ID Task Name Duration Predecessors Month 1 Month 2 Month 3 Month 4

W-2 W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16


1 Pekerjaan Investigasi Tanah Dan Jasa 90 days
Konsultansi Front End Engineering Design
(FEED)
2 A. Persiapan Pekerjaan 3 days
3 A.1. Administrasi dan Data 1 day
4 A.2. Kick-Off Meeting 1 day 3SS
5 A.3. Persiapan Rencana Kerja 2 days 4
6 A.4. Review Secondary Data 2 days 5SS
7 B. Soil Investigasi 14 days
8 B.1. Mobilisasi Peralatan dan Tim Soil 2 days 6
Investigasi
9 B.2. Soil Test 10 days 8
10 B.3. Analisa Hasil Sample Soil Test dan 7 days 9FS-5 days
Uji Laboratorium
11 C. Analisa Kelongsoran 10 days
12 C1. Analisa Stabilitas Lereng 7 days 10
13 C.2. Rekomendasi 3 days 12
14 D. Kajian Analisa dan Proses Pemipaan 77 days
HCE 33 Tie In ke HCE 10A
15 D.1. Analisa Aspek Process 33 days
16 D.2. Analisa Aspek Piping & Pipeline 33 days 15SS+14 days
17 D.3. Analisa Aspek Civil Structure 30 days 15FS-7 days;11
18 D.4. Analisa Electrical, I&C 30 days 15;16
19 D.5. Analisa HSE 14 days 15;16;17;18FS-15 days
20 E. Engineering Estimate 13 days 14
21 F. Dokumen KAK/TOR EPC 10 days 14
22 G. Kajian Kelayakan Operasi dan Finansial 7 days 14
23 H. Presentasi 73 days
24 H.1. Presentasi Laporan Soil Investigasi 0 days 7 H. Presentasi
25 H.2. Presentasi Laporan Awal FEED 0 days 14 H. Presentasi
26 H.3. Presentasi Laporan Akhir FEED 0 days 20;21;22 H. Presentasi
27 I. Laporan 88 days
28 I.1. Laporan Biweekly 82 days
36 I.2. Laporan Akhir FEED 0 days 20;21;22;26 I. Laporan

Task Project Summary Manual Task Start-only Deadline

Project: Jadwal HCE 33 Split Inactive Task Duration-only Finish-only Progress


Date: Sun 06/02/22 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone