Professional Documents
Culture Documents
Certified by:
NOTES : * If the thesis is CONFIDENTIAL or RESTRICTED, please attach with the letter from
the organisation with period and reasons for confidentiality or restriction.
“I hereby declare that I have read this project report and in my
opinion this report is sufficient in terms of scope and quality for the award of the
degree of Master of Engineering (Civil-Geotechnics)”
Signature : ....................................................
Name of Supervisor : PROF. DR. AMINATON BT. MARTO
Date : NOVEMBER 2009
PERFORMANCE OF FULL SCALE EMBANKMENT ON SOFT CLAY
REINFORCED WITH BAMBOO-GEOTEXTILE COMPOSITE AT THE
INTERFACE
November 2009
ii
I declare that this project report entitled “Performance of Full Scale Embankment on
Soft Clay Reinforced with Bamboo-Geotextile Composite at the Interface” is the
result of my own work except as cited in the references. The report has not been
accepted for any degree and is not concurrently submitted in candidature of any other
degree.
Signature : ……………………………
Name : HASNITA BT. HIRMAN
Date : 20 NOV 2009
iii
Dedication
To my beloved mother (Hjh. Latifa Bt. Jalil), my sisters (Haslinda Bt. Hirman,
Hasniza Bt. Hirman, Siti Nadia Bt. Hirman) and my brother (Muhammad Haikal B.
Hirman). Thanks for all your love and supports.
iv
ACKNOWLEDGEMENT
First and foremost I would like to show the most gratitude to Allah S.W.T the
most gracious and merciful for giving me a good health physically, mentally and
spiritually that enable me to complete this master project successfully on time.
ABSTRACT
ABSTRAK
Tambakan jalan dan pembinaan lain di atas lapisan tanah liat lembut masih
menjadi cabaran dalam kejuruteraan geoteknik. Pembinaan sesuatu struktur di atas
tanah liat lembut menjadi lebih penting kerana kawasan bandar di seluruh dunia telah
menjadi lebih padat. Oleh sebab itu, kajian untuk meningkatkan keupayaan galas
tanah ini dijalankan dengan menggunakan tetulang komposit buluh-geotekstil (BGC)
untuk menguatkan tanah. Selain tambakan dengan tetulang BGC, tambakan kawalan,
yang dibina tanpa tetulang pada tanah liat lembut juga dibina untuk memenuhi
objektif kajian ini. Ketinggian akhir tambakan untuk tambakan yang diperkuatkan
oleh BGC adalah 2.97m dan tambakan kawalan adalah sebanyak 3.071m. Tambakan
berskala penuh dibina lengkap bersama dengan instrumen geoteknikal yang bersaiz
16m lebar tapak, 10m panjang dan 1V:2H cerun sisi. Kajian ini adalah bertujuan
untuk menganalisa prestasi tambakan BGC berbanding tambakan kawalan selama
lebih kurang 3 bulan selepas pembinaan tambakan. Semasa fasa pembinaan,
tambakan yang diperkuatkan oleh BGC telah terenap sebanyak 0.26m dan 0.33m
pengenapan berlaku untuk tambakan kawalan, dan ini telah menyebabkan berlakunya
pergerakan sisi pada kedalaman 3.5m adalah 2.63mm dan 4.88mm pada kedalaman
4m, masing-masing bagi tambakan dengan BGC dan tambakan kawalan. Hal ini
dipercayai disebabkan oleh beban tambakan yang dikenakan kepada tanah liat telah
dipegang kuat oleh tetulang BGC, dengan itu dapat mengurangkan enapan dari
berlaku. Di dalam fasa enapan pengukuhan, sebanyak 0.204m dan 0.201m enapan
telah berlaku selepas 103 hari dari pembinaan tambakan masing-masing pada
tambakan dengan tetulang BGC dan tambakan kawalan. Ini menunjukkan bahawa
kadar pengukuhan yang berlaku adalah lebih kurang sama diantara kedua-dua
tambkan. Pada ketinggian akhir tambakan, lebihan tekanan air liang pada tambakan
dengan tetulang BGC adalah 20.98kPa tetapi berkurangan kepada 9.86kPa selepas
103 hari. Bagi tambakan kawalan pula, lebihan tekanan air liang adalah sebanyak
23.47kPa tetapi berkurangan kepada 11.15kPa pada masa yang sama. Dapat
diperkatakan bahawa berlakunya deformasi yang rendah dengan menggabungkan
geotekstil dan buluh, berbanding dengan hanya menggunakan geotekstil sahaja
sebagai pemisah. Oleh kerana itu, tetulang BGC dipercayai mempunyai potensi yang
besar untuk digunakan sebagai bahan penguat dalam tanah liat. Hal ini disebabkan
oleh berlakunya pengurungan tanah daripada penyusunan buluh berbentuk
segiempat. Penyusunan buluh seperti ini dapat mengurung tanah secara lateral dalam
dua arah dan membentuk pasakan atau ‘kocek’ bagi meningkatkan kekakuan buluh.
Tetulang ini berfungsi untuk menyebarkan tekanan menegak secara rata dan
meminimumkan enapan serta-merta. Oleh kerana itu, tetulang BGC dipercayai
mempunyai potensi yang besar untuk digunakan sebagai bahan penguat dalam tanah
liat. Produk akhir dari projek ini boleh menjadi skala ekonomi terhadap pengurangan
kos pembinaan tambakan, khususnya ketika menggunakan bahan-bahan yang boleh
diperolehi secara tempatan.
vii
TABLE OF CONTENTS
1 INTRODUCTION 1
1.1 Background 1
1.2 Problem Statement 2
1.3 Objective of Study 3
1.4 Scope and Limitation of Study 3
1.5 Significant of Study 7
2 LITERATURE REVIEW 8
2.1 Introduction 8
2.2 Soft Soil 8
2.2.1 Soil Classification 8
2.2.2 Characteristic of Clay Soil 9
2.2.3 Problem of Clay Soil 10
2.3 Bamboo 12
viii
3 METHODOLOGY 35
3.1 Introduction 35
3.2 Literature Search 37
3.3 Site Construction Work 37
3.3.1 Site Clearing 37
3.3.2 Installation of Instrumentation 38
3.3.3 Installation of Reinforcement Material 39
3.3.4 Construction of Trial Embankment 40
3.3.5 Data Monitoring and Analysis 40
3.4 Laboratory Work 42
3.4.1 Soil Sample Collection 42
3.4.2 Material Selection 43
3.4.3 Determination of Engineering Properties 43
3.4.4 Soil Testing 43
3.4.4.1 Dry Sieve 45
3.4.4.2 Hydrometer Analysis 45
ix
REFERENCES 90
APPENDICES 94
xi
LIST OF TABLES
LIST OF FIGURES
LIST OF SYMBOLS
sm : Maximum settlement
sr : Maximum reconsolidation settlement
su : Undrained shearing settlement
Sd : Standard deviation
Su : Undrained shear strength
wL : Liquid Limit
wP : Plastic Limit
xn : Bending strength of individual samples
ym : Maximum horizontal displacement
ymr : Reconsolidation horizontal displacement
ymu : Horizontal displacement due to undrained shearing
y : Lateral deformation at any depth, z
z : Depth of any point
B : Pore pressure coefficient
B1 : Observed initial pore pressure response
x : Average value of bending strength obtained from all samples
σvo’ : Initial effective stress
σp : Pre-Consolidation pressure
σt : Tensile strength
σc : Bending strength
∆u : Change in pore pressure
∆σv : Change in stress
γd : Dry unit weight
γr : Saturated unit weight
δ : Deflection under the point load
ε : Strain
φu : Undrained angle of shearing resistance
xviii
LIST OF APPENDICES
INTRODUCTION
1.1 Background
the bamboo. Based on the bamboo’s strength, along with its flexibility, toughness,
lightweightness and economical advantage makes it an exceptional construction
material.
The full scale trial embankments had been constructed at Research Centre of
Soft Soil (RECESS), UTHM, Batu Pahat, Johor. This research is lead by Prof. Dr.
Aminaton Marto from Universiti Teknologi Malaysia (UTM) with a Project No.: 03-
4
The scope of this study focuses on the control embankment and embankment
with BGC. Control embankment was constructed on soft soil with a separation
geotextile (TS40) at the interface. While, embankment with BGC was constructed on
5
soft soil reinforced with bamboo and the geotextile (TS40) laid on top of bamboo for
separation purposes. The performances of bamboos and geotextile are monitored by
the strain gauges attached at selected points. This project analyzed the results from
the geotechnical instrumentation already designed by project leader.
Figure 1.1: Layout of trial embankment with the location of boreholes and
instrumentation (plan view)
6
LITERATURE REVIEW
2.1 Introduction
There are circumstances that need to be taken into consideration after the
construction of embankment due to time such as excess pore pressure, settlement,
and lateral movement. There are several factors that contribute on the performance of
full-scale trial embankment such as the types of foundation soils, applied load from
embankment fill and material that will be used as reinforcement. To obtain basic
understanding of this study, literature reviews focuses on three sections which is
classifications of soil, bamboo and embankment.
and it is categorized by very small particle size where the main element is due to
effects of surface chemical. Organic soils are typically spongy, crumbly and
compressible. They are undesirable for use in supporting structures.
Based on simple definition, soils can be divided into component with particle
size is usually given in terms of the equivalent particle diameter (Head, 1992):
i. Gravel – particles from 60 mm to 2 mm
ii. Sand - particles from 2 mm to 0.06 mm
iii. Silt - particles from 0.06 mm to 0.002 mm
iv. Clay – particles (clay mineral) smaller than 0.002 mm
v. Fines are particles which pass a 63 µm sieve
vi. Clay Fraction is the percentage of particles smaller than 2µm, as
determined by a standard sedimentation procedure
Particles forming clay consist of complex minerals which are mostly flat and
plate-like or elongated, and of a size less than 0.002 mm. The most significant
properties of clays are its plasticity and cohesion. Clay soils able to take and retain a
new shape when compressed or moulded (Whitlow, 1995). The size and nature of the
clay mineral particles, together with the nature of the adsorbed layer, controls this
property. Where the average specific surface is high, this plasticity may be extremely
high and the soil extremely compressible.
Clay soils can creep (deform plastically) over time under constant load,
especially when the shear stress is approaching it shear strength, making them prone
10
to landslides. They develop large lateral pressures and have low permeabilities. For
these reasons, clay soils are generally poor materials for retaining wall backfills.
Being impervious, however, they make better core materials for earthen dams and
dikes.
With low permeability, cohesive soils compress much more slowly because
of the expulsion of water from the small soil pores is so slow. Hence, the ultimate
volume decrease of the cohesive soil and associated settlement of a structure built on
this soil may not occur until some time after the structure is loaded.
