Professional Documents
Culture Documents
National Oil Corporation: Rev Date Description Checked Approved
National Oil Corporation: Rev Date Description Checked Approved
GES L.30
INDEX
1.1 Introduction 4
1.2 Other NOC specifications 4
1.3 Data Sheets 5
1.4 Scope of Supply 5
2.0 DEFINITIONS 5
2.1 Technical 5
2.2 Contractual 7
4.0 CONSTRUCTION 10
5.1 General 21
5.2 Salient Differences 21
6.0 INSPECTION 22
6.1 Procedures 22
6.2 Scope 22
6.3 Nameplates 23
7.0 TESTING 23
8.0 DOCUMENTATION 24
8.1 Introduction 24
8.2 Schedules and Reports 25
8.3 Data and Calculations 25
8.4 Drawings 26
8.5 Final Records Documents and Manuals 26
Figures 29
1.1 Introduction
1.1.1 This specification defines the minimum requirements for construction, inspection, commissioning and testing
of Electrical Trace Heating Equipment.
1.1.2 The specification applies to equipment for refineries, onshore oil and gas installations and processing facilities,
including items purchased either directly or as part of a package.
1.1.3 This specification is generally based on ANSI/NEMA standards. The Vendor/Contractor shall comply fully
with the provisions laid down in this specification. Any exception must be clearly stated and be authorised in
writing by the Owner as failure to do so shall indicate full compliance; any remedial work then necessary, shall
be at the Vendor/Contractor's expense.
1.1.4 In the event of any conflict between this specification and the Data Sheets, or with any of the applicable codes
and standards, the Vendor/Contractor shall inform the Owner in writing and receive clarification from the
Owner before proceeding with the work.
The Electrical Trace Heating Equipment shall typically provide electrical heating for the following types of
installation, or as indicated in the Data Sheets:
- piping,
- instrument housings,
- valves,
- drains.
1.1.5 This general specification will form part of the Purchase Order/Contract, together with any Data Sheets,
drawings and other attachments.
Exclusions
- Trace Heating systems utilising anything other than 'Approved' Heating Tapes,
- 'Hard wired' cables up to the 'cable/heating tape' interface junction boxes,
- Impedance Heating Systems,
- Induction Heating Systems,
- Skin Effect Heating Systems.
The following NOC General Engineering Specifications are an integral part of this specification and any
exceptions shall be approved by the Owner:
The technical data supplied by the Owner for the equipment is given on Data Sheets which are included at the
end of this specification.
The Vendor/Contractor shall complete the Data Sheets with the remaining information.
1.4.1 Equipment
The scope of supply includes (but is not limited to) the necessary items as follows:
1.4.2 Services
The Vendor/Contractor shall include Supply, Installation Supervision, and Commissioning in accordance with
the terms stated in the Purchase Order/Contract.
2.0 DEFINITIONS
2.1 Technical
BASEEFA
Crossover
Where the heating tape crosses, overlaps, or touches another section of the same tape (crossovers are only
allowed when self-limiting heating tapes are being used).
EN
Essential Loads
Those loads which are essential at all times to the safe operation and shutdown of the Plant.
FMRC
A system in which heat is generated in a pipeline or vessel wall by causing current to flow through the pipeline
or vessel wall by direct connection to an ac voltage source from a dual-winding transformer.
A system in which heat is generated in a pipeline or vessel wall by inducing current and hysteresis effect in the
pipeline or vessel wall from an external isolated ac field source.
A complete system consisting of components such as pipelines, vessels, heating elements, heat transfer
medium, thermal insulation, moisture barrier, non-heating leads, temperature controllers, safety signs, junction
boxes, raceways and fittings.
MCB
Miniature Circuit Breaker. A protection device fitted on each of the outputs. An indication of trip after an
overload shall be incorporated for alarm purposes.
MTBF
Mean Time Between Failure. Normally quoted in years. From statistical calculations, the value of the MTBF
predicts the dimensions of an exponential curve of failures against time.
MTTR
Mean Time To Repair. This is the estimated time in hours for a fault to be cleared after an alarm has been
accepted.
NDT
The rms "phase to phase" or "phase to neutral" voltage by which the system is designated and at (or near)
which level, the system normally operates.
Non-Essential Loads
Those loads whose loss may be tolerated safely during infrequent power outages maintenance and repair.
Tubular heaters, strip heaters, heating cable, heating tape, heating blankets, and immersion heaters are
examples of resistance heaters.
A measure of the ability of a self-regulating heating tape to respond to changes in temperature, ie to exhibit the
self-regulating characteristic. The SR index is given by the gradient of the tape power temperature curve, in
W/m/°C.
Site Conditions
The external factors, e.g. altitude, air temperature, wind velocity, vibrations, earthquake, relative humidity,
voltage and frequency variations etc., which may influence the operation of equipment.
A system in which heat is generated on the inner surface of a ferromagnetic envelope attached to a pipeline
and/or vessel.
Stabilised Design
A design of a heating system such that it will stabilise under all conditions (including empty pipe, no-flow, and
maximum flow temperature) at a temperature below the various temperature limits for the system, eg. pipe
stressing temperature limits, hazardous area temperature classification, product temperature limits, withstand
temperature of the heating tape.
Utilisation Voltage
The rms "phase to phase" or "phase to neutral" voltage at the line terminals of utilisation equipment.
2.2 Contractual
Owner
The oil or gas company, an associate or subsidiary, who is the end user of the equipment and facilities.
Vendor
Contractor
Sub-Contractor
A company awarded a contract by a contractor to do part of the work awarded to the Contractor.
Inspection Authority
The organisation representing the Owner or Vendor/Contractor that verifies that the equipment and facilities
have been designed, constructed, inspected and tested in accordance with the requirements of this specification
and the Purchase Order/Contract.
