Professional Documents
Culture Documents
IPC2022
September 26-30, 2022, Calgary, Alberta, Canada
IPC2022-87129
Urso A. Campos, PhD, PE Jonathan L. Robison, PE Gary W. Castleberry Amin Azimi, PhD, PE
GeoEngineers, Inc. GeoEngineers, Inc. GeoEngineers, Inc. GeoEngineers, Inc.
Cary, North Carolina, USA Springfield, Missouri, USA Springfield, Missouri, USA San Diego, California, USA
ABSTRACT
Direct Pipe® (DP) is an innovative trenchless construction Keywords: Direct Pipe®; settlement; MTBM; tunneling;
method that combines aspects of micro-tunneling and horizontal trenchless; construction; LiDAR.
directional drilling (HDD). In the DP method, ground
excavation and pipeline installation are simultaneous. In this 1. INTRODUCTION
method, the jacking frame in micro-tunneling is replaced with a The Direct Pipe® (DP) equipment and method was
pipe thruster and coupling is eliminated. Additionally, reaming developed by Herrenknecht, AG, in Germany in the early 2000s,
the bore hole, which is common with the HDD method, is and the first DP was completed in Germany in 2007. From a
eliminated. The DP method of construction is typically applied practical standpoint, DP is most often compared to the longer-
when subsurface conditions beneath a surficial obstacle are not established method of horizontal directional drilling (HDD), as
conducive for the HDD method of construction due to final hole both methods install pre-fabricated steel pipe in curved sections.
diameter, granular soils, and/or high risks of hydraulic fracture Because DP uses microtunneling technology to excavate the
leading to inadvertent drilling fluid returns. During tunneling ground in its heading, and the ground is continuously cased
operations, the microtunneling boring machine (MTBM) during the one pass installation, the method is capable of
excavates a space or tunnel that is typically a few to several handling ground conditions (such as gravels, cobbles, and
centimeters larger in radius than the jacking pipe; which is weathered bedrock). Finally, compared to conventional
thrust into place continuously behind the TBM. This overcut microtunneling which typically requires shored excavations, DP
annular space and the potential, occasional temporary can launch and exit at or near the ground surface as it is routinely
extraction of the MTBM and jacking pipe represent settlement installed in one or more curved sections.
risks during construction. For this reason, the pipeline
construction team should consider assessing settlement risks Figure 1 depicts a Herrenknecht 750 PT Pipe Thruster and a
associated with DP construction, and subsequently prepare and 42-inch (1,066-mm) Herrenknecht AVN800XC micro-tunneling
deploy a settlement monitoring plan during the pipeline boring machine (MTBM) welded to the leading end of a 42-inch-
construction phase, particularly where the proposed DP diameter sacrificial pipe.
alignment will cross railroad, highway, and/or other sensitive
features that may be adversely affected by settlement. This paper
presents an adopted settlement risk assessment and monitoring
plan for a recent trenchless crossing where the DP method of
construction was utilized to install a pipeline section beneath two
major interstates and a railroad outside of Washington D.C.,
United States. The paper also includes a Finite Element Analysis
(FEA) using Plaxis software with the purpose of exploring the
time variable in settlement analysis. Furthermore, the paper
expands on the planning characteristics of settlement monitoring
utilized during construction, which consisted of conventional
surveying and vehicle-mounted LiDAR scanning.
1 © 2022 by ASME
Groundwater was not observed during the subsurface
explorations. Additionally, lenses of fine-grained materials, like
clays and silts, interbedded within coarser grain materials can
create low permeability regions that are capable of storing
groundwater as a perched water table. As a result of these and
many other factors, groundwater elevations may vary before and
during construction.
2 © 2022 by ASME
was made between the daily measurements and the control
baseline measurement to evaluate changes in elevation at each The additional survey deliverable consisted of surface
benchmark. subsidence monitoring along the alignment using a Trimble
MX9 Mobil LiDAR system. The monitoring program consisted
In addition to the conventional monitoring program, a sensor- in driving the referenced equipment over the alignment once a
mounted drone was utilized to monitor the surface along the Path day, six days a week. Figure 3 shows capture points, defined for
A alignment. The mobile lidar data was collected via truck the monitoring program, along the monitored major interstate.
mounted LiDAR equipment. The truck drove the highway lanes
once a day, usually in the middle of the night when traffic Similar capture points were defined for an adjacent monitored
volume was low. major interstate, and any on/off ramps that were above the
alignment. Similar to the conventional reports, the LiDAR
2.1 Deliverables survey indicated that there were no settlement occurrences along
The conventional surveying delivery consisted in a the tunnel alignment. It is noteworthy that the LiDAR detected
tabulation delivery comparing the original elevation of the small changes on surfaces after storm events. These detections
monuments along the tunnel alignment. There were no visible were triggered by minor erosion and soil displacement due to
indications of settlement during the project and after completion. excess runoff water on surfaces. Furthermore, LiDAR detected
Figure 2 shows a typical deliverable documenting daily survey small changes in elevation due to ongoing asphalt regrading in
elevation measurement, via conventional survey, of critical some of the surveyed lanes.
points along the tunnel alignment.
3 © 2022 by ASME
3. FINITE ELEMENT ANALYSIS IN PLAXIS 4. CONCLUSIONS
The loading conditions considered in our PLAXIS analyses The initial analytical settlement conducted prior to construction
is the short-term condition that occurs immediately after the indicated a potential settlement of up to 2 inches (50.8 mm) if
tunneling is complete and assumes that the MTBM was extracted the MTBM were to be extracted during construction. The
during construction. Figure 4 shows the two-dimensional soil PLAXIS model predicted a total settlement of 0.2 inches (5 mm)
model developed in PLAXIS for the critical section along the if the MTBM were to be extracted during construction. One of
monitored major interstate. The static groundwater was modeled the limitations of the analytical settlement calculation is that it
below the tunnel, as there were no indications of groundwater at can only account for one soil unit, thereby the softer soil unit
the time of subsurface explorations (as discussed in Section 1.1). (clay) was considered for the analysis, resulting in a very
conservative result.
ACKNOWLEDGEMENTS
We would like to thank Dominion Energy Transmission Inc.
for allowing us to share this project with the IPC community. We
would like to also commend Donnie Smith for all the long hours
dedicated to the project performing Construction Observation
activities at the site.
FIGURE 4: TWO-DIMENSIONALSOIL MODEL DEVELOPED
IN PLAXIS REFERENCES
[1] Drake, A.A., Jr., and Froelich, A.J. Geologic map of the
The model consisted of the paved surface of the monitored major Falls Church quadrangle, Fairfax and Arlington Counties and
interstate (dark blue surface), a medium stiff lean clay layer the City of Falls Church, Virginia, and Montgomery County,
(yellow), a very stiff to hard silt layer (light blue), and bedrock Maryland, U.S. Geological Survey, Geologic Quadrangle Map
(green). The soil properties were obtained from a geotechnical GQ-1734 [1 sheet], Scale 1:24,000, 2017.
boring drilled approximately 200 feet (61 m) from the centerline
of the monitored major interstate.
4 © 2022 by ASME