The parameters are very important in analyzing the behavior of this soil so
that it can carry extra loads subjected to the soils. These nature creatures are widely
found in Malaysia along the coastal plains area and with the increasing economic
development over the soil; studies were carried out to determine the typical values of
the soils that can contribute to the failure of the soil structure.
11
For the soft marine clay in Malaysia, Broms (1990) has reported that typical
moisture contents ranges from 60% to 80%. This is different to what has Ting et al.
(1988) and Chen et al. (2003) reported; where the moisture content is typically about
80% to 130% in Penang area and 50% to 100% in Klang area respectively. Brand et
al. (1989) reported that the Muar clay has the water content as high as 100% and
generally exceeds the liquid limit. It is also very common that the moisture content of
the soft clay especially near to the ground level to be higher than the liquid limit.
The in-situ undrained shear strength, Su of soft clay can be directly measured
using field vane shear test. The Su is generally increasing with depth. Typically the
vane shear test results for clay at Klang areas are about 5kPa at depth 2m to 50kPa at
depth 18m (Chen et al., 2003). This is quite similar to Muar Clay and Juru Clay
where the Su ranges between 10kPa at depth 2m to 35kPa at depth 18m, and 10kPa to
30kPa at depth 12m respectively.
Soil compress elastically under light loads but then as shifts and rearrange to
allow increasing amounts of settlement. This stage of settlement is attributed to
primary consolidation, where the rate of settlement is controlled by the time required
to squeeze the pore water out. The most useful compressibility parameters to monitor
the consolidation process are compression index (Cc), recompression index (Cr) and
coefficient of consolidation (Cv).
The compressibility of the soft layers can also be represented using the
compression ratio (Cc/1+eo). For Juru Trial Embankment, Huat et al., (1995) found
out that the compression ratio is in the region of 0.4 to 0.6 and Ting et al., (1988)
reported that the coastal plain areas of Sarawak and Sabah has the average values of
Cc/1+eo vary within a narrow range from about 0.3 in the upper layers to about 0.1 in
the lower layers. Terzaghi and Peck (1967) proposed an empirical correlation
between Cc and Liquid Limit, wL for clays of low to medium sensitivity and wL up to
100% as follow:
As for clay from Klang areas, Huat et al. (1995) proposed the following relationship
for Klang Clay.
This is because of the sensitivity for Klang Clay is usually range around 3 to 8 and
higher Cc values are expected. Another important parameter is coefficient of
consolidation, Cv where it measure time taken for a soil to consolidate. Values of Cv
are different with types of soft clay. This is proofed by foundation soil found for Juru
Trial Embankment and Muar Trial Embankment, where the Cv varies from 0.3 to 0.4
m2/year (Huat et al., 1995) and Cv values range up to about 14 m2/year
(Balasubramaniam, 1989) respectively. According to Brand et al., (1989), Rowe
1972 stated that laboratory determined Cv value, however, are underestimate the rate
of settlement, since the laboratory permeabilities are much lower than the field values
because of the soil macro-structure. Hence, in common practice for design Cv values
are multiplied by 3 to 10 of those measured in oedometer tests.
2.3 Bamboo
Abang Ali (1984) reported that the external diameter of Malaysian bamboos
ranging from 30mm to 111mm with thickness of wall varies between 3mm to 18 mm.
The properties of a selected Malaysia bamboo species are tabulated in Table 2.2.
According to Wong (1995) the bamboo culms diameter and height are ranging from
60mm to 300mm and varies from 0.3m to 36m respectively. While Liese (1986) (in
Thammicha, 1989) stated that the culm diameter ranges from 20mm to 35mm with
height varies up to 35m. Data on culm size for various species is tabulated in Table
2.3. Dannenmann et al., (2007) made a review of culms from different bamboo
species in Northern Laos, as shown in Table 2.4.
Table 2.1: Number of genera, species and areas of bamboo forests in some countries
(Uchimura, 1977)
Country Genera Species Area (1000 Ha.)
Africa 8 14 -
Bangladesh - - 100
Burma - 42 2000
India 13 136 5000
Indonesia 9 31 50
Japan 14 635 170
Madagascar 9 30 -
Malaysia 8 52 100
New Guinea - 8 -
PR China 26 235 2500
Philippines 12 49 200
Taiwan 21 130 110
Sri Lanka - 10 -
Thailand 10 34 1000
According to Abang Ali (1984), bamboos are the fastest growing and highest-
yielding renewable natural resources in this region. Bamboo generally takes two to
five years to grow to maturity. This growth period is relatively short when compared
to timber which normally requires at least ten years. Abang Ali (1984) found that
there is one Japanese species of bamboo (Phyllostachys bambusoides) that tends to
grow as fast as 1.2 meters per days. While, Malaysian bamboo can have a daily
14
increment of 15cm to 18cm (Aminudin and Abd. Latif, 1991) (in Khatib, 2009). This
culm growth is due to differences during the process of growing, where shoot/sprout
elongation takes place day and night; the bamboo of genus Phyllostachys in Japan
grows more during the day, whereas in the tropical region bamboos grow faster
during the night (Thammicha, 1989).
Bamboo is primarily a type of giant grass with woody stems. The stems are
called “shoots” when the plant is young and “culms” or “stems” when the plant is
mature (Iyer, 2002). Each bamboo plant consists of two parts – the “culm” that grows
above the ground and the underground “rhizome” that bears the roots of the plant, as
shown in Figure 2.1. Bamboo usually grows in a group that called “clump”. Bamboo
growing in a clump adds a new shoot around one central culm thereby increasing the
culm size radially. As stated by Aminudin and Abd. Latif (1991) (in Khatib, 2009),
bamboo might have 40 to 50 culms in one clump, which adds 10 to 20 culms yearly.
Table 2.4: Culm evaluation of different bamboo species (Dannenmann et al., 2007)
Species Height Culm Internode Wall
(m) Diameter Length Thickness
(cm) (cm) (cm)
Bambusa pallida 14-17 3-5 30-60 0.2-0.6
Bambusa tulda 12-14 2-4 45-50 0.4-0.7
Dendrocalamus asper 14-16 4-7 Up to 100 0.4-0.7
Dendrocalamus membranaceus 12-18 3.6-4 30-50 0.3-0.6
Gigantochloa apus 16-18 4.5 40-50 0.1-0.2
16
Figure 2.1: The vegetative part of bamboo (Othman and Malek, 2003)
The amount of moisture in bamboo varies within and between the species,
height and age of the living culm. The moisture content has a similar influence on the
strength of the bamboo as it has in timber. Generally, in the dry condition the
strength is higher than in the green condition. For some Malaysia bamboos, moisture
content is about 30% to 130%. However the density of bamboo varies from about
0.5g/cm3 to 0.9g/cm3 with the outer culm having a far higher density than the inner
17
part. Moisture content and density of selected species of bamboo are tabulated in
Table 2.5.
Table 2.6: Physical properties of six Philippine bamboos (Espiloy et al., 1985)
(in Siopongco and Munandar, 1987)
Scientific Name Moisture Content (%) Specific Gravity
Bambusa blumeana 136 0.503
Bambusa vulgaris 95 0.626
Dendrocalamus latiflorus 108 0.575
Gigantochloa aspera 119 0.547
Gigantochloa levis 117 0.541
Schizostachyum lima 174 0.461
18
The strength of bamboo depends on the species and on its age, moisture
content, density and culm height. The mechanical properties of bamboo vary with the
age of the bamboo and the height of the culm, as mentioned by Chauhan (2000) (in
Li, 2004). However, higher moisture content will decrease the strength of bamboo
(Prawirohatmodjo 1990) (in Lybeer, 2005). The strength of this material also related
to its density. The density of bamboo varies approximately from 0.5 to 0.9 g/cm³ but
can differ considerably within the culm (increase with the height of the culm) and
between species (Siti & Abd. Latif 1992; Jamaludin et al. 1995; Kabir et al. 1996;
Subyakto 1996) (in Lybeer, 2005).
Abang Ali (1984) presented a comparison between bamboo and the more
common engineering materials, as tabulated in Table 2.7. It was found that bamboo
is very strong in tension, with a few species having tensile strength as high as that for
mild steel. The ratio of tensile to compressive strength of bamboo can be as high as
seven times. FRIM (1995) has conducted an experiment on selected Malaysian
bamboo to evaluate the mechanical properties of bamboo, as shown in Table 2.8. The
bending stress at proportional limit was ranged from 21MPa to 49MPa and it shows
the differences in static bending strengths of specimens (Table 2.8). For the three
species of Indonesian bamboos (Gigantochloa apus,Gigantochloa verticillata and
Dendrocalamus asper) where the age of bamboo was more than three years were
tested to assess its mechanical properties and Table 2.9 shows the test results
(Siopongco and Munandar, 1987). It can be seen that bamboo has more strength in
tension compared to bending strength. According to Ghavami (2005), the tensile
19
strength of bamboo is relatively high and can reach 370MPa. This makes bamboo an
attractive alternative to steel in tensile loading applications.
Table 2.7: Typical materials properties of bamboo compared with mild steel,
concrete and timber (Abang Ali, 1984)
Material Ultimate Strength (N/mm2) Tensile-Compressive Modulus of
Tension, Compression, Strength ratio, Elasticity
σt σc σt/σc (kN/mm2)
Mild Steel 480 - 1.0 210
Concrete 2-4 25-55 0.1 10-17
Timber 20-110 50-100 1.1 8-13
Bamboo 180-440 38-65 4.8-7.1 7-20
2.4 Embankment
2.4.1 Introduction
Figure 2.2: Simple construction of embankment over weak soil with reinforcement
(Holtz, 2001)
Bearing capacity is the capacity of soil to support the loads applied to the
ground. Soft foundations supporting embankments may fail in bearing capacity
during or soon after construction when capacity of lay embankment exceed the
23
Figure 2.3: Simple illustration of bearing capacity failures (Ochiai et al, 1996)
Rotational failure also known as circular slip failure. These types of failure
normally occur at the edge of embankment and this is due to the driving forces is
greater than the resisting forces. Rotational slope and/or foundation failures can be
resisted by the use of reinforcement with adequate tensile strength and embankment
fill with adequate shear strength. Thus, the tensile strength of the reinforcement must
be sufficiently high to control the large unbalanced rotational moment because failure
can occurs through the embankment, foundation layer and the reinforcement. Figure
2.4 illustrates circular slip failure.