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 8 of 33
Rev 0 1999
Inspector
A qualified individual representing the Owner or Vendor/Contractor or the assigned Inspection Authority, who
verifies that the equipment and facilities have been designed, constructed, inspected and tested in accordance
with the requirements of this specification and the Purchase Order/Contract.
These conditions are fully detailed in GES A.06, and cover the principal conditions affecting the electrical
equipment including maximum and minimum ambient temperature, dust, humidity and altitude etc.
Equipment may be housed in an enclosed, air-conditioned equipment room; full details are given in GES B.12
but the following shall be noted:
Temporary excursions from these limits e.g. during short term power failure, shall be ignored for the purposes
of equipment rating.
3.2.1 General
In general, the requirements specified herein are based on the ANSI/NEMA and other American Codes and
Standards, the most important of which are listed below: Unless otherwise stated, equipment and materials
shall comply with these Codes and Standards.
Unless specified otherwise in the Purchase Order/Contract, the current editions of the Codes and Standards at
the time of order shall be used.
The Vendor/Contractor shall operate and supply certification for a Quality System complying with the
requirements of the ASQ Q9000 Series or BS EN ISO 9000, Part 1 (Design) Part 2 (Production) and Part 3
(Test and Inspection).
ASTM C 450 Practice for Pre-fabrication and Field Fabrication of Thermal Insulating
Fitting Covers for NPS Piping, Vessel Lagging, and Dished Head
Segments
ASTM C 585 Recommended Practice for Inner and Outer Diameters of Rigid Thermal
Insulation for Nominal Sizes of Pipe and Tubing (NPS System)
IEEE 515 IEEE Recommended Practice for the Testing, Design, Installation and
Maintenance of Electrical Resistance Heat Tracing for Industrial
Applications
FMRC Std. Class No. 3611 Electrical Equipment for Use in Class I, Division 2; Class II, Division 2 and Class
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 9 of 33
Rev 0 1999
III, Division 1 and 2 Hazardous Locations
NEMA Standard No. 250 Enclosures for Electrical Equipment (1000 volts maximum)
NFPA 325M Fire Hazard Properties of Flammable Liquids, Gases, and Volatile Solids
When appropriate, equivalent International Standards which may be used as alternatives are listed below and
may be used with the prior approval of the Owner. Equipment and materials complying with IEC
Recommendations shall be at least equal to the requirements of this specification. The Vendor/Contractor shall
advise full details of any deviations to these requirements in his offer if IEC based standards are utilised.
BS 6334 Methods of test for the determination of the flammability of solid electrical insulating
materials when exposed to an igniting source.
BS 6351 Part 3 Code of Practice for the Installation, Testing and Maintenance of Electric Surface
Heating Systems.
IEC 800 Heating Cables with a Rated Voltage of 300/500 V for Comfort Heating
3.3.1 Rating
The Supply voltage and frequency shall be as stated on the Data Sheets or attachments to the material
requisition.
3.3.2 Variations
The Trace Heating System shall operate successfully from zero load to the rated load with a supply voltage
variation of 10% above or below rated voltage and 5% above or below rated frequency.
The typical Trace Heating system configuration is shown in Section 10. The configuration may be different for
various manufacturers, but the basic units forming the system shall conform to details in this section.
3.6.1 Input
(a) Voltage Single phase (see Data Sheet value) with tolerance of ± 10%.
(b) Frequency Nominal System Value, (see Data Sheet value) with tolerance of
±5%.
(c) Inrush current on switching on Limited not to exceed the current at maximum load.
4.0 CONSTRUCTION
(a) The ingress protection of the cabinets shall be NEMA Type "4X" in accordance with NEMA 250.
(b) Cabinets shall be made from heavy gauge 12 gauge (2 mm) minimum, sheet carbon steel or
aluminium, and shall be free-standing, and (unless stated otherwise on the Data Sheets) be designed
for front access only. Access panels (doors) shall be double or full-length hinged and handles, screws
and hinges shall be corrosion resistant.
(c) Cabinets shall be painted in accordance with GES X.06 and manufacturer's standard colour
procedures, unless stated differently in the Data Sheets.
(d) Provision shall be made for Top or Bottom entry cabling; where cables enter from below, the gland
plate shall be accessible and at least 15 inches (400 mm) above finished floor level.
(e) Grounding
All metalwork, cable gland plates and component or sub-assembly chassis shall be bonded to a
ground bar.
The ground bar shall be marked green/yellow and shall be of robust construction. It shall extend the
length of the suite of cubicles. Joints shall be provided between each transport section. At each end
of the grounding bar, a brass terminal shall be provided fitted with a compression lug suitable for a
138 k.c.mil (70 mm2) external grounding conductor.
(f) The system shall have a termination panel for the connection of all external cables to the system. All
circuits which are continued outside the equipment enclosure shall be clearly identified with
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 11 of 33
Rev 0 1999
permanent markers located so such circuits can be quickly identified.
(g) There shall be no common terminal blocks, i.e. each equipment section shall have its own blocks
arranged, so that during maintenance, all terminals can be de-energised.
(h) MCB double pole protection devices with ground-fault circuit-interrupter shall be provided for each
output circuit; an alarm contact shall be provided on each MCB, series connected so that fault trip of
any MCB brings up a local and remote alarm.
(a) Wiring brought out to terminal blocks shall be identified with thermoplastic slip-on wire markers
with permanent printed characters. Snap-on or adhesive type markers are prohibited. Wire markers
shall directly correspond to schematic numbering.
(b) Insulated compression (crimped) terminals shall be provided for all wiring terminating on terminal
blocks. Soldered terminals are not acceptable for connection to terminal blocks.
