Professional Documents
Culture Documents
FABRICATION PROCEDURE
DK DP
Rev Rev Date Description Prepared By Checked By Approved By
TABLE OF CONTENT
1. QUALITY CONTROL
1.1.1 The window of PT. Kurnia abadi padang shall in principle be the Purchase Department. In an urgent
inevitable case, inform the person in charge of the relevant department.
1.1.2 Keeping a secret
It is strictly not allowed for Sub-contractor or second sub-contractor to leak out the secret of the
drawing, document and any related techniques from PT. Kurnia abadi padang to any others company
or third party.
1.1.3 Even if being a secondary subcontractor, it is necessary to get the approval of the works. So, be sure
to make application for the approval in advance and approval guidance of work with responsibility.
1.1.4 All fabrication activity shall be planned and predicted of the result, so approved Inspection and Test
Plan (ITP) shall be follow as mandatory guidance for each activity.
1.1.5 All comment during inspection shall be on the report form.
Cutting
Inspection
Beveling
Inspection
Tack Welding
Inspection
Temporary Assembling
Painting Insurance
(1) As for the titled documents, use those having the signs of inspection and approval.
(2) If there is any doubt in the titled documents, ascertain it from the design engineer in
charge
(3) When the titled document has been modified, be sure to replace with the modified one.
When an indication has been received inevitably by the contact with telephone, keep the
following mentioned in the document: name of design engineer, date of contract and
contents of modification.
(4) When it needs to modify the document issued by PT. Kurnia abadi padang in the aspects
of quality control and price, be sure to give notice by a document and modify after
getting the approval of the section in charge.
(5) Control the acquired documents strictly and don’t handle them roughly. Also, on the
termination of manufacture and delivery of the parts, return the documents to PT.
Kurnia abadi padang right off.
1.2.4 Welding
(1) Get the qualified and certified personnel to engage in the welding work.
(2) Put the welding rods in a desecrator to keep drying at a specified temperature.
(3) Never get any unqualified person to engage in the welding work under any
circumstances.
(3) For the tools, nominate a person responsible for managing them to get him to take in-
charge of the daily maintenance and check of these tools.
(4) With adequate personnel arrangement, always check whether the work is going on as
the delivery data schedule for supervising not to delay the delivery date.
(5) Also, inform the work progress condition at least once a week.
(6) Clean the sections inside the factory at the end of every week and try to tidy up.
(7) Give the highest priority to the safety and if there is any improvement or step to be
taken, perform within that day.
1.2.6 Inspection
(1) Be sure to perform a voluntary inspection as per Inspection and Test Plan (ITP).
(2) Submit the application for witness inspection to the Quality Assurance Dept. one week
before as a rule with the required items put in a prescribed form (a request sheet for
witness inspection).
(3) Judgment of OK/NO shall be according to PT. Kurnia abadi padang inspection
standards.
(4) Compile the inspection records with the contents made clear through pre-arrangement
with PT. Kurnia abadi padang inspector.
(5) Submit the specified number of copies of the inspection records to the Quality
Assurance Dept.
(6) Keep the inspection records at least one year. After one year has elapsed, discard the
records.
(7) Calibrate the inspection tools (micrometer, slide calipers, etc.) periodically (preferably
at about 1-year interval)
2. MANUFACTURING STANDARD
l=leg length
a) In case of rib plate
thickness being t2<16
m/m
Scallop shall be
l=leg length
b) In case of rib plate
thickness being t2<16
m/m
2.2.4 Remove slag produce during work thoroughly during assembling work.
2.2.5 To prevent from shrinkage or deformation, reinforced sufficiently prior to getting work on welding.
The reinforcement must be a proper on size and position to permit withstanding a welding shrinkage
stress.
2.2.6 Assembly based in the center and mark the center used for reference to the last.
2.2.7 Take out all reinforcements.
For removing them, cut by gas cutting, arc air or grinding and be carefully not to damage the base
metal and after cutting, finish smoothly by grinding machine.
2.2.8 For a root gap and groove angle, follow the indications in the drawing or refer to the quality control
standards “Attached data 1. Accuracy of weld joint (groove)”. Also, if there is a defect of the groove
which exerts a bad influence upon the weld quality, remove it before welding.
2.2.9 The weldments of the internal mounting parts must not be covered before the inspection terminates.
2.2.10 Chamfering (1.5c to 2c)
Chamfer the free edges of the major parts by 1.5c to 2c
2.2.11 Dislocation of plate joint, a thinner side shall be within 10% of plate thickness as a target.
2.2.12 Removal of primer on welding section
(1) Wash primer (blue) and Zinc rich primer (gray)
Fillet weldment of main member – 3T
(Example)
2.4 Bending
2.4.1 Do the bending work with the use of press at ordinary temperature in principle, be careful not to
debase the quality of steel materials. However, in an inevitable case, a hot bending work shall be
done.
2.4.2 The hot bending work is done by heating the material more than 900°C as a rule and the bending
work shall not be done in a condition where the material has been cooled down to 200 to 400°C or
there about
2.6 Drilling
2.6.1 Holes must in principle be made by a drill
2.6.2 Remove burrs at the periphery of hole by a grinder
2.7 Treatment of friction face of friction grip with high strength bolt.
2.7.1 Remove mill scale sticking onto the friction face of member which is friction-joined with high
strength bolt by the following methods.