Figure 2.4: Simple illustration of circular slip failures (Ochiai et al, 1996)
24
Figure 2.5: Simple illustration of side displacement failures (Ochiai et al, 1996)
2.4.3.1 Settlement
The settlement of foundation soil (clay soil) that occurred during and after
construction of embankment is due to the applied loads with time, as shown in Figure
2.6. In the first phase, the foundation soil is in overconsolidated condition and has
high rate of consolidation. Therefore, the settlement is small and increases linearly
with increasing of embankment load (OP’). The clay soils becomes normally
25
Figure 2.6: Typical variations in embankment load and settlement with time
(Lerouiel et al., 1990)
Research conducted by Hunter and Fell (2003) shows that the vertical
deformation at the toe of the embankment versus the relative embankment height, as
shown in Figure 2.7. Meanwhile, Figure 2.8 presents the vertical deformation
behaviour beyond the embankment toe (approximately 5 m distance beyond the toe).
In all cases the monitoring point beyond the toe was located within the eventual
failure zone.
variety of soil types from low sensitivity, ductile high plasticity clays to highly
sensitive, low plasticity clays and silts. Works by Hunter and Fell (2003) shows that
for the highly sensitive, low plasticity clay foundations (St. Alban and James Bay)
the amount of vertical deformation is relatively small (up to 10–15 mm) up to
approximately 90% of the eventual embankment failure height.
Figure 2.8: Vertical displacement beyond toe versus relative embankment height
(Hunter and Fell, 2003)
Asrul Azam and Huat (2003) defined lateral movement as horizontal outward
flow of soil when subjected to shear stresses which increase at the different rate with
vertical settlement due to the anisotropic behavior of the soil. Embankment of limited
width induces vertical settlement and lateral deformation of the foundation soil
whereas large fill areas will experience significant vertical settlement. According to
Asrul Azam and Huat (2003), Duncan and Poulos (1981) categorized lateral
deformation for embankment as follows:
i. Deformation within the foundation soil which is relatively softer than the
embankment itself (for example deformations of road embankment on soft
clay as foundation), and
ii. Deformation within the embankment when the foundation soil is relatively
stiffer (more significant when dealing with dam’s foundation where stiffer
foundation is expected).
The observed lateral displacements at the toe of the embankments are shown
in Figure 2.10. From the observations, Hunter and Fell (2003) summarized that:
Asrul Azam and Huat (2003) presented the empirical correlation of lateral
deformation analyses from previous researchers (Mesri et al. (1994), Tavenas et al.
(1979) and Bourges and Mieussens (1979)) Empirical method normally correlates
maximum lateral deformation, ym to the maximum settlement, sm. However, Mesri et
30
al. (1994) correlates undrained shear strength of soil with maximum lateral
deformation as follows:
(2.3)
Tavenas et al., (1979) suggested that to separate lateral deformation into two major
stages which are during construction phase and after construction phase. They
concluded the empirical correlation based on observation on 21 embankments, as
shown in Table 2.10.
where,
Y=y/ym= (lateral deformation at any depth, z)/(maximum lateral deformation)
Z=z/D= (depth of any point, z)/(total deformed clay thickness)
31
Figure 2.11: Maximum lateral deformation for the 3m control embankment at Muar
Trial compared with the selected empirical method (Asrul Azam and Huat, 2003)
32
Figure 2.12: Maximum lateral deformation for the 6m control embankment at Muar
Trial compared with the selected empirical method (Asrul Azam and Huat, 2003)
2.5
1
33
where at a given depth below the central portion of the embankment σp′ is the pre-
consolidation pressure; σvo’ is the initial effective stress; γr is the saturated unit weight
of the embankment soil, If is the stress influence factor (for the applied load, defined
using Osterberg Chart); and B1 is the observed initial pore pressure response
(determined from Figure 2.14).
∆
(2.6)
With further loading the soil reaches a localized failure condition, and Bf > 1
is observed (Figure 2.13). A localized failure occurs where the effective stress
conditions in a portion of the foundation reach the failure surface (it is generally
initiated at a zone in the foundation below the embankment slope and toe). Complete
failure of the embankment does not necessarily occur once a localized failure
condition is reached as the localized failure zone is supported by the surrounding
unfailed soil. Reports by Hunter and Fell (2003) on the excess pore pressure response
of 13 well-monitored embankments on soft ground that were constructed to failure
stated that in most cases, shows that the excess pore pressure response does not
provide an indication of the impending failure because the piezometer is generally
not located within the localized failure zone.
34
Figure 2.13: Relation between pore pressure and vertical total stress caused by an
embankment (after Tavenas and Leroueil 1980)
Figure 2.14: Relation between depth and coefficient of pore pressure, B1
(Lerouiel et al., 1990)
CHAPTER 3
METHODOLOGY
3.1 Introduction
This project is divided into two main categories which are site construction
woks and laboratory works. This chapter discusses the research methodology that
includes testing material samples and analysis of data performed in this study. As
well as, preparation on literature search were carried out to determine basic
understanding of constructing the full scale embankment, behavior of soft soil and
performance of the embankment.
The research work started with the construction of full scale embankment, so
that monitoring process can be conducted to achieve the objective of the study. After
site clearing process, the sub-base was prepared at 150mm from the existing ground
level so that the site will be cleared from peat soil and roots. The geotechnical
instrumentations were installed at the designated location before the installation of
reinforcement materials were laid on the sub-base. Then, a 3m thick lift of
embankment was placed on the reinforcement material. Finally, monitoring process
was carried out to evaluate the performance of the embankment.
The laboratory works begin with the soil sample collection and selection of
the materials namely geotextile and bamboo. Sample of materials were then tested to
determine their characteristics, which mainly carried out using established methods
in accordance with British Standard (BS) and/or the American Society of Testing
Mateial (ASTM). All parameters were then used in modeling process to predict the
36
For site clearance and preparation for construction, first is to determine the
area for construction and do setting out to provide proper construction area. Finally,
preparing the site by clearing, grubbing and stripping of top soil to make preparation
for instrument installation. Figure 3.2 shows site condition before and after clearing.
Before After
After the entire site clearing process was done, geotechnical instrumentations
were installed at the designated location. There are several geotechnical
instrumentation to be installed at the embankment such as piezometer, settlement
gauges, inclinometer, hydrostatic profiler and the instrumentations was connected to
the data logger for monitoring purposes. Figure 3.3 to Figure 3.5 shows installation
of geotechnical instrumentation.
i) Install the strain gauges at selected point on bamboo and geotextile to monitor
the deformation of the materials (Figure 3.6).
ii) Assembly of the bamboo in square pattern on the existing ground (Figure 3.7).
iii) Installation of the geotextile on the bamboo layer (Figure 3.8).
The trial embankment was constructed by the following procedure (Figure 3.9):
i) Laterite soil was imported from nearby site as backfill material for the
embankment.
ii) Eleven (11) tones of smooth-wheel roller compactor had been used to compact
the fill soil and the embankment was compacted in eight layers where the
proposed height of embankment is 3 meter. For first layer, 900mm height of
embankment were constructed to avoid reinforcement material from damage
and with an advancing seven layers with 300mm until it reach about 3m. The
degree of compaction was checked by taking the sample using core cutter and
speedy moisture tester for each layers of compaction.
iii) Install the settlement marker on top of embankment.
There are several aspects that need to be considered in data monitoring and
analysis. Soil instrumentation had to be calibrated to ensure that the instruments are
in good condition. After that is the monitoring process from instrumentation to
computer through data logger for analyzing data. From monitoring process, lateral
displacement, pore water pressure at different depth, settlement of foundation and
settlement of embankment can be determined to evaluate the performance of the trial
embankment. Figure 3.10 shows example of data monitoring for inclinometer
reading to evaluate horizontal displacement. Analysis to the collected data had been
carried out to find the behavior of the whole structure through time. It will be
presented in a graph for easier interpretation.
41
Core cutter
Settlement Marker
a b
Figure 3.10: Data monitoring for (a) Inclinometer and (b) Hydrostatic Profiler
To achieve the intentions and the aim of this research, a careful selection of
materials had been carried out. The study is to use geotextile alone as a separator and
bamboo-geotextile composite system as reinforcement to increase the ultimate
bearing capacity of soft clay layer. Thus the materials used in this study had been
selected which are Semantan Bamboo and Geotextile TS40.
Two types of material had been tested which is soil and bamboo. There are
two categories of soil involved in the proposed work that is foundation soil, (soft
clay) and embankment soil, (laterite). In determining the engineering properties of
the materials used in this research, the British Standard Methods of Test of Soil for
Civil Engineering purposes (BS1377:1990) and the respective American Society for
Testing and Materials (ASTM) standards were referred, depending upon the
suitability and availability of the equipment in the laboratory. However, in the
absence of the standard method, reference were made to earlier work by other
researchers, but modified accordingly. The summary of the tests carried out and the
standard used is as shown in Table 3.1.
important to determine the parameters of the soil so that prediction to the behavior of
the soil in the future can be made. Soil tests conducted for both soft clay and laterite
is tabulated in Table 3.2.
Table 3.1: Summary of tests carried out and the standard used
Material Name of test/Parameters Standard/Method used
Clay Liquid Limit and Plastic Limit BS 1377:Part2:1990:4,5
Specific Gravity BS 1377:Part2:1990:8
Grain Size Analysis
- Sieve BS 1377:Part2:1990:9
- Hydrometer BS 1377:Part2:1990:9
Odoemeter Test BS 1377:1975:Test 17
Consolidation Undrained Test BS 1377:1975
Laterite
Liquid Limit and Plastic Limit BS 1377:Part2:1990:4,5
Specific Gravity BS 1377:Part2:1990:8
Grain Size Analysis
- Sieve BS 1377:Part2:1990:9
- Hydrometer BS 1377:Part2:1990:9
Compaction Test BS 1377:Part4:1990:3
Unconsolidation Undrained Test BS 1377:1975
Bamboo Bending Test ASTM A370
Tensile Test -
Compaction test √
Consolidation Undrained test, CU √
Unconsolidation Undrained test, UU √
Oedometer test √
45
The sample of sand was placed on a tray and is allowed to dry overnight in an
oven maintained at 105oC - 110oC. After drying, the sample was allowed to cool and
their weights are measured. The sieves used for sieving the samples were 5mm,
3.35mm, 2mm, 1.18mm, 600µm, 425µm, 300µm, 212µm, 150µm and 63µm. sieves
are nested together with the largest aperture sieve at the top and the receiving pan
under the smallest aperture sieve at the bottom.
Mechanical sieve shaker were used and is shaken for 10 minutes for all
particle smaller than each aperture size to pass through. After shaking, the mass of
soil retained in each sieve was measured.
As for clay, the procedure for the test is similar but only involved five sieves
size. The sizes were 600µm, 425µm, 300µm, 212µm, 150µm and 63µm, where the
test were carried out after sedimentation test (using hydrometer) on particles passing
63µm.
The principle of hydrometer analysis is based on Stoke’s Law and the test
was conducted to measure the density of soil, pretreated in a suspension in water at
various intervals of time. Hence, to determine the distribution of particle size on fine
grain of soil having size smaller than 63µm. the procedure of this test is explained in
detail in BS 1377:Part2:1990:9.5.