(c) Terminal blocks shall be provided for all externally connected wiring. Terminal blocks shall be one
piece, phenolic, barrier type with pan head screws. A maximum of one wire per terminal is
permitted. Compression type terminal blocks for connection of wires larger than 19.75 k.c.mil (10 sq
mm) are acceptable.
The Vendor/Contractor shall provide a complete set of installation materials for each site, which includes any
inter-cubicle connections, anchor bolts, plinths, lifting eyes, pipe mounting brackets for junction boxes and
thermostats, heating, tape terminating kits etc.
4.4 Alarms
Alarm contacts shall be normally closed, and facilities shall be made for remote relaying of alarms to a central
control room.
Alarms indication states (visual and audible) shall be as stated on Data Sheets and as a minimum include the
following:
Warning plates shall be provided on each compartment door in which an external voltage source is terminated,
giving the warning:
(a) All equipment supplied shall have labels affixed stating the manufacturers name, item code and serial
number, for accurate identification.
(b) All items contained in the equipment shall be marked with the manufacturers code and revision
number.
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 12 of 33
Rev 0 1999
(c) All components, indicator, and switches etc shall be clearly identified and labelled in an unambiguous
manner.
(d) All identification labels shall be WBW traffolyte, screwed labels, self adhesive labels are not
acceptable.
(e) Labels for mineral insulated cables shall show the cable number, voltage, current, type, length, FM or
equal approval number, cold lead length and cold lead wire size.
4.8 Design
The design of the trace heating system is normally carried out in parallel with the main project design. This
will require selection of Vendor/Contractors and tape types at an early stage of design, using estimated
quantities. Tape design data is readily available from Vendor/Contractors, but if necessary the selected
Vendor/Contractor can be asked to assist with design at the appropriate stages.
Note: Efficient liaison between process, piping and electrical designers is needed to ensure that changes in
process and piping are reflected in the trace heating designs. Carrying out trace heating design as part of the
project electrical design ensures that the power distribution for trace heating can be optimised as part of the
project, rather than be added as an afterthought.
Principal heating tape characteristics are listed in the following sections 4.8.2.1 to 4.8.2.4:
(a) The tape consists of two parallel buswires with parallel resistance provided by a semi-conductive
carbon-loaded polymer core. The core material resistance increases as the temperature increases.
For Division 1 and Division 2 areas, armoured cable must be used under both US and IEC codes.
(b) The current drawn by the tape circuit reduces as the temperature increases, an inherently safe feature
for hazardous areas. Normally a controller is not required. A tape which has been submitted by the
Factory Mutual Research Corporation (FMRC) or by BASEEFA to the appropriate tests listed in BS
6351 will have an assigned hazardous area temperature classification derived from the temperature
test; normally the assigned temperature classification is valid and relevant only at the supply voltage
for which the tape is rated.
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 13 of 33
Rev 0 1999
(c) The self-limiting feature of self-limiting tapes prevents hot spots and allows crossovers in
construction.
(d) Consistent tape quality may be difficult to achieve during manufacture and confirmation should be
sought that quality control will ensure that a tape is produced with consistent characteristics along its
complete length, and that performance will not significantly deteriorate over the anticipated life time.
Once installed it is not easy to monitor the performance of the tape.
(e) The tape is flexible, and can be cut to length on site. Terminations are straightforward and can be
carried out on site. The tape is therefore easy to install, and hence to design, since the tape can be
purchased prior to finalisation of design.
(f) The specified maximum withstand temperature of self-limiting tape must be carefully adhered to, as
exceeding these temperatures may cause an irreversible open circuit mode failure, or accelerated
ageing along the part of the line subjected to the high temperature.
(g) The maintained temperature of a self-limiting tape without a controller will vary with ambient
temperature change in thermal insulation characteristics, and tape Self-Regulating Index. Care must
be taken to ensure that the highest maintained temperature does not exceed one of the various
temperature limits for the system (e.g. pipe stressing temperature limits, hazardous area temperature
classification, product temperature limits).
(h) Most self-limiting tapes exhibit current inrush at low temperature operation. This may cause circuit
protective devices to trip unless this problem is adequately addressed. The Vendor/Contractor's
recommendation for MCB rating must therefore be rigidly followed to prevent nuisance tripping. See
Section 4.9.2 (g) in this specification.
(i) Average energy consumption of an uncontrolled self-limiting circuit is greater than that of a
controlled circuit.
4.8.2.2 Medium Temperature Series Resistance Tape (for maintaining temps. up to approx. 320°F (160°C)
(a) The heat is generated by a series fine wire resistive element - typically nichrome. For hazardous area
applications one controller is required for a stabilised design, and two for a non-stabilised design.
(b) Each tape must be specifically designed for a fixed length having a predetermined resistance. This
together with the problems of site terminations results in the need for a complete factory-made
heating tape unit.
(c) Piping/process changes after the manufacture of the tape usually require a complete remake of the
tape.
(e) Open or short circuit failure of the tape will cause the complete tape circuit to be lost, although this
feature has the advantage that all such faults are self-monitoring.
(e) Crossovers may cause burnouts due to hot spots and hence complete loss of tape output. However,
crossovers can be avoided by good design and construction supervision.
(f) Series tapes are generally cheaper than self-limiting tapes but controllers add to system costs.
4.8.2.3 High Temperature Series Resistance Tape (for Maintaining Temps. up to approx. 842°F (450°C)
These heating tapes are usually mineral insulated with seamless metallic sheaths, and have features generally
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 14 of 33
Rev 0 1999
similar to medium temperature series tapes, except for the following:
(a) Difficult to handle and install. If the outer sheath is fractured the hygroscopic nature of the tape
insulation requires the complete tape to be replaced.
(b) Even with factory-made joints, it is sometimes difficult to exclude moisture from the cable, with
subsequent low insulation values.
(c) Once installed and tested, the cable will give good service provided it is left undisturbed. This is very
often difficult to achieve especially where valves or sections of lines are removed.
