DETAILED ESTIMATION OF ROAD WORKS

Project Name: Improvement of Kazipet/Warangal Junction at Km 123+250 of NH-163 in the state of Telangana.

SL. Most Spn


Description of work No. Length Width Depth Qty Unit
No. No.
1 Dismantling Items
Dismantling of Drain- Walls 0 580 0.15 1.00 0.00 Cum
Dismantling of Drain- Slab 0 580 1.20 0.15 0.00 Cum

Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including
cutting and loading in tippers, trimming bottom and side slopes, in accordance with
2 301
requirements of lines, grades and cross sections, and transporting to the embankment location
within all lifts and lead upto 1000m)
SR_Quantity Sheet Attached 986.00
Roundabout 1 1725.00 0.80 1380.00
Total Quantity 2366.00 Cum
Construction of Embankment with approved material obtained from borrow pits with all lifts
3 305 and leads, transporting to site, spreading, grading to required slope and compacting to meet
requirement of table 300-2
SR_Quantity Sheet Attached 71.00
Total Quantity 71.00 Cum

Construction of Sub-Grade with approved material obtained from barrow pits with all lifts &
leads, transporting to site, spreading, grading to required slopes and compacted to meet
requirements of table No.300-2 in layers not exceeding 250mm thick and compacting to it by
mechanical means after adding water to its OMC, so as to achieve 97% compaction of
4
maximum dry density and finish the surface to the required camber, grade and cross section
etc., spreading by dozer, grading by motor grader, consolidation by vibratory road roller and
carriage by tipper complete within a lead 1km, all lifts, loading unloading, all labour, hire
charges of machinery etc., complete
SR_Quantity Sheet Attached 123.00
Roundabout 1 1725.00 0.50 862.50
Total Quantity 986.00 Cum
Construction of Cement Treated Sub Base by providing coarse graded material, spreading in
uniform layers with motor grader on prepared surface, mixing by mix in place method with
5
rotator at OMC, and compacting with vibratory roller to achieve the desired density, complete
as per clause 401.
SR_Quantity Sheet Attached 284.00
Roundabout 1 1725.00 0.15 258.75
Total Quantity 543.00 Cum
Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam
specification including premixing the Material with water at OMC in mechanical mix plant
6 carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base /
base course on well prepared surface and compacting with vibratory roller to achieve the
desired density.
SR_Quantity Sheet Attached 190.00
Roundabout 1 1725.00 0.10 172.50
Total Quantity 363.00 Cum
SL. Most Spn
Description of work No. Length Width Depth Qty Unit
No. No.
Providing and applying primer coat with bitumen emulsion on prepared surface of granular
7 Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using
mechanical means.
SR_Quantity Sheet Attached 2610.00
Roundabout 1 1275.00 1275.00
Total Quantity 3885.00 Sqm
Providing and applying tack coat with bitumen emulsion at the rate of 0.20 kg per sqm on the
8
prepared Bituminour surface cleaned with mechanical broom.
on granular surface- SR 2610.00
Roundabout 1 1275.00 1275.00
Below VUP - Overlaying for Profile Correction 1 1000.00 1000.00
Total Quantity 4885.00 Sqm

Providing and laying Bituminous Concrete with 100-120 TPH type hot mix plant using crushed
aggregates of specified grading, premixed with bituminous binder CRMB 55 grade @ 5.4per
9 cent of mix and filler, transporting the hot mix to work site, laying manually and rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per
MORTH specification clause No. 507 complete in all respects 5th revision

SR_Quantity Sheet Attached 131.00


Roundabout 1 1275.00 0.05 63.75
Below VUP - Overlaying for Profile Correction 1 1000.00 0.05 50.00
Total Quantity 245.00 Cum
Cast in Situ Cement Concrete M20 Kerb Construction of cement concrete kerb with top and
bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade PCC on M-10 grade
10 foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone
laid with kerb laying machine, foundation concrete laid manually, all complete as per clause
408
Separator-1 in between MCW & SR 1 100.00 100.00
Separator-2 in between MCW & SR 1 85.00 85.00
Roundabout 2 75.00 150.00
Island-1 1 20.00 20.00
Island-2 1 20.00 20.00
Total Quantity 375.00 Rmt
Construction of Median and Island with Soil Taken from Borrow Areas (Construction of median
11 and Island above road level with approved material brought from borrow pits, spread, sloped
and compacted as per clause 407)
Separator filling-1 1 500.00 0.400 200.00
Separator filling-2 1 650.00 0.400 260.00
Roundabout 1 450.00 0.650 293.00
Island-1 1 15.00 0.400 6.00
Island-2 1 15.00 0.400 6.00
Total Quantity 765.00 Cum