46
The Atterberg Limit is used to correlate soil strata occurring in different areas
of a site or to investigate in detail the variations of soil properties which occur within
a limit zone. There were two test carried out for Atterberg Limit Test which is Liquid
Limit, wL and Plastic Limit, wP in accordance to BS 1377:Part2:1990:4.3,5.3.
The Plasticity Index, IP is the numerical difference between Liquid Limit and
Plastic Limit, IP = wL – wP where value of IP will categorized the plasticity of the
soils using plasticity chart.
Clay samples were prepared for testing from its natural state. While, samples
of sand are sieved passing 425µm then it was mixed with distilled water and were
leave for 24 hours to mature before proceeding with the test.
Compaction test was carried out using multiple soil batches, where five or
more representative specimens for test are prepared. ‘Light’ and ‘Heavy’ compaction
test were conducted to find a compatibility with site compaction result such as the
47
optimum moisture content and maximum dry density. Both compaction tests were
carried out as described in BS 1377:Part4:1990:3.5 and BS 1377:Part4:1990:3.5
respectively. The procedure used for two types of British Standard Compaction Test
is summarized in Table 3.3.
The test generally follows the procedure given in BS 1377:1975, Test17. The
apparatus referred to, incorporating a fixed ring type of oedometer cell with a test
specimen 50mm diameter and 20mm high.
By using the compacted specimens, where the degree of saturation is less than
100 %, consolidation may occur when the confining pressure is applied and during
shear, even though drainage is not permitted. Therefore, if several partially saturated
specimens of the same material are tested at different confining stresses, they will not
have the same undrained shear strength. Thus, the Mohr failure envelope for
unconsolidated undrained triaxial tests on partially saturated soils is usually curved.
The unconsolidated undrained triaxial strength is applicable to situations where the
loads are assumed to take place so rapidly that there is insufficient time for the
induced pore-water pressure to dissipate and for consolidation to occur during the
loading period.
49
In this research, bamboo was used as one of the reinforced soil material on
one of the trial embankment. However, the guidelines of the design and construction
of the embankment using the above reinforcing materials have not been well-
established. To achieve the objective of the research, first is to determine the bamboo
properties and finally design consideration can be made.
Bending test was conducted at structure laboratory and for the preparation,
samples of bamboo were cut into 1.2m long as well as the supports were designed to
support both end of bamboo while loads are applied. The test was carried out at node
and internode of bamboo, as shown in Figure 3.1. Meanwhile, three transducers were
placed under the bamboo to monitor the displacement during applied loads. Figure
3.2 illustrates condition of bending test were conducted; location of bamboo support,
location of transducers and static applied load.
The bamboo was placed between two supports but both ends were not
restrained. This is to ensure that the bamboo was free to follow the bending action
during the test. A vertical loading was subjected to the center of 1.0m span of
bamboo with 0.5kN increment of loads. In addition, the transducers were placed
underneath the bamboo at the center of 1.0m span and at 0.25m apart from the
support, to measure displacement while loads are applied. Figure 3.3 explains
50
location of transducers with support at both end and point load in the middle of the
span.
Figure 3.11:
3.1 Illustration of the bending test on bamboo
Figure 3.12:
3. Static bending tests on progress
. .
2 3.1
6
with
1
3.2
64
where F is the applied maximum load, L is the free span, d is the outer diameter, di is
the inner diameter and I is the moment of inertia.
3.3
48
where F is the applied maximum load, L is the free span, I is the moment of inertia,
and δ is the deflection under the point load.
respectively. The specimen was placed in the testing machine and load was applied.
Graph of load versus extension were plotted automatically and give result for
maximum load and extension at break. The stress obtained at highest applied force is
the Tensile Strength. The tensile strength, σt has been calculated using the following
formula (Jansen, 2000):
3.4
where Ft is the maximum tensile load at which the piece fails and A is the mean
cross-sectional area.
The calculation for tensile modulus of elasticity using basic formula to find
the elasticity of the material. The tensile modulus of elasticity is calculated using
Equation 3.5.
3.3
4.1 Introduction
Earlier chapter discussed several materials used in this study which are
undisturbed soft clay, lateritic soil and bamboo. Analysis of the test results especially
the engineering properties of these materials are discussed in this chapter. Figure 4.1
shows a soil profile of the construction site, prepared from the geotechnical
investigation that was conducted by Pakatan GeoServices Sdn. Bhd. while Table 4.1
indicates the details of undisturbed soil sample taken at various depth and location.
Based on the soil boring test using wash boring drilling machine and in-situ
test results conducted by Pakatan Geo Services Sdn. Bhd., it can be concluded that
the sub-surface soils consist of very soft to soft SILT/CLAY soils to a depth of
22.5m, followed by a firm to very stiff, SILT/CLAY soils to a depth of 30m below
ground surface. From the in-situ vane shear test, the undrained shear strength of soft
soil is found to be between 17kPa and 20kPa at 3m and 6m depth, respectively. The
deep boring work was terminated at a depth of 34.81m below ground surface after
reaching 3 consecutive Standard Penetration test (SPT), N values equal to 50. At this
level the soils can be described as hard, whitish grey, SILT/CLAY soils. On
completion of the work, the ground water level was found to be at about 0.2 to 0.5m
below the existing ground.
55
2 Very soft to soft, Reddish brown and dark grey mottled, SILT
with traces of sand
N=2
4 Su=17kPa
10
12
16
18
22
Firm, whitish grey, brown and white mottled, SILT with traces of sand
N=6
24
Stiff, whitish grey and brown spotted, SILT with parts of clay and
traces of sand
26 N=14
N=17
28 Very stiff, white and brown mottled, SILT with traces of sand
N=21
N=28
30
Hard, white and brown mottled, SILT with traces of sand
32
34
N=50/160mm
From the combination of dry sieve analysis and hydrometer, the soil
composition had been identified and it is summarized in Table 4.2 while Figure 4.2
shows a complete grain size distribution of soil particle. Based on British Standard
sieve sizes, soil particles smaller than 0.002mm are designated as clay. The shapes of
graph are different with each other and this is due to the different location and depth
of sample, as tabulated in Table 4.1. Some of the sample contained more clay rather
than silt and it could be seen that total average of six samples consist of 60% clay,
29% silt and 11% fine sand, as shown in Table 4.2. Based on the shape of graph the
soil is classified as silty clay.
110
100
90
80
Percent Passing (%)
70 S1 (4m)
60 S2 (1m)
50
S3 (2m)
40
S4 (4m)
30
S5 (1.5m)
20
10 S6 (2m)
0
0.001 0.01 0.1 1 10
Particle Size (mm)
Three samples at different depth were tested on the plasticity of the soil. The
data is tabulated in Table 4.3. The Liquid Limit, wL of clay is found to be in between
60% to 85% and the Plastic Limit, wP ranges between 32% to 34%, hence giving the
Plasticity Index, IP values that varies from 29% to 52%.
As obtained from the Atterberg Limits, the soils can be classified using
Plasticity Chart, as shown in Figure 4.3. Thus, from this chart the soil can be
classified as clay or silt of high plasticity based on the ‘A’ line region. This is due to
the high liquid limit of the soils that ranges between 60% and 86%. The basic
properties of clay are summarized in Table 4.4.
Six samples (Table 4.1) with different depth and location are tested to find the
properties of the consolidation parameters. Table 4.5 shows the result from
oedometer test. The compression Index, Cc of the samples is in the range of 0.16 to
1.04 that indicates that the soils are highly compressible. The coefficient of
consolidation, Cv. and coefficient of permeability, k are in the range of 1.2 to
3.5m2/year and 1.03x10-10 to 3.3x10-10 m/s, respectively. These show that the
consolidation settlement will take a long period to complete due to very low
permeability of the soil.
Figure 4.4 shows the particle size distribution of the fill soil used for the
construction of the embankment. From the figure, the effective grain size, D10 is
0.1mm where, the particle size corresponding to 10% finer. 90% of the particle size
with the diameter finer the 60% and 30% are D60 = 0.8mm and D30 = 0.37mm
respectively. Hence, the uniformity coefficient of the soil, Cu is 2.16 and gradation
coefficient, Cu is 1.71. The properties of laterite soils are tabulated in Table 4.6.
60
100
90
70
60
50
40
30
20
10
0
0.01 0.10 1.00 10.00
Particle Size,mm
Coefficient of gradation,
1.71
Figure 4.5 shows the liquid limit of laterite soil at 20mm cone penetration.
The Liquid Limit, wL of laterite is 69% and the Plastic Limit, wP is 33%, hence give
the Plasticity Index, IP values of 36%.
28
26
Penetration of cone,mm
24
22
20
18
16
14
12
64 66 68 70 72 74 76 78 80 82
Moisture Content, %
Figure 4.6 shows two shape of graph of laboratory compaction result which is
from Modified Proctor test and Standard Proctor test. Heavy compaction test were
carried out to achieve 90% compaction at site. The dry unit weight value achieved
from site compaction is 15.19kN/m3 with 26% moisture content and modified proctor
reached the 90% compaction. The maximum dry unit weight from Modified Proctor
test is 16.6kN/m3 with optimum moisture content of 20%, as shown in Figure 4.6.
While Standard Proctor test give a value of dry unit weight and optimum moisture
content are 15kN/m3 and 25.3% respectively.
62
20
Zero air void
19
Modified
18 Standard
3
D ry D en sity , k N / m 3 17 Sd max =16.6kN/m
16
w op t = 2 0 %
zero air void
Sd max =15kN/m3
15
w o pt = 2 5 .3 %
14
13
12
11
10
16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
Moisture Content, %
The results of UU test were presented in Table 4.7. Firstly, the soils were
compacted to achieve 90% compaction on site. Then, three sample of compacted soil
are taken and each samples were tested with different cell pressure; 50kPa, 100kPa
and 200kPa and give the maximum corrected deviator stress of 506 kPa, 543kPa and
678kPa respectively. Shear strength was developed from both cell pressure and the
deviator stress with a value of 253kPa, 271kPa and 339kPa. Figure 4.7 illustrates a
series of Mohr coulomb circle from different cell pressure. As a conclusion, the shear
strength properties of undrained cohesion, cu and undrained angle of shearing
resistance, φu are 136.8kPa and 23.54o respectively.
63
The bamboos supplied by FRIM, has two different outer diameters of 80mm
and 40mm; and inner diameter of 68mm and 32mm respectively. The node spacing
of bamboo generally varies between 300mm to 500mm. The moisture content of
tested bamboos has an average of 20%. The bending and tensile tests carried out to
the bamboos reveal the results as in the following sections.
64
Standard Deviation,
1
4.1
1
where,
n = total number of samples
xn = bending strength of individual samples
x = average value of bending strength obtained from all samples
Hence,
1
44229.12 70.1
10 1
Thus, the 99% of confident level is between 29.47 MPa to 169.67 MPa. The
summary of bending stiffness analysis of bamboo at node condition is shown in
Table 4.9.