(d) Minimum cable length is usually 30 feet (10 metres), which may cause problems when designing for
short lines. Where a very short length is required, a voltage step-down transformer will be required.
4.8.2.4 Parallel Resistance Tape (for Maintaining Temperatures up to approx 392°F (200°C)
(a) The tape consists of two insulated parallel buswires with fine resistance wire connected to the
buswires at intervals. As with series tape, one controller is required for a stabilised design, two for
non-stabilised.
(b) For a given supply voltage, the tape has a constant power output/metre, regardless of length (although
some reduction in output may occur due to buswire voltage drop). This allows the tape to be cut to
length on site - an aid to design and construction planning (tape can be purchased prior to finalisation
of design).
(d) A zone open circuit due to a resistance wire break/burnout will result in a loss of zone heating
generally 30 to 39" (0.75 to 1 metre), but still allowing the heat output for the remaining part of the
tape to be maintained.
(e) Crossovers will cause hot spots. Damage is usually limited to the loss of a heating zone but may
exceed the hazardous area temperature classification. Crossovers must be eliminated in design and
construction.
(f) Parallel resistance tapes are generally made with non-hygroscopic materials.
(a) Heat loss calculations, as described for example, in IEEE 515 (BS 6351 - Part 2: Sections 6.2 & 6.5)
ensure that adequate heat is available under the worst conditions. The calculations must include
allowances for minimum supply voltage, heating tape voltage drop, and tape resistance tolerances.
An additional allowance of 10% is then added as a contingency to allow for variations in thermal
insulation.
(b) The tape design should take into account the full range of ambient temperature, and tape output
should be based on the minimum ambient expected.
(c) Wherever possible, lines should be straight-traced to ease initial installations and any subsequent
maintenance removal. Straight-traced heating tape should also be installed on the lower half of the
pipe. Spiralling of tape should be avoided by using two or more parallel tapes where necessary to
achieve required heating.
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 15 of 33
Rev 0 1999
(d) Where valves, piping, or other piping components are likely to be regularly removed, the heating tape
should be arranged as follows:
- flexible tape: the tape should be arranged to be unwound from the component without
damage to the heating tape or junction box fitted (See Section 10.0,
Figure 10.5);
- rigid tape: Junction boxes should be provided at either side of the component (See
Section 10.0, Figure 10.5).
(e) All tapes installed in hazardous areas should be FMCR approved, or if relevant, Service Category 22
(BS 6351, Part 2, Table 1) and be FMRC (BASEEFA) or equivalent approved for the hazardous area
temperature classification of the area in which installed. All hazardous area tapes should incorporate
a metallic covering to ensure an earth path for earth fault protection. In the case of flexible polymeric
heating tapes a tinned copper braid should be provided, the braid resistance being equal or lower than
the resistance of one of the conductors. In addition, a flexible non-metallic outer sheath should be
included to provide corrosion and mechanical resistance.
In the case of mineral-insulated high-temperature series resistance tape, the outer sheath of the cable
gives inherent mechanical protection and provides an earth path for earth fault protection. An
additional outer sheath is not required. The correct cable sheath material should be selected to avoid
problems caused by high temperature and corrosion.
(f) Temperature Limitation: Design checks should be carried out to ensure that under all process
conditions and with tape power on or off, certain critical temperature limits are not exceeded. For
example:
(g) Where pipe insulation has originally been selected to reduce noise levels, or for personnel protection,
the design should be reviewed to ensure co-ordination with heating tape design, and to avoid
excessive heat loss. In some cases, increasing the insulation thickness may eliminate the need for
heating tape.
(h) Pipe insulation should be designed to GES N.01. The insulation should be easily removable and
protected from mechanical damage and moisture ingress by metallic cladding. In particular, cladding
joints should be weather-proofed to ensure dry insulation and efficiency of the heating tape.
(i) Where heating tapes penetrate the lagging, 'insulation entry kits' must be provided to prevent moisture
ingress and damage to the heating tape.
(j) An allowance should be made for additional tape associated with the heat loss at valves, pipe support
trunnions, and pipe flanges.
(k) Short stub lengths of pipe up to 10 feet (3 metres) in length may be double traced to avoid
proliferation of junction boxes. The maximum maintained temperature must be checked against the
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 16 of 33
Rev 0 1999
maximum allowable temperature limit at that point.
(a) Heating tapes shall be selected for operation at the nominal voltage applicable at the particular
installation.
(b) The voltage "seen" by the tape will be the nominal system voltage (+ 5%) with a maximum volt drop
between distribution switchboard and tape of 5%. For self-limiting tapes the hazardous area
temperature classification assigned by the FMRC (BASEEFA BS 6351 tests) must be associated
with the positive tolerance voltage. Where a stabilised design is required, the maximum temperatures
must be calculated at the positive tolerance voltage.
(c) The following three methods of zone temperature control are possible comprising:
Generally suitable for frost protection, anti-condensation, and for process conditions where wide
swings in temperature can be tolerated. Where the circuits fed from one sub-distribution board
are all related to frost protection, a thermostat should be arranged to switch the board at the
appropriate ambient temperature. This extends tape life and conserves energy.
For a design where the tape stabilises below the imposed temperature limits. Close temperature
control can be achieved with this method.
For a design where stabilisation cannot be achieved below the imposed maximum temperature limits
at maximum ambients. The second controller provides back-up circuit isolation following a failure of
the primary controller (see Figure 10.1 in section 10.0 of this specification).
(d) Temperature controllers generally available, and suitable for both safe and hazardous area
applications, are either capillary type or solid state with RTD sensors. Capillary-type controllers need
to be mounted close to the sensor. Solid state controllers with RTDs have no such limitations, and
controllers can be mounted in the location most suited to operation and maintenance. In addition,
solid-state controllers and sensors are easier to maintain and replace when damaged.