Section Method
Web of member, flange & gusset plate Shot-blasting or grinding
Spliced plate & filler plate Shot blasting or grinding
2.7.2 A range where surface treatment is given shall be more than 2 times as much as a washer diameter.
Crater treatment: Perform a crater treatment fully not to produce crater crack.
3. WELDING STANDARD
3.1 Welding symbols
The welding symbols shall be in accordance with international Welding symbols.
(2) Reinforcement
Reinforcement must be 3 mm maximum
(1) The leg length in fillet welding must be more than a length indicated in the drawing. (No
length smaller than that indicated is allowable).
(2) T joint
(3) When there is no indication of the leg length in the drawing, the leg length shown below
must be applied to ‘Thinner plates’.
(1) For the weld length and pitch of the intermittent welding, observe the indications in the drawing.
(2) Intermittent welding modes:
a) Parallel intermittent welding
c) When the welding length and welding pitch of the intermittent welding are not indicated in
the drawing, do the welding referring to the table below. However, unless otherwise
specified, both ends must be welded.
3.4.2 Welder
The qualified welders who have received the upper training of PT. Kurnia abadi padang instructor
must engage in the welding work.
Sample of approval / identification after having received upper training:
2) For back chipping in butt welding (however, exclusion of a case where there is a backing metal),
chip before welding a weld root or doing a back welding and remove defect(s) by a grinder or an
arc air gouging.
3) Be careful not to give arc strike to the base metal and make the arc start inside a groove or on a
discarded plate.
The welding machine and attachments used for the welding work have enough capacity and
performance to the kinds of welding materials (diameters and brands) used and allows the work to
carry out safely.
(1) The welding materials, before unsealing and uncasing, must be stored neatly in place which
is safe against moisture, rust and breakage.
(2) The welding materials such as manual welding rods and flux which might get moistened
must be kept in a drying oven or desecrator after having been unsealed and uncased.
(3) The welding materials carried out to the welding worksite must be kept in a proper portable
container.
Straighten each member prior to getting to work on welding and further, clean by removing
detrimental substances sticking to the welding surfaces, e.g., water droplets, rust, paint, oil & fat,
sand and so on, and then start the work.
Connect and fabricate the members correctly with match marks by using adequate jigs and tools.
3.4.9 Preheating
When coming under the following conditions, preheat by gas flame over a range of about 100 mm at
one side from the welding line. Also, measure and make sure of the preheating temperature at a
position of about 50 mm away from the welding line by a temperature choke.
Note: When the atmospheric temperature is below 0°C the welding work should be avoided. This
rule, however, does not apply to the case where the atmospheric temperatures ranges from
0°C to 25°C and the welding is done by heating a base metal at a range of 100 mm from the
welding line so that temperature of the portion becomes 36°C
3.4.11. Straightening
Strain generated from welding must be remedied by a press straightening machine or linear heating
method.
A maximum heating temperature by the heating method and the cooling method shall be as follows:
Maximum heating temperature: 850 to 900°C (Desired temp: 885°C)
Cooling method: Start forced cooling after stopping the heating.
If any defect has been found coming about in the weldment, take the corrective actions referring to
the table below.
4. PAINTING
Stir the paint in a container unsealed once well before putting it into a sealed container for
keeping in store
Note:
There mustn’t have any detrimental defect on the material surface
The material and size must be as specified.
The full size inspection must always be performed by the manufacturer. In inspection, only the
size necessary for the product must be checked.
Inspect the side of the upper frame, gas ducts and hopper connection by using a spine batten.
Check the horizontal and vertical braces referring to the original drawing and check if there is
any part which is unsuitable for assembly or part which cannot be bolted.
Put the reference and center line in the templates and spine batten and make sure they are in
accord with each other.
Note:
Allowable tolerance of full size is ± 1.0 mm
(Between reference lines, between columns, between girders, diagonal line, template &
spine batten)
Perform the dimensional inspection referring to the design / shop drawing and make sure the
dimensions are within the criteria shown below:
The basic dimensional tolerance shall be in accordance with the product accuracy as mentioned
on material certificate.
The detailed dimensional tolerance report and the measuring points of dimensions shall be in
accordance with fabricator standard Inspection report form.
Check the appearance visually and make sure of the following points:
There must be no poor-looking parts such as crack, mar, puncture, etc on the surface of material.
Each cut face mustn’t be poor looking
Each bolt hole must be normal, free of burred
There must be no failure to work or mount
There must be no sticking of mud, sand, heavy oil and fat
Free edge
Less than 100S
Free edge
Less than 2 mm
(4) Width ± 3 mm
(B)
Attached data 3
Accuracy of Weldment
(1) The shipping No. Shall be according to the bill of quantity issued from the Design Dept.
(1) The entering position shall in principle be at an upper right corner facing the products
surface.
(2) For such long materials as a column, brace, etc. the number must be put on the upper
positions viewed from the structures.
(The number are not entered on the concave side of H and U steels)
(3) For the piping, put the number on the upstream side of fluid
(4) Pack small parts (bolts, nuts, packings, etc.) in bags or bind them and attach a tag in
which the shipping No. has been put to each bag or bound thing.
(5) How to enter