65
By the same method, the bending stiffness values of the internodes of bamboo
material obtained from series of laboratory tests are summarized in Table 4.10. From
the results, it can be seen that the failure bending strength varies between node and
internode condition. It can be concluded that the average failure bending strength at
node condition is less than internode value of average failure bending strength which
is 48.75 MPa.
xn x (xn -x)2
1 6.2 43.01 3199.00
2 4.5 31.22 4672.02
3 5.5 38.15 3771.85
4 5.4 37.46 3857.54
5 6 41.62 99.57 3357.86
11 3.9 175.22 5723.50
12 4.8 215.66 13476.78
14 3.8 170.73 5063.88
15 2.5 112.32 162.66
18 2.9 130.29 944.04
Total= 995.68 44229.12
66
After analyzing the data statistically, the average results of tensile strength are
found to be quite distinct between internode and node conditions. The average tensile
strength at node conditions is 48.23 MPa while, at the internode a condition is 93.55
MPa. These values are obtained from Equation 4.1. Similar pattern of results are also
recorded for the average of tensile modulus of elasticity value (Et), where significant
different between node and internode value appears.
The value of Et at node and internode condition are 2.72 GPa and 3.80 GPa
respectively. In this case, it also can be said that the internodes and nodes condition
of bamboo have significant effect to influences the tensile stiffness of bamboo
mattress.
Comparison between bending test and tensile can be concluded in Table 4.14.
The table presents bamboo properties of strength and modulus of elasticity. At node
condition, the strengths of bamboo do not show great different compared to internode
condition, where significant different values appeared. For modulus of elasticity
properties, values of node and internode condition also indicate great different values
of bending and tensile test analysis.
69
Table 4.13: Tensile test results of bamboo at node and internode condition
Type Maximum Tensile New average Tensile New average of
load Strength, of Tensile Modulus of Tensile
(kN) σt Strength, Elasticity, Modulus of
(MPa) σt Et Elasticity, Et
(MPa)
(GPa) (GPa)
10.95 116.33 4.668
15.9 206.86
15.7 190.29 6.115
Node 11.08 171.64 48.23 2.42
1.78 24.08
1.93 31.62
1.78 28.01 2.931
7.09 97.91 5.675
15.58 175.00 5.985
15.17 227.86 7.232
20.8 279.66
Interno 8.66 166.75 93.55 5.240 3.80
de
2.04 41.20 3.309
2.21 44.06 4.841
1.75 32.84
5.1 Introduction
The analysis was carried out for embankment reinforced with Bamboo-
Geotextile Composite (BGC) and control embankment (unreinforced) to observe the
superiority of the BGC reinforced embankment over unreinforced embankment. This
chapter primarily discusses the effect of combining bamboo and geotextile to be a
composite reinforcement, compared to the use of geotextile alone as a separator in
embankment construct over soft clay. The data obtained are from monitoring works,
where the selected instrumentations were placed at designated location, as shown
earlier in Figure 1.1, Figure 1.2 and Figure 1.3. Hence, the results of measurements
up to 11th September 2009, that is after 120 days from the start of construction are
used to analyze the embankment performance. However, there are also data that
cannot be read by the geotechnical instrumentation such as the auto reading
settlement system because it stopped give readings since the start of the construction.
The analysis was carried out based on the data obtained from monitoring
works, started from 14th May 2009 until 11th September 2009. 14th May 2009 is the
start of construction of the embankment, therefore is taken as zero day of monitoring.
Initial plan was to construct the embankments, so that at the end of construction, the
height of the embankment above the existing ground level would be 3.0m. However,
71
the measured fill height of bamboo reinforced embankment is only 2.970m and fill
height of control embankment is 3.071m. Figure 5.1 and Figure 5.2 illustrate the
construction history of both embankments measured at the center of the
embankments. The initial plan was also to construct the embankment as quickly as
possible with backfill compacted to 90% of maximum dry density. However, the
planned rate of filling at each stages and the duration of the rest periods could not be
fulfilled due to the weather conditions and earthworks requirements. Fill thickness is
the embankment height plus the settlements occurred during the construction of the
embankment which was measured using hydrostatic profiler. The performance of
embankments after 120 days of construction has been summarized and tabulated as
shown in Table 5.1.
3.5
2.5
Fill Thickness (m)
1.5
1
Control Emb.
0.5 BGC
0
0 2 4 6 8 10 12 14 16 18
Time - Days
3.5
3
Fill Height (m)
2.5
Control Emb.
BGC
2
0 20 40 60 80 100 120
Time - Days
5.3.1 Settlement
Figure 5.3 to Figure 5.6 illustrate the settlement across the base of the
embankments at different times obtained by using hydrostatic profiler. It is found that
at any instant, the settlements are almost directly proportional to the embankment
thickness. During construction phase (immediate settlement), the foundation soil of
BGC reinforced settled 0.258m (at the center of the embankment), while foundation
soil under the center of unreinforced embankment settled 0.331m, as illustrated in
Figure 5.3 and Figure 5.4.
at the center of the embankment, as illustrated in Figure 5.7 and Figure 5.8. Data of
embankment settlement was collected since 4th June 2009 which is the day after end
of construction and is taken as zero day of embankment monitoring. Maximum
settlement is taken at the center of the embankment. Hence, the maximum settlement
of the surface of BGC reinforced embankment and control embankment is 0.454m
and 0.555m respectively.
From the observation, the primary consolidation settlement occurred for 103
days after end of construction under BGC reinforced embankment was 0.204m, while
it was 0.201m for unreinforced embankment. The settlement values are quite similar
which probably due to about similar amount of excess pore pressure occurs under
both embankments. Excess pore pressure dissipation of 11kPa was observed under
BGC reinforced embankment while for unreinforced embankment it was 12kPa
(from day 18 until day 120).
74
cL
4m
Embankment
16m
0 2 4 6 8 10 12 14 16 18 20 22
0.0
0.1
0.2
0.3
Settlement (m)
0.4
0.5
0.6
0.7
0.8
Day 1
0.9
Day 17
1.0
Distance (m)
Figure 5.3: Settlement at the end of construction across base of BGC reinforced
embankment
cL
4m
Embankment
16m
0 2 4 6 8 10 12 14 16 18 20 22
0.0
0.1
0.2
0.3
Settlement (m)
0.4
0.5
0.6
0.7
0.8 Day 1
0.9 Day 17
1.0
Distance (m)
Figure 5.4: Settlements at the end of construction across base of control embankment
75
cL
4m
Embankment
16m
0 2 4 6 8 10 12 14 16 18 20 22
0.0
0.1
0.2
0.3
Settlement (m)
0.4
0.5
0.6
0.7
0.8
0.9
Day 17 Day 23 Day 26 Day 42 Day 92 Day 120
1.0
Distance (m)
cL
4m
Embankment
16m
0 2 4 6 8 10 12 14 16 18 20 22
0.0
0.1
0.2
0.3
Settlement (m)
0.4
0.5
0.6
0.7
0.8
0.9
Day 17 Day 23 Day 26 Day 42 Day 92 Day 120
1.0
Distance (m)
Settlement of Embankment
(BGC Reinforced Embankment)
cL
0.5m 3m 0.5m
Embankment
16m
0 2 4 6 8 10 12 14 16 18 20 22
0.0
-0.5
Settlement (m)
-1.0
-1.5
-2.0
-2.5
Day 1 Day 2 Day 3 Day 4 Day5 Day 6 Day 14 Day 28 Day 40 Day 55 Day 99
-3.0
Settlement of Embankment
(Control Embankment)
cL
0.5m 3m 0.5m
Embankment
16m
0 2 4 6 8 10 12 14 16 18 20 22
0.0
-0.5
Settlement (m)
-1.0
-1.5
-2.0
-2.5
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 14 Day 28 Day 40 Day 55 Day 99
-3.0
Figure 5.9: Performance of embankment height with foundation settlement for BGC
reinforced embankment
The periodic lateral movement profiles of the inclinometer placed at the toe of
the embankment are illustrated in Figure 5.11 and Figure 5.12. Maximum lateral
movements, recorded until day 120, both occurred at depth of 4.5m. The values are
8.07mm for BGC reinforced embankment and 11.19mm for control embankment, as
shown in Figure 5.11 and Figure 5.12. However, the movements for both
embankments differ significantly during the construction of embankment.
-2
1 Days
7 Days
8 Days
9 Days
-4 10 Days
13 Days
17 Days
Depth, (m)
21 Days
22 Days
-6
23 Days
24Days
25 Days
26 Days
-8 27 Days
35 Days
42 Days
49 Days
71 Days
-10
92 Days
107 Days
120 Days
-12
-10.0
10.0
15.0
20.0
25.0
-5.0
0.0
5.0
-2 1 Days
7Days
8 Days
9 Days
-4 10 Days
13Days
17 Days
21Days
-6 22 Days
D e pth, (m )
23 Days
24 Days
25 Days
-8 26 Days
27 Days
35 Days
42 Days
-10 49 Days
71Days
92 Days
107 Days
-12 120 Days
-14
A vertical stress due to overburden pressure was monitored from two pressure
cells that have been placed under the BGC reinforced embankment and control
embankment. The stresses measured from this two pressure cells differ obviously.
The highest vertical pressure measured by PC2 (under BGC reinforced embankment)
was 36.18kPa, as shown in Figure 5.13 is less than the theoretical estimate of
53.46kPa (unit weight of fill soil of 18kN/m3 multiply by the embankment height of
2.97m). This is because of the placement of BGC reinforcement that carries the
embankment loads. Therefore, reduces stress on the foundation soil and would also
reduce immediate settlement. The vertical stress from PC3 (under control
embankment) of 166kPa was however, significantly high. It is also found that there
appears to be some missing data during the monitoring process and this might be
caused by the unstable flow of electric current supply to the data logger. For PC3, the
recorded data shows malfunction of the instrumentation after 70 days of monitoring.
Figure 5.14 illustrates the total pressure and the excess pore pressure
(piezometer at 3m depth) relationship with time for BGC reinforced embankment. It
appears that both pressures increased with the embankment height (as time
increases). However, the build-up of excess pore pressure is small because the clay is
still overconsolidated and would dissipate relatively quickly. However, the clay
would become normally consolidated when increase in pore pressure would be
similar to the applied stress increase, and dissipation would be much slower.
