Professional Documents
Culture Documents
Page 2
Page 3
- Feed chute
- Mill housing
- Grinding roller pair
- Confining air
- Grinding table
- Tie rods & hydraulic system
- Mill main drive & auxiliary drive
- SEPOL Separator
- Water injection
- Roller pair Dismounting device
Page 5
SEPOL
Hoist carrier
Upper housing
Hoist
Roller pair
Drive
Lower housing
Nozzle ring
Grinding path
Tie rods
Page 6
Feed Chute
Page 7
Overload coupling
Type Syntex 50 TD1 Rotex GS48/50
Scraper jammed
Hot gas
Page 13
Feed chute
Hot gas
20°C
max. 350°C
259°C
261°C
Page 14
Feed Chute
Mill housing
Page 15
Mill doors
Page 16
Rubber seal
Mill doors
Page 17
Mill housing
Page 20
Components
• Roller carrier
• Shaft
• Bearing tension cover
• Roller bearing
• Roller body
• Clamping ring
• Roller tyre
Page 24
view
Page 28
Confining air
Page 29
A wear-measuring inspection of the grinding elements forms the basis for the decision in which
direction to shift the hooks. A shift towards the outside (+Y) is necessary when the inner roller path
shows more advanced wear. A shift towards the centre of the grinding table (--Y) is necessary when
the outer roller path shows more advanced wear.
The roller pair units are delivered with the hook mounted in „zero position (A)”.
When turning around the roller pair units to spread the wear uniformly over the roller tyres, definitely
make sure that the hooks are in the same position relative to the roller unit axis (both in magnitude
and direction) as before turning.
NOTE
The tie rods are always suspended from the outer hooks (20).
Page 37
Remove the roller pair units, turn them around through 180°
outside of the roller mill and re-install them into the roller mill.
After installation of the roller pair units, the oil probes must be
re-calibrated and checked for proper functioning.
Page 39
5 Check the wear on the roller tyres (25) every 6 months during commissioning
every 3 months; see Item
Recording of the wear
6 Check the wear on the guide pins (21) every 3 months the permissible wear is
10 mm
Page 44
2 Retighten the following bolted connections every 6 months at the first start-up and
with the specified tightening torque as per subsequently to every
table in section Repair repair after 30 to 50
- of hook (20) operating hours
- of guide pin (21)
- of outer bearing cover (13)
- of bearing cover plate (14)
- of confining air connection (22) to the
roller carrier
3 Turn around roller pair units as required latest all 2 years see Repair
Page 45
Servicing
No. Work to be performed Frequency Remarks
4 Shift hooks (20) as required see Repair
top up oil
Mill housing
Grinding table
Page 48
1. Technical Data:
• Outside Diameter 5770 mm
• Height 2140 mm
• Number of table liner segm. 6
• Weight of table liners 31570 kg
•Total weight of the Grinding table 110780 kg
Page 50
6 6
11 7 7
10 10
Wedge element
Grinding track
Nock
Dam ring
Table insulation
Page 52
Correct mounting is
very important!
Page 54
adjustable
Page 56
Grinding Table
Insulation
Page 57
- Dam Ring
- Discharge Ring
Page 58
Scraper elements
Wear plates
Page 59
Discharge Ring
Scraper elements
Page 60
3
Page 62
20...25% wear
40...50% wear
Page 63
2 Retighten the following bolted connections every6 months At the first start-up and
with the specified tightening torque acc. subsequently to every
to the drawing specification repair after 30 to 50
- of table body (1) with gear unit operating hours
. of dam ring heightener (4)
- of cover (5.1)
3 Check the seals in the joints between the every 6 months If necessary, stuff with
table liner segments, dam ring and grinding sealing cord and then
table cover strongly compress the
cord
Page 65
Main drive
Mill housing
• Function
• Working side
• Damping side
• Grinding bed measuring device
• Limit switches
Page 69
Two hydraulic cylinders per roller pair ensure that the grinding force is evenly applied
to the rollers, while maintaining the maximum freedom of roller movement.
The hydraulic System permits infinite adjustment of the pressure in order to adapt
the grinding force to actual operating conditions.
When the mill is started up, the hydraulic pressure is lowered in order to reduce the
force applied to the grinding rollers. This in turn reduces the starting torque.
Oil pressure too high - Roller mill too full Check mill operation
Display
Pressure monitor - Balancing of the roller pair Replace defective hydraulic
(61.1 to 61.4) signals units is not performed due to cylinder or piston accumulator
a defective hydraulic cylinder
or piston accumulator
Page 75
Hydraulic oil temperature The radiator (28) is not Check the setting of the
is too high switched off temperature monitor
The piston in the piston Pressure drops on the gas Find and remedy the leakage;
accumulator (32.1 to 32.4) side of a piston accumulator compensate pressure drops
reaches the end position (32.1 to 32.4) by topping up with nitrogen
Display
Uneven running of the
roller mill
Formation of foam in the The hydraulic system was Seal the leak; deaerate the
hydraulic oil (visible on the not hydraulic system;
oil level indicator) sufficiently deaerated or air the hydraulic oil has to be
is exchanged
being sucked through a leak
Page 77
Main drive
Mill housing
Grinding table
Page 78
2.0 Coupling
7.0 Safeguard
Axial bearings
Bearing temperature 70°C Alarm
Bearing temperature 75°C Mill stop
Filter contamination
Differential pressure1,75 bar High pressure System
Differential pressure3,15 (4,5) bar Circulation System
Page 83
Main drive
Mill housing
Grinding table
Page 84
Drive shaft
Mill outlet gas duct
Guide vane adjustment
Guide vanes
Sepol housing
Sepol rotor
Page 86
rotor
guide vane ring upper bearing arrangement
Page 87
Eye bolt
Size M 36
Bearing capacity 16000 kg
Separating air
Flow rate 870000 m3/h
Page 88
Drive unit
Type A
Gear unit
Type B3 SV 09
Drive power 152 kW
Output speed 15 -- 86 1/min
Coupling
Type N--EUPEX A200
Connecting element (6) for the separator
cardan shaft Type 587.55 -- 0.01
Page 90
2.3 Rotor
2.4 Shrunk--on disk or locking device for rotor
2.5 Drive shaft
2.6 Rotor blades
2.10 Upper bearing unit
2.30 Lower bearing unit
2.40 Support for the lower bearing unit
Page 91
Grease to bearing
Grease to
labyrinth seal
Page 94
6 Check of According to
- the coupling (2) manufacturer’s
- the connecting element (6) instructions
Page 101
Speed of electric motor (1) Speed control defective Repair speed control
cannot be adjusted in accordance with
manufacturer’s instructions
Electric motor (1) gets too - Electric motor overloaded - See machine manual of
hot SEPOL separator
- Dust and dirt particles in
cooling system - Clean cooling system of
electric motor
Page 103
Main drive
Mill housing
Grinding table
Page 105
The End