Professional Documents
Culture Documents
and Procedure
Scope of This Chapter
Demonstrate and highlight the overall
procedure and methodology to be followed in
the planning and design of an irrigation
scheme
Planning & Designing an Irrigation
Scheme
Step 1: Preliminary Soil and Topographic Survey
Step 13: Prepare setting out sheets for excavating the canals and
various structures
Step 1: Preliminary Soil and
Topographic Survey
Step 1: Preliminary
Prelim. soil survey to ensure that the area to
be developed can suitably sustain crops
Topographic survey
(a) determine the type of irrigation system to
be used weather (gravity or pumping)
(b) gain an overall idea on the planning and
the alignment of the irrigation units
Step 2: Detailed Soil and
Topographic Survey
detailed soil surveys is performed to
determine the type of crops to be sown in the
area.
Topographic maps are produced to the scale
of 1:10,000 up to 1:20,000 maximum.
Where:
Cd= coefficient of discharge and is given value of 3
A = area of the gate opening in m2
H = head losses through gate in m
Q=Full Supply (F.S.) discharge plus 25%
The width of the gate is selected to satisfy the following criteria:
(a) The opening required for maximum discharge should be less than two-third
(2/3) of the height of the groove
(b) To maintain submergence the underside of the gate should be a minimum of
0.6 m below the downstream water level
(c) With the gate closed there should be a freeboard of 0.3 m from F.S.L to the
top of the gate.
Step 7: Design of Cross-Structures:
Movable Weir Structures
These are the Butcher’s weir which were developed
to meet the particular irrigation requirements in the
Sudan.
The weir consists of round-crested movable gate with
guiding grooves and a self-sustaining hand gear for
raising and lowering it.
Step 7: Design of Cross-Structures:
Movable Weir Structures
There are two series: Movable Weir Series I (M.W.I) and
Movable Weir Series II (M.W.II). They are designed to discharge
up to 5.2 m3/s.
The regulator structure consists of Reinforced Concrete (R.C.)
floor with masonry superstructure and incorporate 6 m bridge.
The minimum head through the structure is 0.3 m.
The width of the weir is selected to pass the F.S.L discharge
with a maximum head over the weir of 0.7m based on the
following formula:
downstream is 0.3 m.
2X1.01 3780-4540
Step 7: Design of Cross-Structures:
Circular Night Storage Weirs
Used as minor canal cross-regulators. Pipe Dia Net Cultivable Area at Head
(m) of Minor –Feddans
The structure consist of circular brick well
erected on a reinforced concrete slab.
1.0 0-1000
The weir is designed to pass a maximum
discharge at a head of 0.2 m over the weir
crest. 1.5 1000-1500
The size of the weir could be based upon
the following formula:
2.0 1550-2050
Where:
Q=F.S.L discharge in m3/s.
2.5 2050-2650
b = length of the weir crest measured at the
internal circumstances
h = upstream head over the weir crest in m. 3.0 2650-3200
Step 7: Design of Cross-Structures:
Field Outlet Pipes
Step 7: Design of Cross-Structures:
Field Outlet Pipes
The field outlet pipes carry the water flow from the minor canal into the Abu XX.
Usually one FOP supplies Abu XX which irrigate 90 Feddans.
The FOPs are spaced 292 m apart and their discharge is given by:
Where:
D is the diameter of the pipe in m
h is the head over the pipe in m.
The FOP was originally designed to pass a discharge of 10,000 m3/day when
the head across it is 15 cm (i.e. 5000 m3/12 hrs).
The Abu XX will thus be able to irrigate the 90 feddans plot in 7 days if watering
in the field continues for 12 hrs from sunshine to sunset (The crop factor is
assumed 400 m3 per feddan per irrigation).
The above situation represents the ideal situation or the original design.
However, due to the poor performance of the FOP and the problems
encountered associated with small heads in the minor canal, the discharge
passing through the FOP is far less than 5000 m3/12 hrs . Sometimes it is even
less than 20% of the required discharge.
Step 7: Design of Cross-Structures:
Bridges
Road bridges are provided on supply canals,
main and major canals.
Bridge carry 6.0 m road constructed on
reinforced concrete span.
Abutment and peirs are constructed using
masonary on a reinforced concrete footings.
The distance apart on Supply and Main
canals are 10 km.
On Minor canals pipe bridges are used where
needed
Step 8: Design of Channel Cross-
Section
Design the sections of the canals using Manning
formula and double check using Lacey formula.
Manning formula:
Where:
n = Manning roughness coefficient
A = Cross-sectional area of flow
R = Hydraulic radius (m)
S = Channel bed slope.
Step 8: Design of Channel Cross-
Section
Lacey Equation :
Where:
Ws = Water surface top width (m)
e = width factor; Q= full supply discharge (m3/s)
b = bed width (m); Dm = mean depth= A/Ws (m)
V = mean velocity (m/s); f = silt factor
E = Wetted perimeter /Ws
S = Water surface slope.
Step 8: Design of Channel Cross-
Section
Establish the cut areas. To balance the earth work and to avoid borrow
soil, Half of the cut area of the cross-section shall be used to establish
the Right Overbank and the other Half shall be used to establish the left
overbank.
Step 9: Design of the Drainage
System
According to the layout of canalization the
drainage system is laid out.
Minor drain Drain the field
Collector drain parallel to major drain
collecting all minor drain out falling into a
main drain which takes the water out from
canalized area to natural drainage paths.
Step 9: Design of the Drainage
System: Drainage Requirements
The current equation to calculate the drainage is:
Where:
Q = Discharge of frequency 1 in 5 wet years (m3/s);
A = Cacthment area in Feddans
C = Runoff coefficient/Factor.
Where:
Q = Design flow;
RF = Rainfall of frequency 1 in 5 wet year
SMD= Soil Moisture Deficit
ET = Evapotranspiration.
Step 9: Design of the Drainage
System: Drainage Requirements
The 1 in 5 year “wet” rainfall for each hydrometrological region
is predicted from the relationship:
Where:
V= mode of the two-days annual maximum rainfall given by:
V= X-0.5772a
X=mean of two days annual maximum rainfall
a= scale factor given by:
Project Headquarters
Divisional Headquarter
Sub-divisional Headquarters
Pumping station colonies
Villages for tenants
Water control personal along canal structures
Drinking Water Supply System
Telephone System
Administration and Staff
Requirements
Housing Schemes
Step 12: Project Costing and Bill of
Quantities
Step 13: Finalization of
Construction Drawings
After completing the layout of canalization, the
following steps should be followed:
The center lines of all canals should be laid out first
with the aid of Bacons. A team of surveyors shall set
out the center lines of canals on the ground.
Along the C.L. of each canal the actual ground
levels were measured at 200 m spacing. These spot
levels shall be handed over to the design engineer to
finalize the longitudinal section as required.
Perform the design the various canals, using
Manning Charts and check with Lacey formula.
Prepare setting out sheets for excavating the
canals and various structures.
Thanks for Attention