Professional Documents
Culture Documents
REVISION HISTORY
02 Document formatted as per DMS policy Asoga Tannimalay Mar 26, 2010
05 Document updated with the latest template Chandran Bendaiya September 06, 2012
COMPANY Changeover
CONFIDENTIAL Printed copies are uncontrolled copies.
2 GBE-KPO-2-023-00
Verify revision and approvals in theRev.
FMS 06
Document Management System on ShareNet.
Table of Contents
Contents Slide(s) Contents Slide(s)
Changeover
3
GBE-KPO-2-023-00 Rev. 06
Overview and Scope
Overview
Changeover is a process of converting or transiting a line, machine or materials from one condition or
system to another.
It happens when there is a transition from one product or module to another.
Quick changeover is measured by the time gap between the ending time of the last good piece produced
from the previous model and the beginning time of the first good piece produced from the next model.
Quick changeover minimizes equipment’s idle time and thereby helps respond much faster to the
customer needs.
Scope
Changeover time
Quick changeover
Quick changeover process step
Impact on OEE
Changeover
4
GBE-KPO-2-023-00 Rev. 06
Objectives
Reduce internal activities by converting them to external activities
Extract the benefits of quick changeover from all the related areas of the production system
Changeover
5
GBE-KPO-2-023-00 Rev. 06
Definition of Changeover
T1 T2
Changeover is defined by the time gap between ending time of the last operating piece
produced from the previous model ‘A’, say T1, and the beginning time of the first operating
piece produced from the next model ‘B’, say T2.
Changeover
6
GBE-KPO-2-023-00 Rev. 06
Purpose of Quick Changeover
Changeover
7
GBE-KPO-2-023-00 Rev. 06
Impact of Quick Changeover
Support s Pull System Implementation: Reduces Inventory :
Quick changeovers facilitate small lot production and Dramatic cost improvements
this in turn facilitates pull systems Reduces Lead Time:
Improves Quality: Shrinks the time it takes to deliver the product to a
Quicker feedback from customer or customer process customer
and reduced process variability Improves Flexibility:
Increases Capacity: Changes in customer demands are easy to
Improved capacity for the bottleneck equipment accommodate without any excess inventory
• Inventory
Allow Smaller Batches Improve Capacity Enable Just-In-Time
(Flexible Production) and Quality Manufacturing • OEE
• Flexibility
OPERATIONS • Manufacturing
SUPPLY CHAIN Lead time
• Productivity
Reduce Inventory Shorter Material Improve On-Time • CAPEX
(Lower Capital Cost) Lead Time Delivery
• Warehouse
Changeover
8
GBE-KPO-2-023-00 Rev. 06
How to go About Quick Changeover?
Key to quick changeover is to convert as many internal activities as possible to external
activities.
An internal activity is a task that can only be executed when the machine is stopped or in an idle
mode.
An external activity is a task that can be done before or after setting up the machine, without
impacting any of the current operations or stopping the machine.
Changeover
9
GBE-KPO-2-023-00 Rev. 06
Before Quick Changeover
• How long does it take to change a tire of your car on your own?
• How long does it take to change a tire in a tire workshop?
Changeover
11
GBE-KPO-2-023-00 Rev. 06
Quick Changeover in Formula 1
• Quick changeover principles can be used and applied in almost all operations or processes.
• In most cases, if the quick changeover principles are followed, drastic reduction in the setup time can be
obtained.
• Video shoot a • Identify activities • Convert internal • Simplify internal and • Standardize systematic
changeover process done before activities that could be external activities steps involved and
changeover performed before with good solutions document them
• Watch and analyze it
changeover
• Identify activities • Conduct training for
• Identify • Sequence the
done during • Internal activities may sustenance and audit
improvement
changeover require modification to changeover process periodically to assure
opportunities steps to minimize the
transfer to external adherence
activities time involved
Changeover
13
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 1: Study Current Changeover Activities
Tasks Involved
a) Video shoot a changeover process
b) Watch and analyze it
c) Identify improvement opportunities
What must be achieved at the end of the activity?
a) Identify internal and external elements (Review the
video multiple times)
b) Identify the total lost production time
c) Observe the variances from the standard process
Activity
a) Record the total time between the production of the
last good part from one run to the first good part of the
These activities are
next run
conducted for the purpose of
observing the activity, and not
the person.
Changeover
14
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 2: Separate Internal and External Tasks
Internal elements:
Operations that must be performed after the machine or process is stopped (Examples: Fine -tune, adjust
and clean, etc.)
