Professional Documents
Culture Documents
Reviewer From FEU Manila
Reviewer From FEU Manila
REVIEW QUESTIONS:
A. NATIONAL BUILDING CODE
DIRECTION: read the items below, match it with the answers on the right side. Place the correct
letter in the parenthesis.
A. Any new construction which increases the height or area of an
( L ) 1. BUILDING PERMIT
existing building/structure.
(K ) 2. CONSTRUCTION
B. A change in the use or occupancy of a building structure or
any portions thereof which has different requirements.
(I ) 3. ERECTION -
C. The systematic dismantling or destruction of a
building/structure, in whole or in part.
(A ) 4. ADDITION
D. The National Building Code with its implementing rules and
regulations to endure safety to occupants.
( J ) 5. ALTERATION
E. Remedial work done on any damaged or deteriorated portions
of a building/structure to restore its original condition.
( H ) 6. RENOVATION
F. A secondary building/structure located within the same
premises, the use of which in incidental to that of the main
( B ) 7. CONVERSION
building/structure.
( H ) 3. OCCUPANT LOADS C. A court bounded on three sides by building lines with one
side bounded by another open space whether private or
public.
(J ) 4. PUBLIC OPEN SPACE
D. A plan prepared after the construction is done showing all
changes, modifications and alterations made as compared to
( A ) 5. PRIVATE OPEN SPACE the original plans and needed for the occupancy permit.
(J) 1. R. A. 9266 A. A window in a roof and level with it or one into a flat roof as a
dome, etc.
(H ) 2. PROJECTING SIGN B. The line by the intersection of the surface of the enclosing wall
of the building and the surface of the ground.
( F ) 3. DISPLAY WINDOW C. An employee shall be paid this of no less than ten (10%)
percent of his regular wage for each hour of work performed
between ten o’clock in the evening and six o’clock in the
(B ) 4. BUILDING LINE morning.
( A ) 8. SKYLIGHTS G. The mark of floor plan directly touching the ground, the
perimeter of which is seen.
(E ) 9 BATAS PAMBANSA BLG. 344 H. A sign fastened to, suspended from or supported on a building
structure, the display surface of which is perpendicular from the
wall surface or is at an angle there from.
(C ) 10. NIGHT SHIFT DIFFERENTIAL
I. Any portion of a building above the first floor projecting over
the sidewalk beyond the first storey wall used as protection for
( G ) 11. FOOTPRINT pedestrian.
(C) 1. AUTOMATIC FIRE SUPPRESSION SYSTEM A. P. D. 1185 prohibits the obstruction of fire exits, fire
hydrants overcrowding beyond authorized capacities, locking
fire exits and use of jumpers.
(H ) 2. COMBINATION STAND-PIPE
B. The time duration that a material or construction can
withstand the effects of standard test. (1, 2 or 3 hours)
(M ) 3. DRY STANDPIPE
C. An integrated system of underground or overhead piping
or both connected to a source of extinguishing agent or
(I) 4. FIRE ALERTING SYSTEM medium, designed in which when activated by its automatic
device, stops fire within the area protected.
(B ) 5. FIRE RESISTANCE RATING D. The time in which fire will spread over the surface of a
burning material.
(J) 6. FIRE WALL E. Use sprinkler system, hose boxes, stand pipe systems, fire
alarm systems, fire walls, fire resistive enclosures, fire exits
to safe grounds, stairways sealed from smoke and heat, exit
(D ) 7. FLAME SPREAD RATING plan, fire resistive doors, fire dampers in centralized air
conditioning ducts, roof vents for fire fighters.
(L) 8. FIRE (FLAME) RETARDANT F. A gate with four arms set at right angles, revolving on a
central post, allowing the passage of only one person at a
time.
(P) 9. FUMIGANT
G. An air compartment or chamber to which one or more
ducts are connected and which form part of an air
( O ) 10. MEANS OF EGRESS distribution system.
H. Pipeline system filled with water supply for the use of the
( N ) 11. PANIC HARDWARE service and the occupants of the building solely for fire
suppression purposes.
(M) 1. DIRECT SELECTION OF AN ARCHITECT A. A method frequently used where there is a continuing
relationship on a series of project. It establishes a fixed
sum over and above reimbursement for the Architect’s
( F ) 2. COMPARATIVE SELECTION OF AN technical time and overhead.
