Professional Documents
Culture Documents
o Vendor Drawing
o Foundation Drawing
o Equipment details
Page 1 of 21
o Low-height rampack jacks
o Chain block
o Vendor-supplied tools, if any
o Rubber mallet
Preparatory Works:
Tools and equipment shall be made operational and available for use.
Ensure tools are color-coded accordingly.
Foundation Preparation:
Page 2 of 21
o After receiving foundation release note, the following points shall be
checked with the latest relevant drawing.
• Distinct position (centre) marking and height (level) marking on the
foundation, It will be referred for alignment work of level and position.
• Size and number of anchor bolt and nuts, position of anchor bolts with
projection.
• Existence of damages and rust of threaded of buried anchor bolts with
projection.
Padding:
o Pads and liners shall be machined flat parallel and larger than the foot
of base frame.
o Pads material shall be in accordance with ASTM A283 Gr. C, D
or equivalent.
Page 3 of 21
o Pad shall be hot dip galvanized in accordance with ASTM A123 or
coated with zinc rich epoxy primer in APCS-1C of SAES-H-101V as
applicable.
o In general, the distance between pads shall not exceed 800mm. If
the distance becomes more than 800mm, an additional pad shall be
added in
between.
o Pad size shall be selected as per the anchor bolt size as follows:
• Bolt diameter M24 or 1 inch and below Pad width 50mm
• Bolt diameter M30-M48 or 1-1/4 to 2 inches Pad width 75mm
• Bolts diameter M56 or 2-1/4 inches and above Pad width 100mm
Setting of Liner
Page 4 of 21
o Prior to the installation of liners and equipment, the liners and
grouting portion of foundation shall be chipped and all concrete laitance
shall be
removed from portion.
o Flat liners shall be installed at the designated position with pads
of cement grout at least seven days before equipment installation. ln
case non-shrink grout material is used; the curing duration shall be
according to the manufacture’s recommendation.
o In case that wedges liners are used the level of padding with a flat
liners need to be adjust to meet with the final equipment elevation.
o Equipment supports are provided with stainless steel (AISI
Standard Type 300) shims minimum 3mm thickness:
• The maximum shim stack height shall not exceed 12 mm thick
• Only one 3 mm (0.125 in.) or thicker shim per mounting foot
is allowed.
• All shims are to straddle hold down bolts and jackscrews.
• Maximum number of shims under any equipment support foot is five
o All mounting surfaces that are not to be grouted shall be coated with
a rust preventive immediately after machining.
o Mounting plates shall not be drilled for equipment to be mounted by
others.
o Anchor bolts shall not be used to fasten drive equipment to the mounting
plates.
o Diametrical clearance between anchor bolts and the anchor bolt holes in
the mounting plates shall be a minimum of 6 mm (1/4 in.)
Page 5 of 21
• Compressor skid, Compressor, Cylinder Heads & other
major components are free from any physical damage.
• All components of the system such as relief valves and control valves
shall be identified with a permanently affixed corrosion resistant tag
showing the component identification number referenced to the piping
and instrument diagram.
• Rotation arrows shall be cast in or attached to each major item.
o Prepare lifting location were the crane will be located and position.
o Prepare and set all rigging accessories according to arrangement.
o Checked wind condition, lift shall not proceed when wind velocity
is greater than required of crane.
o Stabilized ground areas where crane will be located and
positioned. Crane mats shall be provided in accordance to findings of soil
bearing
pressure.
o Crane lift & rigging requirement shall refer to approved document.
o The equipment shall be lifted by lifting lugs, lifting trunnion, tailing lugs
or shell not by nozzles.
o Equipments shall be protected by wooden blocks, rubber or
other suitable material that will prevent equipment from damages
caused by sling wire.
o Install reciprocating compressors on top of the foundation as
per approved lifting plan.
o Equipment shall be set and aligned at the proper position,
elevation, levelness and perpendicularity in accordance’s with the
drawing.
Centering of Compressor:
Page 6 of 21
d. Sliding surface of cross guide
e. Measure with precision level, thickness gauge, straight edge, etc.
f. Confirm the setting position with bob weight on the basis of black line of
axial and cylinder centerline on foundation.
g. Measuring time shall be done before and after grouting.