For most heating tape applications a basic 'on-off' controller will be sufficient to achieve the desired
temperature level. For close temperature control, proportional and derivative control features may be
required. Controller temperature settings should be fully adjustable on site.
(e) Where two controllers are required, an alternative of one controlling controller, together with an
over-temperature fail-safe lockout controller, shall be used. An alarm light with lamp test facility
should be provided, indicating the operation of the lockout controller.
Where lockout of the second controller is operationally unacceptable (eg, cyclic upset temperatures)
the circuit shown in Figure 10.1 in section 10.0 of this specification can be used.
(f) Some critical circuits may require remote temperature monitoring. This can be achieved either by
deriving an analogue output from the heating tape temperature controller or by separate
instrumentation.
(g) Heating tape circuits should be protected with moulded case circuit breakers (mccbs). The mccbs
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 17 of 33
Rev 0 1999
will give overload and short-circuit protection, and should be fitted with a shunt-trip operated by a
ground fault device with a sensitivity of 30mA, and an operating time of 40 milliseconds.
Where self-limiting tapes are employed, current inrush should be considered. The majority of self-
limiting tapes exhibit current inrush at low temperatures. The circuit mccbs should be sized to allow
for current inrush at the expected lowest ambient. Very low temperatures (eg blowdown conditions)
may cause the mccbs to trip and manual reconnection will be necessary. Where this cannot be
accepted operationally, self-limiting tapes exhibiting very low inrush characteristics shall be used.
Alternatively, series or parallel resistance tape should be employed. See Section 4.2(c) in this
specification.
(h) Circuit integrity monitoring: the circuit shown in Figure 10.2 in section 10.0 of this specification,
monitors the integrity of the power system. A faulty circuit can be isolated by operating the
appropriate override switch, leaving remote alarm facilities for the remaining energised circuits still
available.
(i) Critical circuits may require a power supply derived from the emergency generator - these circuits
should be kept to a minimum.
(j) Sizing of incomers and busbars: in the case of switchboards supplying self-limiting heating tapes,
current ratings should be related to heating tape loads under either lowest ambient temperature or
lowest process temperature conditions, whichever is greater.
(k) Junction boxes connected directly to the tape or tape cold end should, where possible, be mounted
directly on the pipe, but clear of the insulation cladding, to minimise the exposed length of the tape or
cold end.
(l) The use of low-weight Ex 'e' (increased safety) boxes will minimise pipe stress caused by the box
support (to be co-ordinated with piping design). BASEEFA certificates for junction boxes should be
checked to ensure that the connected cable core sizes selected are allowable within the certificate.
However, the Ex "e" concept is not recognised in the USA. NFPA allows the use of non-certified
junction boxes in Division 2 areas.
(m) Thermocouples must be located at the point on the line which will experience the highest
temperature, taking all operating conditions into account.
(n) Where possible, the temperature control device shall be located on the downstream side of the pipe.
High temperature, seamless sheath, series-resistance mineral insulated tapes shall be used. The cables are
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 18 of 33
Rev 0 1999
available with alternate sheath materials which have the following sheath temperature limits:
- up to 392°F (200°C) - Copper
- up to 752°F (400°C) - Cupro nickel
- up to 1112°F (600°C) - Stainless steel or Inconel
The selection of sheath materials is also influenced by the need to minimise corrosion.
Self-limiting heating tapes are preferred. Where there is a requirement for close temperature control, and the
use of parallel resistance tapes and thermostats are the economic options, this alternative is also acceptable.
Either parallel resistance or series resistance mineral insulated heating tapes should be used, within their
respective operating and withstand temperature limits.
4.11 Manufacture
(a) The heating tape Vendor/Contractor shall demonstrate that the heating tapes being supplied will have
an estimated twenty-year life under the specified operating conditions within the temperature rating
band assigned to the tape. The Vendor/Contractor shall generally have carried out the following
ageing tests during product development of the tapes:
(b) All electric heating tapes must be manufactured, type and routine-tested in accordance with FMRC,
IEEE or BS 6351 as relevant.
Each Vendor/Contractor must ensure that the manufactured tape will produce the specified heat
output along the complete length of the tape. Batch testing will be satisfactory for parallel and series
heating tapes and for self-limiting heating tapes where accurate temperature maintenance is not
required. Where self-limiting tapes are being used for accurate temperature maintenance, all tape
supplied should be tested by the Vendor/Contractor to ensure that the specified heat output is
maintained along the complete length of the tape.
(c) All electric heating tapes for use in hazardous areas must be certified either by FMRC or, by
BASEEFA, to BS 6351.
(d) The Vendor/Contractor may be required to carry out additional tests for special applications not
covered by previous type tests - for example, stabilised designs within low critical temperature limits.
(e) High temperature mineral insulated heating tape requires particular care in manufacture, handling and
packing, and all techniques recommended by the Manufacturer of the mineral insulated cable shall be
complied with.
(f) All through joints and gland terminations shall be made under factory conditions. Particular care is
required to ensure that moisture entry points are eliminated by carrying out both electrical and non-
destructive testing (NDT) tests at each stage of manufacture.
4.12.1 General
(a) Listed below are general installation and commissioning requirements. Detailed Requirements,
including tape supplier recommendations, shall be covered by a separate document drawn up by the
Vendor/Contractor.
(b) All installation and commissioning requirements of the relevant standard shall be complied with.
(a) Non-corrodible markers shall be fixed at 20 ft (6m) max. intervals over the pipe insulation. The
markers shall read 'CAUTION: ELECTRIC SURFACE HEATING EQUIPMENT INSTALLED
BENEATH THERMAL INSULATION - DO NOT DAMAGE'.
(c) All heating tapes should be stored in accordance with the Vendor/Contractor's requirements, with all
exposed ends sealed.