ARCHITECT
B. The Architect renders full-time supervision ensuring the
quality of control of work, evaluating the work of the
(J ) 3. DESIGN COMPETITION contractor, keeps files and records and manages the
construction.
( A ) 6. COMPENSATION BY MEANS OF E. This is done for complex building projects where the
PROFESSIONAL FEE PLUS EXPENSES Architect acts as an agent of the client in procuring and
coordinating all the necessary services required by the
project, from pre-design to post construction services.
(L) 7. COMPENSATION BY MEANS OF LUMP SUM
OR FIXED FEE. F. One Architect is compared with others and the client
makes a selection based upon the judgment of which firm
is most qualified. The Architect submits information
(P ) 8. COMPENSATION BY MEANS OF PER DIEM concerning the organization, personnel, equipments, past
PLUS REIMBURSEABLE EXPENSES projects, number of years in business, etc.
(C) 11. DESIGN SERVICES K. This method is applicable only to non-creative work
such as accounting, secretarial, research, supervision,
preparation of reports and the like.
(I) 12. SPECIALIZED ALLIED SERVICES
L. This is mostly required in a government contract. This
method is risky, since the Architect’s expenses might
(B ) 13. CONSTRUCTION SERTVICES exceed the agreed amount especially, if there are costly
changes.
(G ) 14. POST CONSTRUCTION SERVICES M. In this method, the client selects his Architect on the
basis of reputation, personal acquaintances, and
recommendation of a friend, or of a former client, or of
(E ) 15. COMPREHENSIVE SERVICES another Architect.
(H ) 1. LUMP SUM CONTRACTS A. The person/s managing the construction in behalf of the
owner. In here, the contract may have been awarded to a
General Contractor and the contractor is directly managed
( C ) 2. UNIT PRICE CONTRACT by the management group.
( B ) 7. GUARANTEED MAXIMUM PLUS E. With the price for goods or services set at the cost of
PARTICIPATION ON SAVINGS materials, labor, etc. plus a specified amount of profit.
(G) 3. CONTRACT PLANS B. This is a proposal bond in the amount of 21/2% of the
total bid price in the form of cash, certified check, manager’s
check, or bank guarantee confirmed by a local bank, payable
(I) 4. QUANTITIES to the owner as guarantee that the successful bidder shall
within 30 calendar days from receipt of NOA or Notice of
Award, enter into contract with the owner and furnish the
(A) 5. SPECIAL PROVISIONS performance bond.
(M ) 10. PREQUALIFICATION BIDS AND E. This is a written notice to the contractor if there is a
AWARDS COMMITTEE (PBAC) decrease in work due to deletion of work items in the project,
or where there is a reclassification of any existing item like
earth excavation to solid rock excavation. not known at the
(O ) 11. OBLIGATIONS time of bidding, or damage to structure due to force majeure.
(H) 1. PROJECT FEASSIBILITY STUDIES A. Pertaining to a whole or to most of its parts, not limited to
one class, field or product, dealing with all or the overall
universal aspects of the subject under consideration, a
(F ) 2. EXECUTIVE SUMMARY circumstance indispensable to some result, that on which
something else is contingent to put into the required state.
(B) 6. JOINT VENTURE D. Only, unshared or exclusive, a person who has legal rights
of possession of land , an object, or a process of manufacture
or distribution.
(D) 7. SOLE PRORIETORSHIP
E. This is a tabulation to show how money is distributed or
used in a continuous movement smoothly particularly the
(C ) 8. CORPORATION working capital.
A. Stop work if the contractor’s performance in not satisfactory or in variance with the contract documents.
B. Carry on the work and deduct costs normally due to the contractor for these corrections.
C. Stop the work if the Architect reports safety problems on the site.
D. Refuse, with good cause, to give the contactor proof the owner can meet the financial obligations of the
project.
__C___ 2. If, during bidding, your client asked you to provide a full-time staff member on the job site during construction,
you would be entitled to extra compensation . Under what provision would this be?
A. CONTRACT SUM
B. CONTIGENT ADDITIONAL SERVICES
C. PROJECT REPRESENTATION BEYOND BASIC SERVICES
D. OPTIONAL ADDITIONAL CHARGES
__B___ 3. The standard owner-architect agreement separates the architect from the contractor with what?
__A___ 4. What is used to encourage the contractor to finish the job or to satisfy mechanics lien claims by sub-contractors?