External elements:
Operations that can be performed while the machine or process is running (Examples: Tools and jig
preparation, pre-heating the mold and extensions etc.)
A high percentage of operations are usually external steps that could be performed before or
after the changeover process.
Changeover
15
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 2: Separate Internal and External Tasks
Activity : Determine the steps that could be performed outside the actual changeover process.
Changeover
16
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 3: Convert Internal Tasks to External Tasks
Changeover
17
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 3: Convert Internal Tasks to External Tasks
Before converting internal operations to external operations, you need to consider the following points:
Internal operations may require some modifications of the current setup conditions before you transfer them
to external operations
There may be internal operations that cannot be transferred to external operations after any
reasonable modifications to the current setup conditions
Some external operations can be easily performed while the machine is running under the current
setup conditions. For example, hand tools and fixture preparation, fixture repair, time reports, etc.
Some external operations can be performed while the machine is running, but may require some
modifications to the current setup conditions. For example, fixture adjustments, die preheating, part
adjustments on the fixture, etc.
Changeover
18
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 3: Convert Internal Tasks to External Tasks
Activity
d. Standardize settings
a. Eliminate searching
e. Make visual marks
b. Arrange tools and materials ahead of time
f. Eliminate trial runs
c. Complete the pre-work before starting the changeover
g. Postpone the “put away” work
Changeover
19
GBE-KPO-2-023-00 Rev. 06
Step 3: Convert Internal Tasks to External Tasks
Changeover External Process – Readiness
SMT: Kit Ready for Changeover SMT: Offline Component Verification SMT: Paste Printing Machine Changeover Cart
• Completed kit ready for pull to • Eliminate line down situation due to Cart is prepared with:
changeover component marking issues • Stencil • Setup template
• Assure quality of components feed to the • First article paper
• Feeders verified and arranged in a • Solder paste
line • SMT fixtures and other tools (as
correct sequence • Online Inquiry System linked • Squeegees
needed)
SMT: Floor Marking with Dance Steps SMT: Multi Feeder Unit (MFU) Movement SMT: Communication Board
• Use floor markings, standard work and Marking • Early signal for the preparation team to
visual management to ease the • Feeder preparation areas are marked in get ready before the changeover start
changeover process details to facilitate smooth MFU • Standard procedure display
movement
Changeover
20
GBE-KPO-2-023-00 Rev. 06
Source : Operation, NPO
Lean in Operations – Mechanical Best Practice
Release 3-22
Site Name : Mechanical Singapore
% Improved
Before
time due to searching high usage. Inventory
After
Metrics Hard Soft
of bending tools Fix tool storage /AR/AP
Soft Tool (UOM) (USD/ (USD/
(USD/
Hardware Installed & Visual
location. Apply color month) month)
month) aids to detect abnormality.
codes of tool. Display
tool profile on rack for Picking time
Customer per tool 6 1.5 75% 180
easy identification of Implementation Start Date
unique tool. (Minute)
28-Feb-08
All 100% Implementation Plan
2-Mar-08
Tools Used Goals X Lead-Time x 1/2 Cost saving Potential Savings/Month
X Lean Defect x1/10 Energy x 9/10
USD 180/month after 100% Implementation
Inventory /
Inventory x1/2 Scrap x1/10 Hard Soft
Six AR/AP
Sigma Productivity x2 Space x1/2 US$0.18K US$XXK US$XXK
Site Yokoten
Implementation Status:
Guide: 81% ~ 100%
Changeover
21
GBE-KPO-2-023-00 Rev. 06
Source : SGA
Lean in Operations – Mechanical Best Practice
Release 7-67
Site Name : Juarez
% Improved
Before
and in the mold during extra electric crane to Inventory
After
Metrics Hard Soft
change over ( Critical have ready next mold ( /AR/AP
Molding (UOM) (USD/ (USD/
(USD/ Standard work
internal activity ) part of the complete month) month)
month)
activity move it from
Customer internal to external) CO Time
15 9 40% 190
( Min) Implementation Start Date
1-Apr-09
Lego 100% Implementation Plan
5-Apr-09
Tools Used Goals X Lead-Time x 1/2
Potential Savings/Month
X Lean Defect x1/10 Energy x 9/10 after 100% Implementation
Inventory /
Inventory x1/2 Scrap x1/10 Hard Soft
Six AR/AP
Sigma Productivity x2 Space x1/2 US$0.19K US$XXK US$XXK
Site Yokoten
Implementation Status:
Guide: 81% ~ 100%
Changeover
22
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 4: Streamline Internal and External Tasks
Changeover
23
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 4: Streamline Internal and External Tasks
• Manually adjust the position to center • Use center pins and guides
Positioning • Manually adjust the front-to-back position • Use stop-blocks to ensure proper position
• Use different die heights in the same press • Standardize the die heights
• Manually adjust temperature and speed • Set temperature and speed at pre-determined
Adjustments (using trial and error) standard
• Manually set programs for automated • Pre-load programs
equipment
Parallel • Perform independent tasks in serial • Perform simultaneous actions for independent
Activities and sequence. task (work balancing if performed by multiple
Streamlined • Need to travel a long distance to retrieve or person)
Movement store tools, gauges, fixtures • Store related documents, tools, gauges,
fixtures close to the changeover area
Changeover
24
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 4: Streamline Internal and External Tasks
Simple attachment: T-
slots
Faster tools –
Specialized loading – Example: air wrenches
Example:
Dedicated sleds, hydraulics,
etc.