In taking the measured record, the indication (+) and (-) of crankshaft
deflection is marked as follows:
Page 7 of 21
Normally deflection gauge is fitted at one half of journal diameter, but
the cap of connecting rod will be touch the gauge at the time of
measurement so it is
In this case,
Page 8 of 21
0 Leveling of crankcase (before anchor bolt grouting).
0 After grouting (after anchor bolts tightening).
Page 9 of 21
• Depending on result of the measurement, confirm level of crosshead
guide and cylinder installed.
• Measuring Method
Page 10 of 21
Setting of Cylinder Support
0 Install lower support to upper support with connection bolts for these
supports as shown in refer to chart below. “Upper and lower supports for
cylinder”.
0 Lift lower support until connection bolts touch to upper side of bolt
holes of upper support. At this time, the bolt hole between upper and
lower support becomes as shown in refer to chart below. “Upper and
lower supports for cylinder”.
0 Fasten connection bolt between upper and lower support with torque
wrench.
Page 11 of 21
o Adjust level of cylinder with small jack. Carry out grouting for lower
support of cylinder.
Grouting
o Non-Shrink Grout. Following items shall be consider before
grouting execution:
o Prior to grouting, concrete repair have been performed in accordance
with SAIC-Q-1062 as based on SAER-5803.
o Grout shall be mixed as per the Grout Manufacturer’s instructions.
o Foundation preparation shall be in accordance with the grout
manufacturers written instruction.
• Concrete foundations shall be cured for a minimum of 7 days before
surface preparations for grouting.
• Laitance, oil-soaked or damaged concrete shall be removed down to
sound concrete by chipping to the level of sound fractured aggregate or
to a minimum of the top 1 inch (25mm) of the concrete.
• All dust and loose particles shall be removed with clean, dry, oil free
compressed air.
• Grout Formwork, where required, shall be constructed with adequate
strength, rigidity and required dimensions to permit grout placement
and avoid leakage.
Page 12 of 21
• A bond breaker shall be applied to the formwork that will be in contact
with the grout.
• After cleaning, the foundation shall be protected with
0.15mm polyethylene sheeting to prevent contamination.
• Concrete surfaces in contact with the grout shall be saturated with
clean water before grout placement. The surface shall be damp but free
from standing water.
• Joints in the grout shall be located as shown in the drawings or
as recommended by the manufacturer.
• Grout shall be placed in only one direction to prevent trapping
air; Grouting shall be quick and continuous to avoid
segregation, bleeding or premature initial set.
• Re-tempering of grout by adding water after stiffening is not permitted.
• If the grout is placed through grout holes, it shall be placed from one
hole continuously until the grout has passed a second hole. A liquid head
pressure shall be maintained at the first access hole until a head pressure
is established at the second hole and continued in a similar fashion until
the next hole.
• Grout shall be mixed, placed and cured in accordance
with manufacturer’s written requirements. The contractor shall
read, understand and comply with the manufacturer’s instructions
as printed on each unit.
• The grout shall be cut back to the lower edge of the base plate by 45°
angle unless otherwise indicated.
Page 13 of 21
o Form joints and interface between forms and concrete foundation are
sealed with grout manufacturer’s recommended sealant.
o Maximum depth of pour and length to width ratio shall be as
per manufacture’s recommendations.
o Elevation of the formworks shall be check to ensure that the top surface
of the grout will match the elevation shown on the construction
drawings.
o Three coats of paste wax shall be applied to the inside surface of forms or
other manufacturer recommended procedure for preventing bonding of
the epoxy grout to the formwork.
o Suitable shelter or enclosures shall be provided to protect the foundation
and base plate from direct sunlight, dew, rain or other inclement
weather. During cold weather, adequate enclosure and heating shall be
provided to maintain foundation and base plate temperature with
acceptable range specified by the grout
manufacturer.
o Expansion joints in epoxy grout shall be spaced at a maximum of 48
inches (1.4 m) unless otherwise specified in the contract documents.
o Expansion joints shall be made from closed-cell neoprene
or polyethylene foam board, having a minimum thickness of 1 inch (25
mm) unless otherwise noted in the contract documents.
o Expansion joints shall be fixed into position to prevent movement and
shall be sealed at formwork and at the concrete base to prevent epoxy
grout from passing around or underneath the joint during placement.
• All mounting plate/soleplate outside corners shall have a minimum of
50mm radius to prevent cracking of the foundation grout due to stress
concentration at the corners.