A. RETAINAGE
B. FIXED LIMIT
C. SURETY BOND
D. LIQUIDATED DAMAGES
__B___ 5. What fee method would you prefer if your Client was doing the first project and did not yet have a program?
A. FIXED SUM
B. MULTIPLE OF DIRECT PERSONNEL EXPENSE
C. PERCENTAGE PF CONSTRUCTION COST
D. UNIT COST BASED ON SQUARE METER
__D___ 6. A project is about 60 percent complete when the owner begins receiving field reports from the Architect stating
that the contractor is failing to properly supervise the job, resulting in incorrect work. After several weeks of this,
the owner becomes worried and asks the Architect what to do. What should be done if the work is being
performed under the terms and conditions of the BUILDING CONTRACT?
A. After receiving the Architect’s field reports, the owner should stop the work and arrange for a meeting
between the owner, the owner, Architect and the contractor to determine the cause of the problems and what the
contractor intends to do. If the contractor does not correct the work, the owner should carry out the work with
other contractors and deduct the cost by change order from the original contractor’s construction cost.
B. The Architect should recommend that the owner give the contractor written notice of non-conformance with
the contract documents and if, after seven days the contractor has not begun corrective measures, terminate the
contract.
C. The Architect and owner should discuss the problem to see if the owner would be willing to accept it in
exchange for the reduction in the contract sum. If not, the owner should give seven days written notice to
terminate the contract and find another contractor to finish the job.
D. The Architect should, with the owner’s knowledge, reject non-conforming work and notify the contractor that
it must be corrected promptly. The Architect should remind the owner that the owner can have the work
corrected after giving the contractor two (2) seven day written notices to correct the work.
__D___ 7. Which of the following describes agency?
A. The Architect acts on behalf of the owner, making decisions and expediting the work and taking
responsibilities the owner would normally have.
B. The Architect mediates between the owner and the contractor and vendors for the benefit of the owner.
C. The Architect is the principal of the relationship who balances the needs of the contractor and the owner.
D. The Architect works fir the owner in certain designated area with the authority to act on the owner’s behalf.
__B___ 8. You have a client who owns a large manufacturing plant and needs to expand to new facilities without
interruption in production. The owner has already arranged for a flexible line of credit to finance construction
but wants to minimize project cists. If the new facility will be very similar to the previous one, only sized for
grater production capacity, which type of construction would you recommend?
A. DESIGN-BUILD
B. FAST-TRACK
C. MULTIPLE PRIME CONTRACT
D, DESIGN-AWARD-BUILD
A. I, III, and V
B. I, II, III, and V
C. II, III, IV, and V
D. all of the above
A. The Architect is responsible for the defect in the work if he or she sees it but fails to report it to the
contractor.
B. The owner has the sole right to make changes in the work but must do it through the Architect.
C. The Architect does not have to verify and test reports given by the owner.
D. By the time construction documents are almost completed, the architect still does not have to give a
reasonably accurate construction price.
__B___ 11. Which of the following would be used to formally incorporate a substitution into the work prior to the award of
the contract?
A. CHANGE ORDER
B. ADDENDUM
C. ALTERNATE LISTING
D. CONSTRUCTION CHANGE DIRECTIVE
___D__ 12. Which of the following are part of the bidding documents?
I. SPECIFICATIONS II. INVITATION TO BID 111. LIST OF SUB CONTRACTORS
IV. OWNER-CONTRACTOR AGREEMENT V. PERFORMANCE BOND
A. Refuse to accept the bid, stating that the deadline has passed.
B. Ask if there are no objections from the other bidders to accept the bid since none has been opened yet.
C. Accept the bid with prejudice.
D. Accept the bid since none has been opened but make a mental note to look on it with disfavor when you are
evaluating it.
A. Bidding procedure mist be clearly and extensively outlined in the instructions to bidders because there are so
many variations of the procedures.
B. Bidding is nearly always necessary for public works or government projects.
C. Open bidding usually presents more problem than other type.
D. Competitive bidding takes more than negotiation but can result in a lower construction cost.
__C___ 4. If the lowest bid come in 20 percent over your client’s construction budget, what would be the best advise
you could give your client?
A That you revise the design at no cost to reduce the construction cost.