Less traveling distance to
Fail-safe positioning of search or retrieve tools
major components or parts
Less time
Changeover
25
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 4: Streamline Internal and External Tasks
• Searching for or retrieving materials that are required • Ensuring that proper materials are provided in all the
to perform a changeover areas of the plant
Changeover
26
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 4: Streamline Internal and External Tasks
X X
b) Pre-position all tools and tools and equipment
Stage material close and complete close, while the machine
c) Organize for sequential use is running
a) Eliminate excess fastening a) Remove or attach non-critical a) Reduce threads a) Use extra manpower
points parts externally b) Specialized tools b) Automation
b) Redesign for natural-gravity fit b) Modular subassembly c) Air wrench
with no fasteners d) Clamps
Fasten
e) T/U slots
f) Magnetics
g) Hydraulics
Changeover
27
GBE-KPO-2-023-00 Rev. 06
Step 4: Streamline Internal and External Tasks
Streamline Internal Changeover Process
Top Bot
1 2
SMT: Chip Placer SMT: Top and Bottom Assemblies Together SMT: Paste Printing Machine
• Auto-change nozzle during • Auto recognition of the Top and Bottom sides • New squeegee attached to reduce internal
production using the PCB mark time
• Machine auto recognizes the side and selects
the program
Mechanical: Stamping Die Adjustment Mechanical: Soft tool – Bending Process Mechanical: Fabrication Process
• Fixation block to easily fix the die • Specially designed four in one combo tool • Multi model setup
• Place the die on machine and push to the to reduce internal task time • Common tools setting eliminate internal task
required location – No adjustment needed
Changeover
28
GBE-KPO-2-023-00 Rev. 06
Best Practice
Lean in Operations – Mechanical Release 8-64 Source : Internal
Site Name: FMTS
Title : Metal Stamping Machine Down Time Reduction
Operations/
Problem Action Taken Results Method for Sustaining
Station
1) Operators to clear 1) Designed slip plane Savings
% Improved
Before
out machine waste of waste material to Inventory
After
Metrics Hard Soft
material & Take long replace manual cleaning /AR/AP
Molding (UOM) (USD/ (USD/
(USD/ Standard work
time. process and eliminate month) month)
month)
2) Long time for die cleaning time & scratch.
setup & Location 2) Designed & installed
Customer adjustment die locking jig to reduce
CO Time
45 25 44%
( Min) Implementation Start Date
3) High defects caused die setup time.
3-May-09
All by waste material, high 3) Setup die location
Down time 100% Implementation Plan
mold broken rate. fixture to eliminate 4.5 0.5 89%
(Hrs/Day) 25-May-09
adjustment
Tools Used Goals X Lead-Time x 1/2 Defects 6% 1% 83%
Potential Savings/Month
X Lean X Defect x1/10 Energy x 9/10 Crew 8 0 100% 2000 after 100% Implementation
Inventory /
Inventory x1/2 Scrap x1/10 Hard Soft
Six AR/AP
Sigma X Productivity x2 Space x1/2 US$2.0K US$XXK US$XXK
Cleared out by
automation;
Long down time Site Yokoten no down time
to clear out Implementation Status:
Guide: 81% ~ 100% Die lock Jig
Changeover
29
GBE-KPO-2-023-00 Rev. 06
Best Practice Source : Internal Kaizen
Lean in Operations – Mechanical Release 8-71 Site Name: Mech Shanghai
% Improved
Before
are using at other shortage, Engineer Inventory
After
Metrics Hard Soft
machine, Operator need modify the program on /AR/AP
Soft tool (UOM) (USD/ (USD/
(USD/ Standard work
to modify the program computer in advance, month) month)
month)
on machine during when copy to machine
changeover. when changeover.