(d) The surface to which the electric heating tapes will be fitted shall be free from rust, burrs, grease, oil
etc., and be completely dry. All pipe painting must be completed prior to heating tape installation.
(e) To minimise damage the thermal insulation and insulation cladding shall be applied as soon as
possible after installation and testing of the heating tape.
(f) Inspection should be carried out by fully trained supervisors at all stages of installation and should
include electrical insulation resistance tests before and after the application of thermal insulation.
(g) Series and parallel resistance heating tape circuits must not incorporate crossovers.
(h) Care shall be taken, during installation of the tape, to ensure intimate contact with the surface to be
heated. This particularly applies to series and parallel tapes. If the maximum heater-to-heater surface
separation, as allowed by the tape FMRC (or BASEEFA) certificate, cannot be ensured during
installation, heat transfer aids must be employed. The trace heating applications for Caustic lines
shall be approved by the Owner.
(i) Heating tape shall not be spliced on site. All connections shall be made within junction boxes.
(j) All pre-commissioning and commissioning tests shall be recorded on formalised commissioning
record sheets.
(k) Particular care is required in the on-site handling and installation of high temperature mineral
insulated heating tape to avoid damage to the cable and the ingress of moisture. All care and
handling techniques recommended by the Vendor/Contractor of the mineral insulated cable and the
heating tape shall be complied with.
4.12.3 Maintenance
All heating tape installations shall be regularly checked to ensure the integrity of all circuits.
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 20 of 33
Rev 0 1999
Maintenance checks shall include the following:
After pipeline maintenance, the heating tape should be checked to confirm that it is undamaged and
correctly reinstalled.
5.1 General
This specification is primarily written for equipment manufactured in accordance with the American (NEMA)
Standards.
If it is necessary or advantageous to purchase equipment in accordance with International (IEC) Standards, the
specification can still be utilised but the salient differences occurring should be noted as detailed below.
This section does not attempt to list every difference between American (NEMA) standards and IEC standards,
but covers only those salient differences that could affect the final installation if not properly addressed during
the design phase.
The NEMA Standards in many cases utilise imperial units (feet, pounds, degrees fahrenheit, etc), whilst the
IEC Standards utilise SI units (metres, grammes, degrees celsius etc).
Note: For electrical equipment, the (American) Institute of Electrical and Electronic Engineers (IEEE) have
recommended that the use of the imperial (British-American) units in use be reduced as rapidly as possible in
favour of the SI units, with certain implementations such as the use of horsepower being phased out first.
IEC cable CSA's are always in metric dimensions (mm2). American conductor sizes are often American Wire
Gauge (AWG) for the smaller sizes and circular mils (c.mil) for larger sizes. However because circular mil is
a term universally used in the USA and based on the mil (one thousandth of an inch), this specification refers
solely to c.mil and not to AWG.
5.2.3 Grounding
Concerned with the nature and location of an intentional electrical interconnection between the Electrical
System Conductors and Ground. In British Practice, the terms "Grounding" and "Ground" are replaced by
"Earthing" and "Earth". In British Practice, a ground-fault circuit-interrupter is called an earth-leakage circuit
breaker (ELCB),
Full details of the comparison of IEC and American practices are detailed in GES L.35 and are not reiterated
here.
If is intended to purchase a transformer to IEC Standards, reference should be made to the contract hazardous
area drawing produced from the principles stated in GES L.35 to establish the enclosure type needed.
Note: The National Electrical Code NFPA 70, Article 500 and API.RP500 cover the American approach to
hazardous (Classified) areas in some detail.
6.0 INSPECTION
6.1 Procedures
(a) The Vendor/Contractor shall allow the Inspector free access to all areas of manufacture, fabrication,
assembly and testing.
(b) The Vendor/Contractor always has the responsibility to provide adequate quality control and
inspection of equipment and materials as defined in ISO 9000. Any inspection by Owner or his
Inspector shall not relieve the Vendor/Contractor of these responsibilities or those under his
guarantees.
(c) If inspection is waived, the required data shall be forwarded to the Owner. If submission of data is
not requested, all data shall be retained by the Vendor/Contractor for issue to the Owner or Owner on
demand, for at least five years.
(d) The Vendor/Contractor shall provide a safe working environment for the Inspector and alert the
Inspector of potential hazards.
6.2 Scope
6.2.1 The inspection requirements are covered by the document "General Conditions of Purchase" which forms part
of the Purchase Order/Contract. Additional requirements are given below.
6.2.2 Inspector shall inspect the equipment to ensure that it complies with the requirements of the latest revision of
this specification and Data Sheets, drawings or other attachments to the material requisition, and the latest
revision of the Vendor/Contractor's documentation and data relating to the specific Purchase Order/Contract.
(c) dimensions,
(e) terminals,
(h) accessories,
Inspector shall ensure that any shortcomings in the Vendor/Contractor's documentation or data are rectified
before any equipment or material is accepted for shipment.
6.3 Nameplates
Each item shall be provided with a rating plate of stainless steel fitted in a visible position, showing the
appropriate items listed below. The entries on the plate shall be indelibly marked (by etching, engraving or
stamping).
7.0 TESTING
Tests shall be performed in accordance with the applicable codes, the requirements of the Data Sheets and
include, as a minimum, the following Routine Tests.
7.2.1 The Vendor/Contractor's basic routine witnessed factory tests are required and shall include, but not be limited
to, the following tests to ensure that the specification for the equipment has been met at the rated
environmental conditions:
Subsequent to these tests, the acceptance or rejection of the equipment will be at the discretion of the
Inspector.
7.3.1 In all cases the Vendor/Contractor shall submit test procedures in writing to the Owner for approval prior to
the start of the testing programme.
