SAYAN ENTERPRISES

HAZARD IDENTIFICATION & RISK ASSESSMENT( HIRA)


oc. No:-SE/HIRA/1.5-L/R-01 Department : CIVIL
Process / Activity : WHITE WASHING AND PAINTING Date of Study: 20.09.2022
Risk Assessment
Type Manning Facility Hazard Source Consequence * Ranking (1/2/3)
(Score)

Process/ Equipment
Evaluation
Sub Processes /
Sl No.

Remarks / Team including


Hazard

CO/CP/CE etc.

Domino Effect
Activities Reference concerned

Detectibility
HB/HC/OHF
Employee(s)

Probability
ILL Health

S (26-75)
UA (>75)
OAI / IAV

Duration

A (2-25)
Severity
LR/OR

Injury

IS (1)
Scale
R NR Own OS Own OS
Making scaffolding Fall of malt.
1 OR
√ √ √ HB
√ 1 2 3 1 3 18
Fall of tools
OR
√ √ √ HB
√ 1 1 3 1 3 9
Slippage of
person
OR
√ √ √ OHF
√ 1 2 3 1 3 18

Preparation of paint / Skin


2
Lime Wash Contamination
OR
√ √ √ HB
√ 1 1 1 3 3 9 Safety
Smelling Paint
fumes
OR √ √ √ HB
√ 1 1 1 3 3 9 Supervisor

Lifting of paint Fall of Paint on


3
eye
OR
√ √ √ HB
OM 1 2 3 1 3 18

Climbing & getting Slippage


4
down of Scoffolding
OR
√ √ √ HB
OM 1 2 3 1 3 18

Application of paint Skin


5
contamination
OR
√ √ √ HB
HC √ 1 2 3 1 3 18

R- Routine HB- Human Behaviour CO- Change in Organisation UA - Unacceptable


Occupational Health Measure Required / Not Required NR - Non Routine HC- Human capability CP- Change in Process S - Significant
OS -Out Source OHF- Other Human factors CE- Change in Equipment A - Acceptable
Comments : LR - Legal Requirement IAV- Inside affecting Vicinity IS - Insignificant
OR - Other Requirement OAI- Outside affecting inside

* Injuries and Ill health to be mentioned as below: Authorised Signature


C- Cut Injury, F-Fracture, M- Fall of material, P- Fall of person, B- Burn injury, E- Eye injury S- Electrical shock,HC- Haz. chemical exposure
OM- Other minor injury, OS- Other serious injury
R- Respiratory problem, H- Hearing impairment, D- Dehydration, ER- Ergonomic problem, T- Temporary physical problem, O- Other serious health problem