Customer CO Time
15 0 100% 3267
( Min) Implementation Start Date
9-Jun-09
All 100% Implementation Plan
9-Jun-09
Tools Used Goals X Lead-Time x 1/2
Potential Savings/Month
X Lean Defect x1/10 Energy x 9/10 after 100% Implementation
Inventory /
Inventory x1/2 Scrap x1/10 Hard Soft
Six AR/AP
Sigma X Productivity x2 Space x1/2 US$3.27K US$XXK US$XXK
Site Yokoten
Implementation Status:
Guide: 81% ~ 100%
Changeover
30
GBE-KPO-2-023-00 Rev. 06
Source: Internal Kaizen
Lean in Operations - Mechanical Best Practice
Release 4-22
Site Name: FTM1 (PTP, Malaysia)
% Improved
Before
as support pin are support block instead of Inventory
After
Metrics Hard Soft
FTM 1- inserted one at a time. pins for quick setup. (UOM)
/AR/AP Change support pin to
(USD/ (USD/
PCA 2) Potential crack 2) Achieve Zero Defect month) month)
(USD/ support block for all KME
month) CM88
components on bottom by using the Poka Yoke
side at board due to im- rubber support block to
Customer proper support pin set- eliminate crack
CO Time
83 20 76% 3267
( Sec) Implementation Start Date
up. component on bottom
9-Jun-09
HP side of board.
<0.5 100% Implementation Plan
Defects 0 100%
% 9-Jun-09
Tools Used Goals X Lead-Time x 1/2
Potential Savings/Month
X Lean X Defect x1/10 Energy x 9/10 after 100% Implementation
Inventory /
Inventory x1/2 Scrap x1/10 Hard Soft
Six AR/AP
Sigma
Before Kaizen
Productivity x2 Space x1/2
After Kaizen
100% Defect
US$3.27K US$XXK US$XXK
Improvement
Site Yokoten
Implementation Status
Guide: 51% ~ 80%
Changeover
31
GBE-KPO-2-023-00 Rev. 06
Lean in Operations – Productivity Best Practice Source : Internal
Site Name : Infra Guadalajara North
Release 7-40
Title: Increase in Number of CO with Super Load
Operations/
Problem Action Taken Results Method for Sustaining
Station
There is and excess of A super load for SMT Savings
% Improved
Before
wip for ceramic that contains all Inventory
After
Metrics Hard Soft
PCBA's because they ceramic units is /AR/AP
SMT (UOM) (USD/ (USD/
(USD/
Standard work for water
run in big lots once per developed. month) month)
month) spider
week.
Customer # of CO 0.16 5 3025% 1900
Implementation Start Date
9-Feb-09
Motorola CO Time 100% Implementation Plan
90 4 96% 17800
( Min) 9-Jun-09
Tools Used Goals X Lead-Time x 1/2
Potential Savings/Month
X Lean Defect x1/10 Energy x 9/10 after 100% Implementation
Inventory /
Inventory x1/2 Scrap x1/10 Hard Soft
Six AR/AP
Sigma Productivity x2 Space x1/2 US$XXK US$19.7K US$XXK
Site Yokoten
Implementation Status:
Guide: 81% ~ 100%
Changeover
32 32
GBE-KPO-2-023-00 Rev. 06
Lean in Operations – Productivity Best Practice
Release 8-17
Source : SGA
Site Name: Nanjing
% Improved
Before
long because the setup squeegee with 2 slots and Inventory
After
Metrics Hard Soft
require 4 screws . fixed 2 permanent screws on /AR/AP
SMT (UOM) (USD/ (USD/
(USD/ Standard work
2) 1st internal C/O was the squeegee to be locked in to month) month)
month)
reduce by using magnet the base and prevent drop of
for quick change over. during operation.
Customer However during 2) The locking is further
CO Time
26 10 62% 66
( Sec) Implementation Start Date
operation, the squeegee strengthen with the magnetic
9-May-09
Alcatel drop ( average 7X per effect between the base and
Drop Times 100% Implementation Plan
hour) squeegee . 7 0 100% 240
(Times/Hr) 9-Jun-09
Tools Used Goals X Lead-Time x 1/2
Potential Savings/Month
X Lean X Defect x1/10 Energy x 9/10 after 100% Implementation
Inventory /
Inventory x1/2 Scrap x1/10 Hard Soft
Six AR/AP
Sigma X Productivity x2 Space x1/2 US$XXK US$0.3K US$XXK
Changeover Time
Basic steps in a changeover activity Average proportion of time
Preparation activities 30%
Mounting and removing tasks 5%
Measurements, settings, and calibration 15%
Trial Run (Sample), test, adjust activities 50%
Changeover
34
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
How it Works
Step 2: Separate
Internal and External
Externals Internals Run
Tasks
Step 4: Streamline
Internal and External
Externals Internals Run
Tasks
Externals Internals Run
Changeover
35
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 5: Standardize and Document the Procedure
Changeover
36
GBE-KPO-2-023-00 Rev. 06
Systematic Approach to Quick Changeover
Step 5: Standardize and Document the Procedure
The standardization step should include tracking the performance of the fast changeover
program to ensure that the new process generates the expected performance output.