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 23 of 33
Rev 0 1999
7.4 Site Acceptance Test Requirements
The Vendor/Contractor shall submit a schedule of Site Acceptance Tests that are to be undertaken to ensure
that the equipment is satisfactory.
The test schedules shall be approved by the Owner. There shall be a separate set of acceptance tests for each
item supplied.
The initial acceptance tests shall be performed by the Vendor/Contractor when all relevant equipment has been
installed.
Fourteen days after the systems have been put into service, or fourteen days after the initial acceptance tests,
whichever is the earliest, the Final Acceptance Tests shall be effected by the Vendor/Contractor, and be
witnesses by the Inspector.
Final acceptance of the system will be given following satisfactory Final Acceptance Tests.
All copies of test certificates shall be furnished with final drawings as called for in documentation section. The
Final Acceptance Tests shall be witnessed by the Inspector who shall retain one copy of the certified tests.
7.6.1 Supply
All necessary test leads, power cords and ancillaries shall be provided.
Note:
All instruments and apparatus used in the performance of the tests shall have been calibrated to an agreed
standard at a laboratory of National standing within the period of 15 months of the test date. The cost of
carrying out such calibrations shall be borne by the Vendor/Contractor in all cases.
8.0 DOCUMENTATION
8.1 Introduction
This section covers the documentation required for the design, fabrication, inspection and testing for all the
equipment, components and services to be provided against this specification.
8.1.2 The detailed list of documents that are required will be included with the Purchase Order/Contract, however,
as a minimum, the following listed documents will provided by the Vendor/Contractor as and when required
by the Vendor Documentation Requirements (VDR) list:
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 24 of 33
Rev 0 1999
. General Arrangement,
. Foundation Layout,
. Single Line Diagram,
. Schematic and block wiring diagrams,
. Isometric and Installation Details,
. Calculations.
8.1.3 The documents as listed may be considered as a minimum requirement; all details to confirm compliance with
the relevant specifications and to allow a full and continued appraisal to be made of the Vendor/Contractor's
proposals and interpretations of the ordered equipment, should be submitted in accordance with the schedule
specified in the Purchase Order/Contract.
8.1.4 Any production or procurement undertaken by the Vendor/Contractor which is prior to the relevant
documentation being submitted and reviewed by the Owner is at the Vendor/Contractor's risk.
8.1.5 On all documentation the Purchase Order/Contract number, equipment title, tag number and project name shall
be quoted.
8.1.6 All documentation shall be checked and signed by the checker before submission.
8.2.1 The Vendor/Contractor shall submit with his tender a preliminary quality control plan and proposals for
Factory acceptance and site acceptance tests.
8.2.2 The Vendor/Contractor shall include with his tender documentation a statement of proposed Sub-
Vendors/Sub-Contractors, a document submission schedule for all documents based on a review cycle of three
weeks and outline programme for procurement and production activities.
8.2.3 The Vendor/Contractor shall incorporate any revisions agreed with the Owner during the enquiry review stage.
8.2.4 Monthly reports shall be submitted by the Vendor/Contractor detailing design, procurement, production and
documentation activities, the format of which shall be agreed with the Owner.
8.3.1 The Vendor/Contractor shall supply with his tender completed Data Sheets containing all the relevant
information necessary for appraisal of the design by the Owner.
8.3.2 Project specific instructions will be issued to the Vendor/Contractor with the Purchase Order/Contract, which
describes the data and calculations to be submitted, and the methods of submission.
8.3.3 The Vendor/Contractor shall be responsible for obtaining approvals from the Inspection Authority.
8.3.4 All calculations shall be carried out in clear and logical manner. Where conditions involve the use of formulae
or methods not specified in the Design Code, the source of these formulae or methods shall be clearly
referenced.
8.3.5 Computer calculations will only be acceptable if all input is shown, together with calculated values of
intermediate terms and factors and options chosen, as well as final calculated dimensions, stresses or other
values and the computer program has been validated to the satisfaction of the Owner.
8.3.6 Calculations and drawings that are interdependent, i.e. foundation loading and equipment footprint, shall be
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 25 of 33
Rev 0 1999
presented for appraisal together.
8.4 Drawings
8.4.1 The drawings listed with the Purchase Order/Contract shall be sent by the Vendor/Contractor to the Owner
and/or the Inspection Authority for review and approval.
8.4.2 The components and process to produce the ordered equipment shall be shown in sufficient detail to be fully
appraised eg, outline drawings, components list and schematic.
8.4.3 General arrangement drawings shall be to scale and show the relative location and main dimensions of all
components including elevations.
8.4.4 Detail drawings which may be included on the general arrangement shall include thicknesses and dimensions
of all components.
8.4.5 As-built drawings may be the general arrangement drawings marked-up with the actual as-built dimensions.
8.5.1 Two copies of the Data Dossier shall be supplied, and shall be a record of the manufacturing process. Where
stated in the Purchase Order/Contract; besides the electrical documents itemised in Section 8.1.2, it shall
contain the following:
8.5.2 Six sets of the Installation, Operations and Maintenance Manual (IOM) shall be specifically compiled for the
equipment supplied. A compendium of manufacturer's data for a range of like products is not acceptable. The
IOM shall contain the following:
The IOMs shall be presented in A4 format, and be securely bound in heavy duty 4 ring binders.
8.5.3 The Vendor/Contractor shall produce as built documents revised to indicate field changes.
8.5.4 The Vendor/Contractor shall supply one set of mylar original drawings.
All documentation (drawings, calculations and Data Sheets etc.) shall be produced by the Vendor/Contractor
in electronic format.
The format shall be compatible with that used by the Owner and shall be agreed at the commencement of the
contract.
In addition to the 'hard copies' required under the contract, copies of the electronic records shall be issued to
the Owner for all approved documentation, this forming part of the Vendor/Contractor's contractual
obligations.
