy Steel)의 NDT(R.T) Heating Pad에서 Damage Ceramic부분의
Damaged Heating 는 ASME B31.3 Para 341.3에DML하면 Heating Element가 Base Material에 Shock
Pad PWHT 전후에 실시하게 되어있다. 발생 시킴. Damaged Ceramic Element
PWHT 후의 R.T 결과 Defect가 교환 및 Pad Repair 후 정기적인 Pad
나타나면 Repair후 재열처리를 Element Testing을 실시 하였으며 또한
시행해야 되기 때문이다. R.T에 Accept 모두 열처리 작업은 Ready for S.W on
된 Welding Joint를 PWHT시행했는데 상태에서 Inspector이 확인 후 S.W On
열처리 (PWHT)후 Welding Joint에 실시했음.
심한 Arc Strike와 같은 흠집이 생겼음.
별첨 #1
Procedure for Dissimilar Welding
(Dissimilar welding P4+P8)
1. Verify the type of disposition
2. Marking on welding joint for identification of disposition(Type "A" and "B")
3. TYPE "A"(375 RETURN LINE)
1) CUT OUT THE COUPON AS PER TYPICAL dwg Type "A"
2) Fabricate and replace the coupon(A) as per typical DWG.
3) Preheateing and welding based on PQR CF-04
4) PWHT on(a) side only
5) R.T and P.T on both side (a) and (b)
4. TYPE "B" (550 OUTLET LINE)
1) Cut out the P8 stainless steel coupon(0) as per typical DWG, type "B" on both side (a) and (b)
2) PQR will be performed based on build up welding to support WPS
3) Qualify WPS
4) Beveling the welding joint on both side (a) and (b)
5) Preheating will be performed before build up welding
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 60 of 76
6) Build up welding will be performed min 2 layer(5mm) on joint (a) with inconnel 82 according to
approved WPS
7) PWHT is required on joint (a) after build up welding
8) P.T will be performed before weld out
9) Rebeveling and grinding the P8 coupon(b) which was cut out to be confirmed the coupon was not
performed PWHT
10) Fit up the coupon(B)
11) Welding out according to approved procedure
12) R.T and P.T will be performed after welding on both side(a) and (b)
11. REFERENCE
b) Organization Chart
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 63 of 76
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 64 of 76
Insulation-Equip M2 30,793
Insulation-Pipe M 73.165
Excavator 81 1,806
Bar Ea 3,003
Beam Mt 53,152
Gravel M3 771,717
Remicon Ea 150,947
Sand M3 134,393
Timber Ea 552,115
1 A/G Piping
S-Total 368
S-Total 243
Trailer M-mth 57
Pick-up M-mth 94
Boom-Truck M-mth 61
Compressor M-mth 65
Sedan M-mth 4
Total 145,073
G 1CML) 1CML)
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 73 of 76
E9018-B3
1000
ER318L
Dry Desk
Oven#1 ER316
Dry E8018-B2
(3.2mm) mm)
Dry
4800
Oven#3 E316-16
Dry Re-Use
Dry
Oven#5
(2.6mm)
Oven#6
Storage for Carbon Steel Welding Welding Material Issue & Storage for Alloy Steel & Stainless Steel
Material Return Welding Material
4 Air Conditioner 3
7 Bench Vice 1
10 Chair 4
11 Chairs 43
12 Chipping hammer 5
13 Claw Bar 2
14 Cleaning Tool 1
15 Container 6m x 2m 4
16 Desk 2
18 Dust Bin 10
20 Elec. Grinder 7” 16
21 Elec. Grinder 4” 12
22 Elec. Oven 1
26 File Round 10
28 Fire Blanket 10
29 Fire Extinguisher 2
30 Fire Extinguisher 12
31 Flat File 10
33 G.I Shackle 1” 2
36 Hammer Ball 3
37 Hammer Claw 3
38 Hilti M/C 4
39 Hydraulic jack 6
41 Kitchen Cabinet 1
42 Kitchen Tool 1
43 Meeting Table 4
44 Monkey Plier 2
48 Oxy/Ace Gauge 10
49 Paper tray 7
PIPING WORK MANUAL DOC.NO. : 기계기술-M-P-01
REV. NO. PAGE NO.
II. FIELD INSTALLATION WORK 0 76 of 76
51 Pipe Clamp 4” 3
52 Pipe Clamp 6” 2
53 Pipe Clamp 8” 2