81
300
During
Construction After Construction
Total Stress (kPa) 250
200
PC3
150
Control Embankment
100
Bamboo Reinforced
PC2
50
0
0 20 40 60 80 100 120 140
Time - Days
Pressure - Days
(Bamboo Reinforced)
During
70 Construction
After Construction
60
Total Stress
40
30
20
10
0
0 20 40 60 80 100 120 140
Time - Days
Figure 5.14: Relationship between total stress and excess pore pressure measured
under BGC reinforced embankment
82
The variation of excess pore pressure with time beneath centers of the BGC
reinforced embankment and unreinforced embankment are shown graphically in
Figure 5.15 and Figure 5.16. Three (3) pore pressure data had been collected at
various depths (3m, 5m and 7m) beneath the center of embankment. During
construction phase of BGC reinforced embankment, the excess pore pressure
increase proportionally with the embankment height and achieved maximum value of
20.98kPa (for piezometer at 3m depth) which is 15.22kPa less than the overburden
pressure of the embankment (36.18kPa). Whereas, excess pore pressure after 103
days (day 120) was recorded at 9.86kPa (for piezometer at 3m depth) and 6.18kPa
(for both piezometer at 5m and 7m), as shown in Figure 5.15. As mentioned in
previous section, increased in pore pressure are very quickly during the construction
and dissipation take place at slower rate with time when the increase in pore pressure
would be similar to the applied stress increase.
From Figure 5.15 and Figure 5.16, there are several missing data caused by
inaccurate data, automatically collected by data logger, due to insurgence of power
supply. However, from the data obtained, it is observed that the piezometer located at
greater depth does not obviously affected by overburden exerted to the foundation
soil.
83
Bamboo Reinforced
50
During
45 Construction After Construction
35
30
25 P2-3m
P2-5m
20 P2-7m
15
10
0
0 10 20 30 40 50 60 70 80 90 100 110 120 130
Time - Days
Control Embankment
50
During
45 Construction
After Construction
40
Excess Pore Pressure (kPa)
35
30 P3-3m
P3-5m
25
P3-7m
20
15
10
0
0 10 20 30 40 50 60 70 80 90 100 110 120 130
Time - Days
Strain gauges were attached to the culm to measure stresses induced in the
bamboo. A total of 30 strain gauges, or 15 pairs, were placed at the designated
position along the bamboo culm, and 14 strain gauges were attached on the
geotextile, as shown in Figure 1.3. These strain gauges allowed strain changes on the
reinforcement material (bamboo culms and geotextile) to measured using strain
85
meter. The detection is achieved via a set of wire leads emerged from the sloping
surface of the embankment. However, a number of these gauges were lost, usually by
detachment from their wire leads, during their embedment and maybe due to the
chemical interaction between soil and strain gauge. Only three (3) gauges still
recording the data at bamboo which is, B-042(Top), B-043(Bottom) and B-
053(Bottom).
Gauges B-042(T) and B-043(B) are a pair gauges placed near the centerline
of base embankment and gauge B-053(B) were placed near the edge of embankment,
as illustrated earlier in Figure 1.3 an also in Appendix C. During construction phase,
the elongation recorded for gauges near the centerline of base embankment were
greater than elongation occurred near the edge of embankment. As can be seen in
Figure 5.17, elongation of gauges at bottom position of bamboo made by B-043(B)
was 0.000358mm which is higher than B-053(B) of 0.000244mm. At the end of
construction, gauge B-042(T) elongate 0.00045mm smaller than gauge B-043(B) of
0.000358mm elongation.
Stresses induced in the bamboo culm could be obtained from the measured
strain value multiply with the appropriate Young’s modulus value already
determined in the laboratory, i.e. σ=ε × E, where σ is stress induced in bamboo
culm, ε is measured strain value and E is Young’s modulus of bamboo obtained from
laboratory test (taken in the form of average value). For an example, tensile stress
induced in the bamboo culm at the end of construction is summarize as follow:
Bending stress,
σb = ε × Eb
= 0.000358 × 19.4GPa
= 6.95MPa
86
Tensile stress,
σt = ε × Et
= 0.000358 × 3.11GPa
= 1.11MPa
From the calculation, bending stress induced in the bamboo culm is much
higher than tensile stresses which exceed 83.3%. It also indicates that both stresses
are less than bending strength and tensile strength, respectively that was obtained
from laboratory test (refer Table 4.14). Hence, during the construction of the
embankment, the BGC reinforcement has successfully functioned as reinforcement to
carry the external load from the embankment. Results of bending stress and tensile
stress for three (3) observed gauges are tabulated in Table 5.2.
0.0008
During
Construction
After Construction
0.0006
0.0004
Elongation (mm)
0.0002
0
0 10 20 30 40 50 60 70 80 90 100 110 120
-0.0002
-0.0004
B-043
-0.0006 T-042
B-053
-0.0008
Time - Days
Table 5.2: Result of bending stress and tensile stress induced in bamboo culm
Strain gauge T042 B043 B053
Stresses (kPa) σb σt σb σt σb σt
End of construction 8.73 1.40 6.97 1.11 4.73 0.76
After 103 days 0.16 0.02 6.79 1.09 4.62 0.74
*σb is bending stress
*σt is tensile stress
CHAPTER 6
6.1 Introduction
6.2 Conclusion
The BGC reinforcement system has generally been used to improve soft
foundation soil to carry light construction on it. Form this study, it has been proved
that it can be extended to the construction of embankment on soft soil whereby the
bamboo acts principally as a reinforcement material while geotextile as a filter and
separator. In bamboo-geotextile composite system, good tensile strength and bending
stiffness of bamboos were exploited together with geotextile to minimize and affect
well distribution of overburden exerted on the soft subsoil through bending and
tension developed in the system. The result shows significant improved in both
vertical and lateral movement of foundation soil under the bamboo-geotextile
88
i. The types of foundation soil obtained from the site are a combination of clay
and fine silt with high plasticity index ranges from 29% to 52%. The
undrained shear strength of soft soil is found to be between 17kPa and 20kPa
at 3m and 6m depth, respectively. The soils are highly compressible with
compression index, Cc is in the range of 0.16 to 1.04. Based on high value of
coefficient of consolidation and low permeability of the soils, it is anticipated
that the consolidation settlement will take a long period to complete. For, the
backfill soil it has an undrained cohesion of greater than 100kPa and
undrained angle of shearing resistance, φu of 23.54o when compacted to 90%
relative density. The bulk unit weight of laterite soil is 18kN/m3 with natural
moisture content of 21%.
ii. The tensile strength, bending strength and modulus of elasticity, of the
bamboo at internode condition were found to be greater than at node
condition. This is due to the cells in the internodes are axially oriented that
make it strong whereas the directions of the cell-elements in the nodes are
arranged perpendicular to the previous ones to provide the transverse
interconnection. This is thought that the internodes and nodes condition of
bamboo have significant effect to influence the stiffness of bamboo grids.
iii. In BGC reinforced embankment, the stresses induced in bamboo are found to
be much lower than the maximum strength of bamboo obtained from
laboratory tests. It shows that the BGC reinforcement is successfully
functioned as reinforcement to carry the external load from the embankment.
Hence, BGC reinforcement has a great potential to be used as reinforcement
system in soft clay.
i. The same study need to be conducted on the spacing between the bamboos.
This is to find the appropriate spacing in enhancing the usage of bamboo as a
reinforcement material to strengthen the embankment structure.
ii. This study was conducted limited to the constant load which is the self-
weight of the embankment. Extended study should be carried out on dynamic
loading due to vehicles movement.
iii. The same study should be conducted with other species of bamboo to
improve further the study on bamboo in the construction application in
Malaysia.
90
REFERENCES
Leroueil, S., Magnan, J.P. dan Tavenas, F. (1990). Embankments on soft ground.
West Sussex, England. Ellis Horwood.
Li, X. (2004). Physical, Chemical, And Mechanical Properties Of Bamboo And Its
Utilization Potential For Fiberboard Manufacturing. Master Thesis, Faculty of
the Louisiana State University and Agriculture and Mechanical College.
Liu, C. and Evett, J.B. (2004). Soils and Foundations. Sixth Edition. Singapore:
Prentice-Hall.
Lybeer, B. (2005). Age-related anatomical aspects of some temperate and tropical
bamboo culms. Faculteit Wetenschappen, Universiteit Gent.
Ochiai, H., Watari, Y., and Tsukamoto, Y. (1996). Soil Reinforcement Practice for
Fills Over Soft Ground in Japan. Geosynthetics International, Vol.3, No.1, pp.
31-48.
Othman, A.R and Malek, J. (2003). Garis Panduan Perladangan Buluh di Malaysia.
FRIM Technical Information, Handbook No. 33.
Siopongco, J.O. and Munandar M. (1987). Technology Manual on Bamboo as
Building Material. Regional Network in Asia for Low-Cost Building Materials
Technologies and Construction System. Forest Products Research and
Development Institute, Phillipine.
Tavenas, F., Mieussens, C. and Bourges, F. (1979). Lateral Displacements in Clay
Foundations Under Embankments. Canadian Geotechnical Journal. Vol. 16, No.
3, pp. 532-550.
Terzaghi, K., and Peck, R.B (1967). Soil Mechanics in Engineering Practice. John
Wiley and Sons, New York.
Thammicha, S. (1989). Bamboo. Proceedings of A Workshop on Design and
Manufacturing of Bamboo and Rattan furniture. Jakarta, Indonesia, pp. 1–12.
The Malaysian Highway Authority (1989a). Proc. of the International Symp. On
Trial Embankments on Malaysian Marine Clays. Kuala Lumpur. Vol. 1.
The Malaysian Highway Authority (1989b). Proc. of the International Symp. On
Trial Embankments on Malaysian Marine Clays. Kuala Lumpur. Vol. 2.
Ting, W.H., Wong, T.F. and Toh, C.T. (1988). Design Parameters for Soft Ground in
Malaysia. Journal of Southeast Asian Geotechnical Society. Vol. 19 No.1.
Whitlow, R. (1995). Basic Soil Mechanics Third Edition. Addison Wesley Longman
Limited, England.
93
Wong, K.M. (1995). The Bamboos of Peninsular Malaysia. Forest Research Institute
Malaysia (FRIM) in Collaboration with Forest research Centre, Forestry
Department, Sabah, Malaysia. Malayan Forest Records, No. 41.