USE TARGETS TO MAINTAIN AND IMPROVE THE RESULTS OF THE WORKSHOP
Target
Average
May changeover times for Line 23
Minutes
70 Targets must
60
Analysis address the
changeover time
50 and the man-hours
First trial
40
per changeover to
Second trial Target ensure that the
30 expected benefits
are being realized.
20
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Day
Changeover
37
GBE-KPO-2-023-00 Rev. 06
Quick Changeover Rules
• Always remember that the rapid changeover begins and ends with the 5S concept.
• Never forget that bolts are our ‘Enemies’. Eliminate or turn them less than once.
• Eliminate walking.
• Keep in mind standards are standard, and they are NOT flexible.
Changeover
38
GBE-KPO-2-023-00 Rev. 06
Quick Changeover Mind Set
Most improvements involve common sense and changes in our basic attitudes.
Changeover
39
GBE-KPO-2-023-00 Rev. 06
Avoid the Large Batch Vicious Cycle
Changeover Takes
a Long Time
Don’t Changeover
Often
Changeover
40
GBE-KPO-2-023-00 Rev. 06
Lean Mentality
Inventory does not add value so the physical space it occupies is a waste.
Inventory requires extra pallets and racks, manpower to track, count, transport and store.
Large lots create long lead times.
Waste is generated from obsolete inventory accumulated due to inaccurate order forecasting.
Large lots drive higher scrap and rework rates.
Standardized changeovers improve safety through job simplification and standardization.
Changeover
41
GBE-KPO-2-023-00 Rev. 06
External Activities from Flextronics Operations
External activity includes all tasks that can be done before or after setting up the machine, without impacting the current
operations or stopping the machine. Examples from our manufacturing are as below.
Bending Machine
Nurse
Doctor
PCBA bottom support foam is used in the Injection mold heating time is reduced by partially
chip placement machine to eliminate the pre-heating the mold outside the machine. Common test platform provides avenue for
relocation of the support pin. multi-model testing.
Goal is to convert internal steps into external steps and reduce both
Changeover
42
GBE-KPO-2-023-00 Rev. 06
Quick Changeover Benefits
Quick changeover allows production in smaller batches to enable just-in-time (JIT)
manufacturing and faster feedback on quality.
Changeover
43
GBE-KPO-2-023-00 Rev. 06
Quick Changeover and its Impact to Operations
Successful implementation and sustained quick changeover in a factory provides multiple benefits to
manufacturing. Here are the examples from the various business processes.
Changeover
44
GBE-KPO-2-023-00 Rev. 06
Quick Changeover and its Impact to OEE
• OEE evaluates and indicates how effectively the manufacturing equipment is performing.
• OEE performance is categorized into three measurable components:
Availability
Performance
Quality
Quick changeover is a key contributor to improve availability.
Changeover
45
GBE-KPO-2-023-00 Rev. 06
Ideas for Improvement
Step 4: Streamline Internal and External Tasks
Ideas for Improvements
Seeking for solution: Key-holes “Only the last turn tightens a nut or bolt, and the first one loosens
it”.
Fasten
here
Changeover
47
GBE-KPO-2-023-00 Rev. 06
Ideas for Improvements
Seeking for solution: Dies are of different heights, and the operators have to change the
clamping bolts.
Shim the If centre height Shim and cassette-type holders with a fixed-
smaller die to of the tool is position holder on the machine
equalize the important,
height shim top and
bottom
Changeover
48
GBE-KPO-2-023-00 Rev. 06
Ideas for Improvements
Recommended solutions to increase the changeover efficiency by reducing both internal
and external time.
Power tool is used to reduce the tightening and Digital display is used to eliminate the
removal time adjustment.
Shadow board is used to eliminate searching Scale and pointer are used to eliminate
adjustment.
Changeover
49
GBE-KPO-2-023-00 Rev. 06
Thank you