• Baseplate leveling jack screws shall be provided with stainless steel
leveling pads.
• Mounting plate jackscrews shall be liberally coated with paste wax or
grease to prevent grout adherence.
• Mounting plate jackscrews shall be liberally coated with paste wax or
grease to prevent grout adherence.
• Suitable shelter or enclosures shall be provided to protect the grouted
foundations from direct sunlight and weather.
• Foundation and base plate temperature are within the acceptable range
specified by the grout manufacturer until the grout has cured.
Page 14 of 21
voids shall be filled according to epoxy grout
manufacturer’s recommendations.
• After the void grout has cured, the base plate shall be recheck to ensure
that all voids are filled with grout. Any voids still exist shall be rectified.
• Exposed expansion joints shall be sealed with the epoxy
grout manufacturer’s recommended sealant.
The final level of the epoxy grout is flush with the top horizontal chamfer
edges built into the formwork.
Page 15 of 21
• Level of driver unit shall be confirmed at the same time.
0 Level of driver unit shall be measured at the machined surface of base
plate of motor by using the sprit level.
0 Level shall be confirmed in parallel direction and right angle direction
of shaft.
• Temporary alignment of main motor shall be confirmed before setting
anchor bolts.
0 Temporary alignment shall be done according to tolerance at final
alignment.
0 Tolerance at final alignment.
o Eccentricity of coupling is within 10/100 mm.
0 Parallel ness of coupling is within 5/100 mm.
0 Leveling of driver unit is within 30/100 mm.
0 The dropping value of crankshaft coupling by putting flywheel should
be considered.
Page 16 of 21
0 Parallelness of coupling within 5/100mm
• After 2nd alignment, motor base plate shall be grouted.
• After confirming the final alignment and connecting the coupling of
main motor and compressor deflection of crankshaft shall be confirmed
within standard value. Standard clearance shall be referred to
“Installation Record”.
Setting of Flywheel
• Preparation for Flywheel Setting
° Cleaning of the setting surface of flywheel on crankshaft coupling, main
motor coupling, and the bolt holes.
° Cleaning of flywheel surface (both sides) and the bolt holes.
0 Before sliding of main motor, confirm the electrical personnel to
protect for main motor is necessary or not. If necessary, appropriate
electrical protection to be carried out.
0 Remove LO in plugs of bearing housing, and fill in LO with appropriate
quantity.
0 Make match marks for relative position (at four corners of main
motor) between main motor and sole plate by using center punch and
steel compass. So it is easy to install the main motor at regular position
for restoration.
0 Set the dial gauges at main motor front and rear, left and right side
(total 4 points) on the main motor base plate.)
0 Remove all of shims between main motor and sole plate to avoid the
Page 17 of 21
damage during motor sliding work. Make clear identification for
mounting positions of shims before removing.
0 Slide main motor around 25mm to anti coupling side, which is relative
amount between end plate of main motor and crankshaft coupling to set
the flywheel.
° Fix main motor with jack-bolts in front and rear, and left and right
corner not to move main motor.
• Setting of Flywheel.
0 Lift up the flywheel again to return the vertical and horizontal amount
of dial gauges “zero” position. Refer to attached sample picture.
0 After tightening bolts with hydraulic pressure, tighten the lock nuts of
coupling bolts.
0 After tightening lock nuts, measure deflection of crankshaft. Measure
upper clearance of guide bearing and main bearing with thickness gauge,
and confirm any no irregular contact.
Page 19 of 21
the foundation.
• Fitting of the suction pulsation suppressor.
°ଶ Clean the packing seat of connecting flange and
the cylinder.
0 Hang up the pulsation suppressor horizontally.
°ଶ Confirm the fitting direction of the pulsation
suppressor with general arrangement drawing.
0 Slowly bring the pulsation suppressor to cylinder connecting part.
0 Slightly tighten the flange on the cylinder and pulsation suppressor
through packing.
°ଶ Fit the support for suction pulsation suppressor under
the pulsation suppressor through adjusting liner. Suspend
the foundation bolt on the support.
a. Measure the clearance between the flange of the pulsation suppressor
and the cylinder in longitudinal and vertical direction of the pulsation
suppressor at four places and adjust the clearance so that the difference
in within 0.1 mm, using small jack provided by MES.
Page 20 of 21
Page 21 of 21