All bare surfaces which are exposed during transit or storage shall be given a coat of temporary rust inhibiting
material.
Surface preparation, painting and painting materials shall be in accordance with GES X.06.
9.2 Spares
The Vendor/Contractor shall submit with his proposal, a priced list of recommended spares for start-up and
two years operation for review by the Owner. This list shall include, but not be limited to:
This section describes the minimum requirements for the preservation and protection of equipment during the
sea and land transportation and storage prior to installation.
The probable storage period will be specified in the order/enquiry and will extend from the time of despatch to
the time of unpacking at site. If the storage period is not stated, a minimum period of 24 months shall be
assumed. Packing to be suitable for sea freight.
(a) After mechanical completion at the works, the equipment shall be left in a clean dry condition.
(b) The Vendor/Contractor shall be responsible for loading and anchoring the item(s) to prevent damage
during shipment.
GENERAL ENGINEERING SPECIFICATION GES L.30
ELECTRICAL TRACE HEATING Page 27 of 33
Rev 0 1999
The Vendor/Contractor shall submit his procedures for packing and preservation for review by the Owner.
9.4 Shipping
The equipment shall not leave the Vendor/Contractor's works for shipment until the release has been approved
by the Owner's Inspector.
9.5 Warranty
The Vendor/Contractor shall warrant all material and services supplied against any defect for a period of
twelve (12) months after commissioning, or twenty-four (24) months from the date of delivery to site,
whichever is the shorter period, or for the period stipulated in the Order.
Should any item be found defective, the Vendor/Contractor shall be responsible for all costs associated with
restoring the equipment to the standard specified by the Purchase Order/Contract.
Figure 10.1 - Arrangement for Dual Electronic Controllers where lock out of Second Controller
is not required.
S:\NOC9077\ADMIN\SPECIFICATIONS\L-SERIES\L-30\GESL30RF
DATA SHEET NO.
ELECTRICAL TRACE HEATING (CALCULATION)
P.O. / CONTRACT No.
CLIENT
1 VENDOR / CONTRACTOR
2 DETAILS
3 A. See enclosed sketch
4 B. See enclosed scope of work
5 C. From drawings
6 D. From specification
7 E. Verbally
8
9 HEATING DUTY (See Notes 1 to 4)
10 Frost Protection (water) maintain/ heat up/ melt out/ other
11 MATERIAL OF PIPE metal/other
12 MAX OPERATING TEMP. OF PIPE CONTENTS °F(°C)
13 MIN AMBIENT
14 External °F(°C)
15 Internal °F(°C)
16 PIPEWORK LOCATION external/internal
17 non-hazardous/hazardous
18 "T" Class Division Gas Group
19
20 THERMAL INSULATION
21 Type mineral wool/other
22 Thickness in(mm)
23 ELECTRICAL SUPPLY/TOLERANCE V +/- %
24
25
26 CONTENTS OF PIPE
27
28 TEMP TO BE MAINTAINED °F(°C)
29
30 IS MAINTAINED TEMP CRITICAL? yes/no
31 Max permissible pipe temp °F(°C)
32 Min permissible pipe temp °F(°C)
33 Max ambient temp °F(°C)
34
35
36 ARE CONTENTS STATIONARY? yes/no
37 HEAT-UP TIME REQUIRED hrs
38 TEMP RISE °F(°C) Pipe: Contents:
39 MASS lb(kg) Pipe: Contents:
40 DENSITY lb/ft³ (kg/m³) Pipe: Contents:
41 SPECIFIC HEAT Btu/lb (kJ/kg) Pipe: Contents:
S:\l-series\l-30\dl3001R0.xls
DATA SHEET NO.
ELECTRICAL TRACE HEATING
P.O. / CONTRACT No.
CLIENT
PLANT SHEET 1 of 2
1 VENDOR / CONTRACTOR
2 SUPPLY
3 Volts +/- % Phase HZ +/- %
4 Fault Level kA Secs. Ground Fault CB Fitted Yes/No
5 Ground Fault Sensitivity mA Trip Time msec.
6
7 TEMPERATURE MAINTENANCE:
8 Freeze protection of water lines yes/no
9 Product to be heated
10 Temperature to be maintained °F(°C)
11 Pipe, tank or vessel material
12 Dimensions, diameters and lengths
13 Insulation type
14 Insulation thickness
15 Cladding type
16 Minimum ambient temperature °F(°C)
17 Maximum ambient temperature °F(°C)
18 Maximum exposure temperature i.e. °F(°C)
19 Pipework or vessels steam purged yes/no °F(°C)
20
21 TEMPERATURE RAISING:
22 Product
23 Specific heat of product (State units)
24 Specific gravity of product (State units)
25 Latent heat of fusion/evaporation (State units)
26 Time required for raising temperature hours
27 Quantity of flow rate (State units)
28
29 APPLICATION ENVIRONMENT:
30 Application indoors or outdoors indoors/outdoors
31 Damp or corrosive conditions present yes/no
32 Elevation of work feet (metres)
33 Access equipment required yes/no
34 Area classification
S:\l-series\l-30\dl3002R0.xls
DATA SHEET NO.
ELECTRICAL TRACE HEATING
P.O. / CONTRACT No.
CLIENT
1 VENDOR / CONTRACTOR
2
3 INSTALLATION:
4 Quote for a) installation of trace heat system yes/no
5 b) installation of thermal insulation
6 Location of job site yes/no
7 Power points available for hand tools yes/no
8
11
12
13
14
17 TAPE TYPE:
18 Self limiting (variable power)/Series resistance (constant power)/Parallel resistance (constant power)
19
20 TAPE REFERENCE
21
22 TAPE watts/foot(metre)
23
24 SPIRAL PITCH
25
30
31
32
33
34 APPROVALS
S:\l-series\l-30\dl3002R0.xls