Professional Documents
Culture Documents
Abstract: Norwegian TSO Statnett has selected outdoor insulation for a new ±525 kV
HVDC project, NordLink, between Norway and Germany. Part of this link will be overhead
line close to the Norwegian coast and it was decided to use composite insulators for this
line. In order to verify the pollution and ice performance of the insulators intended for
relatively cold, humid and coastal area a special test program was developed and
included the pollution testing and ice testing.
At present there is no standard IEC pollution test method available for composite
insulators and, especially, for DC applications. The innovative specially-developed
pollution test presented in this paper used the CIGRE-recommended for AC procedure
described in CIGRE TB 555, which comprises the following steps: gentle cleaning of the
insulators, pre-conditioning of the surface by dry kaolin powder and application of the
pollution layer by spraying. While the standard voltage application was used for the
withstand test, the flashover voltage tests were performed in accordance with the Rapid
Flashover Test. This procedure is described only in the draft of coming in 2017 CIGRE
Technical Brochure and earlier was mostly applied for AC insulators. Detailed description
of different practical steps of new procedures applied for DC composite insulators is
presented in the paper.
For the ice test there is also no standard IEC procedure and thus the test was
constructed as a combination of relevant IEEE Standard for ice testing and IEC pollution
test requirements for ceramic insulators. One V-shaped insulation structure with insulator
length of more than 6 m was tested. The glaze type of ice was accreted using a structure
of aluminium beams, mirroring the V-shaped insulator structure, which was hung from the
crane in the climate test hall. Detailed description of different practical steps of new
procedure applied for DC composite insulators is presented in the paper.
The knowledge obtained as a result of the application of innovative pollution and ice tests
is essential for the ongoing discussions within IEEE/CIGRE/IEC.
The goal of this investigation was to develop The basic test procedure complied with the solid
innovative pollution and ice test methods to verify layer test procedure described in the IEC 61245
the applicability of the preliminary chosen insulator [3]. This standard, however, covers only glass and
options for the specific environment. The test ceramic insulators, thus to achieve the pollution
methods should be innovative, because at present application on composite insulators a special pre-
conditioning procedure was applied according to
CIGRE Technical Brochure (TB) 555 [4]. It is
virtually impossible to contaminate composite
insulators without such procedure. It was also
decided to test the insulators without providing
specific recovery time for hydrophobicity (i.e.
elapsed time between the application of pollution
and voltage application). This was rather
conservative approach assuming cold and humid
Norwegian environment. The CIGRE-
Figure 2: Insulator contaminated by spraying
recommended procedure [4] comprises the
method after pre-conditioning by dry kaolin.
following steps: gentle cleaning of the insulators;
pre-conditioning of the surface by dry kaolin
The final actual SDD/NSDD levels were measured
powder; application of the pollution layer (e.g. by
on a large and small sheds and on the sheath of
spraying).
the polluted insulators and then averaged.
Comparison between the target and actual results
Before the contamination the insulators were
is presented in Table 1. The SDD values were fully
thoroughly cleaned by warm water and a sponge,
in correspondence with the target values, while the
Further pre-conditioning was performed by
NSDD values were slightly higher, however within
applying by brush a dry inert material in powder
the acceptable margin (about 25%).
form (in this case kaolin) on the clean and dry
insulator surface, see a close look in Figure 1.
Table 1: Target/actual average pollution levels
This layer was applied as uniformly as possible
taking special care at the transition areas from
Target Actual
sheath to the sheds. After the application, most of Test
SDD/NSDD, SDD, NSDD,
the powder was blown off by compressed air until objects 2 2 2
mg/cm mgcm mgcm
only a very thin layer remained on the insulator
surface. The adequacy of this layer was controlled Short
0,03/0,1-0,2 0,03 0,25
visually. The pre-conditioning temporarily masked insulators
sufficiently the surface hydrophobicity of the
Short
composite insulators allowing their further insulators
0,12/0,1-0,2 0,11 0,24
contamination by spraying (standard method
according to the IEC 61245). The suspension Full-scale
0,10/0,1-0,2 0,10 0,25
comprised a mixture of tap water, kaolin and salt insulators
(NaCl). The amount of salt was chosen to achieve
the target Salt Deposit Density (SDD). The density
of suspension was adjusted for the target value of Flashover voltage tests on shorter insulators tested
Non-soluble Deposit Density (NSDD). The in vertical operating position were performed using
specially prepared suspension was sprayed onto the Rapid Flashover Test method [5], [6]. The
the insulator, see Figure 2. polluted and dried insulators were placed into the
test hall as shown in the set-up presented in
Figure 3. Voltage of negative polarity was applied
at the preliminary chosen starting level and the
insulators were wetted by letting steam fog of
standard intensity according to the IEC 61245 into
the hall.
4 ICE TESTING
Glaze type of ice (transparent ice with The ice was accreted using water with a
3
density 0,7-0,9 g/cm ) conductivity of approximately 100 S/cm, this
value corresponds to the maximum value
Applied water conductivity 100 S/cm measured earlier at Statnett in service [10]. During
the ice application, the air temperature in the test
hall was kept around -8°C. The target ice thickness
Ice load of 12 kg/m (on power line) which
at the standard rotating cylinder was specified as
corresponds to 23 mm thickness at the
23 mm, this was checked using this standard
standard rotating monitoring cylinder.
cylinder exposed to water spray in the same way
as insulators under the test. During the first ice
For each test the complete insulator arrangement
accretion, the time needed to get the required ice
was first subjected to the specified ice conditions,
thickness was defined. At the second and the third
and thereafter subjected to a voltage withstand
ice accretions, both the standard rotating cylinder
test. A special set-up was used for the application
and the estimated time were used to define the
of ice on the V-shaped insulator arrangement; see
duration of the ice accretion phase. Prior to the
front view of set-up in Figure 7. The glaze type of
start of each test, small samples of ice were
ice (clear transparent ice) was accreted using
removed from the insulators. The volume and
water spraying from approximately 1 m distance.
weight were measured by using cold oil in a
To allow for correct positioning of the spray
measuring cylinder and a scale. Some samples
system, a structure of aluminium beams, mirroring
were then thawed and the conductivity was
the V-shaped insulator structure, was hung from
measured when the thawed water had reached the
the crane and supported by the wall of the climate
room temperature.
test hall. The structure carried 4 arrays of fixed
spray nozzles fitted with special heaters for
Example of ice accretion on the insulation structure
temperature control and defrosting. The distance
just before the test is presented in Figure 9. It is
between the nozzles in each array was about 0,5
considered that the ice accretion simulated well the
m, and the complete installation comprised in total
service case, i.e. that the icicles grew downwards,
of 20 nozzles. A schematic drawing of complete
without bridging the shed spacing of the inclined
spay system is in Figure 8.
insulators of the V-string.