B. That the project be bid out again using another list of contractor.
C. That you and the client work to revise the scope of the project to reduce cost.
D. That all the deduct alternates be accepted to reduce the bid, and that the client authorize a slight increase in
construction cost to bring the two together.
__B___ 6. In what order should the following activities take place during project closeout?
I. Preparation of the final certificate of payment II. Punch list III Issuance of the certificate of substantial
completion IV. notification by the contractor that the project is ready for final inspection V. Receipt of
consent of surety.
A. The owner can make use of the work for the intended purpose and the requirements of the contract
documents have been fulfilled.
B. The contractor has completed correcting punch list items.
C. The final certificate for payment is issued by the Architect and all documentation has been delivered to the
owner.
D. all of the above.
__D___ 8. During the periodic visit to the site the Architect notices what appears to be an undersized variable air volume
box
being installed. What should the Architect do?
A. Notify the mechanical engineer to look at the situation during the next site visit by the engineer. Note the
observation on a field report.
B. Find the contractor and stop work on the installation until the size of the unit can be verified by the
mechanical engineer and compared against the contract documents.
C. Notify the owner in writing that the work is not proceeding according to the contract documents. Arrange a
meeting with the mechanical engineer to resolve the situation.
D. Notify the contractor that the equipment may be undersized and have the contactor check on it. Ask the
mechanical engineer to verify the size of the unit against the specifications and report to the Architect.
__C___ 9. An Architect would use this instrument if the building department required additional exit signs beyond those
shown on the approved plans when the project is 90 percent completed?
I. field reports to the owner II. field test III. scaffolding IV. reviewing claims of the sub contractor
V. reviewing shop drawings
__C___ 12. If a contractor makes a claim for additional money due to extra work cause by unforeseen circumstances,
the Architect must respond within:
A. 5 days
B. 7 days
C. 10 days
D. not until supporting data are submitted.
L. MISCELLANEOUS QUESTIONS.
__A___ 1. Which of the following would NOT be found in a project manual?
A. bid log
B. subsurface soil condition report
C. site work specifications
D. bid bond
__D___ 3. What is likely to occur if the drawings and specifications are NOT thoroughly coordinated?
I. a decrease of the actual cost from the estimated cost because the contractor bid on a less expensive material
shown on the drawings while the same was called out as a more expensive type in the specifications.
II. a lawsuit
III. the need for a change order during construction to account for modifications required to correct discrepancies
in the two documents.
IV. an increase of cost because the contractor bid the least expensive choice between two conflicting requirements
when the client wanted the more expensive option.
A. I, III, and IV
B. I and III
C. II, IV, and V
D. III, IV and V
Part 2 Products
2.01 Metal Support Material
General: To the extent not otherwise indicated, comply with ASTM C734 for metal system supporting gypsum
wallboard.
Ceiling suspension main runners: 11/2 inches steel channels, cold rolled
Hanger wire: ASTM A641, soft, Class 1 galvanized, pre-stretched: sized in accordance with ASTM C754.
Hanger anchorage devices: size for 3 x calculated loads, except size direct-pull concrete inserts for 5 x
calculated loads.
Steel: ASTM C645: 25 gauge, 21/2 inches deep, except as otherwise indicated.
ASTM C645:25 gauge, 3 inches deep, ASTM C645: 20 gauge, 6 inches deep.
Runners: Match studs: type recommended by stud manufacturer for floor and ceiling support of studs,
and for vertical abutment or drywall work and other work
Furring members: ASTM C65: 25 gauge, hat-shaped
Fasteners: Type and size recommended by furring manufacturer for the substrate and application indicated.
A. fasteners
B. hanger wire
C. hanger anchorage devices
D. ceiling suspension main runners
__B___ 5. In specifying asphalt roofing shingles, which of the following types of specification would you probably NOT
use?
A. descriptive
B. base bid or equal
C. reference standard
D. base bid with alternate approved manufacturers
1. Both narrow scope and broad scope sections can be used in the project manual.
II. For the contractor, drawings are more binding than the specification if there is a conflict.
III. Specifications show quality: drawings show quantity.
IV. Proprietary specifications are the same as prescriptive specifications.
V. They should not be open to interpretation if they are the base bid type.
A. I, III, IV and V
B. I, III, and V
C. II, III, and IV
D. all of the above
__D___ 7. Where would you find requirements for testing a plumbing system?