94
APPENDIX A
B1 B2 B3
Load, kN D1, mm D2, mm D3, mm Load, kN D1, mm D2, mm D3, mm Load, kN D1, mm D2, mm D3, mm
0 0 0 0 0 0 0 0 0 0 0 0
0.5 1.9 1.54 1.93 0.7 2.2 1.91 2.15 0.4 1.1 1.01 0.84
1.2 3.59 3.08 3.31 1 1.8 1.65 1.45
1 3.39 2.78 3.42
1.5 4.19 3.61 3.83 1.5 2.59 2.27 2.08
1.5 4.79 3.91 4.72
1.9 4.93 4.23 4.46 2.1 3.38 2.85 2.69
2 5.79 4.78 5.6 2.6 6.19 5.23 5.45
2.5 6.69 5.58 6.36 2.6 3.98 3.27 3.14
3 6.89 5.78 6.01
3 4.48 3.6 3.51
3.1 7.58 6.34 7.07 3.4 7.58 6.32 6.55
3.7 5.28 4.13 4.09
3.5 8.48 7.13 7.81 4 8.28 7.01 7.25
4 5.78 4.43 4.46
4 9.27 7.78 8.45 4.4 9.07 7.66 7.92
4.9 10.07 8.41 8.66 4.4 6.27 4.78 4.84
4.5 10.07 8.38 9.03
4.5 11.19 9.12 9.36 5 7.01 5.29 5.38
5 10.96 9.16 9.81
4.3 12.76 9.97 10.32 5.5 7.67 5.74 5.89
5.5 11.86 9.84 10.5
4.5 13.56 10.48 10.89
5.8 12.76 10.7 11.32
4.3 16.93 12.81 13.51
6 13.35 11.25 11.9
2.4 19.91 14.44 15.18
6.3 14.64 12.17 12.87
6.3 15.54 12.85 13.61
6.2 15.84 13.12 13.88
5.9 15.84 13.1 13.87
B4 B5 B6
Load, kN D1, mm D2, mm D3, mm Load, kN D1, mm D2, mm D3, mm Load, kN D1, mm D2, mm D3, mm
0 0 0 0 0 0 0 0
0 0 0 0
0.4 0.8 1.25 1.14 0.4 1.79 1.61 2.07
0.5 2.61 2.11 2.83 1 1.9 2.26 2.05 1 4.5 3.8 5.16
1 4.28 3.53 4.24 1.6 2.92 3.15 2.83 1.4 6.29 5.32 7.4
1.5 5.58 4.69 5.28 2 3.5 3.72 3.23 1.9 7.82 6.57 9.15
2 6.47 5.52 6 2.5 4.49 4.52 3.74
2.4 9.53 7.94 11.1
2.9 5.11 5.1 4.28
2.5 7.47 6.39 6.74 3 11.1 9.16 12.69
3.5 5.98 5.8 4.97
3 8.57 7.43 7.67 3.6 12.3 10.13 13.83
3.9 6.68 6.4 5.55
3.5 9.56 8.34 8.43 4 13.1 10.81 14.61
4.5 7.51 7.1 6.24
4 10.46 9.18 9.19 5 8.31 7.76 6.91 4.4 14.09 11.54 15.41
5.5 9.08 8.39 7.54 4.9 14.92 12.23 16.13
4.4 11.39 10.01 9.92
6 9.97 9.06 8.23 5.4 15.89 12.99 16.87
4.9 12.88 11.32 11.12 6 17.19 13.95 17.82
5.4 14.75 12.83 12.53 6.4 18.38 14.84 18.67
4.7 18.7 15.66 15.32 6.8 19.77 16 19.78
4.4 20.69 16.99 16.67 5.6 21.17 16.97 20.76
B7 B8 B9
Load, kN D1, mm D2, mm D3, mm Load, kN D1, mm D2, mm D3, mm Load, kN D1, mm D2, mm D3, mm
0 0 0 0 0 0 0 0 0 0 0 0
0.5 1.1 1.16 1.08 0.6 1.79 1.83 1.65 0.5 1.2 1.25 0.96
1 2 2.08 1.92 1 2.69 2.74 2.51 1 2.2 2.33 1.81
1.5 3.92 3.92 3.63 1.5 3.3 3.34 2.64
1.6 3 2.98 2.74
2 4.4 4.34 3.5
2 3.6 3.61 3.3 2 5.08 4.99 4.69
2.5 5.5 5.33 4.35
2.5 4.39 4.32 3.94 2.5 6.07 5.91 5.6
3 6.63 6.37 5.27
3 5.09 4.97 4.54 2.9 7.26 6.97 6.7
3.5 7.99 7.66 6.54
3.5 5.78 5.6 5.12 3.4 9.05 8.54 8.23 3.6 8.39 7.88 6.64
4 6.58 6.26 5.74 3.3 15.01 13.35 13.12 4 10.09 9.26 7.95
4.6 7.58 7.14 6.59 3.7 16.07 14.31 12.8
5 8.37 7.79 7.21
5.4 9.27 8.54 7.94
5.2 12.65 11.17 10.44
96
0 0 0 0 0 0 0 0
0 0 0 0
0.5 2.19 2.04 1.83
0.4 1.6 1.61 1.25 0.5 1.99 1.77 1.56
0.9 3.51 3.21 2.92
1.1 3.29 3.2 2.54 1 3.99 3.48 3.06
1.5 5.27 4.71 4.31
1.5 4.29 4.17 3.35 1.5 5.58 4.92 4.31 2.1 6.97 6.05 5.56
2 7.31 6.43 5.63 2.5 8.26 7.15 6.6
2 5.58 5.35 4.34
2.4 8.97 7.85 6.88 2.9 9.65 8.27 7.67
2.5 6.68 6.39 5.23
2.9 10.79 9.38 8.25 3.5 11.34 9.62 8.97
3 7.78 7.33 6.03 3.9 13.03 10.96 10.23
3.4 12.95 11.15 9.87
3.5 8.97 8.49 7.01 4.3 15.12 12.68 11.8
3.9 16.93 14.22 12.77
3.9 10.37 9.7 8.06 3.5 20.44 16.47 15.21 4.8 18 15.88 14.28
4.1 11.96 11.05 9.24 4.3 16 16.2 14.28
4.1 12.18 11.28 9.43
3.3 14.84 13.39 11.02
Bending Diameter
Test for of Inner
Sample bamboo Bamboo, Diameter, Maximum Displacement
No. sample d di Length load at break
(mm) (mm) (mm) (kN) (mm)
1 At node 80 68 1000 6.2 13.12
2 At node 80 68 1000 4.5 10.48
3 At node 80 68 1000 5.5 5.74
4 At node 80 68 1000 5.4 12.83
5 At node 80 68 1000 6 9.06
6 At Internode 80 68 1000 6.8 16
7 At Internode 80 68 1000 6.4 8.54
8 At Internode 80 68 1000 7.4 8.54
9 At Internode 80 68 1000 4 9.26
10 At Internode 40 32 1000 4.1 11.28
11 At node 40 32 1000 3.9 14.22
12 At node 40 32 1000 4.8 15.88
14 At node 40 32 1000 3.8 13.91
15 At node 40 32 1000 2.5 14.02
18 At node 40 32 1000 2.9 12.5
13 At Internode 40 32 1000 3.7 11.81
16 At Internode 40 32 1000 1.8 12.36
17 At Internode 40 32 1000 4.5 11.13
BENDING TEST RESULT (node)
i. Bending Strength
Diameter Bending
Bending of Inner Average of Strength New average of
Test for Bamboo, Diameter, Maximum Displacement Moment of Bending Bending Representative, Bending
Sample bamboo d di Length load at break Inertia Strength, σb Strength, σb Strength, σb
No. sample (mm) (mm) (mm) (kN) (mm) (m4) (MPa) (MPa) (MPa)
xn x (x n - x)
2
Therefore,
x - S d = 29.47
x + S d =
98
169.67
ii. Bending Modulus of Elasticity Bending
Diameter Average of Modulus of New average of
Bending of Inner Bending Bending Elasticity Bending
Test for Bamboo, Diameter, Maximum Displacement Moment of Modulus of Modulus of Representative, Modulus of
Sample bamboo d di Length load at break Inertia Elasticity,Eb Elasticity Εb Elasticity, Eb
No. sample (mm) (mm) (mm) (kN) (mm) (m4) (MPa) (MPa) (GPa)
xn x (x n - x)
2
Therefore,
x - S d = 9716.20
x + S d = 73808.48
99
BENDING TEST RESULT (internode)
i. Bending Strength
Diameter Bending
Bending Test of Inner Average of Strength New average
Sample for bamboo Bamboo, Diameter, Maximum Displacement Moment of Bending Bending Representative, of Bending
No. sample d di Length load at break Inertia Strength, σb Strength, σb Strength, σb
(mm) (mm) (mm) (kN) (mm) (m4) (MPa) (MPa) (MPa)
xn x (x n - x) 2
6 At Internode 80 68 1000 6.8 16 9.61063E-07 47.17 2845.92 47.17
7 At Internode 80 68 1000 6.4 8.54 9.61063E-07 44.40 3149.66 44.40
8 At Internode 80 68 1000 7.4 8.54 9.61063E-07 51.33 2419.17 51.33
9 At Internode 80 68 1000 4 9.26 9.61063E-07 27.75 5295.49
10 At Internode 40 32 1000 4.1 11.28 7.41919E-08 184.21 100.52 7004.01 48.75
13 At Internode 40 32 1000 3.7 11.81 7.41919E-08 166.24 4318.93 166.24
16 At Internode 40 32 1000 1.8 12.36 7.41919E-08 80.87 385.95 80.87
17 At Internode 40 32 1000 4.5 11.13 7.41919E-08 202.18 10335.04
TOTAL = 804.14 35754.18 390.00
Therefore,
x - S d = 29.05
x + S d = 171.99
100
ii. Bending Modulus of Elasticity
Bending
Diameter Average of Modulus of New average
Bending Test of Inner Bending Bending Elasticity of Bending
Sample for bamboo Bamboo, Diameter, Maximum Displacement Moment of Modulus of Modulus of Representative, Modulus of
No. sample d di Length load at break,δ Inertia Elasticity,Eb Elasticity Εb Elasticity, Eb
(mm) (mm) (mm) (kN) (mm) (m4) (MPa) (MPa) (GPa)
xn x (x n - x) 2
6 At Internode 80 68 1000 6.8 16 9.61063E-07 9212.88 1643977655 9212.88
7 At Internode 80 68 1000 6.4 8.54 9.61063E-07 16245.34 1123157295 16245.34
8 At Internode 80 68 1000 7.4 8.54 9.61063E-07 18783.67 959463302.2 18783.67
9 At Internode 80 68 1000 4 9.26 9.61063E-07 9363.88 1631756170 9363.88
10 At Internode 40 32 1000 4.1 11.28 7.41919E-08 102065.11 49758.88 2735941791 22.81
13 At Internode 40 32 1000 3.7 11.81 7.41919E-08 87974.01 1460396063 87974.01
16 At Internode 40 32 1000 1.8 12.36 7.41919E-08 40893.72 78591099.51 40893.72
17 At Internode 40 32 1000 4.5 11.13 7.41919E-08 113532.42 4067064688
TOTAL = 398071.03 13700348064 182473.50
Therefore,
x - S d = 5518.71
x + S d = 93999.05
101
102
APPENDIX B
Tensile
Tensile Test Diameter of Maximum Extension at Modulus of
Sample for bamboo Bamboo, d Length Width Thickness Area load break Stress, σt Strain, δ Elasticity, E
2
No. sample (mm) (mm) (mm) (mm) (mm ) (kN) (mm) (MPa) (GPa)
1 At node 80 500 11.65 8.08 94.13 10.95 12.46 116.33 0.02492 4.668
