Professional Documents
Culture Documents
Research Proposal
Research Proposal
INTRODUCTION
The reservoir,
Weir structure,
Conduit system,
Powerhouse,
Tailrace structure,
The main task of this project is power generation. The water retaining structure is a
concrete gravity weir, with the maximum height of about 48.5m and the total
reservoir storage capacity of 536,000 m3. The total length of the conduit system is
about 5584m, with the maximum diversion discharge of 29m3/s. The powerhouse
is externally located. It houses two Pelton turbines of 65 MW each (total capacity
130MW).
i. Intake
Trash racks 4 nos (6.75m x 4m each)
Intake Gate 1 no
Gate Shaft:
Internal Dia. 6m
Height 28m
ii. Sand Trap
Underground sand trap and gate chamber:
Sand trap chamber Dimensions 8.3 m x 6.5m/ 4x200m
Inlet Chamber length 70.1m
Outlet Chamber length 70.1m
Access tunnel to inlet Chamber 60.6m
Access tunnel to outlet Chamber 125.0m
Flushing canal length 125.2m
v. Penstock Tunnel
Length 202 m
Cross section 5.1m x 4.65m (wxh)
vi. Penstock
Diameter 2.6 m
Length 1412.6 m
(From Surge Tank to Powerhouse)
Access tunnel to Pressure tunnel 764.0m
vii. Powerhouse
External powerhouse:
Substructure depth 20 m
Superstructure length 39.6 m
Width 29 m
Height 32.2 m
viii. Tailrace
Open tailrace canal length 190 m
Covered canal length 75 m
ix. Head
Max. Operating level 1218. 0 m.a.s.l
Min. operation level 1206.0 m.a.s.l
(Normal drawdown level)
Turbine axis 677. 5 m.a.s.l
Max. Gross head 540. 5 m
Min. gross head 528. 5 m
x. Losses
Head losses for Qdesign=29 m3/s 24.4 m
Max. net head for Qdesign 516.1 m
Min. net head Qdesign 504.1 m
2. PROBLEM STATEMENT
Since the execution of Mangla Dam in Azad Kashmir in 1974, no specific
hydropower generation project was maneuvered (designed or constructed) up to
2000. When WAPDA promulgated the nascence of Vision 2025 under which a n. of
dams were planned to be designed and constructed , no trained professionals were
available owing to the dearth of such water related projects in the country in the
previous years. Even at present, the hydraulic engineers who are required to
incorporate hydraulic analysis for the appropriate design of such structures (i.e.
pipe network system in hydropower projects) are handicapped in Pakistan, as no
guidelines/specifications exist for the same.
I, therefore, intend to carry out research on this specific issue of hydraulic design of
conduit systems and related structures, as a case study of Duber Khwar Hydropower
project, subsisted in WAPDA vision 2025.
3. OBJECTIVES
To carry out hydraulic design i.e. head loss and hydraulic grade line calculation
for the availability of the required discharge and velocity u/s of the power
generation machines to accomplish the target of intended power generation of
the hydropower project.
To study the water hammer wave effects on the structure and the dissipation of
the said effects by the provision on surge tanks and associated chambers,
through the calculation of back wave velocity and wave levels in surge tank and
chambers.
To conduct the hydraulic calculations for tailrace structure d/s of power
generation house to study the effects of high velocity water profile on the outlet
structures.
H =hf+hl+hv
Energy losses within conduits fall into two general classifications:
(a) Surface resistance (friction) caused by shear between the confining boundaries and
the fluid and
b) Form resistance resulting from boundary alignment changes.
5. Methodology
Study of general features of structures related to the research work (i.e.
Power Intake structure, Sandtrap structure, Headrace tunnel, Pressure tunnel,
Surge tank, Tailrace structures etc.)
Selection of the corresponding design data from the available sources.
Recommendations for hydraulic analysis and designing Civil Engineering
Structures and its subsequent comparison with international codes and
specifications (such as USACE Engineering Manuals ,USBR Manuals ,
AWWA Manuals etc.).
Recommendation by Supervisor
Date: Date:
Recommendation by Chairman
Signature of Chairman