4 At node 80 500 12.58 6.11 76.86 15.9 14.37 206.86 0.02874 7.198
6 At node 80 384 11.38 7.25 82.51 15.7 11.95 190.29 0.031119792 6.115
9 At node 80 381 10.6 6.09 64.55 11.08 8.65 171.64 0.022703412 7.560
3 At Internode 80 500 12.81 6.95 89.03 15.58 14.62 175.00 0.02924 5.985
10 At Internode 80 392 10.29 6.47 66.58 15.17 12.35 227.86 0.031505102 7.232
15 At Internode 80 414 11.9 6.25 74.38 20.8 13.15 279.66 0.031763285 8.805
5 At node 40 300 13.54 5.46 73.93 1.78 13.48 24.08 0.044933333 0.536
12 At node 40 390 11.92 5.12 61.03 1.93 6.6 31.62 0.016923077 1.869
13 At node 40 385 12.15 5.23 63.54 1.78 3.68 28.01 0.009558442 2.931
14 At node 40 386 12.15 5.96 72.41 7.09 6.66 97.91 0.017253886 5.675
2 At Internode 40 500 12.22 4.25 51.94 8.66 15.91 166.75 0.03182 5.240
7 At Internode 40 392 12.38 4 49.52 2.04 4.88 41.20 0.01244898 3.309
8 At Internode 40 390 11.53 4.35 50.16 2.21 3.55 44.06 0.009102564 4.841
11 At Internode 40 389 12.45 4.28 53.29 1.75 7.71 32.84 0.019820051 1.657
103
104
Machine: INSTRON-5567
5567
Standard: ASTM A370
SAMPLE -T15
TENSILE TEST RESULT (node)
i. Tensile Strength
Bending Diameter
Test for of Average of Tensile Strength New average of
Sample bamboo Bamboo, Maximum Extension Tensile Tensile Representative, Tensile Strength,
No. sample d Length Width Thickness Area load at break Strength, σt Strength, σt σt
(mm) (mm) (mm) (mm) (mm2) (kN) (mm) (MPa) (MPa) (MPa)
xn x (x n - x)
2
1 At node 80 500 11.65 8.08 94.13 10.95 12.46 116.33 63.74 116.33
4 At node 80 500 12.58 6.11 76.86 15.9 14.37 206.86 9705.62
6 At node 80 384 11.38 7.25 82.51 15.7 11.95 190.29 6715.67
9 At node 80 381 10.6 6.09 64.55 11.08 8.65 171.64 4006.51 171.64
5 At node 40 300 13.54 5.46 73.93 1.78 13.48 24.08 108.34 7100.58 48.23
12 At node 40 390 11.92 5.12 61.03 1.93 6.6 31.62 5885.76
13 At node 40 385 12.15 5.23 63.54 1.78 3.68 28.01 6452.97
14 At node 40 386 12.15 5.96 72.41 7.09 6.66 97.91 108.85 97.91
Therefore,
x - S d = 32.71
x + S d = 183.97
106
ii. Tensile Modulus of Elasticity
Average of New average of
Diameter Tensile Tensile Tensile Tensile Modulus Tensile
Sample of Maximum Extension Strength, Modulus of Modulus of of Elasticity Modulus of
No. Bamboo, d Length Width Thickness Area load at break σt Strain, δ Elasticity, Et Elasticity, Representative, Εt Elasticity, Et
2
(mm) (mm) (mm) (mm) (mm ) (kN) (mm) (MPa) (GPa) (GPa) (GPa)
xn x (x n - x) 2
1 80 500 11.65 8.08 94.13 10.95 12.46 116.33 0.02492 4.668 0.010 4.67
4 80 500 12.58 6.11 76.86 15.9 14.37 206.86 0.02874 7.198 6.911
6 80 384 11.38 7.25 82.51 15.7 11.95 190.29 0.03111979 6.115 2.390 6.11
9 80 381 10.6 6.09 64.55 11.08 8.65 171.64 0.02270341 7.560 8.948
5 40 300 13.54 5.46 73.93 1.78 13.48 24.08 0.04493333 0.536 4.57 16.264 2.42
12 40 390 11.92 5.12 61.03 1.93 6.6 31.62 0.01692308 1.869 7.291
13 40 385 12.15 5.23 63.54 1.78 3.68 28.01 0.00955844 2.931 2.684 2.93
14 40 386 12.15 5.96 72.41 7.09 6.66 97.91 0.01725389 5.675 1.223 5.67
TOTAL = 36.550 45.72 19.39
Therefore,
x - S d = 2.01
x + S d = 7.12
107
iii. Tensile Modulus of Elasticity x Area (EA)
Tensile Average of
Diameter Tensile Modulus of Tensile Tensile Modulus
Sample of Maximum Extension Strength, Elasticity x Modulus of of Elasticity New average of
No. Bamboo, d Length Width Thickness Area load at break σt Strain, δ Area (EA) Elasticity, Representative, Εt Tensile (EA)
2
(mm) (mm) (mm) (mm) (mm ) (kN) (mm) (MPa) (GPa) (GPa) (GPa)
xn x (x n - x) 2
1 80 500 11.65 8.08 94.13 10.95 12.46 116.33 0.02492 439.406 189083.501 439.41
4 80 500 12.58 6.11 76.86 15.9 14.37 206.86 0.02874 553.236 301035.625 553.24
6 80 384 11.38 7.25 82.51 15.7 11.95 190.29 0.03111979 504.502 249933.324 504.50
9 80 381 10.6 6.09 64.55 11.08 8.65 171.64 0.02270341 488.032 233737.050 488.03
5 40 300 13.54 5.46 73.93 1.78 13.48 24.08 0.04493333 39.614 342.00 1228.185 39.61 342.00
12 40 390 11.92 5.12 61.03 1.93 6.6 31.62 0.01692308 114.045 11985.144 114.045
13 40 385 12.15 5.23 63.54 1.78 3.68 28.01 0.00955844 186.223 32998.195 186.22
14 40 386 12.15 5.96 72.41 7.09 6.66 97.91 0.01725389 410.922 165122.882 410.92
TOTAL = 2735.981 1185123.90 2735.98
Therefore,
x - S d = -69.47
x + S d = 753.46
108
TENSILE TEST RESULT (internode)
i. Tensile Strength
Diameter
Bending Test of Average of New average of
Sample for bamboo Bamboo, Maximum Extension at Tensile Tensile Tensile Strength Tensile Strength,
No. sample d Length Width Thickness Area load break Strength, σt Strength, Representative, σt σt
2
(mm) (mm) (mm) (mm) (mm ) (kN) (mm) (MPa) (MPa) (MPa)
xn x (x n - x)
2
3 At Internode 80 500 12.81 6.95 89.03 15.58 14.62 175.00 1354.44 175.00
10 At Internode 80 392 10.29 6.47 66.58 15.17 12.35 227.86 8039.53 227.86
15 At Internode 80 414 11.9 6.25 74.38 20.8 13.15 279.66 20013.32
2 At Internode 40 500 12.22 4.25 51.94 8.66 15.91 166.75 815.19 166.75
7 At Internode 40 392 12.38 4 49.52 2.04 4.88 41.20 138.20 9408.99 41.20 93.55
8 At Internode 40 390 11.53 4.35 50.16 2.21 3.55 44.06 8860.92 44.06
11 At Internode 40 389 12.45 4.28 53.29 1.75 7.71 32.84 11099.42
TOTAL = 967.37 59591.81 654.86
Therefore,
x - S d = 38.54
x + S d = 237.85
109
ii. Tensile Modulus of Elasticity
Average of New average
Tensile Tensile Tensile Modulus of Tensile
Sample Diameter of Maximum Extension Tensile Modulus of Modulus of of Elasticity Modulus of
No. Bamboo, d Length Width Thickness Area load at break Strength, σt Strain, δ Elasticity, Et Elasticity, Representative, Εt Elasticity, Et
2
(mm) (mm) (mm) (mm) (mm ) (kN) (mm) (MPa) (GPa) (GPa) (GPa)
xn x (x n - x) 2
3 80 500 12.81 6.95 89.03 15.58 14.62 175.00 0.02924 5.985 0.475 5.98
10 80 392 10.29 6.47 66.58 15.17 12.35 227.86 0.031505102 7.232 3.751 7.23
15 80 414 11.9 6.25 74.38 20.8 13.15 279.66 0.031763285 8.805 12.313
2 40 500 12.22 4.25 51.94 8.66 15.91 166.75 0.03182 5.240 0.003 5.24
7 40 392 12.38 4 49.52 2.04 4.88 41.20 0.01244898 3.309 5.30 3.946 3.31 3.80
8 40 390 11.53 4.35 50.16 2.21 3.55 44.06 0.009102564 4.841 0.207 4.841
11 40 389 12.45 4.28 53.29 1.75 7.71 32.84 0.019820051 1.657 13.239
TOTAL = 37.069 33.94 26.61
Therefore,
x - S d = 2.92
x + S d = 7.67
110
iii. Tensile Modulus of Elasticity x Area (EA)
Tensile Average of
Modulus of Tensile Tensile Modulus New average
Sample Diameter of Maximum Extension Tensile Elasticity x Modulus of of Elasticity of Tensile
No. Bamboo, d Length Width Thickness Area load at break Strength, σt Strain, δ Area (EA) Elasticity, Representative, Εt (EA)
2
(mm) (mm) (mm) (mm) (mm ) (kN) (mm) (MPa) (GPa) (GPa) (GPa)
xn x (x n - x)
2
3 80 500 12.81 6.95 89.03 15.58 14.62 175.00 0.02924 532.832 278294.4 532.83
10 80 392 10.29 6.47 66.58 15.17 12.35 227.86 0.031505102 481.509 226779.5 481.51
15 80 414 11.9 6.25 74.38 20.8 13.15 279.66 0.031763285 654.844 421913.3 654.84
2 40 500 12.22 4.25 51.94 8.66 15.91 166.75 0.03182 272.156 71214.4 272.16
7 40 392 12.38 4 49.52 2.04 4.88 41.20 0.01244898 163.869 348.04 25145.5 163.87 348.04
8 40 390 11.53 4.35 50.16 2.21 3.55 44.06 0.009102564 242.789 56403.0 242.789
11 40 389 12.45 4.28 53.29 1.75 7.71 32.84 0.019820051 88.294 6888.806 88.29
TOTAL = 2436.293 1086638.86 2436.29
Therefore,
x - S d = -77.52
x + S d = 773.61
111
112
APPENDIX C